Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport...
Transcript of Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport...
![Page 1: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/1.jpg)
2nd September 2008
Presentation on
Mumbai Urban Transport Project Dr. P. C. Sehgal
Managing Director
Mumbai Railway Vikas Corporation
Mass Urban Transport Projects
8th BIMSTEC Training Course on Design and Maintenance of
Passenger Coaches
Railway Staff College, Vadodara
![Page 2: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/2.jpg)
Details of Presentations
MRVC will make the following three presentations:
Speaker Subject Details
Dr. P. C. Sehgal Managing Director
Mass Urban Transport Projects
Details of projects, funding arrangements, salient achievements, etc.
Shri Alok Kapoor Dy. Chief Electrical Engineer
Latest Developments in EMUs
Will cover specific technical details of EMUs being procured by MRVC for Mumbai suburban system
Shri Rajeev Sharma Chief Signal & Telecom Engr.
On Board Radio Communication System through GPS and Train Management System
Details of signaling system being planned for Mumbai suburban system
![Page 3: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/3.jpg)
6.
Afforestation &
Rainwater
Harvesting
1.
Social
Upgradation 2.
Introduction of
State of Art
Technology
3.
Passenger
Amenity
Upgradation
5.
Noise
Reduction
4.
Energy
Conservation
MRVC
![Page 4: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/4.jpg)
Mumbai Suburban Railway System Background
• Mumbai has been the commercial capital of India since pre-independence days
• Due to its peninsular geography, the city has grown linearly
• Britishers realized that only an efficient suburban railway system can become the prime mover of growth
• Suburban railway system set up in 1925
• Latest technologies of 1500v DC traction and DC Electric Multiple Units available at that time used.
![Page 5: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/5.jpg)
Green
Area
Island
City
Greater Mumbai
Area: 445 Sq Kms
Mumbai Suburban Railway System
![Page 6: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/6.jpg)
Mumbai Suburban Railway System An Overview
• 319 route Kms.
• 876 Track Kms (including 52 Kms already added in MUTP).
• 6.3 million passengers per day.
• 2385 trains per day
• Fleet of 227 rakes (9 car eq.) which are run in 9 and 12 car compositions.
• Mumbai Suburban Railway System is a part of Indian Railways which is a department of the Central government.
![Page 7: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/7.jpg)
Mumbai Suburban Railway System
• The designed carrying capacity per nine-car train is 1,800 passengers (900 sitting and 900 standing) and as against this figure, at present in a nine-car train, during the peak period 5,000 passengers (900 sitting plus more than 4,000 people in standing condition) travel.
• This has resulted in, what is known as, practical super dense crush loading conditions in Mumbai.
• Loading of 16 passengers per square metre, which is highest in the world, is obtained.
![Page 8: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/8.jpg)
Mumbai Suburban Railway System Existing Major Problems
Overcrowding/overloading
Lack of investment
Obsolete technology
Encroachments
Limitation of carrying capacity
Ventilation and jerking problems
![Page 9: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/9.jpg)
Mumbai Suburban Railway System Overcrowding
![Page 10: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/10.jpg)
Overcrowded Stations
![Page 11: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/11.jpg)
Difficult Entry & Exit
![Page 12: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/12.jpg)
Mumbai Suburban Railway System Overloading in trains
Mumbai is the commercial capital of India and has ample employment opportunities.
Large number of people were attracted to Mumbai for livelihood.
Abnormal increase in population.
Growth of suburban traffic leading to overloading in the trains.
![Page 13: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/13.jpg)
Mumbai Suburban Railway System Overloading in trains
Monthly season ticket in Mumbai suburban service is quite affordable i.e. in one US$, 500 Kms is covered by passengers.
Railway suburban transport system became the main mode of transport for the people.
Increase in suburban trains in Mumbai did not keep pace with the passenger demand .
Loading in the existing suburban trains increased.
The traveling conditions in trains became unbearable.
