Presented at Great Designs in Steel - Autosteel/media/Files/Autosteel/Great Designs in Steel... ·...
-
Upload
vuonghuong -
Category
Documents
-
view
215 -
download
0
Transcript of Presented at Great Designs in Steel - Autosteel/media/Files/Autosteel/Great Designs in Steel... ·...
The Real Cost of Laser Welding
Presented at Great Designs in Steel
Stan Ream, Laser Technology Leader
Jim Tighe, CFO
EWI
Outline • How do you measure cost?
• How does your boss measure cost?
• The “ABCs” of laser welding costs.
• Blank welding study cases
• How important is the laser in the laser system?
• Other factors that influence welding cost.
How to you measure cost? - or how are you graded? -
• Cost of the laser
• Cost of the motion system
• Cost of associated automation
• Operating consumables
• Number of staff on the line
• How do Controllers look at cost? – Sunk Cost
• “Can’t we continue using what we have?”
– Cash Outlay • “What’s this going to cost?”
– ROI / Break-Even • “When are we going to be ahead?”
• We need to speak a common language to come to the right answer – The “ABCs” (activity based costing) – Meaningful discussions on making investments
Process Elements
Operational Cost Summary
Cost Elements
Accountant Speak
Production Speak
Process Elements Operational
Cost Summary Cost
Elements
Direct Variable
Consumables
Capital
Equipment
Other Costs
Tooling
Payroll
Employees
Overhead
Sunk Costs
Acc
ou
nta
nt
Spea
k
Pro
du
ctio
n S
pea
k
Process Time, Load/Unload Time, Maintenance Cycles, Useful Life
Allocated Floor Space
Custom Fixturing, Useful Life
Air, Gas, Electricity…
Staffing Quantity and Level, Shift Routines
Co
st /
Pro
du
ctiv
ity
“Fully Burdened Cost per
Part”
“Cost of a Part”
Much to Consider - don’t even try to read this now -
Welding Process Cost Calculator: User Input - Variable with Process
User Input - Infrequent
Calculated Output - Metrics
Calculated Output - Cost
Need to "fix" to become part of the model
Cost Elements Input Units Operation Elements Operational Cost Summary Output Units
Compressed Air -$ $/100cf standby compressed air usage - cfh
process compressed air usage - cfh
Helium Gas (laser) 34.36$ $/100cf laser helium gas usage 1.70 cfh Consumable Cost (laser and process gas) 41.84 $/hr
helium plasma assist gas usage (60 cfh x 2) 120.00 cfh
Nitrogen Gas (laser) 3.95$ $/100cf laser nitrogen gas usage 0.35 cfh
CO2 Gas (laser) 3.90$ $/100cf laser CO2 usage 0.07 cfh
Argon Shielding Gas 6.54$ $/100cf welding trailing shield gas usage - cfh
Other Gas -$ $/100cf
Wire -$ $/lb. filler wire diameter - inch
filler wire speed - inch/min
Electric Power 0.0600$ $/(kw-hr) Runtime electric power 120 kw Runtime Electric Power 6.34$
Standby electric power 50 kw Standby Electric Power 0.36$
Total Electric Cost 6.70$ $/hr
PROCESS EQUIPMENT - 6kW CO2 Laser 400,000$ $ process equipment space 5,000 ft.2 Avg. PROCESS EQUIP. - Depreciation 7.81 $/hr
PROCESS EQUIPMENT - Salvage Value % 10 % load time 0 sec Avg. FIXTURING EQUIP. - Depreciation 0.00 $/hr
Avg. PART HANDLING EQUIP. - Depreciation 68.35 $/hr
FIXTURING EQUIP. - ___ -$ $ Travel speed 260 in/min 6.5 m/min Average Total Equipment Depreciation 76.16 $/hr
FIXTURING EQUIP. - Salvage Value % 10 % Weld length 60.00 inch/weld 1.5 m Average Interest on Equipment 12.58 $/hr
number of welds per part 1 welds/part Average Depreciation & Interest (8 years) 88.74 $/hr
PART HANDLING EQUIP. - 2 Station Clamp Line 3,500,000$ $ indexing time per part - sec/part Asset Value at End of 8 Years $390,440
PART HANDLING EQUIP. - Salvage Value % 10 % unload time - sec
1st YR PROCESS EQUIP. - Depreciation 17.36 $/hr
1st YR FIXTURING EQUIP. - Depreciation 0.00 $/hr
1st YR PART HANDLING EQUIP. - Depreciation 151.91 $/hr
Total Equipment Depreciation 169.27 $/hr
First Year Equipment Interest 25.39 $/hr
First Year Depreciation & Interest 194.66 $/hr
Cycle Time 13.85 seconds/part
Output Coupler 2,000$ $/ea. Output Coupler life 1,000 hours
