Presentation to Hon. MERC
on-Implementation of Recommendations of
final report on ‘ PARTIAL GRID DISTURBANCE IN MUMBAI
SYSTEM’ Dt. 05th Aug 2011
2
Power System Scenario of Mumbai System
Bilateral Purchase on
MSETCL Network
(914 MW)
Mumbai Generation(2277 MW)
TPC -1777 MWR-Infra-500
MW
Mumbai Demand
(3191 MW)
TPCL+BEST-1566
R-Infra - 1625
Power Scenario in Mumbai Area(Peak demand) as on 2nd June 2011
3
TPC +BEST
Demand 1566
R-Infra Demand
1625
Total Demand
3191
Total Gen 2277
Short fall - 914 TPC
+BEST Demand
1640
R-Infra Demand
1702
Total Demand
3342
Total Gen 2277
Short fall 1065
TPC +BEST
Demand -1752
R-Infra Demand
1819
Total Demand
3571
Total Gen 2277
Short fall1294
TPC+BEST
Demand 2048
R-Infra Demand
2126
Total Demand
4174
Total Gen 2277
Short Fall 1897
TPC +BEST
Demand 1873
R-Infra1944
Total Demand
3817
Total Gen 2277
Short fall
1540
2nd June 11
2013-14
2011-12
2012-13
2014-15
Forecasted Power Scenario of Mumbai
(All figs in MW)
4
In addition to above load growth, identified triggering loads are expected up to 2014-15 as under
Development of commercial complex in Airport area - 80 MW
Rehabilitation slum in Airport area by HDIL - 60 MW
Development of Commercial complex in Godrej Vikroliarea and vertical load development in other area - 200 MW
Development of Kohinur city, Neelkanth gammon, Vidhyvihar containers, Bhandari Estate, Swan Mill and Sahakar Nagar in Kurla area - 125 MW
Total triggering load - 465 MW
5
Above load growth and addition due to triggering loads needs to be considered for planning Mumbai system grid for FY 2014-15.
In addition to above, presently about 230-250 MW load of MSEDCLin Kalyan, Ambarnath, Saksett and Kolsett area is fed through TPCL EHV net work, which is expected to increase to 330 MW by 2014-15.
This clearly indicates that transmission system network forMumbai needs to planned to cater about 5000 MW loads by FY 2014-15.
6
STU planning for Mumbai region upto 2014-15
7
i) Second ckt. stringing of 220 kV Borivali (MSETCL) – Borivali (TPC)
D/c line (TPC) – DEC -11 Status
ii) 220 kV Kalwa – Salsette 3rd Ckt (TPC)( April 13)
iii) LILO of 220 kV Boisar (MSETCL) – Borivali (MSETCL) at
Ghodbunder (R-Infra) – DEC-11 Status
iv) Conversion of existing 220 KV D/C corridor from Kharghar to Boisar
with Multi circuit Towers using High Ampacity twin 525 sq mm AAAC
conductor. Status
v) New 220 kV Kharghar – Borivali - Boisar D/c line with twin 525 sq mm
AAAC conductor on the above M/C towers. Status
Proposed plan to meet the Mumbai Load
8
a) 400 KV Navi Mumbai (PGCIL)-(2010-11).
i. 400 KV Navi Mumbai(PG)-Vapi D/C line.
ii. LILO of 400 KV Pune(PG)-Kalwa(MSETCL) S/C line.
iii. 220 KV Navi Mumbai (PG)-Taloja D/C line
iv. LILO of 220 KV Kandalgaon-Kharghar line.
b) 400 KV Kudus(MSETCL)-(2012-13).
i. LILO on 400 KV Tarapur - Padghe D/C line at Kudus S/S
ii. 400 KV Babhaleshwar-Kudus D/C Quad line.
iii. 220 KV D/C line to 220 KV Wada-II
iv. 220 KV D/C line to 220 KV Bhiwandi-IV (Rajlaxmi) S/S.
c) 400 KV Vikhroli(TPC)-(2013-14).