![Page 14: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/14.jpg)
Mumbai Suburban Railway System Overloading in trains
(In Millions)
0
5
10
15
20
25
30
Mumbai 7.78 11.08 14.53 19.2 22.45 27.26
1971 1981 1991 2001 2011* 2021*
* Estimated
Population growth in Mumbai
![Page 15: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/15.jpg)
Mumbai Suburban Railway System Overloading in trains
1951-
52
1961-
62
1971-
72
1981-
82
1991-
92
2001-
02
2004-
05
%
increase
from
1951-52
Passenger
carried
(millions)
292 454 915 1459 1795 2275 2314 792%
Average trip
length
(Kms)
13.8 14.0 16.5 18.8 22.5 26.9 29.6 214%
Passenger
Kilometers
(millions)
4031 6365 15123 27392 40462 61195 68632 1695%
No. of trains 741 960 1161 1577 1889 2055 2441 329%
Suburban traffic growth in Mumbai
![Page 16: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/16.jpg)
Mumbai Suburban Railway System Lack of Investment
All over the world, traditionally the
suburban/metro network operation, including the buses, is being looked after by the local and state governments.
In Mumbai, the rail based suburban network was operated by the Central Government and the operating loses were also absorbed by the Central Government.
![Page 17: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/17.jpg)
Mumbai Suburban Railway System Lack of Investment
The development charges collected by the State Government were not used for the expansion of suburban systems in Mumbai.
As a consequence, the existing suburban system was neither patronized by Central Government nor by State Government, mainly due to requirement of huge
amount of funds.
![Page 18: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/18.jpg)
Mumbai Suburban Railway System Obsolete technology
Mumbai suburban railway system is being operated on 1500V DC traction system, introduced since 1925.
With the increase in loading, each 12-car train draws 5,000 Amps.
![Page 19: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/19.jpg)
Mumbai Suburban Railway System Obsolete technology
When two trains are leaving and two trains are reaching Churchgate station, approximately 10000 to 15000 Amps current is drawn from the system.
Due to drawal of heavy current, large number of traction substations have been set up.
Practically at each station, traction substation is existing.
![Page 20: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/20.jpg)
Mumbai Suburban Railway System Obsolete technology
For increasing the suburban services and number of coaches per train, additional substations have to be set up, which is not considered advisable from the technical safety consideration.
It became difficult to increase the number of trains and to add additional number of coaches.
Need to have 25000V traction system was felt.
![Page 21: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/21.jpg)
Mumbai Suburban Railway System Encroachments
When large number of people migrated to Mumbai from other cities and rural areas of Maharashtra and other States, the surplus vacant railway land available in Mumbai suburban sections became the soft target for encroachment.
Thus when the need was felt to increase the number of railway corridors in Mumbai, it became difficult to get the encroached railway land vacated from encroachers.
![Page 22: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/22.jpg)
Mumbai Suburban Railway System Encroachments
![Page 23: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/23.jpg)
Mumbai Suburban Railway System Encroachments
![Page 24: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/24.jpg)
![Page 25: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/25.jpg)
Mumbai Suburban Railway System Encroachments
Since the encroachers were staying near the existing railway tracks, the train speeds was reduced to 30 K/ph from safety considerations and this led to reduction in line capacity.
![Page 26: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/26.jpg)
Mumbai Suburban Railway System Limitation of carrying capacity
On the existing corridors, mail/express, freight, passenger and suburban trains are operated and existing corridors are being utilized to their full capacity and it has been difficult to increase the number of services in the existing system.
In order to create extra carrying capacity to run additional trains, new additional corridors had to be set up.
![Page 27: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/27.jpg)
Mumbai Suburban Railway System Ventilation and jerking problems
Lack of ventilation is a major problem in Mumbai suburban trains. During peak periods, CO2 level inside the coaches is as high as 2500 ppm.
Experience of jerks during braking and during run as starting and stopping of the trains is not smooth.
![Page 28: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/28.jpg)
![Page 29: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/29.jpg)
Mumbai Suburban Railway System
Strategy to solve the problems
![Page 30: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/30.jpg)
Mumbai Suburban Railway System Strategy to solve the problems
Formation of Mumbai Railway Vikas Corporation to implement the railway projects in Mumbai with World Bank assistance.
