PRESENTATION TO 5TH DISTRIBUTION UTILITY FORUM (DUF)...
Transcript of PRESENTATION TO 5TH DISTRIBUTION UTILITY FORUM (DUF)...
MSEDCL OVERVIEW
PRESENTATION TO 5TH DISTRIBUTION UTILITY
FORUM (DUF) MEETING
2
MSEDCL AT A GLANCE (MARCH 2019)
Particulars Nos.
Nos. of Consumers 2.66 Crs
Area Covered 3.08 Lakh Sq.KM
Towns 457
Villages 41,095
Zones 16
Circle 45
Divisions 142
Sub-Divisions 633
Section Offices 3227
Employees strength 65,146
Annual Sales 1,09,531 Mus
Annual Revenue from Sale of Power
~ 72,227Cr.
HO
Regional Office
Zone
Circle
Division
Sub-Division
Section
3
MSEDCL INFRASTRUCTURE
Particulars Unit FY 18-19
Sub-Stations Nos. 3,679
HT Lines Ckt-kM 3,78,503
DTCs Nos. 6,10,447
LT Lines Ckt-kM 6,71,482
Sales (incl Franchisee) MU 1,09,531
No. of Ag Connections Nos. 42,20,682
Total No. of Consumers Nos. 2.66 Crs
4
CONSUMER AND REVENUE MIX (FY 18-19)
Provisional As on March
19
Residential, 74%
Commercial, 7%
Industrial, 1%
Agriculture, 16%
Others, 1%
Consumers (Approx 2.66 Cr.)
Residential, 13,587 , 19%
Commercial, 9,033 , 12%
Industrial, 30,202 , 42%
Agriculture, 12,419 , 17%
Others, 6,986 , 10%
Revenue from Sale of power (Rs.72,227 Crs)
Residential, 21065,
19%
Commercial, 7679,
7%
Industrial, 40164,
37%
Agriculture, 34109,
31%
Others, 6514, 6%
Sales (1,09,531 Mus)
5
BOOK PROFIT / LOSS (RS. CRS)
(303) (134)
117
(902) (1,085)
(1,505)
(808) (871)
(280) (366)
(5,336)
785 492 450
(6,000)
(5,000)
(4,000)
(3,000)
(2,000)
(1,000)
-
1,000
2,000
06-07 06-07 07-08 08-09 09-10 10-11 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19
(Prov.)
Profit/(Loss) after Tax
Profit/(Loss) after Tax
*
*Loss in FY 2015-16 is increased to Rs.5336 Crs which is mainly due to booking of delay payment charges to Genco
& Transco in FY 2015-16. (Rs.3886 Crs)
6
STATUS AND FINANCIAL IMPACT OF OPEN ACCESS
1255
1698 1880
1344 1227
4535
6378
7995
5009 4843
2060
3200
3741
2740 2622
328
374
413
208 183
0
50
100
150
200
250
300
350
400
450
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
2014-15 2015-16 2016-17 2017-18 2018-19
MW Mus Revenue Loss in Crs. No. of consumers
7
KEY ISSUES
Frequent shifting of Open Access Consumers - Between DISCOM and other sources of
power and USO on DISCOM resulting in stranded capacity.
Determination of Cross Subsidy Surcharge - CSS has been capped to +/- 20% of ABR
Tariff design and rationalization
Determination of Additional Surcharge
Determination of Stand-By charges
Group Captive Consumers.
- Determination of Captive Status only at end of year.
- 26% equity share capital and 51 % self consumption as per Electricity Rules 2005.
- Change of shareholding pattern during the year to avoid CSS and AS
- No provision for Payment Security like LC or Bank Guarantee.
- Matters pending since long before various legal forums.
Banking of RE power
8
FINANCIAL IMPACT OF SOLAR ROOFTOP
2016-17 2017-18 2018-19
LT 6 37 133
HT 15 34 156
Total 21 71 289
0
50
100
150
200
250
300
350
MW
2016-17 2017-18 2018-19
LT 1 9 15
HT 1 17 49
Total 2 26 64
0
10
20
30
40
50
60
70
Rs. C
rs.
