Prince William County Department of...

52
Prince William County Department of Transportation Joint Mobility Report May 6, 2019 Ricardo Canizales - Director Department of Transportation

Transcript of Prince William County Department of...

Page 1: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

Prince William County Department of Transportation

Joint Mobility ReportMay 6, 2019

Ricardo Canizales - DirectorDepartment of Transportation

Page 2: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

Burwell Road (Rural Rustic)

Updates: Anticipating final plan approval by

VDOT in early/mid May 2019. Project is scheduled for construction by

Public Works in late Spring 2019. Anticipated completion of easement

acquisition is May 2019.

Status: Under Design Construction begins – June 2019. Construction ends – November 2019.*

Purpose: Pave Burwell Road from the existing paved road to Fauquier County lineBrentsville Magisterial District

*Timeline date changed due to a delay in the Right-of-Way process.

2Quarterly Mobility Report | Monday, May 6, 2019

UNDER DESIGN

Page 3: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

3

Broad Run Station and Yard Improvements

Purpose: Expand station and train storage capacity

Updates: Design concept under review by Norfolk Southern. Ongoing coordination with Manassas Regional Airport,

City of Manassas, and Federal Transit Administration.

Status: Under design PE and NEPA completion – 2019. Final design begins – 2019. Construction complete – 2022.

VIRGINIA RAILWAY EXPRESS

Quarterly Mobility Report | Monday, May 6, 2019

Page 4: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

4

Discovery Boulevard Extension (Thomasson Barn Road Extension)

Quarterly Mobility Report | Monday, May 6, 2019

Purpose: Construct two lane roadway with terminus at Hornbaker Road

Updates: Box culvert was installed in March 2019. Entrance to Data Center is completed. Roadway construction on schedule for completion

in May 2019.

Status: Construction Construction began – November 2018. Construction ends – May 2019.

UNDER CONSTRUCTION

Page 5: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

5

Innovation Pedestrian Improvements

Quarterly Mobility Report | Monday, May 6, 2019

Purpose: Construct sidewalks on Discovery Boulevard, Innovation Drive, and University Boulevard

Updates: Right-of-Way acquisitions is ongoing. Bid documents started. Final plan submission made to VDOT and

PWC.

Status: Under Design Utility relocations complete – May 2019. Construction award – Late Summer 2019. Construction begins – Fall 2019. Construction ends – Spring 2020.

UNDER DESIGN

Page 6: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

6

OMNIRIDE Western Maintenance Facility

Quarterly Mobility Report | Monday, May 6, 2019

Purpose: Construct bus storage yard and maintenance facility

Updates: Groundbreaking event for project was

held on January 23, 2019 at 11:00 AM. Once completed, the WMF will serve as

the base for western county services and support future enhancements along the I-66 corridor as well as throughout western Prince William County.

Status: Under Construction

Page 7: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

7

Route 28, Phase II

Quarterly Mobility Report | Monday, May 6, 2019

Purpose: Four lane widening of Route 28 from Fitzwater Drive to Vint Hill Road

Updates: Northbound curb and gutter installation is ongoing

with 65% completed. Northbound bridge girders placement was

completed. Project is nearing 80% completion and on

scheduled for 100% completion by contract completion date.

Status: Under Construction Construction ends – October 2019.

UNDER CONSTRUCTION

Page 8: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

8

Route 28, Phase III

Quarterly Mobility Report | Monday, May 6, 2019

Purpose: Six lane widening of Route 28 from Linton Hall Road to Pennsylvania Avenue

Updates: Right-of-Way review and authorization to

initiate acquisition granted by the County was completed.

A total of 28 properties are impacted. Project final plans were approved by VDOT. Construction is scheduled to begin in late

Summer 2019. A trail connection from Route 28 to VRE

property is in Phase 1 design.

Status: Under Design Construction begins – Summer 2019. Construction ends – Spring 2022.

UNDER DESIGN

Page 9: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

9

Vint Hill Road Extension

Quarterly Mobility Report | Monday, May 6, 2019

Purpose: Construct a turn lane on Vint Hill Road from Sudley Manor Drive to Garry Glen RoadUpdates: The 36” waterline installation is ongoing including jack

and bore operation under the gas lines. Jack and Bore operations will be completed soon.