Resettlement and Rehabilitation of 15,000 project affected households to get the encroached railway land vacated.
Introduction of new traction technology at 25 kV AC converting from 1500V DC system.
Increasing the length of trains from 9 to 12 car, thus creating 33% extra carrying capacity.
Introduction of rakes with new technology having IGBT based traction control system with regenerative braking.
![Page 31: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/31.jpg)
Mumbai Suburban Railway System Strategy to solve the problems
To take care of deteriorating traveling conditions in the suburban railway system of Mumbai, Govt. of Maharashtra and Indian Railways came forward and Mumbai Railway Vikas Corporation Ltd (MRVC) was set up with the following main objectives:
Bringing down the over crowding in peak hour peak direction 9-car train to 3000 passengers as against existing around 5000.
Segregate the suburban train operation from the main line passenger and freight services.
![Page 32: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/32.jpg)
Mumbai Suburban Railway System Strategy to solve the problems
To achieve the above objectives, works requiring investment of Rs. 10,000 crores (US$ 2.5 billion) approximately were identified. It was decided to undertake the capacity enhancement works in Mumbai in three phases.
In Phase I, works worth Rs. 3125 crores (US$ 781 million) were identified and it was decided to take a loan upto 50% of requirement from World Bank..
![Page 33: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/33.jpg)
Mumbai Suburban Railway System Strategy to solve the problems
The loan would be repaid by levy of surcharge in three stages on the existing passenger tickets.
Apart from that, a non-refundable grant was to be given by Govt. of Maharashtra and Indian Railways.
![Page 34: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/34.jpg)
Mumbai Railway Vikas Corporation 1. World Bank Loan 1613 Jointly Taken By IR & GOM 2. Counterpart Funding Grant by IR 756 GOM 756 3. TOTAL 3125
Resettlement of 15000 families
Construction of new lines
Procurement of New Trains
Maintenance facilities
Import of New
Technology
Levy of surcharge collected by CR & WR
GOM IR
WORLD BANK
Commercial development of
Railway land & air space
806 cr
756 cr
806 cr
756 cr
![Page 35: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/35.jpg)
![Page 36: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/36.jpg)
MUTP Phase I (Rail Component)
• New Lines: INR US$ (million) • Quadrupling of Borivali-Virar section 416.0 cr. 109 • WR 5th line Santacruz-Mahim 59.0 cr. 15 • Kurla Thane Additional pair of lines 166.0 cr. 42
• Sub-Total (New Lines) 641.0 cr. 166
• EMU procurement & manufacture: 1359.2 cr. 340
• DC to AC Conversion 380.4 cr. 95
• Resettlement & Rehabilitation: 290.0 cr. 73
• Optimisation & Other Works: • Optimisation of Western Railway 50.1 cr. 13 • Optimisation of Central Railway 99.5 cr. 100 • Optimisation of Harbour line 19.7 cr 5 • Virar Car Shed 93.0 cr 18 • Maintenance facilities for EMUs 64.3 cr. 16 • Stabling lines for EMUs 48.5 cr. 12 • Track Machines 31.3 cr. 8 • Institutional strengthening & studies 48.2 cr. 12 • Sub-Total 454.6 cr. 184
• Grand Total 3125.2 cr 781
![Page 37: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/37.jpg)
Mumbai Suburban Railway System
Resettlement & Rehabilitation
![Page 38: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/38.jpg)
Mumbai Suburban Railway System Resettlement & Rehabilitation
For getting the encroached railway land free for implementing the railway projects, it was decided that each and every project affected households will be given a house of 225 sq. ft. at different locations.
15,000 new flats have been constructed and all the project affected households have been resettled.
![Page 39: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/39.jpg)
Mumbai Suburban Railway System Resettlement & Rehabilitation
All the resettled people are happy and they are feeling socially upgraded and their standard of living has also been upgraded substantially.
MRVC has spent Rs. 400 crores (US$ 100 million) to take care of the social obligations.
