Primary Care Co Commissioning Committee Risk Register Agenda … · 2019-06-20 · Primary Care Co...
Transcript of Primary Care Co Commissioning Committee Risk Register Agenda … · 2019-06-20 · Primary Care Co...
1 21 February 2018
Primary Care Co Commissioning Committee Risk Register Agenda Item 309.
December 2017
The table below provides a summary Risk Profile of the Primary Care Co Commissioning risk register for the risks that require further work to provide assurance that they are being managed effectively and any gaps in assurance or controls are being addressed,
Risk No
CCG Priority / Objective Risk Current risk
6 Commission sustainable high quality
services within available resources.
Risk to Business continuity from eMBED as provider of IM&T to GP practices.
20
7 Commission sustainable high quality
services within available resources.
Risk to maintaining a sustainable workforce with appropriate skills due to difficulties in recruiting GPs and PNs at a time when the retirement rate will increase over next 2 years
16
8 Commission sustainable high quality
services within available resources
There is a risk of some or all the ETTF bids being unsuccessful which may impact on the ability of primary care to expand the services delivered from their practices and maintain facilities to cope with increasing list sizes.
12
9 Commission sustainable high quality
services within available resources
Risk of capacity of GPs not being able to respond to patient demand alongside need to provide mentoring to trainees, students and Advanced Nurse Practitioners
12
10 Commission sustainable high quality
services within available resources
Risk associated with the change in funding formulae which means practices need to contribute 66% of funding and that all practices may not be able to raise this level of funding Note: Three funding streams required
- NHSE capital - Practice contribution
Revenue costs- CCG
12
11 Commission sustainable high quality services within available resources
Inability to deliver General Practice Forward View due to lack of management resources to drive forward plans.
12
2 21 February 2018
12 Commission sustainable high quality services within available resources
Inability to procure extended access to primary care services as set out in NHSE General Practice Forward View and Planning Guidance
16
13 Commission sustainable high quality
services within available resources Inability of eMBED to deliver key IM&T projects within timelines set by NHSE or as required by capital improvement plans Risk added August 2017
20
14 Commission sustainable high quality
services within available resources Inability of SRCCG to provide appropriate level of resource( skills and capacity) to support the GP International Recruitment project across the HCV STP Risk added August 2017
20
3 21 February 2018
Risk Threshold Matrix
The risk tolerance/appetite under which risks can be tolerated is a score of 11 or below where the assessment has been undertaken following the implementation of controls and assurances. Risks scored at 12 or above must have an associated action plan. Risks scored at 16 or above must be notified to the Board through the Assurance Framework or via exception reporting.
Monitoring of Provider Services Monitoring of CCG risks
1-5 Low No Commissioner action.
Minimal action may be required Manage/monitor situation within team
Clinical judgement regarding
specific risks may override thresholds
6-11 Medium No Commissioner action.
Minimal action may be required Manage/monitor situation within team
12-15 High
Commissioners will closely monitor the Provider action plan. Persistent risks which remain at this score for over 6 months
will be subject to a Commissioner Appreciative Enquiry. Where 6 or more areas of risk are scored as “High” at any
one time, a Commissioner Appreciative Enquiry will be considered based on clinical judgement.
Action/s within 6 – 8 months
Usually handled within the team by line manager
16-20 Very High
The Trust will be given 3 months to mitigate the risk. If the risk score is not reduced to at least “High” after a period of 3 months then it will be subject to a Commissioner Appreciative Enquiry
Action/s within 3 – 6 months
Senior managers to lead on management
25 Extreme
Immediate Commissioner Appreciative Enquiry.
Immediate action to remove/reduce risks. Action to be taken
on recommendations / further controls within 8 weeks. Action
/ treatment plan required.