Storm drainage activities are ongoing including pipe installation.

Roadway paving has begun. Project nearing 35% completion and on schedule for

completion by contract date.

Status: Under Construction Construction began – October 2018. Construction ends – November 2019.

UNDER CONSTRUCTION

Page 10: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

10

Intersection Improvements at Prince William Parkway and University Boulevard

Quarterly Mobility Report | Monday, May 6, 2019

Purpose: Construct intersection improvements at the intersection of Prince William Parkway and University Boulevard (Quadrant Roadway Intersection)

Updates: Traffic counts and data collection are complete. Preliminary design is ongoing for submission to the

County in March 2019. Public Information Meeting is anticipated in May

2019.

Status: Under Design Design began – December 2018. Design ends – January 2020. Construction advertisement begins – December 2020. Construction ends – December 2022.

UNDER DESIGN

Page 11: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

11

University Boulevard Extension

Quarterly Mobility Report | Monday, May 6, 2019

Purpose: Construct two lane roadway from Edmonston Drive to Sudley Manor Drive

Updates: Preliminary Field Inspection (PFI) plans

submission were delivered to VDOT in April 2019.

Design activities have begun. PIM is anticipated in June 2019.

Status: New Project/Under Design Design began – November 2018. Design ends – December 2019.

UNDER DESIGN

Page 12: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

12

Balls Ford Road Interchange

Quarterly Mobility Report | Monday, May 6, 2019

Brentsville/Gainesville Magisterial DistrictsPurpose: Design and Construct a Diverging Diamond Interchange at Route 234 Bypass and relocated Route 621 (Balls Ford Road)

Updates: Public Information meeting was held on April

3, 2019. Tri-party agreement with Norfolk Southern

Corporation and VDOT was drafted and submitted for review and approval to both agencies.

RFQ for a design-build contract is scheduled for advertisement May 2019.

Status: Under Design Design-build begins – January 2020. Construction ends – December 2022.

UNDER DEVELOPMENT

Page 13: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

13

Balls Ford Road Widening

Quarterly Mobility Report | Monday, May 6, 2019

Brentsville/Gainesville Magisterial DistrictsPurpose: Widening from two to four lanes from Doane Drive to Route 234 Business

Updates: Design phase is ongoing. Public Hearing was held on May 7, 2019 at the Life

Church located on Balls Ford Road.

Status: Under Design Design began – June 2018. ROW begins – Fall 2019. Construction bid advertisement – October 2020. Construction ends – November 2022.

UNDER DESIGN

Page 14: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

14

Route 646 Aden Road Bridge

Quarterly Mobility Report | Monday, May 6, 2019

Brentsville Magisterial District

Purpose: Construct bridge replacement over railroad

Updates: Bridge is open to traffic.

Status: Under Construction Construction completion – May 2019.

Photo courtesy of Roger Snyder

Page 15: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

15

Sudley Manor Drive and Bethlehem Road

Quarterly Mobility Report | Monday, May 6, 2019

Brentsville Magisterial District

Purpose: Study the access concerns on Sudley Manor Drive

Updates: Temporary measures installed to restrict

movements. Continue to monitor for possible permanent

feature measures.

Status: Completed

Page 16: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

16

Dumfries Road Sidewalk Project

Quarterly Mobility Report | Monday, May 6, 2019

Coles Magisterial District

Purpose: Construct a sidewalk from Counselor Road to Tayloe Drive

Updates: Nutrient credits were purchased in March 2019. Bid document for PS&E submitted to VDOT was finalized

in April 2019. VDOT approved construction plan in April 2019.

Status: Under Design Design ends – April 2019. Construction advertisement – June 2019. Construction ends – April 2020.*

*Timeline date changed due to a delay in the Right-of-Way process.

UNDER DESIGN

Page 17: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

17

Brentsville Road Interchange at the Parkway

Quarterly Mobility Report | Monday, May 6, 2019

Coles Magisterial District

Purpose: Construct an innovative interchange at Route 234 and Brentsville Road

Updates: Accepted proposal was advertised for

interested parties in November 2018 with a closing date of April 1, 2019.

Two competing proposals were received by the closing date currently being reviewed by the PWC DOT staff.