![Page 40: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/40.jpg)
Mumbai Suburban Railway System Resettlement & Rehabilitation
With removal of encroachments, 3.2 lakhs sq. mtrs. of encroached railway land both on Central and Western Railways has been vacated.
With the completion of this important task, the work of laying of additional tracks between Borivali and Virar was completed and the section was dedicated to the nation on 7th July 2007.
For laying of additional tracks between Kurla and Thane, the work is in progress.
![Page 41: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/41.jpg)
Mumbai Suburban Railway System Resettlement & Rehabilitation
Mr Robert B. Zoellick, President, World Bank, during his visit to Mumbai had inspected the resettlement sites and appreciated the efforts put in by Railways and Govt. of Maharashtra in rehabilitating the project affected households.
He has also mentioned about this important issue during his address in the recently concluded SDN Workshop held in World Bank’s HQ in Washington DC in February 2008.
![Page 42: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/42.jpg)
Mumbai Suburban Railway System Resettlement & Rehabilitation
![Page 43: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/43.jpg)
Mumbai Suburban Railway System Resettlement & Rehabilitation
![Page 44: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/44.jpg)
Mumbai Suburban Railway System Resettlement & Rehabilitation
![Page 45: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/45.jpg)
Mumbai Suburban Railway System
EMU Procurement
![Page 46: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/46.jpg)
EMU Procurement
• Total No. of rakes - 174, 9 Car.
• MRVC Contract - 101, 9 Car.
• GP-194 - 56, 9 Car.
• GP-194 (30%) - 17, 9 Car.
129, 12-car + 2, 9-car
![Page 47: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/47.jpg)
Mumbai Suburban Railway System
In next 3 to 4 years, Mumbai suburban system will get 129 12-car rakes with passenger amenity features.
It is felt that with the provision of passenger friendly improved features overall upgradation of passenger amenities will take place.
The main important feature of the new EMU trains which public has liked the most is that the CO2 level inside the coaches had been reduced from 2500 ppm to 1400 ppm during the peak period.
New trains for Mumbai suburban system
![Page 48: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/48.jpg)
Progress
1st Rake 12th Nov. 2007 (W.R.)
2nd Rake 17 Dec. 2007 (W.R.)
3rd Rake 13th Jan. 2008 (W.R.)
4th Rake 21st Feb. 2008 (C.R)
5th Rake 7th April 2008 (C.R)
6th Rake 13th May 2008 (CR)
7th Rake 26th May 2008 (CR)
8th Rake 13th June 2008 (CR)
9th Rake 4th July 2008 (CR)
10th Rake 31st July 2008 (CR)
![Page 49: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/49.jpg)
Progress
11th Rake 8th Aug 2008 (C.R.)
12th Rake 17th Aug. 2008 (C.R.)
13th Rake 23rd Aug. 2008 (C.R.)
14th Rake Under commissioning (C.R.)
15th Rake Under commissioning (C.R.)
With the introduction of new rakes
126 additional services (74,12 car & 52, 9-car)
123 services earlier running with 9-car have been converted to 12-car
![Page 50: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/50.jpg)
New Rake in Public Service (WR)
![Page 51: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/51.jpg)
21-02-08
Introduction of new EMU rake
in public service (CR)
![Page 52: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/52.jpg)
Passenger Information System Display
![Page 53: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/53.jpg)
Stainless Steel Grab Handles & Partitions
![Page 54: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/54.jpg)
2nd Class Polycarbonate Seats and improved interiors
![Page 55: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/55.jpg)
Ergonomic Motorman Driving Desk
![Page 56: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/56.jpg)
External Air Blowers for forced ventilation
![Page 57: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/57.jpg)
Air Springs for Better Riding
![Page 58: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/58.jpg)
INTRODUCTION OF NEW TECHNOLOGY EMU RAKES : IMPROVED FEATURES
• Use of 3 Ph AC Traction motor having 20% higher horse power.
• Higher speed potential of 100 Kmph as against existing 80 Kmph.
• Higher acceleration and deceleration of 0.54 m/s2 and 0.76 m/s2.