(In principle clearance from MERC on 02/06/2011)
i. 400 KV Kharghar(MSETCL)-Vikhroli S/C line.
ii. 400 KV Marve(TPC)-Vikhroli D/C line.
iii. 400 KV Navi Mumbai(PG)-Vikhroli S/C line.Continue…
9
d) 400 KV Ambernath (MSETCL)-(2014-15).
i. LILO on 400 KV Padghe - Nagothane D/C line at Ambernath S/S.
e) 400 KV Ghodbunder (R-Infra)- (2014-15).
i. 400 KV Kudus-Ghodbunder D/C line.
ii. 400 KV Boisar(PG)-Ghodbunder D/C line.
f) 400 KV Marve(TPC)-(2014-15).
i. 400 KV Marve-Vikhroli D/C line.
g) +/- 150 KV, 700 MW IGBT HVDC light (R-Infra)
Continue…
11
Proposed STU Plan
PGCIL’ s Lines
MSETCL’s Existing Lines
Newly proposed Lines
Additional strengthening Required for 3x800 MW Dehrand Project by TPCL
• 400 KV Nagothane – Marve / Dharavi (TPCL) D/C Quad Line – About 600 MW Power is expected to be pushed into Mumbai via this line during 2014-15.
12
Benefits of 400 kV Vikhroli , 400 kV
Ghodbunder S/s and
+ 150 kV, 700 MW HVDC Lights
13
SrNo Lines
Existing Network
Case I Case II Case III Case IV Case V
With 400 KV Vikhroli
With 700 MW
Nagothane– Aarey
HVDC Link
With 400 KV Ghod‐bunder
With 400 KV Vikhroliand Ghod‐bunder
With 400 KV Vikhroli, 700 MW
Nagothane –Aarey HVDC Link
and 400 KV Ghodbunder
Flow in MW
1 220 KV Kalwa – Salsette 3 circuits(D/C exist) 322 466 540 490 326 230
2 220 KV Salsette‐ BorivaliD/C (TPC)
234 390 140 62 170 46
3 220 KV Borivali (TPC) –Aarey D/C 436 296 40 302 290 18
4220 KV Borivali (MSETCL)
– Gorai S/C ( R‐Infra 11‐12)
‐ 154 123 67 72 50
5220 KV Chembur – Drive
In D/C ( R‐Infra 12‐13)
‐ 426 200 222 304 170
6220 KV Trombay
(MSETCL) – Chembur D/C( R‐Infra 11‐12)
‐ 370 332 340 298 220
Continue…
SrNo Lines
Existing Network
Case I Case II Case III Case IV Case V
With 400 KV Vikhroli
With 700 MW
Nagothane –Aarey HVDC
Link
With 400 KV Ghod‐bunder
With 400 KV Vikhroliand Ghod‐bunder
With 400 KV Vikhroli, 700 MW
Nagothane –Aarey HVDC Link
and 400 KV Ghodbunder
Flow in MW
7 220 KV Salsette – Airport S/C (TPC 12‐13) ‐ 182 190 193 187 190
8220 KV Trombay (TPC) – Saki S/C (TPC 12‐13)
‐ 180 173 170 175 173
9 220 KV Ghodbundar– Versova S/C 84 69 40 200 178 119
10220 KV Ghodbundar
– Gorai S/C ( R‐Infra 11‐12)
‐ 92 79 254 231 186
11220 KV Ghodbundar
– Dahisar D/C ( R‐Infra 12‐13)
‐ 12 30 398 346 296
12220 KV Dahisar –
Borivali (R‐Infra) D/C( R‐Infra 12‐13)
‐ 64 46 320 272 220
13220 KV Borivali (R‐Infra) – Borivali
(TPC) D/C 442 240 224 304 194 122
14 Import to Mumbai Network 894 1666
(Addl.‐772)1540
(Addl.‐646)1700
(Addl.‐806)2132
(Addl.‐1238)2300
(Addl.‐1406)
Implementation of Recommendations of final
report on Partial Grid Disturbance in Mumbai
16
Implementation of Recommendations
17
SrNo Recommendations Remarks / Present Status
6.1.1
Review of protection setting at all interconnecting point between Tata, RInfra, MSETCL and Transmission and distribution interconnection.Review of existing protection schemes.Relay configuration checks on regular intervals.
Relay setting audit was carried out on all critical lines and equipment to check the relay configuration and settings.Regular relay configuration checks will be carried out along with relay testing.
Reconfiguration of Alert and Trip mode of relays on account of overload
It is confirmed that no over load alarm stage is wired for tripping of line.
Single phase auto reclosing scheme to be implemented for all overhead lines including 220 KV lines in Mumbai.
Existing
Auto reclosing of Hybrid (O/H+U/G) lines.
TPCL to implement A/R after changing breaker mechanism from 3 phase simultaneous opening to single pole opening.
Auto reclosing of Hybrid (O/H+U/G) lines will be explored.