Director to lead on the management. Escalate to Audit and Governance Committee
4 21 February 2018
Risk No
Risk Description Lead Person
Initial Risk Current Risk Key Controls Key Assurances (Internal and external)
Gaps in Control and Assurance
Actions required Last review date
C L Rating (CxL)
C L Rating (CxL)
6 Confidence in eMBED to provide level of expertise and resource to support practices. Risk added 13.05.15 Risk reduced to 9 Risk increased to 15 May 2017 Risk increased 28.06.17 Risk split to capture risks associated with Business as usual and project delivery Aug 2017
SC 5 3 15 5 4 20 Service specifications and SLA in place for all current services. IM&T account management meetings and reports review and monitor standard of service delivered. Weekly con calls around project delivery Service reviews discussed at transition Board IM&T strategy developed by IM&T Group now transferred to PCDG Number of complaints monitored Assurance reports from eMBED on action of
alerts and compliance with standards Practice and CS Business Continuity Plans updated, refresh and CCG holds copies of plans.
Involvement of wider practice membership in developing service specification. Escalate through contract management meetings Meetings with practices arranged as IT workshop so as to make clear roles and responsibilities.
IM&T delivery plan to be agreed. IM&T CCG dashboard to be accepted by eMBED and populated .
Improve communications to practices Assess eMBED resilience and ability to deliver projects Continue to raise issues at CMB Ensure contract variations and project end reports reflect status
Decem
ber
20
17
5 21 February 2018
Risk No
Risk Description Lead Person
Initial Risk Current Risk Key Controls Key Assurances (Internal and external)
Gaps in Control and Assurance
Actions required Last review date
C L Rating (CxL)
C L Rating (CxL)
7
Risk to maintaining a
sustainable workforce with
appropriate skills due to
difficulties in recruiting GPs
and PNs at a time when the
retirement rate will increase
over next 2 years
PG 4 4 16 4 4 16 CCG is member of workforce planning Group and attends Y&H HEE meetings from Jan 2016. LMC acting as a coordinator of output from different groups and committees Practices submitting work force data through Y&H HEE and CCG receives quarterly reports but all practices need to be encouraged to use this portal. Workforce development plan includes multidisciplinary recruitment plan. Complaints and Patient Relations reports PTL schedule of events commenced for 2017-18 with in house coordinator Branded recruitment plan in place
Access reports Patient satisfaction surveys Health watch survey being carried to assess access to primary care Patient Participation Group work and planned engagement events CQC reports Work plan and progress reports provided to PCDG. Retirement plans assessment completed in May 2017 and informs recruitment and retention plan Member of LWAB
Progress report on International GP Recruitment from Programme Board
Develop career paths in Primary care Establish diary of recruitment events over next 12 months and CCG to attend. Identify workforce planning tool
Strategic workforce plan for 2015-2020 against which to measure progress being drafted.
Decem
ber
20
17
6 21 February 2018
Risk No
Risk Description Lead Person
Initial Risk Current Risk Key Controls Key Assurances (Internal and external)
Gaps in Control and Assurance
Actions required Last review date
C L Rating (CxL)
C L Rating (CxL)
8
Following outcome of ETTF bids into cohort 1 & 2 there are risks associated with timeliness of delivery of the projects which may impact on the access to funds after 2019 and on the ability of primary care to expand the services delivered from their practices and maintain facilities to cope with increasing list sizes and services delivered. Risk added June 2016 Risk amended Dec 2016 Risk details amended 28.06.17
RM 3 3 9 3 4 12 Scoring matrix agreed by CCG and subgroup assessed all bids against criteria Threshold for submission agreed Strategic Feasibility study carried out to assess CCG area requirements alongside individual bids NHS PS engaged to work up detailed business case for Scarborough South Schedule of meetings with partners and landlords to progress projects Updates provided to PCCC
F&C committee over see submissions and impact on revenue assessed.