• Reduction in journey time of about 4 to 5 minutes in a typical Churchgate-Borivali or CSTM-Thane section.
![Page 59: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/59.jpg)
INTRODUCTION OF NEW TECHNOLOGY EMU RAKES : IMPROVED FEATURES
• Forced Ventilation System
• Computerized passenger information system with LED display.
• Station announcement on running trains using Global Positioning System (GPS) technology.
![Page 60: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/60.jpg)
INTRODUCTION OF NEW TECHNOLOGY EMU RAKES : IMPROVED FEATURES
• Energy saving of about 30% saving 20 crore (5 million) units of energy every year due to re-generative braking .
• Benchmark for CO2 emission in power house is 1 Kg of CO2 emission for every unit of energy.
• There would be a saving of 2 lakh tonnes of CO2
emission every year.
![Page 61: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/61.jpg)
Carbon Credit
• The project idea note was made in consultation with Central and Western Railways and submitted to World Bank.
• It has been included in the approved list of CDM projects.
![Page 62: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/62.jpg)
VENTILATION Problem
![Page 63: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/63.jpg)
Ventilation system
• MRVC procured a portable carbon dioxide meter and measured the CO2 levels inside the running trains.
• The CO2 levels in the existing SDCL condition was 2500 ppm.
![Page 64: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/64.jpg)
Ventilation system
• Detailed study was carried out referring ANSI/ASHRAE standard to modify the RDSO specification.
• ANSI/ASHRAE standard 62-2001 recommends that the maximum indoor CO2 concentration should be less than 700 ppm above the outdoor air concentration
![Page 65: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/65.jpg)
Ventilation system Fresh Air Requirement
• Passenger Loading per coach:
– Seating Capacity 90 passengers
– Normal standing for peak 90 passengers
– Total passengers traveling 570 passengers
in SDCL
![Page 66: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/66.jpg)
Ventilation system Fresh Air Requirement
• CO2 Generated per Coach: – CO2 generated per passenger .018 m3/hr
– CO2 generated by 570 10 m3/hr
passengers in SDCL
• Calculation of Fresh Air Requirement:
– Fresh Air Required = Total CO2 generated Permissible PPM = 10 m3/hr 700 X 10-6 = 15000 m3/hr
ADDITIONAL FRESH AIR REQUIRED = 15000 m3/h
![Page 67: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/67.jpg)
The Design Concept
VENTILATION SYSTEM
![Page 68: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/68.jpg)
Photograph of Mock-Up
VENTILATION SYSTEM
![Page 69: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/69.jpg)
Comparative CO2 Levels In SDCL EMU Train
1510
2060
21802370
1760
1520
1370
1140
1050
880920
810
1440
1440
1340
760
900
1100
500
700
900
1100
1300
1500
1700
1900
2100
2300
2500
07
:15
:33
07
:20
:33
07
:25
:33
07
:30
:33
07
:35
:33
07
:40
:33
07
:45
:33
07
:50
:33
07
:55
:33
08
:00
:33
08
:05
:33
08
:10
:33
08
:15
:33
08
:20
:33
08
:25
:33
08
:30
:33
08
:35
:33
Time in PM
* Above Comparative Graph Shows an appreciable reduction in CO2 level in the EMU Train fitted with Forced Ventilation System
CO
2 L
ev
el
in P
art
s p
er
Mil
lio
n (
PP
M)
Existing Conventional Rake without Ventilation System
New DC/AC Rake with Forced Ventilation System
Dadar
Bandra
Andheri
*
Borivali
*
Mum
bai C
entr
al
Charn
i Road
Dahis
ar
*
Mira R
oad
*
Bhayender
![Page 70: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/70.jpg)
New EMU Bogie
Reduced Jerks & improved riding
![Page 71: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/71.jpg)
Mumbai Suburban Railway System
Improved illumination level:
The lighting inside the coaches has been improved to 300 lux from present 120 lux.
![Page 72: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/72.jpg)
Mumbai Suburban Railway System
Passenger Information System:
GPS based passenger information system has been provided in all the coaches with following facilities:
• Automatic announcement of approaching stations in three languages, i.e. English, Hindi and Marathi.