Effect of auto reclosing on Turbine-Generator shaft to be studied
Impact on generator shaft in case of auto reclosurefailure under study by TPCL & R-Infra
Dynamic line ratings Yet to Start . A Pilot project will be explored
Continue…
Implementation of Recommendations
18
Sr no Recommendations Remarks / Present Status
6.1.2
Review of Mumbai Islanding scheme and UFR and df/dt load shedding settings in view of increasing demand
UFR / df/dt relays already in place. Mumbai islanding scheme review will be taken up in WRPC protection committee meet
The under frequency and over frequency settings of generators to be checked to ensure that conservative setting leading to unit tripping does not jeopardize the island
The settings adopted on units are generally in line with the national practice. OEMs recommendations have been considered while selecting UF & OF settings
Pilot project on installation of PMU for availability of synchrophaser data to Control Centers
Proposal will be put up to MERC PMU installation in various stations in Mumbai in FY 13. These PMUs will need to integrate with the proposed scheme of PGCIL for Western region for effective utilization
Continue…
Implementation of Recommendations
19
SrNo Recommendations Remarks / Present Status
6.2.1
Shifting of R-Infra Aarey load to TPCL substations in view of high loading on 220 KV Aarey-Borivli lines.
Loading expected to go down after commissioning of proposed 220kV LILO of Borivli - Boiser line at Ghodbunder R/S.COD-Dec-2011. TPCL to inform availability of 220 KV bays at 220 KV Saki(TPCL) S/S within one week. Bays are available at 220 KV Saki(R-Infra) S/S.
In-feed lines and substation equipments at MSETCL Borivli substation should be upgraded by MSETCL to handle higher loading 220 KV Borivli-Borivli line.
220 KV Borivali(MSETCL)-Borivali(TPC) 2nd
Ckt-Dec-2011.
Enhancing/modifying existing load trimming schemes to avoid tripping of healthy line during contingencies.
Overload trimming schemes & quantum connected for trimming on critical checked for healthiness. Requirement of additional schemes based on loading of other network to be identified.
6.2.2
Up-grading of substation equipments.Study on Bus Split operation
Proposed to operate in bus split mode once line reconfiguration completed at TrombayNew equipment will be procured with higher fault level capability.
Interconnecting 220 KV TPCL Saki with R-Infra Saki
TPCL to Check availability of bays at Saki(TPC) S/S. Bays are available at Saki (R-infra) S/S.
Existing
Implementation of Recommendations
20
Sr No Recommendations Remarks / Present Status
6.2.36.2.2
Augmentation in Mumbai generation explicitly or implicitly
400 KV network connectivity and HVDC to fill up the gap of implicit generation addition
400 KV Vikhroli (TPCL) and Ghodbunder (R-Infra to be taken up immediately
Possibility of additional interconnection/LILO of existing 220 / 400 KV lines.Bringing extra power to Mumbai by any means to cater the load growth of Mumbai
400kV connectivity with Vikhroli R/S –from Navi Mumbai (PG) S/S.
• 400kV Kharghar – Vikhroli • 400kV Boiser – Ghodbunder(R-Infra)• 400 KV Ambernath• 400 KV Marve
• Mumbai Plan
Implementation of Recommendations
21
SrNo
Action Suggested Action taken
1 Current Carrying capacity of all the 220kV Transmission lines in Mumbai
need to be calculated and made available to the
system operators for ready reference.
Thermal limit of each line will be calculated and sent to SLDC.
Implementation of Recommendations by MSETCL
22
Sr No Action suggested Action taken
1 Strengthening of associated infeed lines and substation equipment at 220 KV Borivali S/S
1)Single 0.4 ACSR conductor is being replaced by twin 525 sq mm AAAC conductor for 220 KV Kalwa – Borivali & 220 KV Boisar – Borivali lines. Work is already taken up and expected to be completed by June-122) The existing 2x125 MVA, 220/100 KV have been replaced by 2x200 MVA 220/100 KV ICT’s at Borivali S/S.3) The existing old control and relay panels have been replaced by new C&R panels with fully numerical protective relays in order to ensure correct and reliable protection.
2 Split bus arrangement at 220 KV Kalwa S/S
At present all the three 400/220 KV ICT’s are connected to 220 KV side of
400/220 KV S/S. In order to reduce the fault level at 220 KV S/S , a proposal for connecting 220 KV side of 400/220 KV ICT 1 at old 220/100 KV Kalwa S/S is
prepared and is under process.
3 System studies of bus splitting arrangement
Short Circuit studies for Maharashtra N/W for the period 2009-10 to 2013-14 have already been carried out with the
help of M/s PRDC in July 2010
Present status of MERC Approved schemes of MSETCL
23
Present status of MERC approved MSETCL schemes
SrNo Schemes Approved
cost in Cr Commissioning Date as per DPR
Date of Approval byCommissio
n
Scheme details Status of Project
Expected Date of commissioning
1
Development & Commissioning of
Balancing and Settlement Mechanism Software for
MSLDC
1.78 December, 2008
20-03-2007( approval
no.227 dated
3.12.2008)
Development of BSM software for
implementation of ABT in Maharashtra.