Cooling Water Filters 1,000$ $/ea. Cooling Water Filters life 1,000 hours
Blower 5,000$ $/ea. Blower life 4.00 yr
Focus Optics, 2 sets 6,000$ $/set Focusing Optics Life 1,000 hours/set Long Term Parts Costs 15.52 $/hr
Beam Delivery Optics 10,000$ $/set Beam Delivery Optics Life 10,000 hours/set
Beam Trap 1,000$ $/ea. Beam Trap 500 hours
Clamp feet 1,000$ $/ea. Clamp feet 3,000 hours
Belts 1,000$ $/ea. Belts 1.50 yr
Laser RF Tube 22,000$ $/item RF tube life 1.60 yr
Laser Vacuum Pump 2,500$ $/item Vacuum Pump life 2.50 yr
Operator Burdened Wage ( req'd) 20.75$ $/hr Operator Loading 2 operators/line
Handler Burdened Wage 17.70$ $/hr Handler Loading 4 lines/handler
Supervisor Burdened Wage 38.00$ $/hr Supervisor Loading 6 lines/supervisor
Maintenance Burdened Wage 28.00$ $/hr Maintenance Loading 6 lines/maint tech Direct Labor Cost 56.93 $/hr
Tool Maker Burdened Wage (indirect) 34.00$ $/hr Tool Maker Loading (indirect) 12 lines/tool maker
Engineering Support Staff burdened wage (indirect) 60.00$ $/hr Engineering Staff Loading, including QA 6 lines/engr. Indirect Labor 12.83 $/hr
Maintenance Functions
Laser Tuning 2.00 hrs/month
Focus Optics Cleaning 12.00 hrs/month
Beam Path Alignment 6.00 hrs/month
Other Maintenance 16.00 hrs/month
Total scheduled maintenance 36.00 hrs/month
Unscheduled maintenance 16.00 hrs/month
Total Maintenance 52.00 hrs/month Process Utilization 88% % of possible
meals & breaks 0.73 hrs/shift
Plant Space Cost with Utilities 45.00$ $/ft.2/yr facility schedule 3 shifts/day Plant Availability 720 shifts/yr
yearly schedule 240 days/yr Plant Availability 5,760 hours/yr
Cost of Money 5 %/yr Process Availability 5,232 hours/yr
Direct Facility Cost 39.06 $/hr
New
Equ
ipm
ent
O/H
Long
-Ter
m P
arts
Dir
ect V
aria
ble
Pay
roll
Blank Welding Cost Theme - already a very well known laser welding application -
shock absorber A-Pillar
B-Pillar roof reinforcement
lift gate inner
wheel house
side ring
rear door inner
front door inner floor pan front rail
engine rail
wheel house
bumper
The Example Welding System - circa 1995, courtesy TWB -
Base Case System Features
• 2 Machine Operators
• 2 Moving Clamps
• 6kW CO2 Laser
• Mechanical Beam Switch
• Semi-Robotic Loading
• Full Robotic Unloading
• Operator Beam Alignment
Laser Blank Welding Process Notes • Quality and Productivity Are Driven by:
– Edge Preparation
– Fit-up
– Process Alignment
Concavity Mismatch
Ideal
Many Things Can Go Wrong
Mismatch Mismatch
Concavity
Lack of Penetration
Convexity
Lack of Fusion
Steady Trend to Thinner Gauge - greater process precision required -
0.8 mm to 1.9 mm 0.7 mm to 1.2 mm
1996 2013
Cautionary Cost Comments! • Consumable costs used in the following cases
are not absolute or necessarily current.
• Equipment costs are amalgams of past and current information, not highly accurate.
• Welding speeds are conservatively stated.
• Calculated cost comparisons are believed to be directionally accurate but not absolute.
• Please don’t sue us!
Baseline System Cost - for analysis only…not current or actual -
• 6kW CO2 laser: $500,000
– Includes portion of plant-wide chiller system
– Includes beam delivery to both stations
• 2 Station Clamp Line: $3,500,000
– Includes robots
– Includes conveyors
– Includes de-stacking pallets
Baseline System Consumables
• Electricity – Laser – Chiller – Machine
• Gas – Laser: helium, nitrogen, CO2 – Welding process: helium, argon, CO2 – Beam path: nitrogen or clean, dry air
Replacement Components - short and long term…examples only -
• Laser – Output coupler and/or output window (3-6 mo.) – Cooling water filters (3-6 mo.) – Blower (3-6 yr)
• Beam delivery – Final focusing mirror (3-6 mo) – Beam path mirrors (2-5 yr)
• Clamp line – Beam trap (1-3 mo.) – Clamp feet (9-12 mo.) – Belts (1-2 yr.)
Baseline Optics Maintenance Time - example for analysis only -
• Laser – Resonator tuning (2 hr/mo) – Output coupler/window cleaning (2 hr/mo.)