There is exponential rise in Solar Rooftop.
Rise in No. of consumers : 1074 to 14392 and Solar Generation : 4 Mus to 253 Mus.
Solar Capacity in MW Cross Subsidy Impact in Rs. Crs.
9
KEY ISSUES AND GROSS METERING
Net-Metering affect the Cross subsidy structure of tariff
Industrial Consumers opt to install Solar Rooftop as Captive Generation without opting for Net metering
Gross Metering:
Entire injected power is procured at APPC rate or rate discovered through Competitive Bidding.
No loss of sales to DISCOM and Full recovery of Distribution Cost
Cross subsidy maintained within the category of consumers
Gross Metering provides level playing field to all consumers.
MERC Distribution OA Regulations, 1st amendment 2019 : Gross metering for the consumers who opt for Open Access as well as Solar Rooftop.
THANK YOU
11
DISTRIBUTION OPEN ACCESS (DOA) Open Access (OA) has been introduced in Maharashtra since 2005. However, it started gaining
momentum since 2010.
Eligibility: Consumer having contract demand of 1 MW and above.
Special Energy Meter (SEM) is mandated and adjustment of units is in 15 mins time block.
OA consumer can avail Long term (> 7 years), Medium Term (> 3 months but < 5 years) and Short
Term (< 1 month including Day Ahead) Open Access.
OA consumers have to bear Transmission and wheeling charge and loss, Cross subsidy Surcharge
(CSS) and Additional Surcharge (AS introduced since Nov-2016). CSS and AS is not applicable for
captive consumers but ASC is applicable to group captive consumers
OA consumers opted for STOA, as the transmission charges were levied on actual consumption (per
kwh instead of KVA/ month). In case of repeated STOA, MERC has introduced multiplying factor
limited to two times the charge with effect from June 2019.
Banking on ToD basis is allowed for RE generation. Upto June 2019, banking was allowed on yearly
basis. However, from June 2019 onwards banking is on monthly basis.
12
SOLAR ROOFTOP – REGULATION 2015
Eligibility: Capacity less than 1 MW; including Consumer catering to a common load such as a Housing Society
Ownership: Generating System may be owned and/or operated by Consumer, or by a third party leasing such System to the Consumer.
Cumulative Capacity: connected to a particular Distribution Transformer shall not exceed 40% of its rated capacity
Individual Project Capacity: Shall not exceed his CD (in kVA) or Sanctioned load (in kW)
Energy Accounting:
If electricity exported exceeds imported, excess shall be carried forward to the next Billing Period as credited Units of electricity.
If electricity imported exceeds exported, Discom to raise bill for the net electricity consumption after adjusting the credited Units.
Unadjusted net credited Units at the end of each financial year shall be purchased by the Discom at APPC approved by MERC for that year, within first month of the following year
RPO/REC: Electricity consumed by consumer, if such Consumer is not an Obligated Entity, qualify towards meeting the Solar RPO of the DISCOM; such energy not eligible for REC
Eligible Consumer can avail subsidy or incentives if offered by the Central / State Government on capital cost of the Rooftop Solar PV system; MEDA will be the Nodal Agency for such subsidy or incentives
13
FINANCIAL IMPACT OF SOLAR ROOFTOP
2016-17 2017-18 2018-19
LT 2 28 69
HT 2 66 184
Total 4 94 253
0
50
100
150
200
250
300
So
lar G
en
era
tio
n i
n M
us
2016-17 2017-18 2018-19
LT 996 4888 13692
HT 78 254 700
Total 1074 5142 14392
0
2000
4000
6000
8000
10000
12000
14000
16000
Nu
mb
er o
f S
ola
r G
en
era
tors
There is exponential rise in Solar Rooftop.