In the Name of Allah The Beneficent, The Merciful

Page 2: Presentation sayed

Proposed Residential Area at Mukim Datu Mengkebang, Derah Batu Mengkebang, Jajahan Kuala Kari, Negeri

Kelantan Darul Naim

uniselUNIVERSITY SELANGOR

Engineered by:

1. Eng. Feroz Faizmand

2. Eng. Mustafa Jameel

3. Eng. Ahmad Habib

4. Eng. Sayed Asadullah

Page 3: Presentation sayed

Table of Contents Introduction to Project Earthworks Road Works Drainage System Sewage System Water Supply System Environmental and Management Planning

Page 4: Presentation sayed

INTRODUCTION TO THE PROJECT

CHPTER ONE

Page 5: Presentation sayed

The Project

FAMA Consultant is pleased to introduce his new project with the following descriptions.

---Introduction

Address Total Area The Project

Mukim Datu Mengkebang, Derah Batu Mengkebang, Jajahan Kuala Kari, Negeri Kelantan Darul Naim

42,834.00 m2

1. Site Clearance, Cut and Fill, Slopes and Retaining walls2. Drainage System3. Sewage System4. Water Supply System5. Road, Shoulder and Road Curbs

Page 6: Presentation sayed

The Project---Land UsagesType Of Property Quantity Total Area Used m2 Total Area Used %

Double Story Houses 82 12,786.5 29.85Green Area and STP 1 1,459.85 3.41Surau 1 676.91 1.58Sport Complex 1 1,069.68 2.50Water Tank 1 649.49 1.52Roads, Side walks and Drainage

- 24,714.59 57.70

Double Story Shops 8 695.42 1.62Slope and Retaining wall - 781.56 1.82

Page 7: Presentation sayed

EARTH WORKCHPTER TWO

Page 8: Presentation sayed

Earthworks are essential activity need to be done before any construction activity starts.

Creating a levelled or sloppy plat forms. It includes number of activities from site clearing, to

excavating for structures or pipes. Earthwork is one of most risky phases in the construction

of a project because of the multitude of unknowns.

Earth Work---Introduction:

Page 9: Presentation sayed

Earth Work

Page 10: Presentation sayed

Earth Work

Page 11: Presentation sayed

Earth Work

Page 12: Presentation sayed

1)Sites Clearing Clearing of the area Grubbing Stripping Topsoil Backfill of holes Dumping

2)Excavation Excavation in Soil

3)Filling Fill the material Compaction of Filling

Earth Work---Earth Work Stages:

Page 13: Presentation sayed

An earthmoving operations in which material is excavated and removed from one location and is used as a fill material at another location.

Earth Work---Cut and Fill

Page 14: Presentation sayed

Control Line Method Cross Sectional Method Grid method Software

Earth Work---Calculation Method:

Page 15: Presentation sayed

The grid system method involves; dividing the area into small equal squares, purposing a level for the ground and calculating the volume of the soil, (Either cut or Fill).

Earth Work---Grid Method:

Page 16: Presentation sayed

For this project the cut and fill volume after calculation using grid method are:

Cutting volume = 59,498.37 m³ Filling volume = 59,486.83 m3

Earth Work---Calculation Summary:

Page 17: Presentation sayed

Item Work DescriptionMeasured units Quantity Rate (RM) Amount (RM)

1 Cutting

1.1 common excavation in cuttings m^3 59,498.37 3.5 208,244.30

2 Fillm^3 59,486.83 2.5 148,717.08

2.1Suitable material from common excavation to form

embankment (Fill)

3 Retaining Wall

m^2 702 250 175,500.003.1

Supply and installation of wall component including reinforcing 10 dons, anchor blocks, joint fillers cushion pads, fasteners and inclusive of cast in situ wall panels

4 Slop works

m 1,415.25 62 87,745.504.1

Slope stabilization works horizontal drains, supply and install 100 mm horizontal drains with 75 mm diameter

perforated PVC pipe wrapped with non woven Geotextile, 9 m long

5 TOTAL COST 620,206.88

Earth Work---Bill of Quantity:

Page 18: Presentation sayed

The difference in cut and fill will be used to make a hilly area.