• Beam path – Mirror cleaning (2 hr/mo.) – Mirror alignment (2 hr/mo.) – Focus mirror cleaning (15 min/day)
The Cost of Floor Space
• Portion of building depreciation
• Lighting
• HVAC
• Maintenance
• Expressed as $/ft2/yr
Cycle Time Elements* - one of two stations @ 6 m/min weld speed- 1. Pick & Place Part A 2. Index Part A Into Fixture 3. Clamp Part A 4. Pick & Place Part B 5. Stage Part B to Part A 6. Clamp Part B 7. Cycle Start 8. Weld Head Move into Position 9. Weld (part length / travel speed) 10. Cycle Stop 11. Unclamp Fixture 12. Switch Beam to Station 2 13. Lift Welded Part & Exit 14. Retract Fixture
Single Station Cycle Time = 36 seconds
Beam-On Percentage = 42% * Example Values Only
• Same parts & operating sequence
• 2 Operators
• No down-time included
Cycle Time Elements* - both stations @ 6 m/min weld speed-
Dual Station Cycle Time = 19 seconds Beam-On Percentage = 79%
* Example Values Only
Some of the Inputs to the Base Cast Cost Elements Input Units Operation Elements
Compressed Air -$ $/100cf standby compressed air usage - cfh
process compressed air usage - cfh
Helium Gas (laser) 34.36$ $/100cf laser helium gas usage 0.80 cfh
helium plasma assist gas flow per station 60.00 cfh
Nitrogen Gas (laser) 3.95$ $/100cf laser nitrogen gas usage 0.20 cfh
CO2 Gas (laser) 3.90$ $/100cf laser CO2 usage 0.04 cfh
Argon Shielding Gas 6.54$ $/100cf welding trailing shield gas usage - cfh
Other Gas -$ $/100cf
Wire -$ $/lb. filler wire diameter - inch
filler wire speed - inch/min
Electric Power 0.0600$ $/(kw-hr) Runtime electric power 120 kw
Standby electric power 50 kw
PROCESS EQUIPMENT - 6kW CO2 Laser 500,000$ $ process equipment space 5,000 ft.2
PROCESS EQUIPMENT - Salvage Value % 10 % Cycle Start gas flow 1 sec
FIXTURING EQUIP. - ___ -$ $ Travel speed 240 in/min 6
FIXTURING EQUIP. - Salvage Value % 10 % Weld length 60.00 inch/weld 1.5 m
number of welds per part 1 welds/part
PART HANDLING EQUIP. - 2 Station Clamp Line 3,500,000$ $ Beam Switch time per part 2 sec/part
PART HANDLING EQUIP. - Salvage Value % 10 % unload time 0.5 sec
Beam-on Time Per Part 15.0 sec
New
Eq
uip
men
tD
irect
Vari
ab
le
More Inputs to the Base Case Output Coupler 2,000$ $/ea. Output Coupler life 1,000 hours
Cooling Water Filters 1,000$ $/ea. Cooling Water Filters life 1,000 hours
Blower 5,000$ $/ea. Blower life 4.00 yr
Focus Optics, 2 sets 6,000$ $/set Focusing Optics Life 1,000 hours/set
Beam Delivery Optics 10,000$ $/set Beam Delivery Optics Life 10,000 hours/set
Beam Trap 1,000$ $/ea. Beam Trap 500 hours
Clamp feet 1,000$ $/ea. Clamp feet 3,000 hours
Belts 1,000$ $/ea. Belts 1.50 yr
Laser RF Tube 22,000$ $/item RF tube life 2.00 yr
Laser Vacuum Pump 2,500$ $/item Vacuum Pump life 2.50 yr
Operator Burdened Wage ( req'd) 20.75$ $/hr Operator Loading 2 operators/line
Handler Burdened Wage 17.70$ $/hr Handler Loading 4 lines/handler
Supervisor Burdened Wage 38.00$ $/hr Supervisor Loading 6 lines/supervisor
Maintenance Burdened Wage 28.00$ $/hr Maintenance Loading 6 lines/maint tech
Tool Maker Burdened Wage (indirect) 34.00$ $/hr Tool Maker Loading (indirect) 12 lines/tool maker
Engineering Support Staff burdened wage (indirect) 60.00$ $/hr Engineering Staff Loading, including QA 6 lines/engr.
