Presentazione standard di PowerPoint · Parallel Lender: AIIB, CDC B Lender: EAB, GdG 11 Strictly...
Transcript of Presentazione standard di PowerPoint · Parallel Lender: AIIB, CDC B Lender: EAB, GdG 11 Strictly...
Activity Sectors
–
–
&
<
« »
–
&
✔ ✔ ✔
✔ ✔
&
–
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
&
✓
✓
&
✓
✓
✓
✓
✓
✓
&
✓
–
–
–
––
USD$ 169/MWh for 20 years from COD
Plant Installation TypologyGround mounted – Fix structure
Overall Capacity23.1 MWp PV
PPA
Projects StatusIn operation
Falcon Ma’an (Jordan, I Round Project)
Enerray is among the shareholders of an SPV that has been awarded a 23.1 MWp PV project under Jordan I round public tender. Theproject reached the financial close in 2015 and the commercial operation date in October 2016. The generated electricity is being sold tothe national grid for a fixed tariff, according to the terms and conditions of the PPA signed between NEPCO and the project company.
▪ Project Sponsor▪ Main contractor for EPC and O&M
services
Sovereign Guarantee
Project Description Financials
Enerray Financing led by IFC (World Bank)
Investment opportunities23.1 MW PV - Jordan – In Operation
Strictly confidential10
Within the II Round of the FiT Programme issued by the Egyptian Government, Enerray is acting as Developer, Sponsor and EPC and O&MContractor for three PV projects for a total capacity to be installed equal to 115 MWp divided in one plant of 65.7 MWp and two of 25MWp each, all located in Benban. Financial close reached in October 2017, construction phase in progress and commercial operation dateexpected in Q1/Q2 2019. All the projects, financed on a non recourse basis by IFC (World Bank), have signed a 25 years PPA with the localgrid operator (EETC – Egyptian Electricity Transmission Company) with a Sovereign Gurantee issued by the Egyptian Ministry of Finance
Investment opportunities115 MW PV (65,7 MWp, 24,9 MWp, 24,9 MWp) - Egypt - Under Construction
▪ Financial Close reached in October 2017
▪ COD (exp.): Q2 2019
USD$ 84/MWh for 25 years from COD
Plant Installation TypologyGround mounted - Tracker system
Overall Capacity65,7 MWp PV24,9 MWp PV24,9 MWp PV
PPA
Projects StatusDevelopment stage
Egypt - FiT Programme: PV Projects
▪ Developer▪ Sponsor▪ Main contractor for EPC and O&M
services
Sovereign GuaranteeProvided by MoF (Ministry of
Finance)
Project Description Financials
Enerray Lead Arranger: IFC (World Bank)
Parallel Lender: AIIB, CDCB Lender: EAB, GdG
Strictly confidential11
Together with a local partner, Enerray is developing a 30 MW PV project in the North of Cameroon on a 20 years BOT basis. The first stages ofpermitting are being completed, the Environmental Impact Study have been performed and the Connection and Grid Impact Study is inprogress. Once fully permitted, the project will be eligible to sign a Power Purchase Agreement with the local grid operator. PPA tariff shall bein a range from 120 €/MWh to 140 €/MWh and the terms of the agreement shall be directly negotiated with the local governmentalauthorities, including a sovereign guarantee
Investment opportunity30 MW PV - Cameroon – Under Development
▪ MOU signed with Government▪ SPV established▪ Land secured▪ Feasibility studies done▪ Environmental Impact Study done▪ Connection and GIS in progress ▪ PPA signature (exp.): Q3/Q4 2018
20 years at 130 €/MWh
Plant Installation TypologyGround mounted – Tracker system
Overall Capacity30 MW PV
PPA
Projects StatusDevelopment stage
Cameroon - PPA Project
▪ Project Co-Developer/Sponsor▪ Main contractor for EPC and O&M
services
Sovereign Guarantee
Project DescriptionMain Financial Targets
(Expected)
Enerray
Project TypeBOOT (20Y)
Income Tax Exemption5 years
Custom Duties Exemption
Strictly confidential
–
/
▪
▪
▪
▪ /
/
▪ /▪
&
––
Head Office
Enerray S.p.a.
Via J. F. Kennedy, 10 - 40069 Zola Predosa (BO) - Italy
P +39 051 6162611
F +39 051 6162640
www.enerray.com
Branch Offices:
AMMAN BANGKOK BUENOS AIRES CASABLANCA DUBAI JEDDAH QUERÉTARO nSÃO PAULO