Status: TBD Design begins – TBD Design ends – TBD Construction begins – TBD Construction ends – TBD

UNDER DEVELOPMENT

Page 18: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

18

Featherbed Lane Paving

Quarterly Mobility Report | Monday, May 6, 2019

Gainesville Magisterial District

Purpose: Extend surface road from the end of the existing tarmac beyond General Trimbles Lane

Updates: Design plans were submitted and approved by

VDOT. Construction begins in July 2019.

Status: Under Construction Design began – June 2018. Design ends – April 2019. Construction begins – July 2019. Construction ends – August 2019.

UNDER CONSTRUCTION

Page 19: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

19

I-66 Park and Ride Haymarket

Quarterly Mobility Report | Monday, May 6, 2019

Gainesville Magisterial DistrictPurpose: Construct an approximately 230 space lot in the northeast quadrant of I-66 and Route 15

Updates: Open to the public and began commuter bus

service in December 2018. Lot is in use.

Status: Completed

Page 20: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

20

Route 1596 Williamson Boulevard

Quarterly Mobility Report | Monday, May 6, 2019

Gainesville Magisterial DistrictPurpose: Construct turn lane and install traffic signal at Stonehouse Drive

Updates: Right-of-Way and utility phase began. Anticipated to be construction by on-call staff. A

final determination will be made once the Right-of-Way phase is complete.

Status: Under Design Construction begins – if done in-house,

construction is scheduled to start by end of 2019.

Page 21: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

21

Route 28 at Fauquier Drive

Quarterly Mobility Report | Monday, May 6, 2019

Gainesville Magisterial DistrictPurpose: Operational Improvements at Fauquier Drive

Updates: New Project, Preliminary Design underway. Extend southbound Route 28 right turn lane

and Intersection reconfiguration.

Status: Under Construction Construction begins – Fall 2019.

Page 22: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

22

Transform 66- Outside the Beltway

Quarterly Mobility Report | Monday, May 6, 2019

Gainesville/Brentsville Magisterial Districts

Purpose: Construct two new express lanes in each direction on I-66 from I-495 to Gainesville (University Boulevard) and multimodal improvements to address current congestion and future needs.

Updates: Construction activities are ongoing with the

completion of lane shifts, working behind barrier, utility relocation, preliminary demolition, retaining wall, and bridge pier construction.

Traffic impacts and lane closure information are available to the public at transform66.org.

Status: Under Construction Construction began – December 2017.

Page 23: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

23

Transform 66- Outside the Beltway-Balls Ford Road Parking Lot

Quarterly Mobility Report | Monday, May 6, 2019

Gainesville Magisterial District

Updates: Lot is anticipated to be completed and

opened to the public in December 2022.

Clearing and grubbing is complete. Construction began.

Page 24: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

24

Transform 66- Outside the Beltway-University Boulevard Route 29 Park and Ride Lot

Quarterly Mobility Report | Monday, May 6, 2019

Gainesville Magisterial District

Updates: Lot is anticipated to be partially

opened in Summer 2019 with 960 spaces.

Clearing and grading has been completed.

Construction is underway.

Page 25: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

25

Neabsco Mills Road

Quarterly Mobility Report | Monday, May 6, 2019

Neabsco and Woodbridge Magisterial Districts

Purpose: Four lane widening from Route 1 to Dale Boulevard

Updates: Right-of-Way plans were submitted to VDOT in

April 2019. Right-of-Way acquisition is anticipated to initiate in

Winter 2020 once authorization is received.

Status: Under Design Design began – June 2017. Final design plans – December 2019. ROW authorization – Winter 2020. Construction advertisement – December 2020. Construction begins – March 2021. Construction ends – April 2023.

UNDER DESIGN

Page 26: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

26

Smoketown Road/Opitz Boulevard Pedestrian Improvements

Quarterly Mobility Report | Monday, May 6, 2019

Neabsco and Occoquan Magisterial Districts

Purpose: Reconstruction of ADA ramps and crosswalk at the intersection of Smoketown Road and Opitz Boulevard

Updates: VDOT authorization of Right-of-Way was

granted. Additional funding for project completion

appears necessary and will be discussed with VDOT.

