PRESENTATION ON WATER SERVICES BACKLOGS
description
Transcript of PRESENTATION ON WATER SERVICES BACKLOGS
PRESENTATION ON WATER SERVICES BACKLOGS
Municipal Manager4 May 2007
2
Outline Background Locality Map Backlog Figures Budget Requirements Bucket Eradication Projects Funding Required For Buckets Challenges
3
4
Background
– 8 municipalities in 37 294 km2 – Population = 810 214 = 12.4% of Provincial population– 3rd Largest DM in the EC– Mostly rural and youthful
5
Backlog FiguresLocalMunicipality:
Total Population WaterBacklog (R)
Sanitation Backlog (R)
Total
Emalahleni LM 116,945 46,383,437 55,314,923 101,698,360
Inkwanca LM 20,489 490,904 21,845,355 22,336,259
Intsika Yethu LM 196,816 87,727,856 102,191,773 189,919,629
Inxuba Yethemba LM 61,058 4,123,644 10,678,517 14,802,161
Lukhanji LM 194,144 66,569,326 50,972,858 117,542,184
Ngcobo LM 150,597 284,561,192 102,608,463 387,169,655
Sakhisizwe LM 54,665 10,288,601 13,769,867 24,058,468
Tsolwana LM 32,977 19,976,426 31,830,559 51,806,985
Chris Hani DM 810,214 R 520,121,386 R 389,212,315 909,333,701
6
Budget Requirements Service 2007/8 2008/9 2009/10 2010/11
Water 260,060,693 260,060,693
Sanitation 97,303,078 97,303,078 97,303,078 97,303,078
TotalMTEF (BILL)
357,363,772
207,000,419
357,363,772
161,918,181
97,303,078
189,186,000
97,303,078
7
Bucket Eradication Projects 6976 Buckets in total 1120 Buckets already eradicated
(06/07) 5856 Buckets still to be eradicated 11 Projects for buckets 3 projects completed 5 projects under construction 3 projects at planning stage
8
Bucket Eradication
9
Funding Required For Buckets Total required for buckets
R150m. Funds already available R77m.
[MIG (R45m), DHLGTA (R12m), Equitable Share R10m and DBSA Loan R10m]
Funds still required R73m
10
Challenges More funding required to meet water and sanitation backlogs Figures do not include dilapidated infrastructure and bulk for
augmentation especially Karoo towns Creating a balance between basic infrastructure and LED High costs per capita due to scattered villages Sustainability of VIPs Communities want water borne to replace buckets If R73m is ring-fenced from R207million then committed
projects would be delayed and costly Non-performing service providers Few contractors with high ratings with respect to CIDB Retention of skilled personnel (engineers) Implementation of the Supply Chain Management
Regulations
11
THE END