Software development is completed
First bill will be generated from 1st
August 2011.
2
Augmentation of Transformer Capacities in various EHV
Substations in thearea of
Transmission O&Mcircle Kalwa
49.04 March, 2012
23-05-07 ( approval
no.198 dated
08.01.10)
Installation of additional 4x167 MVA, 400/220/33
kV ICTs at 400 kV Kharghar Substations
Tender to be floated
(Considering the development of load priority was given
to Kalwa and Padghe S/S.)
Expected Date-March-2013
24Continue…
Present status of MERC approved MSETCL schemes
SrNo
Schemes Approvedcost in Cr
Commissioning Date as per DPR
Date of Approval byCommissio
n
Scheme Details Status of
ProjectExpected Date of
commissioning
3 Strengthening of
Transmission System for
Mumbai
161.21 March, 2013 31-05-2007( approval
no.421 dated
18.05.11)
1) Construction of LILO on
220 KV Kharghar - Kalwa at Nerul S/S
2)Construction of LILO on 220 KV Kharghar - Kalwa at
220 kv Tiffil3)Construction of 220 KV M/C line on narrow base
M/C towers from LILO point near Nerul to Trombay s/s 4) Construction of LILO on
220 kv Kalwa - Borivali M/C line at 220 KV Mulund s/s 5)Construction of LILO on
220 KV Borivali - Boisar M/C line at 220 KV Tarapur
6)Construction of LILO on 220 KV Kharghar - Kalwa
M/C line at 220 KV Siemens
7)Construction of LILO on 220 KV Mulund - Borivali line
at 220 KV Bhandup GIS
The work of Kharghar-
Kalwa-Borivali–Boisar 220
KV M/C line is under
progress.Forest
clearance is awaited on
completion of this line
The proposed link line work will be taken
up.
Work completed
March -2013
Sept-2011
25Continue…
Present status of MERC approved MSETCL schemes
SrNo Schemes Approved
cost in Cr Commissioning
Date as per DPR
Date of Approval
by Commissio
n
Scheme Details Status of ProjectExpected Date
of commissioning
4 Augmentation and
Replacement OfICT and
transformers in Kalwa S/S
61.18 March, 2011 17-04-08( approval no.2713 dated
1.12.09)
Installation of addl. 4 x 167 MVA,
400/220/33 kV ICT and Replacement of 3 x 200
MVA, 400/220/33 kV ICT by
3 x 167 MVA, 400/220/33 kV ICT at
400 kV Kalwa Substation
Completed 3 x 167 MVA 400/220/33kV
ICT commissioned on 03.11.10.
One spare ICT 1 X 167 MVA commissioned on 31.12.10.Replaced ICT commissioned on 30.11.10
5 Establishment of 220kV
Indoor GIS Substation at
Bhandup, Mumbai.
93.85 March, 2009 03-12-08approvalno.1120
dated 24.05.07
1. LILO on220kV
Mulund-Borivali feeder-II at Bhandup S/S
2. 4x50 MVA, 220/22kV T/fs with 22KV indoor
switchgear.
1.Tower-NA, Erection-NA, Stringing-0/2
2.Civil-96%, electrical-90 %
1. Sept-11
2. Sept-11
6 Establishment of
220kV Substation at Knowledge Park, AiroliDist. Thane
54.19 March ,2009 28-08-09approvalno.1415
dated 4.07.07
1) Construction of 220
kV D/C Line on M/C tower
LILO on 220 kV Kalwa – Padghe Line
2) Installation of 2 x 50MVA, 220/22 kV T/Fs
Completed
Completed
Commissioned on 24.03.10
Commissioned on 26.03.10
26Continue…
Present status of MERC approved MSETCL schemes
SrNo Schemes Approved
cost in Cr
CommissioningDate as per
DPR
Date of Approval by Commission
Scheme Details
Status of Project
Expected Date of
commissioning7 Establishment of
220/22 kV Sub-Station in Bhiwandi-
IV,Dist.Thane
54.91 March , 2012 01-12-2009( approval
no.635 08.06.11 )
1. LILO of 220 kV
Kalwa-PadgeD/C Line at Bhiwandi –IV
2. 4×50 MVA ,
220/22 kV transformer
Order placed on
M/S Areva & M/S Jyoti
No- 9764 Dt 29-06-11
Nov-12
8 Augmentation of 400 kV Kharghar S/S with Six other
EHV S/S
184.44 March, 2011 31-12-2009(approval
no.198 dated 8.1.10)
Addition 4x167 MVA, 400/220/33 kV ICTs at
400 kV KhargharS/S
Specified at Sr no.2
(Civil work allotted)
9 Replacement of existing RTUs and commissioning of additional RTUs &
DCs for Load Despatch Centers
at Kalwa and Ambazari
63.29 March ,2009 Approval no.1163
dated 31.5.07
1) 55 Nos of Replacement of existing old
RTUs 2) 10 Nos
Replacement of existing old
DCs
89 RTU-DCCommissind out of 14
e0
Scheme is likely to be
completed by September
2011.