Status: Under Construction Construction advertisement – Late Spring

2019. Construction begins – Summer 2019. Construction ends – Fall 2019.

UNDER CONSTRUCTION

Page 27: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

27

Old Bridge Road Sidewalk

Quarterly Mobility Report | Monday, May 6, 2019

Occoquan Magisterial District

Purpose: Construct a sidewalk from the entrance of Tacketts Mill to Minnieville Road

Updates: Task order modification (new alternative) was

negotiated with ATCS in April 2019. The alternative will utilize some available asphalt on

the road to avoid construction of the retaining wall and relocation of significant utilities.

Status: Under Design Design began – August 2018. Design ends – Summer 2019. Right-of-Way and Utilities begins – July 2019. Construction begins – November 2019. Construction ends – Summer 2020.

UNDER DESIGN

Page 28: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

28

Dumfries Road North Shared Use Path

Quarterly Mobility Report | Monday, May 6, 2019

Potomac Magisterial District

Purpose: Construct a Shared Use Path from Country Club Drive to Exeter Drive

Updates: Storm pipe activities are ongoing. Retaining wall steel drilling and pilling are ongoing.

Status: Under Construction Construction award – October 2018. Construction began – November 2018. Construction ends – July 2019.

UNDER CONSTRUCTION

Page 29: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

29

Fuller Heights Road

Quarterly Mobility Report | Monday, May 6, 2019

Potomac Magisterial District

Purpose: Intersection improvements at Fuller Heights Road (Quantico Marine Corps Base Entrance)

Updates: Design activities are ongoing. Coordination with Base Project is

ongoing.

Status: Under Design

Design began – March 2019. Design ends – September 2019. Construction begins – February 2020. Construction ends – November 2020.

UNDER DESIGN

Page 30: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

30

Inn Street

Quarterly Mobility Report | Monday, May 6, 2019

Potomac Magisterial District

Purpose: Construct a connection between Joplin Road (existing Inn Street) and Jefferson Davis Highway – Route 1

Updates: Project construction advertisement is

scheduled for May 2019. Project includes construction of box culvert. Final plans are in review.

Status: Under Design Design began – February 2019. Design ends – May 2019 Construction begins – July 2019. Construction ends – November 2019.

UNDER DESIGN

Page 31: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

31

Quantico Station Improvements

Quarterly Mobility Report | Monday, May 6, 2019

Potomac Magisterial District

Purpose: Construct station improvementsUpdates: Intercity Passenger Rail Operating and Capital Fund

(IPROC) funding agreement executed and notice-to-proceed pending.

Final design pending receipt of IPROC grant NTP. Temporary platform IFB issued in January 2019.Status: Under design Design completed – Fall 2018. Construction advertisement – 2019. Construction begins – 2019. Construction complete – TBD.Related projects: Arkendale to Powell’s Creek 3rd track by DRPT.

VIRGINIA RAILWAY EXPRESS

Page 32: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

32

Route 1 Widening- Town of Dumfries

Quarterly Mobility Report | Monday, May 6, 2019

Potomac Magisterial District

Purpose: Widen Route 1 (Fraley Boulevard NB) from 2 to 6 lanes to serve two-way traffic with pedestrian/bike facilities.

Updates: Evaluating comments received from a public hearing

on October 18, 2018. Team working on property impacts. Design activities are ongoing.

Status: Under Design Design began – Fall 2017. Construction begins – TBD.

Page 33: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

33

Annapolis Way

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Roadway improvements for Annapolis Way

Updates: Woodbridge TRIP funds secured, and project task

order initiated on March 27, 2019. Held a pre-scoping kickoff meeting with the

design firm on March 28, 2019 to introduce the project and discuss and review owner needs and project objectives.

Project initiation/scoping is ongoing. Design will being in Spring 2019. Coordination with adjacent development is

ongoing.

Status: Under Design Design begins – Spring 2019. Design ends – TBD. Construction begins – TBD. Construction ends – TBD.

UNDER DESIGN

Page 34: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

34

Blackburn Road Pedestrian Improvements

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Construct a sidewalk/multi-use trail from Route 1 to the newly constructed Neabsco Boardwalk across from Rippon LodgeUpdates: Construction is nearing completion with boardwalk

section at 100% completed awaiting handrail. Project will be completed in April 2019.