• Platform indicator.
• Emergency announcement by control.
• LED based head code.
![Page 73: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/73.jpg)
Mumbai Suburban Railway System
Passenger Information System:
Platform Indicator LED based head code
![Page 74: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/74.jpg)
Mumbai Suburban Railway System Reduction in number of substations
The number of traction substations on Western and Central Railways will be reduced from the existing 66 to 22.
This will also improve the voltage condition in the entire Mumbai suburban section and will enable us to increase the length of trains from 9 to 12.
![Page 75: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/75.jpg)
Mumbai Suburban Railway System
Cost Reduction of EMUs
![Page 76: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/76.jpg)
Mumbai Suburban Railway System
The cost of MRVC (nine-car) rake is Rs. 20 crores (US$ 5 million) approximately. The cost of a fully imported nine-car rake of similar features would be around Rs. 60 crores. The cost reduction has been achieved by adopting the following strategy:
The equipments with improved design features have been
designed by M/s Siemens, Germany. Out of total ordered quantity, only 30% equipments will be got manufactured abroad and 70% are to be manufacture in the facilities to be set up by
M/s Siemens in India. An interest free advance of Rs. 180 crores (US$ 45 million) has
been given to M/s Siemens, Germany.
![Page 77: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/77.jpg)
Mumbai Suburban Railway System
Reduction in Cost Sr.
No.
Equipment Location of
factory set
up in India
Cost per motor coach % Saving
Imported
Equipment
Indigenized
equipment
1. Traction motor Kalva Rs. 65.40 lakhs (0.16 million
US$)
Rs. 51.36 lakhs
(0.12 million
US$)
21.47%
2. Power
converter
Nashik Rs. 96.14 lakhs
(0.24 million
US$)
Rs. 84.31 lakhs
(0.21 million
US$)
12.30%
3. Auxiliary
converter
Nashik Rs. 32.87 lakhs
(0.08 million
US$)
Rs. 21.85 lakhs
(0.06 million
US$)
33.53%
4. Power
transformers
Vadodara Rs. 30.12 lakhs
(0.08 million
US$)
Rs. 22.25 lakhs
(0.06 million
US$)
26.13%
![Page 78: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/78.jpg)
Mumbai Suburban Railway System
Improved features of passenger amenity items were developed indigenously at ICF with the features matching with the international standards. This also led to cost reduction.
By manufacturing the coach body and shell at ICF, which is Indian Railway’s manufacturing unit, the cost of manufacture has been kept low as no profit margins have been included in the cost.
The cost of nine-car rake built by ICF is Rs. 20 crores (US$ 5 million) approximately as against Rs. 60 crores (US$ 15 million) of imported rake with the similar features.
Reduction in Cost
![Page 79: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/79.jpg)
Mumbai Suburban Railway System
Eco Friendly Features
![Page 80: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/80.jpg)
Mumbai Suburban Railway System
In the existing trains, lot of noise is being generated on account of acceleration, braking and working of compressors, etc.
The present level of noise inside the coaches is more than 85 db.
With the use of compressor of modified design and IGBT step-less control with regenerative braking, the noise level inside the coach has been reduced to 65 to 68 db.
Noise Control
![Page 81: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/81.jpg)
Mumbai Suburban Railway System
For laying of additional tracks between Borivali-Virar and Kurla-Thane, 3500 mangroves were cut.
MRVC has taken up the responsibility to upgrade the environment and planted 13,000 mangroves.
The survivability of these trees is checked at every six month by the World Bank team and I am happy to announce that the survivability rate of such mangroves is 80%.
Afforestation
![Page 82: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/82.jpg)
Mumbai Suburban Railway System
Mangrove Plantation:
Afforestation
![Page 83: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/83.jpg)
Mumbai Urban Transport Project
Phase II
![Page 84: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/84.jpg)
MUTP Phase II
MUTP Phase II has been
sanctioned in the Railway
Budget 2008-09
![Page 85: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/85.jpg)
Sr. No.
