Westport School Building Project
PRESENTATION TO THE BOS
October 30, 2017
-
From where we started . . .
PCBs detected at WMS
School Committee
voted to close WMS
Funding for
Feasibility Study
approved
Educational Visioning & Program;
Design Options
Developed
7-2011 11-2014 5-2015 6-2016
-
. . . through this year. . .
Feasibility Study
Completed; Preferred
Option Submitted to
MSBA
Community Design
Approved byMSBA
2-2017 3-2017
Model School Option
Evaluated
3-2017
Schematic Design
Developed
4-2017
-
. . . . to where we are now and what’s next
Complete Cost
Estimates & Total Project Budget
Obtain Local
Approval of
Schematic Design
Submit Schematic Design to
MSBA
Obtain MSBA
Approval of Project Scope & Budget
TOWN Approval:
Town Meeting &
Ballot Vote
10-2017 11-2017 11-2017 12-2017 1/2- 2018
-
THE MOST COST EFFECTIVE RESPONSE TO THE LOSS OF THE
WMS BUILDING• We will secure MSBA funding for
approximately half of the eligible costs of the replacement building.
• We will secure MSBA funding for approximately half the cost of removing the old Middle School building and remediating the site.
PresenterPresentation NotesSLIDES FADE IN ON CLICK (5-8, 6-8, 5-12, 6-12, 7-12), Pros and Cons of A1-I
-
THE MOST COST EFFECTIVE RESPONSE TO THE LOSS OF THE
WMS BUILDING• By eliminating the need to continue to use
the existing WHS, we consolidate operating and maintenance costs into one building which will house 60% of WCS students.
• We also avoid costs of rebuilding or renovating WHS building that we would have had to face in the near future.
PresenterPresentation NotesSLIDES FADE IN ON CLICK (5-8, 6-8, 5-12, 6-12, 7-12), Pros and Cons of A1-I
-
EVALUATION MATRIX
-
EVALUATION MATRIX
-
PRELIMINARY DESIGN PRICING TABLE
-
COMPARATIVE 30-YEAR COST ANALYSIS FOR TAXPAYERS
-
$ 4.8M: Abatement & Demolition of Existing MS$ 9.7M: Site Work and Improvements
$ 65.4M: New Building Construction$ 79.9M: Total Construction Cost (“hard”)
$ 17.1M: Project Related Costs (“soft”)
$ 97.0 M: Total Estimated Project Budget*
(*) The Total Estimated Project Budget is based on the 10/23/17 Schematic DesignConstruction Cost Estimate prepared by JLA/PM+C, and estimated project budget costsprepared by Daedalus/CGA.
ESTIMATED PROJECT BUDGET
PresenterPresentation NotesUPDATE WITH NEW FIGURES
-
DETAILED PROJECT COST ESTIMATES
• Feasibility Study/SD: $ 0.7M• Abatement/Demolition: $ 4.8M• Site Work & Improvements: $ 9.7M• Construction (Building): $ 48.6M• Escalation Costs: $ 3.5M• Design & Pricing Contingency: $ 6.3M• General Contractor Costs: $ 7.0M• Project Related Costs: $ 9.4M• FF&E/Technology Purchases: $ 2.5M• Construction/Owner Conting.: $ 4.0M• Est. MSBA Recovery Cost: $ 0.5M• TOTAL ESTIMATED BUDGET: $ 97.0M
-
MAINTENANCE BUDGET OVERVIEW
• WCS Maintenance Budget Overview
School Years Budget Grade/Building Change2011-2012 $319,6662012-2013 $185,7582013-2014 $240,0952014-2015 $223,931 2nd gr. to MAC - 5th gr. to WES2015-2016 $219,747 6th gr. To WES – 7/8th gr. to HS
Projected Maintenance cost for the New School Building $36,450
PresenterPresentation NotesThe Massachusetts School Building Authority (MSBA) expects Districts to spend approximately 10% of its budget on maintenance. Additional incentive points can be awarded if they feel that our buildings have been well maintained. Prior to the discovery of the PCB’s, the Westport Middle School was rated a 3 out of a high ranking of 4, according to the MSBA. Cost per school varies each year, depending on greatest need. For example, this year we have invested more in removing asbestos tiles at the MAC compared to our other schools. Another year we removed the carpet at the high school due to health and safety concerns. We have a district line item that our Head of Maintenance, Mike Duarte, maintains.
-
SCHOOL OPERATING BUDGET
FY18 2017-2018 $17,716,616FY17 2016-2017 $17,145,822FY16 2015-2016 $16,815,053FY15 2014-2015 $16,013,860FY14 2013-2014 $15,873,326
- With proposition 2.5%, we can expect that our budget will increase approximately 2.5% each year.
PresenterPresentation NotesOur staffing is based on the number of students we have and programs offered. Even if our enrollment increased by 5%, we do not feel we would need any additional funds, other than for the normal cost of inflation. We have the right number of staff currently based on the number of students we have and based on the DESE requirements. We will quite possibly reassign some staff. For example, our current Technology teacher may now teach in the Makerspace classroom. Our current courses are being re-written for 21st century learners. When the new school is open, high maintenance costs and modular units will no longer be on the table.