Status: Under Construction Construction began – June 2018. Construction ends – walk through with Parks and

Recreation is scheduled for April 25, 2019.

UNDER CONSTRUCTION

Page 35: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

35

Rippon Landing Neighborhood Park Parking Lot

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Construct a parking lot at Rippon Landing

Updates: Clearing activities are complete. Construction is in progress and on schedule for

completion in Spring 2019. Plans for trail extension were approved by PWC

Environmental Services in April 2019.

Status: Under Design (Parking) Design completion – December 2018. Design completion of trail – Spring 2019. Construction begins – Spring 2019. Construction ends – June 2019. Construction of Trail Extension begins – May

2019.

UNDER DESIGN

Page 36: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

36

Express Drive Sidewalk

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Construct missing section of the sidewalk at the front of the Woodbridge VRE station to improve commuter safety

Updates: Construction of the sidewalk by county forces will

resume in early May 2019.

Status: Under Construction Construction began – November 2018. Construction ends – Spring 2019.

UNDER CONSTRUCTION

Page 37: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

37

Horner Road Sidewalk Project

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Construct a sidewalk from Forest Glen Road to Kilby Elementary SchoolUpdates: Right-of-Way acquisition completed. Plans, Specification, and Estimate (PS&E) are

anticipated for submission to VDOT in Spring 2019.

Construction authorization is anticipated in late Spring 2019.

Status: Under Design Design ended – September 2018. Construction advertisement – early Summer

2019. Construction begins – Summer 2019. Construction ends – Fall 2019.

UNDER DESIGN

Page 38: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

38

I-95 Auxiliary Lane

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Improve Operations, reduce weaving

Updates: Governor Announcement – January 2019. Scope defined, schedule being developed.

Status: Preliminary Engineering Design starts late 2019

Page 39: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

39

Opitz Boulevard Sidewalk Project

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Construct a sidewalk from Potomac Library to Potomac Center Boulevard

Updates: Design activities were finalized for final VDOT approval

in March 2019. Right-of-Way negotiations were completed. Bid document review is ongoing. Plan approved by VDOT.

Status: Under Design Construction advertisement – Fall 2019. Construction award – Spring 2020. Construction begins –Spring 2020. Construction ends – Summer 2020.

UNDER DESIGN

Page 40: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

40

Rippon Station Improvements

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Construct station improvementsUpdates: Preliminary engineering (PE) design and NEPA analysis are

ongoing for side and island platform completion pending CSXT design review.

Anticipated completion in 2022. Ongoing coordination with CSXT, DC2RVA third track PE

design.Status: Under design PE design complete – Fall 2018. Final design complete – Fall 2019. Construction complete – 2022.

Related projects: DC2RVA 3rd track by DRPT.

VIRGINIA RAILWAY EXPRESS

Page 41: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

41

Route 1- Featherstone to Mary’s Way

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Six lane widening on Route 1 from Featherstone Road to Mary’s Way

Updates: Duct bank activity on Phase 1 were completed end April

2019. Waterline activities on Phase 1 are 95% complete. Dominion began relocation (conduit installation) in April

2019. Road construction bid is scheduled for advertisement in

January 2020. Phase 1 utility is complete.

Status: Under Construction Utility and waterline relocations began – August 2018. Construction (duct bank) ends – November 2019. Road Widening Construction Advertisement- Winter

2020. Construction ends – Fall 2021.

UNDER CONSTRUCTION

Page 42: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

42

Route 1/123 Interchange

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Six lane widening on Route 1 from Featherstone Road to Mary’s Way

Updates: Construction activities are ongoing. Bridge construction is ongoing. Drainage work at railroad continues.

Status: Under Construction Phase I – Route 1 widening from Annapolis

Way to Mary’s Way. Phase II – Interchange, unfunded ($80M).

Submitted to the Virginia Smart Scale Program for funding evaluation on August 8, 2018. Is not recommended for under current scenario.

Page 43: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

43

Route 638 Blackburn Road at Rippon Boulevard

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Intersection improvements

Updates: Right-of-Way acquisition is underway.

Status: Under Design Construction advertisement – Fall 2019.

Page 44: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

44

Southampton Street Sidewalk

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Construct a sidewalk and other improvements from Montgomery Avenue to Pine Lane

Updates: Project construction completed. Awaiting

installation of streetlights.