Earthwork was designed using grid method. From the calculation data, the amount of cutting volume is 59,498.37 m³ and filling volume 59,486.83 m³.

Earth Work---Conclusion:

Page 19: Presentation sayed

ROAD WORKCHPTER THREE

Page 20: Presentation sayed

Road is an important aspect in development of certain area, it provide linkage between area to another area and hence improve the social growth to an area.

Road Work---Introduction:

Page 21: Presentation sayed

The location of a road and its design are considerably influenced by the topography, physical features, and land use of the area traversed. The topography of the profile of a road can generally be divided into three groups, namely flat, rolling and mountainous.

Road Work---Introduction:

Type Description

Flat terrain

The natural ground cross slopes in a flat terrain are generally below 3%

Rolling terrainThe natural ground cross slopes in a rolling terrain are

generally between 3 – 25%

Mountainous terrain

The natural ground slopes in a mountainous terrain are

generally above 25%

Page 22: Presentation sayed

To propose the vertical and horizontal alignment of the service road.

To design the flexible pavement thickness for each layer of the pavement structure.

To propose safe and convenient route of road user by complying with all technical Requirements.

Road Work---Objectives:

Page 23: Presentation sayed

The critical point of any road pavement design is the commercial vehicle which is considering the main parameter of designing

In our area the volume of commercial vehicle per day is too low, so that’s why we used the JKR new standard for the low volume of commercial vehicle, thus assuming that a the surrounding area will be developed in the early future so we design the main road by assuming a higher amount of commercial vehicle.

Road Work---Road Design:

Page 24: Presentation sayed

Road Work---Road Design: Main Road

Page 25: Presentation sayed

Road Work---Road Design: Sub Road

Page 26: Presentation sayed

Traffic signs or road signs are signs erected at the side of or above roads to provide information to road users.

Road signs in Malaysia are standardized road signs similar to those used in other nations but with certain distinctions.

Malaysian traffic signs use Malay, the official and national language in Malaysia. However, English is also used for important public places as tourist attractions, airports, railway stations and immigration checkpoint. Some places, both of the language, Malay and English are used in the road sign.

Road Work---Road Sign

Page 27: Presentation sayed

Road signage is including the road marking and also signage board. Most of the road signage put at the T-junction. Hump used to control the speed of vehicles to slow down the speed of vehicles.

The proposed road marking and signage plan is shown in the project plan.

Road Work---Road Design:

Page 28: Presentation sayed

Item Work Descriptionmeasuresd

unitsQuantity Rate (RM)

Amount (RM)

1 Main Road

1.1

Sub-Base Sand blanket/blinding or approval equivalent material as sub-base compacted to required gradients, cambers, falls and cross falls as specified250mm Thick, to receive crusher run

m^2 2,736.89 7.50 20,526.68

1.2

Road-baseCrusher run spread, levelled and compacted to required gradients, cambers, falls and cross falls as specified150mm Thick, to receive bitumen binder

m^2 2,736.89 13.91 38,070.14

1.3Surfacing Asphaltic concrete binder course as specified100mm Thick, slopping not exceeding 15 degree from horizontal

m^2 2,736.89 24.50 67,053.81

Road Work---Bill of Quantity:

Page 29: Presentation sayed

2 Sub-Road

m^2 7,994.63 6.24 49,886.49

2.1

Sub-Base Sand blanket/blinding or approval equivalent material as sub-base compacted to required gradients, cambers, falls and cross falls as specified150mm Thick, to receive crusher run

2.2

Road-baseCrusher run spread, levelled and compacted to required gradients, cambers, falls and cross falls as specified200mm Thick, to receive bitumen binder

m^2 7,994.63 15.91 127,194.56

2.3Surfacing Asphaltic concrete binder course as specified40mm Thick, slopping not exceeding 15 degree from horizontal

m^2 7,994.63 20.50 163,889.92

Road Work---Bill of Quantity:

Page 30: Presentation sayed

4Road Kerb Cast-in-situ concrete kerb including jointing, excavation, backfilling, bedding and disposal of surplus materials. Type SM2

m 2,318.00 34.70 80,434.60

5

Road Marking Hot-applied superimposed reflectorised thermoplastic road markings 3mm thick hot-applied superimposed reflectorised thermoplastic road markings with 20% glassbead as specified in BS 3262 and in the drawing.