-
WHAT WE GET FOR OUR MONEY
-
THE NEW 5-12 SCHOOL WILL INCLUDE:
• New 187,100 GSF Co-Located Middle-High School serving 860 students
• New regulation size varsity athletic fields• Elevated community indoor walking track• New Diane B. Snyder Tennis Courts and
relocated Memorial Garden • Abatement & demolition of the vacated
WMS• State of the art de-nitrification septic
system which will tie in the WES and the Library
PresenterPresentation NotesFADE IN ON CLICK
-
• New efficient plumbing fixtures for the WES• New well for the site (serving the new
school, the Library, and the WES)• Fire hydrants on site to serve Library and
WES• Improvements to site traffic, access,
egress, and parking• Centralized WCS Maintenance Department• Full Sprinkler System
THE NEW 5-12 SCHOOL WILL INCLUDE:
PresenterPresentation NotesRegulation size field CURRENTLY not regulation sized
-
SITE PLAN
PresenterPresentation NotesTalk about: fields, library, septic, water, bathroom fixtures, de-nitrification, traffic, tennis courts, parking
-
FIRST FLOOR PLAN
-
SECOND FLOOR PLAN
-
TYPICAL CLASSROOM
PresenterPresentation NotesWhat is 21st century learning. Collaboration, group projects, team work. New college teaching and learning approaches. My experiences as teaching has changed.
-
MAKERSPACE
PresenterPresentation NotesDiscuss need for hands on learning. Lack of seats at Diman. Shop class. Tools and machinery.
-
COURTYARD
-
SOUTH FACADE
-
MSBA STATEWIDE COST COMPARISON
PresenterPresentation NotesPLEASE IMPROVE IF POSSIBLE
-
FEASIBILITY STUDY COSTS ALREADY INCURRED
Total Project Budget FSA Budget per BRR Encumbered Billed to Date Balance
OPM Feasibility Study 167,000$ $ 167,000 167,000$ -$ A&E Feasibility Study 455,000$ $ 455,000 441,450$ 13,550$ Environmental & Site 70,000$ $ 70,000 69,654$ 346$
HAZMAT 16,200$ $ 16,200 16,200$ -$ Geotech/GeoEnviro 20,500$ $ 20,500 20,500$ -$
Site Survey 12,300$ $ 12,300 12,300$ -$ Wetlands -$ $ - -$
Traffic Study 21,000$ $ 21,000 20,654$ 346$ Other 8,000$ $ 3,065 480$ 7,520$ FSA Budget Subtotal 700,000$ 695,065$ 678,584$ 21,416$
Amount Submitted to MSBA (PR 1-10) $ 657,626 Amount Reimbursed by MSBA (PR 1-10) $ 291,964
Effective Reimbursement
44.40%
Reimbursement Status (46.79%)
Sheet1
Total Project BudgetFSA Budget per BRREncumberedBilled to DateBalance
OPM Feasibility Study$ 167,000$ 167,000$ 167,000$ - 0
A&E Feasibility Study$ 455,000$ 455,000$ 441,450$ 13,550
Environmental & Site$ 70,000$ 70,000$ 69,654$ 346
HAZMAT$ 16,200$ 16,200$ 16,200$ - 0
Geotech/GeoEnviro$ 20,500$ 20,500$ 20,500$ - 0
Site Survey$ 12,300$ 12,300$ 12,300$ - 0
Wetlands$ - 0$ - 0$ - 0
Traffic Study$ 21,000$ 21,000$ 20,654$ 346
Other$ 8,000$ 3,065$ 480$ 7,520
FSA Budget Subtotal$ 700,000$ 695,065$ 678,584$ 21,416
Reimbursement Status (46.79%)Effective Reimbursement Rate
Amount Submitted to MSBA (PR 1-10)$ 657,62644.40%
Amount Reimbursed by MSBA (PR 1-10)$ 291,964
-
WHAT WILL IT COST ME IN ADDITIONAL TAXES?
*Based on 3.79% interest rate for 25-Year Bond and 3.58% for 30-Year Bond. Data provided by Unibank –Westport’s Financial Advisor. Costs are preliminary and do not include any short-term financing. Interest ratessubject to change based upon market conditions. Tax Rates based on Fiscal 2017 ($3,166,154,960) assessedvaluation and $100,000 home valuation (for computing purposes). Does not include any short-term borrowing.
OPTION $58.3 M BOND / 25 YEAR TERM (Level Debt)PreferredSolution
Middle/High School
$100,000 Property Value $400,000 Property Value (Avg.)Per Year Per Month Per Year Per Month
TOTAL $97.0 M$116 $10 $464 $39MSBA $38.7 M
TOWN $58.3 M
OPTION $58.3 M BOND/ 30 YEAR TERM (Level Debt)PreferredSolution
Middle/High School
$100,000 Property Value $400,000 Property Value (Avg.)Per Year Per Month Per Year Per Month
TOTAL $97.0 M$102 $9 $408 $34MSBA $38.7 M
TOWN $58.3 M
PresenterPresentation NotesUPDATE, explain debt exclusion. Not permanent
-
COST PER STUDENT
• Westport vs. Comparable Towns and State average, based on Enrollment and Socioeconomics.