27Continue…
Present status of MERC approved MSETCL schemes
Sr.No Schemes Approved
cost in Cr
Commitioning Date
as per DPR
Date of Approval by Commission
Status of Project
Expected Date of
commissioning
10
Construction of 220 kV M/C Lineson M/C Narrow Base Towers for strengthening of
Transmission System for
Mumbai
566.32 March, 2012
(Approval no.1671 dated
28.08.09)
Erection-49/410, Stringing-11.17/516forest clearance
awaited Dec-2012
28Continue…
Present status of MERC approved MSETCL schemes
SrNo Schemes
Approvedcostin Cr
Commissioning Date as per DPR
Date of Approval by Commission
Remark Status of Project
Expected Date of
commissioning
11
Augmentation of Substations
under LE (Life Extension) scheme for
replacement of old outdated and deteriorated CBs,CTs, PTs, Control
Cables, LAs, Isolators
Batteries and other substation allied materials.
44.51 March, 2013 Approval no.679 dated
14.06.11
Replacement of
various equipmentsof 19 EHV
substationsunder
Washi Zone
Indent placed
with CPA on Dt. 28-
07-11
29Continue…
Present status of MERC approved MSETCL schemes
Sr.No Schemes Approved
cost in Cr
Commiss-ioning
Date as per DPR
Date of Approval by Commission
Scheme details Status of Project
Expected Date of
commissioning
12
Augmentation of Transformer
Capacities in Four EHV Substations in
Kalwa Circle
36.23 March, 2012
Approval no.823 dated
28.06.11
1) Additional 3×50 MVA 220/22 kV Transformer at 220 kV Kolshet & Nerul
S/S 2) Replacement of 1x125 MVA ICT by 1x200 MVA, 220/100 kV ICT at 220
kV Padghe S/S 3)Replacement of 1x20
MVA Transformer by 1x50 MVA, 100/22 kV
Transformer at 100 kV Washi S/S
Kolshet S/S –tender to be
floatedNerul S/S –
Work in progress . Old
T/F being used.Foundations
ready
Dec 11
13
Installation of additional
Transformer at 220 kV Bhiwandi-II (Kamba) S/S, District- Thane
10.87 March, 2012
Approval no.1517 dated
15.11.10
i) Additional 1x50 MVA, 220/22 kV Transformer. ii) 22 kV GIS bays – 15 Nos work in progress by
M/s Siemens
Space not available . 100 KV O/H line to be shifted by cable. 220 Kv line crossing
involved. Proposal under preparation 30
Present status of MERC Approved schemes of TPCL & R-Infra
31
TPCL
R‐Infra
Conclusion:‐1) 400 KV Navi Mumbai (PG) S/S is expected in Nov 2011 . Hence TPCL
should immediately take up the work of 400 KV Navi Mumbai(PG) –Vikhroli S/C Quad line along with 400 KV Vikhroli S/S.
2) R‐infra to take up the work of 400 KV Ghodbunder S/S and associated lines.
3) Inter connection of 220 KV Saki(R‐Infra) & 220 KV Trombay (TPCL) .4) Inter connection of 220 KV Saki(R‐Infra) & 220 KV Saki (TPCL) .5) Shifting of R‐Infra’s Aarey load to TPCL’s Saki S/S6) 220 KV Borivali(MSETCL)‐Borivali(TPC) 2nd Ckt (TPC Dec 11)7) Conversion of existing 220 KV corridor from Kharghar to Boisar with
High Ampacity conductor and strengthening of this corridor (MSETCL)
8) LILO of existing 220 KV Boisar(MSETCL)‐Borivali (MSETCL) at 220 KV Ghodbunder S/S (R‐Infra) 10 KM (Dec‐11)
9) Commissioning of 220 KV Kalwa – Salsette 3rd Ckt
32