m

 

a) Continuity Line 869.15 2.70 2,346.71

c) Center Line/Lane Line 202.40 1.80 364.32

d) Edge Line 2,318.00 2.70 6,258.60e) Stop Line 60.50 5.40 326.70

6

Signagen

No

 

a) Kilometre post: inclusive of all necessary works at location 6.00 140.00 840.00

b) Direction arrow 26.00 65.00 1,690.00

c) Stop Sign 26.00 65.00 1,690.00

7 TOTAL COST 560,572.5

Road Work---Bill of Quantity:

Page 31: Presentation sayed

Ministry of Works Malaysia, MOWs tried to provide a better safety of road in Malaysia alongside with the Government efforts to reduce traffic accident and to achieve its targets.

Although studies shown that causes to most of the accident is because of the drivers themselves

MOWs always make it positive effort in order to improve traffic accident by giving further stress on engineering aspect with proactive and reactive action during design, construction and maintenance stage.

Road Work---Conclusion:

Page 32: Presentation sayed

DRAINAGE SYSTEMCHPTER FOUR

Page 33: Presentation sayed

Drainage System

Water is the main contributor to the wear and damage of roads. The water can be in the form of ground water, surface water (streams and rivers) or rain and it can damage the road in several ways:

• By washing away the soil (erosion and scouring)• By making the road body less resistant to traffic (i.e. weakening the load bearing

capacity)• By depositing soils (silting) which may obstruct the passage of water, or• By washing away entire sections of the road or its structures.

Typical problems caused by poor drainage include:

---Introduction

• Rutting • Cracking

• Potholes • Erosion

• Washout • Heaving and Flooding

Page 34: Presentation sayed

Drainage System

An efficient drainage system is essential to allow water to flow off and away from the road as quickly as possible. This is achieved by a system consisting of the following components: Road surface drainage which enables the water to flow off the road surface, Side drains which collect and lead the water away from the road, Road embankments in flood prone terrain, lifting the road surface well above

the highest flood levels, Catch-water drains which catch surface water before it reaches the road, Scour checks, preventing erosion in the ditches by slowing down the flow of

the water, Culverts which lead the water from the side drains under the road to the other

(lower) side, Bridges and drifts which allows the road to cross rivers and streams in a

controlled manner throughout the seasons.

---Objectives

Page 35: Presentation sayed

Drainage System

The design of drainage system is based on:

Urban storm water management Manual for Malaysia (MASMA) published by department of irrigation & drainage, Malaysia, 2000.

Polynomial approximation of IDF curves:

Polynomial expressions in the form of equation have been fitted to publish IDF curves for the 35 main cities/towns in Malaysia. From MASMA.

Ln ( r I t)= a + b ln (t) + c ( ln (t))2 + d (Ln (t))3 ……….. (1)

Where:

( r I t)= The average rainfall intensity (mm/hr) for ARI and duration t

r= Average return interval (years)

t= Duration (minutes)

a,b,c,d are Fitting constants dependent on ARI

---Design Rainfall Intensity

Page 36: Presentation sayed

Drainage System

Description:

---Design Rainfall Intensity

Average return interval (ARI) a b c d

50 years 5.3578 0.5094 -0.2056 0.0131

100 years 5.0646 0.7917 -0.2583 0.0161

The value of a,b,c, &d obtained from Table 13.A MASMA Manual Coefficients for the IDF Equations for the Different Major Cities and Towns in Malaysia (30≤ t ≤ 1000 min) selected t= 12 hrs = 720 min

Summary of design rainfall intensity: total design rainfall using rational methodDesign Intensity for 50 years= 50 I 720 = 34.37 mm/hr Q100= CIA Design intensity for 100 years= 100 I 720= 39.65 mm/hr Main channel Q100= 0.61 m3/s

Sub-channel Q100=0.024 m3/s

Page 37: Presentation sayed

Drainage System

To design the channel we have to use the manning’s equation

Q= 1/n AR2/3 S1/2

Summary of channel design

Main channel design Q= 2.7 m3/s > 0.61 m3/s ok!

v= 2.18 m/s < 4.00 m/s ok!