Maintenance Functions
Laser Tuning 2.00 hrs/month
Focus Optics Cleaning 12.00 hrs/month
Beam Path Alignment 6.00 hrs/month
Other Maintenance 16.00 hrs/month
Total scheduled maintenance 36.00 hrs/month
Unscheduled maintenance 16.00 hrs/month
Total Maintenance 52.00 hrs/month
meals & breaks 0.73 hrs/shift
Plant Space Cost with Utilities 45.00$ $/ft.2/yr facility schedule 3 shifts/day
yearly schedule 240 days/yr
Cost of Money 5 %/yrO/H
Lo
ng
-Term
Par
tsP
ayro
ll
Base Case Outputs
Operational Cost Summary Output Units
Consumable Cost (laser and process gas) 15.01 $/hr
Runtime Electric Power 6.34$
Standby Electric Power 0.36$
Total Electric Cost 6.70$ $/hr
Avg. PROCESS EQUIP. - Depreciation 9.76 $/hr
Avg. FIXTURING EQUIP. - Depreciation 0.00 $/hr
Clamp Line & Material Handling 68.35 $/hr
Average Total Equipment Depreciation 78.12 $/hr
Average Interest on Equipment 12.90 $/hr
Average Depreciation & Interest (8 years) 91.01 $/hr
Asset Value at End of 8 Years $400,452
1st YR PROCESS EQUIP. - Depreciation 21.70 $/hr
1st YR FIXTURING EQUIP. - Depreciation 0.00 $/hr
1st YR PART HANDLING EQUIP. - Depreciation 151.91 $/hr
Total Equipment Depreciation 173.61 $/hr
First Year Equipment Interest 26.04 $/hr
First Year Depreciation & Interest 199.65 $/hr
Cycle Time 18.50 seconds/part
Total Hourly Cost 236.54$ $/hr
Net Productivity 171 parts/hour
Total Laser Welding Cost per part 1.38$ $/part
Modify the Base Case Elements
• Add Seam Trackers ($100k)
• Increase Welding Speed to 9m/min
• Modify load sequence
• No Other Changes
blank travel plasma light
assist gas nozzle
helium assist gas
focus mirror
flat mirror
welding laser
beam input
focusing beam
fiber optic to detectors
collimator
visible laser
tracking
camera
output to control
Modified Cycle Time Elements* - one of two stations @ 9 m/min weld speed- 1. Pick & Place Part A 2. Index Part A Into Fixture 3. Clamp Part A 4. Pick & Place Part B 5. Stage Part B to Part A 6. Clamp Part B 7. Cycle Start 8. Weld Head Move into Position 9. Weld (part length / travel speed) 10. Cycle Stop 11. Unclamp Fixture 12. Switch Beam to Station 2 13. Lift Welded Part & Exit 14. Retract Fixture
Single Station Cycle Time = 25 seconds
Beam-On Percentage = 40% * Example Values Only
• Same parts on each clamp
• Operators need improved timing
Modified Cycle Time Elements* - both stations @ 9 m/min weld speed-
Dual Station Cycle Time = 12 seconds Beam-On Percentage = 66%
* Example Values Only
Impact of Seam Tracking • 37% Increase in productivity
• 27% Cost Reduction per part
• $1.01 vs $1.38 per part
Total Hourly Cost 237.54$ $/hr
Net Productivity 235 parts/hour
Total Laser Welding Cost per part 1.01$ $/part
Upgrade the Laser • Replace the 6kW CO2 Laser with 8 kW fiber-
delivered laser (disc or fiber laser)
• Eliminate helium gas shielding
• Eliminate beam switch time
• Keep seam tracking
• Increase welding speed to 12 m/min
• No net increase in system cost, i.e. assumes alternate initial design with this laser
Fiber-Delivered Cycle Time Elements* - one of two stations @ 12 m/min weld speed-
1. Pick & Place Part A 2. Index Part A Into Fixture 3. Clamp Part A 4. Pick & Place Part B 5. Stage Part B to Part A 6. Clamp Part B 7. Cycle Start 8. Weld Head Move into Position 9. Weld (part length / travel speed) 10. Cycle Stop 11. Unclamp Fixture 12. Switch Beam to Station 2 13. Lift Welded Part & Exit 14. Retract Fixture
Single Station Cycle Time = 23 seconds
Beam-On Percentage = 33% * Example Values Only
• Clamp functions and manual loading become greater portions of cycle time.
Fiber-delivered, 8kW Laser* - both stations @ 12 m/min weld speed-
Dual Station Cycle Time = 10 seconds Beam-On Percentage = 75%
Impact of Change to 8kW Fiber-Delivered Laser
• 54% Increase in Productivity
• 39% Reduction in Cost/Part
Total Hourly Cost 224.51$ $/hr
Net Productivity 363 parts/hour
Total Laser Welding Cost per part 0.62$ $/part
Summary Conclusions
• Fiber-delivered (1 um) lasers are a better choice for laser blank welding.
• Strong return on welding system performance can be achieved with improved process precision.
• Understanding the true cost and value of production solutions requires detailed analysis.
w w w . a u t o s t e e l . o r g
North American
Light Vehicle Metallic Material Trends
Great Designs in Steel is Sponsored by:
Use your web-enabled device to download the presentations from today’s event
PRESENTATIONS WILL BE AVAILABLE MAY 3