Work
Cost at Current Prices (in cr) (March 2008)
Completion Cost (in cr)
(Upto 2013)
1 5th & 6th Lines CSTM-Kurla 537 659
2 5th & 6th Lines Thane-Diva 115 133
3 6th Line Mumbai Central-Borivali 430 522
4 Extension of Harbour Line from Andheri to Goregaon
88 103
5 DC to AC Conversion 237 293
6 EMU Procurement & manufacture 2324 2930
7 Maintenance Facilities for EMUs 167 205
8 Stabling Lines for EMUs 111 141
9 Technical Assistance & Institutional Strengthening 52 62
10 Resettlement & Rehabilitation 109 124
11 Station Improvement & Trespassing Control 111 128
Grand Total 4281 5300
![Page 86: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/86.jpg)
Financing of MUTP Phase II
• Cost 5300 cr • Grant by GOM 1545 cr • Grant by IR 1545 cr • Loan* 1910 cr • Revenue from 300 cr comml. development**
*Loan to be repaid by continuation of Phase I surcharge.
**Depending upon FSI realized, equal financial relief to GoM and MoR will be available.
![Page 87: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/87.jpg)
Mumbai Railway Vikas Corporation 1. Loan Jointly By IR & GOM 1910 2. Commercial Development 300 3. Grant by IR 1545 4. Grant by GOM 1545 3. TOTAL 5300
Resettlement of 2850 families
Construction of new lines
Procurement of New Trains
(96 rakes)
Maintenance facilities
Station Improvement
Levy of surcharge collected by CR & WR
GOM IR
Loan
Commercial development of
Railway land
955 cr 955 cr
1545 cr 1545 cr
300 cr
![Page 88: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/88.jpg)
Implementation Plan for MUTP Phase II
• MUTP Phase II is proposed for implementation in two
parts.
• MUTP Phase II (a): (World Bank funded)
EMU procurement
DC to AC Conversion
EMU maintenance facilities
EMU stabling lines
![Page 89: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/89.jpg)
Implementation Plan for MUTP Phase II
• MUTP Phase II (b): Resettlement & Rehabilitation 6th Line Mumbai Central-Borivali Extension of Harbour Line from Andheri
to Goregaon 5th & 6th Line Diva-Thane 5th & 6th Line Kurla-CSTM Station improvement & trespassing
control
![Page 90: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/90.jpg)
Implementing Agency for MUTP Phase II Works
• MUTP Phase II (a): (World Bank funded)
EMU procurement MRVC/ICF/RDSO DC to AC Conversion MRVC/CR EMU maintenance facilities CR/WR EMU stabling lines CR/MRVC
![Page 91: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/91.jpg)
Implementing Agency for MUTP Phase II Works
• MUTP Phase II (b): R&R MMRDA 6th line BCT-Borivali WR Extension of Harbour Line MRVC (from Andheri to Goregaon) 5th & 6th line Diva-Thane MRVC 5th & 6th Line Kurla-CSTM CR Station improvement & trespassing control CR/WR
![Page 92: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/92.jpg)
6.
Afforestation &
Rainwater
Harvesting
1.
Social
Upgradation 2.
Introduction of
State of Art
Technology
3.
Passenger
Amenity
Upgradation
5.
Noise
Reduction
4.