Timeline chart required for each project against which to monitor delivery
Consider measuring utilisation of premises to identify under utilisation. Explore opportunities to retain clinical functions in practices with back office functions relocated/centralised. Review impact of revenue following DV valuation
Decem
ber
20
17
7 21 February 2018
Risk No
Risk Description Lead Person
Initial Risk Current Risk Key Controls Key Assurances (Internal and external)
Gaps in Control and Assurance
Actions required Last review date
C L Rating (CxL)
C L Rating (CxL)
9 Risk of capacity of GPs not being able to respond to patient demand alongside need to provide mentoring to trainees, students and Advanced Nurse Practitioners Risk increased to 12 May 2017
3 3 9 4 3 12 Patient satisfaction survey annual report Complaint reports Ability to recruit trainees Member of Y&H HEE Member of LWAB
Number of training practices and mentors in practices to support students
Combined assessment framework for ACP
Develop a workforce recruitment and retention plan by Oct 2017
Decem
ber
20
17
8 21 February 2018
10
Risk associated with the change in funding formulae which means practices need to contribute 66% of funding and that all practices may not be able to raise this level of funding Note: Three funding streams required
- NHSE capital - Practice contribution - Revenue costs- CCG
RM 3 3 9 3 4 12 Strategic Feasibility study carried out to assess CCG area requirements alongside individual bids NHS PS engaged to work up detailed business case for Scarborough South Schedule of meetings with partners and landlords to progress projects Updates provided to PCCC
F&C committee over see submissions and impact on revenue assessed.
Timeline chart required for each project against which to monitor delivery
Review impact of revenue following DV valuation Work with practices and architects to ensure cost efficient design and delivery of projects
Octo
ber
20
17
9 21 February 2018
11
Inability to deliver General Practice Forward View due to lack of management resources to drive forward plans.
SB 4 3 12 4 3 12 Primary care strategy approved GPFV delivery plan approved and updated quarterly Progress reported to PCCC Updates provided to Business Committee, Governing Body and CoCR RAG rated reports to NHSE and LMC
GPFV STP monthly meetings
Resource allocation to delivery plan not yet approved Work plan not approved
Resource allocation to delivery plan to be completed Primary care work plan , including GPFV actions, QIPP projects and contract changes to be documented and signed off by Business Committee and PCCC GPFV STP meeting minutes to be taken to PCDG/PCCC
Octo
ber
20
17
10 21 February 2018
12
Inability to procure extended access to primary care services as set out in NHSE General Practice Forward View and Planning Guidance
SB 4 4 16 4 4 16 Risk to delivery discussed at PCDG and PCCC Resources agreed as interim solution and work commenced and service specification
Lack of delivery plan
Awaiting NHSE guidance on procurement routes
Develop engagement plan with patients and stakeholders to inform service specification. Draft service specification being progressed Combined work with VoYCCG about Ryedale solution. Establish governance for procurement committee.
Octo
ber
20
17
11 21 February 2018
13 Ability of eMBED to deliver key IM&T projects within timelines set by NHSE or as required by capital improvement plans Risk added August 2017
5 3 15 5 4 20 Monthly CMB meetings SLA in place Monthly service review meetings Draft dashboard in place from June 2017
Project end reports Contract variation requests Robust assurance reports from eMBED
Customer satisfaction reports
Raise at Contract Management meetings Request agreed timeline and project management framework from eMBED Monitor project development and delivery closely through weekly calls Review CCG expertise and capacity on delivery of LDR and associated IM&T projects
Octo
ber
20
17
12 21 February 2018
14 Ability of SRCCG to provide appropriate level of resource( skills and capacity) to support the GP International Recruitment project across the HCV STP Risk added August 2017
Governing Body lead GP identified Minimal local Project Management ( one day/week) secured NHSE STP clinical advisor included in steering group.
NHSE and HEE requirements Y&H Responsible Officer included in discussions.
Formal steering group to be established across HCV STP
Discuss appointment of STP project manager as per funding bid at meeting in October 2017 Agree funding for local PM with NHSE and steering group Establish local steering group Progress reports to be established and presented to PCCC
Octo
ber
20
17
Definitions
Initial Risk = risk without controls.
Current risk = risk with controls or controls which have yet to be put in place
13 21 February 2018
Risk Scoring Matrix Methodology Table 1 Consequence score (C) Choose the most appropriate domain for the identified risk from the left hand side of the table. Then work along the columns in same row to assess the severity of the risk on the scale of 1 to 5 to determine the consequence score, which is the number given at the top of the column.