Sub-channel design Q= 0.4 m3/s > 0.024 m3/s ok!

v= 1.36 m/s < 4.00 m/s ok!

---Channel Design

Page 38: Presentation sayed

Drainage System---Channel Provided

Sub- channel Main channel

Page 39: Presentation sayed

Drainage System

A culvert is a device used to channel water.

There are three primary materials that culverts are made out of steel, precast concrete and polymer (plastic). They can also be built as a hybrid between steel and concrete.

For this project, we have decided to use 1500x1500mm precast box culvert proposed as the culvert for road crossing the drain.

---Culvert Provided

Type: Precast culvertSize : 1500x1500mm

Page 40: Presentation sayed

Drainage System---Bill of Quantity

Item Work Descriptionmeasuresd

unitsQuantity Rate (RM) Amount (RM)

1 Main Drain

1.1

SURFACE DRAINAGEDRAINAGEExcavationExcavating trenches starting from formation level;earthwork support, part return, fill in and ram andremainder deposit, spread and level within siteTo receive drain pipes not exceeding 200mm nominalsize, not exceeding 2.00m average 1.00m deep

m 119.18 11.33 1,350.31

1.2

Main drain Supply, lay and joint precast U‐drain size1200x900 with dry weather flow andwithout lid

119.18 410.00 48,863.80

Page 41: Presentation sayed

Drainage System---Bill of Quantity

2 Sub Drain

m 3,258.26 11.33 36,916.092.1

SURFACE DRAINAGEDRAINAGEExcavationExcavating trenches starting from formation level;earthwork support, part return, fill in and ram andremainder deposit, spread and level within siteTo receive drain pipes not exceeding 200mm nominalsize, not exceeding 2.00m average 1.00m deep

2.2

sub drain Supply, lay and joint precast U‐drain size600x450 with dry weather flow andwithout lid

m 3,258.26 140.00 456,156.40

3 coverm 3258.26 105 342117.3

3.1Precast reinforced concrete drain coversize 1000mm x 600mm x 225mm thick

4 culvert

m 78.44 900 705964.1

Construct and complete box culvertincluding all necessary works; size1500mm x 1500mm

5 TOTAL 905,785.79

Page 42: Presentation sayed

Drainage System

The 1.2 m width x 0.9 m depth main drains have proposed, and for

sub drains the 0.6 m width x 0.45m depth channel is proposed. To

drain out the storm water. Culvert 1500x1500mm have been

proposed at the road which crossing the drain. Overall theses

proposed channels and culverts can carry the amount of rainfall for

this area. The overall cost for the drainage system is RM905785.79

---Summary

Page 43: Presentation sayed

SEWAGE SYSTEMCHPTER FIVE

Page 44: Presentation sayed

Sewage System

Sewerage system is essential for any commercial, residential and industrial buildings.

Sewerage system is a network of pipes, pumps, and force mains for the collection of wastewater or sewage, from a community to ensure their hygiene and health.

Modern sewerage systems fall under two categories: domestic and industrial sewers and storm sewers. Sometimes a combined system provides only one network of pipes, mains, and outfall sewers for all types of sewage

---Introduction

Page 45: Presentation sayed

This part is to study and plan for the overall sewage generation and collection based on the present layout plan.

Sewage System---Objectives

Page 46: Presentation sayed

Proposed sewer lines will collect the sewage generated from the new residence buildings, commercial buildings, surau, sport complex and will transfer them using the proposed pipes and manholes to the sewerage treatment plan within the project site.

The proposed reticulation system will consist of HDPE pipe and precast clay manholes.

Sewage System---Proposed Sewage Design

Page 47: Presentation sayed

The design of the sewer pipes and manholes of this project are based on the following standards:

“ M.S 1228: 1991, code of practice of design and installation of sewerage systems” by the standard and industrial research institute Malaysia ( SIRIM).