Energy
Conservation
MRVC
![Page 93: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/93.jpg)
Progress of MUTP
Phase I Works
![Page 94: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/94.jpg)
Traction Sub Stations
Traction Transformer Installation Jogeshwari
Tower Errection Bandra Traction Transformer Foundation
Mahalaxmi
![Page 95: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/95.jpg)
Work at Various Sectioning Posts
Kandivali -Control Room Kandivali - Equipment Foundation
Goregaon - Control Room Goregaon - Equip Foundation & Cable trench
![Page 96: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/96.jpg)
Work at Various Sectioning Posts
Mahim -Control Room Mahim – Civil Engg Works
Mahim - Control Room inside Mahim - Equipment Foundation
![Page 97: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/97.jpg)
Work at Various Sectioning Posts
VileParle Andheri
Santacruz Mumbai Central
![Page 98: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/98.jpg)
Work at Various Sectioning Posts
Goregaon -Control Room Andheri - Equipment Foundation
Kandivali - Control Room inside Mahim - Equipment Foundation
![Page 99: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/99.jpg)
Cable Laying – Through winching
![Page 100: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/100.jpg)
Joint Chamber for making 110 kV Cable Joint
Cable Joint Chamber
![Page 101: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/101.jpg)
Joint Chamber for making 110 kV Cable Joint
Inside view of Cable Joint Chamber
![Page 102: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/102.jpg)
AFTC
Equipment
World Bank Team’s
inspection at Atgaon
![Page 103: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/103.jpg)
Digital Axle Counter Panel at Badlapur
First Station on Mumbai Suburban Section with only Digital Axle Counters
for vehicle detection
![Page 104: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/104.jpg)
Digital Axle Counters Kalyan 1st July 08
Submerged Tracks DAC Working
Train arriving PF 4 DAC still Working
![Page 105: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/105.jpg)
Box Pushing Work in Progress at WEH
![Page 106: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/106.jpg)
Box coming out at other end at WEH
![Page 107: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/107.jpg)
Girders placed in position for carriageway at WEH
![Page 108: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/108.jpg)
2nd Phase of Road commissioned
Extended Bridge
![Page 109: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/109.jpg)
Earthwork in progress at approach to the Mithi River Bridge
![Page 110: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/110.jpg)
Piling in progress for approach retaining wall
![Page 111: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/111.jpg)
Approach retaining wall under construction
![Page 112: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/112.jpg)
Fabrication of gantry for unobstructed piling work in Mithi River
![Page 113: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/113.jpg)
Dahanu Road FOB commissioned
![Page 114: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/114.jpg)
Vaitarna launching of FOB girder in progress
![Page 115: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/115.jpg)
DRD yard remodelling for new goods shed
![Page 116: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/116.jpg)
New Goods Shed at DRD commissioned
![Page 117: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/117.jpg)
Geo textile being laid
![Page 118: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/118.jpg)
Hydraulic stitcher for Prefabricated Vertical Band Drains
![Page 119: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/119.jpg)
PVD Band Drains
![Page 120: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/120.jpg)
Track Machines
![Page 121: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/121.jpg)
Improvements to Marine Lines and Charni Road stations
• The report for improvement for Marine Lines and Charni Road stations on Western Railway has been finalized by the National Institute of Design, Ahmedabad.
• Western Railway has sent the proposal to Railway Board.
![Page 122: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/122.jpg)
Pathway with Galvalume roof Pathway with Ferrari Technical Textile roof
Entrance
Proposed look and feel of the stations
![Page 123: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/123.jpg)
Proposed look and feel of the stations
![Page 124: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/124.jpg)
Proposed look and feel of the stations
![Page 125: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/125.jpg)
Proposed look and feel of the stations
![Page 126: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/126.jpg)
Construction of world-class station
at Carnac Bunder (CSTM)
• The report for construction of world-class station and commercial development at Carnac Bunder has been submitted by the consultant.
• The report has been sent to Railway Board.
![Page 127: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/127.jpg)
Carnac Bunder
![Page 128: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/128.jpg)
Carnac Bunder
![Page 129: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/129.jpg)
Carnac Bunder
![Page 130: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/130.jpg)
Carnac Bunder
![Page 131: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/131.jpg)
Carnac Bunder
![Page 132: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/132.jpg)
Carnac Bunder
![Page 133: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/133.jpg)
Carnac Bunder
![Page 134: Presentation on Mumbai Urban Transport Projectaitd.net.in/pdf/8/3. Mass Urban Transport Project.pdf2nd September 2008 Presentation on Mumbai Urban Transport Project Dr. P. C. Sehgal](https://reader035.fdocuments.us/reader035/viewer/2022063000/5f0d99b57e708231d43b28b4/html5/thumbnails/134.jpg)
Website:www.mrvc.indianrail.gov.in