Consequence score (severity levels) and examples of descriptors
1 2 3 4 5
Domains Negligible Minor Moderate Major Extreme
Patient and staff safety
Minimal injury requiring no / minimal intervention or
treatment.
No time off work
Minor injury or illness, requiring minor intervention
Requiring time off work for
>3 days
Moderate injury requiring professional intervention
Requiring time off work for 4-14 days. RIDDOR reportable
incident
An event which impacts on a small number of patients
Major injury leading to long-term incapacity / disability
Requiring time off work for
>14 days
Mismanagement of patient care with long-term effects
Incident leading to death
Multiple permanent injuries or irreversible health effects
An event which impacts on a
large number of patients
14 21 February 2018
Consequence score (severity levels) and examples of descriptors
1 2 3 4 5
Domains Negligible Minor Moderate Major Extreme
Quality
Peripheral element of treatment or service
suboptimal
Informal complaint/ inquiry
Overall treatment or service suboptimal
Formal complaint
Local resolution
Single failure to meet internal
standards
Minor implications for patient safety if unresolved
Reduced performance rating
if unresolved
Treatment or service has significantly reduced
effectiveness
Local resolution (with potential to go to
independent review)
Repeated failure to meet internal standards
Major patient safety
implications if findings are not acted on
Non-compliance with national standards with
significant risk to patients if unresolved
Multiple complaints / independent review
Low performance rating
Critical report
Unacceptable level or quality of treatment / service
Gross failure of patient
safety if findings not acted on
Inquest / ombudsman inquiry
Gross failure to meet national standards
Human Resources / Organisational Development
Short-term low staffing level that temporarily reduces service quality (< 1 day)
Low staffing level that reduces the service quality
Late delivery of key objective/ service due to lack
of staff
Unsafe staffing level or competence (>1 day)
Low staff morale
Poor staff attendance for mandatory/key training
Uncertain delivery of key objective/service due to lack
of staff
Unsafe staffing level or competence (>5 days)
Loss of key staff
Very low staff morale
No staff attending
mandatory/ key training
Non-delivery of key objective/service due to lack
of staff
Ongoing unsafe staffing levels or competence
Loss of several key staff
No staff attending mandatory
training /key training on an ongoing basis
15 21 February 2018
Consequence score (severity levels) and examples of descriptors
1 2 3 4 5
Domains Negligible Minor Moderate Major Extreme
Statutory duty / inspections
No or minimal impact or breech of guidance/ statutory
duty
Breech of statutory legislation
Reduced performance rating
if unresolved
Single breech in statutory duty
Challenging external recommendations / improvement notice
Enforcement action
Multiple breeches in statutory duty
Improvement notices
Low performance rating
Critical report
Multiple breeches in statutory duty
Prosecution
Complete systems change
required
Zero performance rating
Severely critical report
Adverse publicity / Reputation
Rumours
Potential for public concern
Local media coverage – short-term reduction in public
confidence
Elements of public expectation not being met
Local media coverage – long-term reduction in public
confidence
National media coverage with <3 days service well below reasonable public
expectation
National media coverage with >3 days service well below reasonable public
expectation. MP concerned (questions in the House)
Total loss of public
confidence
Business Objectives Insignificant cost increase /
schedule slippage
<5 per cent over project budget
Schedule slippage
5–10 per cent over project budget
Schedule slippage
Non-compliance with national 10–25 per cent over
project budget
Schedule slippage
Key objectives not met
Incident leading >25 per cent over project budget
Schedule slippage
Key objectives not met
16 21 February 2018
Consequence score (severity levels) and examples of descriptors
1 2 3 4 5
Domains Negligible Minor Moderate Major Extreme
Finance Small loss Risk of claim
remote
Loss of 0.1–0.25 per cent of budget
Claim less than £10,000
Loss of 0.25–0.5 per cent of budget
Claim(s) between £10,000
and £100,000
Uncertain delivery of key objective/Loss of 0.5–1.0 per
cent of budget
Claim(s) between £100,000 and £1 million
Purchasers failing to pay on
time
Non-delivery of key objective/ Loss of >1 per
cent of budget
Failure to meet specification/ slippage
Loss of contract / payment
by results
Claim(s) >£1 million
Service / business interruption
Impact on environment
Loss/interruption of >1 hour
Minimal or no impact on the environment
Loss/interruption of >8 hours
Minor impact on environment
Loss/interruption of >1 day
Moderate impact on environment
Loss/interruption of >1 week
Major impact on environment
Permanent loss of service or facility
Extreme impact on
environment
17 21 February 2018
Table 2 Likelihood score (L) What is the likelihood of the consequence occurring? The frequency-based score is appropriate in most circumstances and is easier to identify. It should be used whenever it is possible to identify a frequency.