“Malaysia sewerage industry guidelines (volume I – V)” by national water services commission or suruhanjaya perkhidamtan Air Negara (SPAN)

Sewage System---Design Standards

Page 48: Presentation sayed

Sewage System---Summary of Calculation and Design

Defention Main Pipe Sub Pipe

Q Produced m3/s 4.85x10^-3 1.0*10^-3material HDPE HDPEn value 0.0120 0.0120

Diameter mm 250.0000 100.0000angle 93.0400 93.0400

AREA mm^2 49062.5000 7850.0000hydraulic radius R 0.1575 0.0855

slope 0.0025 0.0025 Q pipe m^3/s 0.1550 0.0590

Discharge Checking 0.155 > 4.85x10^-3 0.059 > 1.0x10^-3Result OK! OK!

Velocity Produced 0.9 0.85

Velocity Checking m/s 0.8<0.9<4 0.8<0.85<4

Result OK! OK!Length m 153.20 764.22

Page 49: Presentation sayed

Sewage System---Bill of Quantity

Item Work Description Measuresd units Quantity Rate

(RM)Amount

(RM)

1Main Pipe  

Excavation and filling with Pipe size 200mm (HDPE) m 153.20 86.50 13,251.80

2Sub Pipe  

Excavation and filling with Pipe size 100 mm (HDPE) m 764.22 67.50 51,584.85

3

Manholes  Type: Clay Material Cover: Steel Size: 1200*1200*1000With Installation

Unit 14.00 300.00 4,200.00

4 TOTAL 69,036.65

Page 50: Presentation sayed

WATER SUPPLYCHPTER SIX

Page 51: Presentation sayed

The water supply industry is important not only to maintain the health of the community, but for the sustainability of industry, business and agriculture.

Without adequate water supplies our present society would never have evolved, and our lives today would be unrecognizable.

Like the other service providers, electricity, telephone and gas, the water utilities deliver their product to the home, which requires a network of distribution pipes to service each household.

Water Supply---Introduction:

Page 52: Presentation sayed

To comply with design manual published by Syarikat Air Terengganu (SATU) and Malaysian Standard (MS) 1395 : Specification For Pillar Hydrant

To provide sufficient water supply requirement for the development area based on domestic demand and external fire hydrant system

Water Supply---Objectives:

Page 53: Presentation sayed

1- 2-

3-

Water Supply---Water Supply Components:

Page 54: Presentation sayed

In our stage we are going to design the distribution system

Which contain the Reservoir (storage tank), Main pipes, Sup-pipes, Fire hydrant.

Water Supply

Page 55: Presentation sayed

In order to design the water distribution system we need to know the water demand for our area

Water demand is based on population served, per capita consummation, and service factor, industrial and other special demand.

In estimating water demand, various factors should be taken into account directly or indirectly.

Water Supply---Water Demands:

Page 56: Presentation sayed

Water demand in our area is basically contain 1. 82 units with 5 person each house + Fire hydrant2. Surau 150 person 3. Complex centre 200 person 4. 8 Shopes

Summary of water demand 175380+1200+11000+3000= 190580 L/day

= 190580 L/day X 2.5 (factor)

= 476.45 m3/day

Water required for 3 days

= 476.45 m3/day x 3 = 1429.35 m3/day

Water Supply---Water Demands:

Page 57: Presentation sayed

TANK DESIGN

The design of tank is based on 3 days water demand.

Tank shape; circular

Diameter = 23 m

Height = 3.5 m

Total volume of tank = (π (11.5)2) x 3.5= 1454.16 m3 > 1429.35 m3 ok!

Tank material is Fibber Reinforced plastic

PIPE DESIGN

Four types of pipes have been used1. Main pipe

2. Fire hydrant pipe

3. Pipe in one raw of the houses

4. Pipe for one house

Water Supply---Tank and Pipe Design:

Page 58: Presentation sayed

1- Main pipe Q demand = 0.004 m3/s

Pipe provided : steel pipe of 150mm diameter

Q design = 0.009 m3/s > 0.004 m3/s

2- Fire hydrant pipe Q demand = 0.001 m3/s

Pipe provided : steel pipe of 120mm diameter

Q design = 0.004 m3/s > 0.001 m3/s

3- Pipe in one raw Q demand = 0.0003 m3/s

Pipe provided : PVC pipe of 50 mm diameter

Q design = 0.0057 m3/s > 0.0003 m3/s

4- Pipe for one house

Q demand = 0.00003 m3/s

Pipe provided : PVC pipe of 20 mm diameter

Q design = 0.00053 m3/s > 0.00003 m3/s

Water Supply---Tank and Pipe Design:

Page 59: Presentation sayed

Item Work Description Measured Units Quantity Rate (RM)

Amount (RM)

1 Main Pipe  

1.1 Excavation and Installation m 480.00 21.25 10,200.00

1.2 Pipe: Steel, 150mm m 480.00 133.30 63,984.00

1.3

Pipe Fittings:

Unit

 

T- Shape 10 23.20 232.00

90- Degree 7 30.40 212.80

45- Degree 4 15.60 62.40

Water Supply---Bill of Quantity:

Page 60: Presentation sayed

2 Sub Pipe  

2.1 Excavation and Installation m 641.53 20.00 12,830.60

2.2 Pipe: PVC, 50mm m 641.53 2.20 1,411.37

2.3

Pipe Fittings:

Unit

 

T- Shape 81 20.50 1,660.50

90- Degree 108 30.40 3,283.20

45- Degree 8 15.20 121.60

3 Water Meter  

3.1 Water Meter Unit 92 37.00 3,404.00

Water Supply---Bill of Quantity:

Page 61: Presentation sayed

4 Fire Hydrant  

4.1 Fire Hydrant Unit 9 1,945.00 17,505.00

4.2

Pipe: Steel, 150mm m 400 10.60 4,240.00Pipe Fittings:

Unit

 

T- Shape 6 31.50 189.00

90- Degree 10 50.40 504.00

45- Degree 4 18.90 75.60

5 Water Tank  

5.1 water tank together with tank tower and instullation Unit 1 500,000

.00 500,000.00

6 TOTAL COST 619,916.07

Water Supply---Bill of Quantity:

Page 62: Presentation sayed

VPC pipes are no longer use in Malaysia because it’s easy to break.

Fiberglass Reinforced Plastic (FRP) Tank is proposed as a elevated storage water tank. Because it is easily to be assembled by bolting them together, The designed meet highest standard of sanitary storage and Have high strength to weight ratio and it is lighter than steel panel.

Water Supply---Conclusion:

Page 63: Presentation sayed

WATER SUPPLYCHAPTER SEVEN

Page 64: Presentation sayed

E.M.P

EMP is a process which ensures that all environmental matters are taken into account quite early in the project at planning process itself.

It takes into consideration not only technical and economic considerations but also, traditional aspects like impact on local people, biodiversity etc.

Purpose of EMP• EMP was formulated to protect the environment and provide a guide

for an overall environmental management• It also forms the basis for reporting on an environmental management

performance during the implementation of various activities during construction and operations of the proposed project

---What is EMP?

Page 65: Presentation sayed

E.M.P

Identification of key potential environmental impacts and proposing an action plan for mitigation during pre-construction, construction & operational stages

Establishing appropriate standards and procedures for mitigation and monitoring the environmental impacts

Benefits & Advantages of EMP Lower project costs in the long-term Increased project acceptance Improved project design Informed decision making Environmentally sensitive decisions Increased accountability and transparency Reduced environmental damage Improved integration of projects into their environmental and social settings

---Objectives

Page 66: Presentation sayed

E.M.P

Agriculture

Construction (Road networks, Malls, Townships, Dam etc)

Industries

Electrical projects

Waste disposal

Any developmental projects around Protected Areas / Nature Preserves

Clean Development Mechanism CDM project

---Which type of projects under go EMP?

Page 67: Presentation sayed

E.M.P

The proposed development has been studied from all angles

This report has recommended various measures to control and

manage the environment and hence reduce the environmental

impact to its minimum level

The proposed development is expected to improve the living

standard of the surrounding residents and community

---Summary

Page 68: Presentation sayed

NO

DESCRIPTION COST (RM)

1 EARTH WORK 620,206.88

2 ROAD WORK 560,572.50

3 DRAINAGE 905,785.79

4 SEWAGE 69,036.65

5 WATER SUPPLY 619,916.07

6 TOTAL 2,775,517.89

TOTAL COST OF THE PROJECT

Page 69: Presentation sayed

Thank You

Any Question!