Status: Under Construction Design ended – April 2018. Construction began – Fall 2018. Construction ends – April 2019.

UNDER CONSTRUCTION

Page 45: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

45

Potomac/Neabsco Mills Commuter Garage

Quarterly Mobility Report | Monday, May 6, 2019

Woodbridge Magisterial District

Purpose: Construct a 1,414 space garage within the vicinity of the Neabsco Mills Widening Project.

Updates: Project to be delivered using Design-Build

delivery contract. Final location negotiations were submitted for

BOCS approval on April 9, 2019. Land acquisition of Site J was approved by the

BOCS on April 9, 2019.

Status: Under Design Location study began – March 2018. Location study ended – August 2018. Preliminary design begins – Spring 2019. Construction ends – Fall 2023.

UNDER DEVELOPMENT

Page 46: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

46

Route 28 Corridor Feasibility Study-Environmental Assessment

Quarterly Mobility Report | Monday, May 6, 2019

Various Magisterial Districts

Purpose: Complete the NEPA process to determine the best alternative to relieve congestion on Route 28.

Project Summary: PWC DOT is determining the feasibility of

obtaining the permits from the bypass. The project was not included in the Smart Scale

review.

Status: Ongoing NEPA Process began – Spring 2018. NEPA Process ends – Depending on the type

of NEPA, Winter 2019 or Spring 2021.

UNDER DEVELOPMENT

Page 47: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

47

OMNIRIDE I-66 Commuter Choice

Quarterly Mobility Report | Monday, May 6, 2019

Various Magisterial Districts

Purpose: To bring new/enhanced services to the western end of the County service area.

Updates: OMNIRIDE has applied for funding for new or

enhanced commuter transit services in the FY20 call for projects Service to supplement new University Commuter

lot opening in 2019. Potential enhancements and restructuring

opportunities based on more parking capacity. Promotional support for slugging in the I-66

corridor.

Status: Projects are being evaluated by Commuter Choice working group.

Page 48: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

48

OMNIRIDE Rebranding

Quarterly Mobility Report | Monday, May 6, 2019

Various Magisterial Districts

Purpose: Transitioning new buses into the fleet and retiring older vehicles. Updates: OMNIRIDE has taken delivery of 37 new MCI

Commuter Motor coaches. Wrapping buses with new design and

logos Project was completed late December

2018.

Status: All new buses are wrapped.

Page 49: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

49

OMNIRIDE NOVA Transit Pass

Quarterly Mobility Report | Monday, May 6, 2019

Various Magisterial Districts

Purpose: Partner with Woodbridge NOVA campus to offer discounted transit pass for students, faculty, and staff.

Updates: Flash pass for student/staff IDs. Only for the Woodbridge campus. Unlimited travel on local and Metro Express buses

for the Spring semester (through May 31, 2019).

Status: Pass sales began in January 2019. On-campus promotion began in February 2019.

Page 50: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

50

Route 29 at Vint Hill Road

Quarterly Mobility Report | Monday, May 6, 2019

Prince William/Fauquier County Line

Purpose: Improve stopping sight distance

Updates: Project will reduce hills approaching Vint Hill

Road. Route 29 Northbound Closure planned from

July 8 to August 2, 2019. Construction ends September 2019.

Status: Under Design Advertised and Design-Build contractor

selected. CTB approved. Construction activities begin early Summer

2019, which will include the closure of Route 29.

Page 51: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

51

Potential Future Projects

Quarterly Mobility Report | Monday, May 6, 2019

Devlin Road Widening University Boulevard Extension (Devlin Rd to Wellington Road Route 28 Bypass Sudley Road Corridor Intersection Improvements Route 55 Improvements Minnieville Road/Prince William Parkway Intersection

Improvements Old Bridge Road/Gordon Blvd Intersection Improvements Summit School Road Extension Van Buren Road Extension Mobility Improvements in North Woodbridge Other safety/operational and bike/ped projects

Page 52: Prince William County Department of Transportationwdcsite.org/wp-content/uploads/2019/05/PWC_Qtr2... · Purpose: Design and Construct a Diverging Diamond Interchange at Route 234

52Quarterly Mobility Report | Monday, May 6, 2019

QUESTIONS?