Likelihood score
1 2 3 4 5
Descriptor Rare Unlikely Possible Likely Almost certain
Frequency How often might it / does it
happen
This will probably never happen/recur
Do not expect it to happen/recur but it is possible it may do so
Might happen or recur occasionally
Will probably happen/recur but it is not a persisting issue
Will undoubtedly happen / recur, possibly frequently
Probability Percentage likelihood of
occurrence 0-5% 6-20% 21-50% 51-80% 81-100%
18 21 February 2018
Table 3 Risk scoring = consequence x likelihood (C x L) Calculate the risk score by multiplying the consequence score by the likelihood score.
Risk Matrix
Likelihood
(1) Rare
(2) Unlikely
(3) Possible
(4) Likely
(5) Almost certain
Consequence (1) Negligible
1 2 3 4 5
(2) Minor
2 4 6 8 10
(3) Moderate
3 6 9 12 15
(4) Major
4 8 12 16 20
(5) Extreme
5 10 15 20 25
1-5 Low
6-11 Medium
12-15 High
16-20 Very High
25 Extreme
The risk tolerance/appetite under which risks can be tolerated is a score of 11 or below where the assessment has been undertaken following the implementation of controls and assurances.
19 21 February 2018
Committee roles & responsibilities – January 2014
Senior Management Team Business Quality & Performance Finance & Contracting Communication &
Engagement
Business continuity
Policy management
Information governance
Freedom of Information
Corporate records keeping
Access to Health Records
SIRO
Caldicott Guardian
Employment rights
Training provision for persons
working in – lead for liaison with
Deanery & WFP
Equality & Human Rights
Whistle blowing
Health & Safety
Human Resources
Co-operation with Prison Service
Vehicles for Disabled (section 5)
Sustainability
Research Governance
Security
Crime & Disorder Act – work with
Police on strategy for drugs &
alcohol
NHS Outcomes Framework and
delivery against domains
Compliance with Children’s Acts
Compliance with Mental Health Act
Delivery of operational
plans (including QIPP ,
and OD, plans)
Service redesign and
project delivery (CCG
objectives and priorities)
Winter planning
National Strategy
Implementation (e.g.
autism, dementia)
NHS 111
Medicines Management
Recommendations to
Governing Body
Emergency Planning
MAJAX
Risk Management
Choice Agenda
End of Life
Autism strategy
Safeguarding
Infection Control
NICE guidance
Serious Incident Reviews
Quality & Patient Safety-
provider reports
Quality of 1⁰ care
(support to NHS CB)
Quality of specialist
commissioning
NHS Outcomes
Framework and delivery
against domains
Continuing Health Care
Complaints ( providers)
IFR process
AQP
Ability to make direct
payments to patients
Power to generate
income
Data Quality – policies /
strategy (inc data group)
Partnership Contracting
Medicines Management
(financial)
Continuing Care Funding
Monitoring delivery of
QIPP initiatives
Monitoring delivery of
financial plan
(commissioning and
management budgets)
Communications &
Engagement
Patient Experience
Media Management
Consultation
Equality & Diversity
Satisfaction surveys (staff)
Complaints (commissioning)