Schools Enrollment Per Pupil Cost Teacher SalaryLenox 792 $18,526.35 $72,502 Berkshire Hills 1420 $18,486.39 $72,737State Average ---- $15,544.93 $76,442 Millbury 1761 $15,268.32 $75,339 Carver 1685 $14,554.64 $67,255Westport 1583 $14,144.18 $75,172S-Tolland Granville 1705 $13,955.67 $63,846Uxbridge 2052 $13,925.87 $72,813Oxford 1889 $13,437.57 $65,114Bourne 2222 $13,175.42 $76,269 Lunenburg 1709 $12,982.32 $76,147 Narragansett 1531 $12,807.10 $67,147
PresenterPresentation NotesState that these towns are the ones used by DESE to compare with Westport, ANN ADD TALKING POINTS
-
COST PER STUDENT
FY16 Westport $14,144.18
Per Pupil Expenditure should decrease when the new school building is built based on the following factors:
• Modular units cost savings*• Reduction of 1/3 of energy costs resulting in $100K utility
savings per year• Maintenance cost savings• Increase in Chapter 70 Funds (student retention through grade
12)
*Modular Unit cost $70,991(FY18), last year of 3 yr lease, 1 year rollover (FY19), purchase price (FY20) $325,000.
PresenterPresentation NotesANN ADD TALKING POINTS
-
WHY IT WOULD HAVE BEEN A MISTAKE TO BUILD ON THE WHS
SITE
-
TOWN BUILDING VALUES
Building Size Assessed Value
Potential Market Value
Current High School
174,416 sq ft $15,969,500 $6,400,000
Town Hall 7,845 sq ft $ 548,500
Town Hall Annex 8,720 sq ft $ 516,300
Highway Garage 11,040 sq ft $ 434,900
Senior Center 5,124 sq ft $ 372,700
Total Non-High School
32,729 sq ft
PresenterPresentation NotesInsert information form Shana
-
WHY BUILD NOW?
ONE TIME OPPORTUNITY
Almost 50% reimbursement of eligible costs
Climbing interest rates and construction costs
Community use
Increased property values
PresenterPresentation NotesWhy should people w/o children vote for the school?
-
WHAT IF WE VOTE “NO”• Loss of at least $40M of state funding• WCS is removed from the MSBA pipeline• Left with WHS which is 70 years old,
inefficient, and outdated and will need to be replaced within 10 years
• Cost to replace WHS in 10 years will be significantly greater with rising interest rates and construction costs.
• We would have to conduct a new Feasibility Study WITHOUT MSBA funds
• Unlikely to be accepted back into the MSBA pipeline. ALL future project costs at Town expense.
-
WHAT IF WE VOTE NO”• WMS will still be an albatross to Westport• Loss of state funds toward the demolition and
abatement of the WMS (approximately half the cost)
• Overcrowding at WCS will still need a solution• Need to buyout modular classrooms at MAC
for a cost of $325K• Left with recurrent cost of maintaining WMS
at $100K+/year• Loss of students to other high schools• Impact on Westport businesses as families
move or seek education elsewhere
Westport School Building Project From where we started . . . . . . through this year. . .. . . . to where we are now and what’s nextTHE MOST COST EFFECTIVE RESPONSE TO THE LOSS OF THE WMS BUILDINGTHE MOST COST EFFECTIVE RESPONSE TO THE LOSS OF THE WMS BUILDINGEVALUATION MATRIXEVALUATION MATRIXPRELIMINARY DESIGN �PRICING TABLECOMPARATIVE 30-YEAR COST �ANALYSIS FOR TAXPAYERSESTIMATED PROJECT BUDGET DETAILED PROJECT COST ESTIMATESMAINTENANCE BUDGET OVERVIEWSCHOOL OPERATING BUDGETWHAT WE GET FOR OUR MONEYTHE NEW 5-12 SCHOOL WILL INCLUDE:THE NEW 5-12 SCHOOL WILL INCLUDE:SITE PLANFIRST FLOOR PLANSECOND FLOOR PLANTYPICAL CLASSROOMMAKERSPACECOURTYARDSOUTH FACADEMSBA STATEWIDE COST COMPARISONFEASIBILITY STUDY COSTS ALREADY INCURREDWHAT WILL IT COST ME IN ADDITIONAL TAXES?COST PER STUDENTCOST PER STUDENTWHY IT WOULD HAVE BEEN A MISTAKE TO BUILD ON THE WHS SITETOWN BUILDING VALUESWHY BUILD NOW?WHAT IF WE VOTE “NO”WHAT IF WE VOTE NO”