Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout: One CMO’s Perspective

Transcript of Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley...

Page 1: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

Presented By:

Pam Gouldsberry, Contracts Group ChiefCorlee Brown, ACOLinda Rowe, ACOShirley Leonard, ACO

Risk-Based Initiative for Contract Closeout:

One CMO’s Perspective

Page 2: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

2

Agenda

• Background – DCMA VA

• Closeout Overview from DCMA VA Perspective

• T&M Initiative

• Alternative Closeout Approaches– High Risk Contractor

– Anteon Closeout Initiative

Page 3: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

3

Background – DCMA VA

Challenges: Unique Situation

WorkloadStaffingPrioritiesAggressive Goals

Page 4: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

4

From Physical Completion to Closed

Final Incurred Cost Proposal Due

6 Months 4 Months

Final Voucher Due

0-12 Months

Contractor FY Ends

Physical Physical CompletionCompletion

Settlement of Final Rates

Varies

CLOSEDCLOSED

Industry

DCAA

DCMA

DFAS

Services

Process Payment of

Final Voucher

Review/Process Final Voucher

Varies due to circumstances12-24 Months

Audit of Final Incurred Cost Proposal Due

DCAA Actuals8 –12 months

Flexibly Priced Closeout Timeline

DCAA Actuals30 Days

OPRs

Page 5: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

5

Contract Closeout Key Players

ONE FOCUS

Achieving the Goal Together

Indu

stry

Indirect Cost Props Final Inv/Vchrs Pkg

Refund Checks

DFAS

Reconciliation

Final Payment

Additional Funding

Property Disposition

Replacement Funds

Acceptance

Services

Indirect Cost Audits

Final OH Rates

Subcontract Audit

FV Review

DC

AA

DC

MA

Coordinate all Closeout Actions

Page 6: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

6

T&M Initiative

What is it?• Risk-Based Approach

• Utilize fixed labor rates• Accept provisional G&A rate

• Streamlines the Contract Closeout Process• Settlement of Rates not required • Abbreviated Final Voucher • Expedites payment and closeout

60% T&M Contracts

Page 7: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

7

T&M Initiative – Teaming for Success

• Contractor Participation

• DCMA/DCAA Kickoff meeting for initial low risk contractors

• Lack of individual contract audits is an incentive

• Communicate conflicting priorities (canceling funds, etc.)

DCAA

Page 8: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

8

T&M Initiative Process

• Selection of contractors for participation

• Performance of risk assessments

• Getting contractors to participate

• Timely submission of final vouchers

• Sampling of final vouchers

Page 9: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

9

DCAA Reduced audit effort on low risk

contractors

DCMA Reduced reconciliation effort allowing

ACO to focus on active work Prevents funds from canceling Contract closes within FAR mandated

timeframes

Contractor Abbreviated final voucher process

saving time and dollars Submit Final Voucher before Final Rate

Settlement

DCAA Reduced audit effort on low risk

contractors

DCMA Reduced reconciliation effort allowing

ACO to focus on active work Prevents funds from canceling Contract closes within FAR mandated

timeframes

Contractor Abbreviated final voucher process

saving time and dollars Submit Final Voucher before Final Rate

Settlement

Benefits

Integrated Effort - DCMA, DCAA, ContractorsIntegrated Effort - DCMA, DCAA, Contractors

PartneringBusiness

Judgement

Risk

Page 10: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

10

Results!!!

• Contractors approved (low risk) 23/55

• High risk contractors (alternative approach) 4• Contracts closed

3,151

Page 11: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

11

High Risk Alternative Approach

• Background– Contractor Cooperative– Billing System Deficiencies– Significant G&A Costs Questioned in prior

audits– Contractor unable to generate sufficient

volume of final vouchers/monthly basis

Page 12: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

12

Overview of Risk-Based Process

– Identified 341 IDIQ Delivery Orders with rates settled

– DCAA determined increment/decrement factor for each IDIQ contract

– Unbilled amount< $50,000 contractor waived payment at Basic Level

– All credits were refunded to Government

Page 13: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

13

Benefits/Results

• Contractor – Reduced Final Voucher Preparation– Closeout Backlog Decreased

• Government– <60 days over 340 Delivery Orders closed

• Wynne Phase III contracts closed (app. 200)

– Replacement funds not required– Excess funds returned to Services

Page 14: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

14

Anteon Closeout Initiative

• Background– Low Risk Contractor– Multiple Acquisitions– Large Number of Overage Contracts with

Delinquent Final Vouchers

• Challenges– Close Large Number of Contracts (2,000+)– Meet Regulatory Requirements– Satisfy DCAA and DFAS Internal Operational

Requirements

Page 15: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

15

Anteon Closeout Initiative

• Process– MOA Between DCMA and Contractor– Agreement with DCAA and DFAS– Streamlined Submission Format– Accelerated Cumulative Allowable Cost

Worksheet (CACWS) Audit

Page 16: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

16

Anteon Closeout Initiative

• Submission Format– Use Spreadsheet Format (CACWS)– Group Like Vouchers (Credits, Debits, Zeros)– Streamlined Final Documents

• Form SF1034s, Releases, Assignment of Refunds, Rebates, and Credits)

– Deviation for Form DD 1597 (Closeout Worksheet)

– Concurrent Audit by DCAA

Page 17: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

17

Anteon Closeout Initiative

• Results– Final Vouchers with Documentation

• 2,056 Contracts• Provided by Contractor in 30 Days

– DCMA Reviewed 1,702 Final Vouchers– Currently in Payment Process

• 734 Contracts

– Closed 968 Contracts in 3 Months

Page 18: Presented By: Pam Gouldsberry, Contracts Group Chief Corlee Brown, ACO Linda Rowe, ACO Shirley Leonard, ACO Risk-Based Initiative for Contract Closeout:

18

Questions