Presentation on Benchmarking

download Presentation on Benchmarking

of 39

Transcript of Presentation on Benchmarking

  • 8/13/2019 Presentation on Benchmarking

    1/39

    PRESENTATION ON

    BENCHMARKING

  • 8/13/2019 Presentation on Benchmarking

    2/39

  • 8/13/2019 Presentation on Benchmarking

    3/39

    PATH AHEAD

    Selection of peer organisations for BBGS plant

    We selected Plant Load Factor (PLF) to be the key parameteron which to select the best organisation

    A list of Thermal Power Stations were made having PLF greater than 90% in 2003-04. They are :

  • 8/13/2019 Presentation on Benchmarking

    4/39

    PATH AHEAD (Contd)

    Name of Station Capacity (MW) State PLF (%) Dahanu 500 (2x250) Maharashtra 98.3

    Kothagudem V 500 (2x250) Andhra Pradesh 92.2 GSECL (G5) 210 Gujarat 91.7

    GHTP 420 (2x210) Punjab 91.6 Vijaywada 1260 (6x210) Andhra Pradesh 91.3

    Mettur 840 Tamil Nadu 91.3 Rihand 1000 Uttar Pradesh 90.6

    Rayal Seema 420 Andhra Pradesh 90.3 AE Co 60 Gujarat 90.1

    List of Thermal Power Stations having PLF >= 90%

  • 8/13/2019 Presentation on Benchmarking

    5/39

  • 8/13/2019 Presentation on Benchmarking

    6/39

    PATH AHEAD (Contd)

    In the list, Vijaywada and Kothagudem V belongs to APGENCO Both Vijaywada and Kothagudem V were consistently winning

    prestigious awards presented by the Government of India

    Vijaywada Thermal Power Plant has won the Meritorious ProductivityAward for twenty consecutive years and Incentive Award for elevenconsecutive years

    Kothagudem Thermal Power Plant V has won the MeritoriousProductivity Award and Incentive Award for four consecutive years

    These two plants were selected for initial visits

  • 8/13/2019 Presentation on Benchmarking

    7/39

    Meritorious Productivity Award

    An award given by the Government of India against therating given for performance during peak hours

    Incentive Award

    An award given by the Government of India for Efficient& Economic operation

  • 8/13/2019 Presentation on Benchmarking

    8/39

    Under the category of Meritorious Productivity Awards, the gold medal isgiven to power stations for generation of more than 7500 units/kW/year,the silver medal for generating 7100 to 7500 units/kW/year and bronzemedal for 6600 to 7099 units/kW/year.

    Shields are given for generating 6000 units/kW/year or more. These awardsare therefore an indicator of the efficiency of the power plant.

    Meritorious productivity awards were introduced in 1983 and are given onfinancial year basis

    The incentive scheme for lowering of specific fuel oil consumption andauxiliary power consumption was started in 1992 and is given on calendar

    year basis.

  • 8/13/2019 Presentation on Benchmarking

    9/39

    Parameters based on which

    the study will be conducted are:

  • 8/13/2019 Presentation on Benchmarking

    10/39

    LIST Main Plant Operation Plant Load Factor

    Plant Availability Factor Specific Coal Consumption Specific Oil Consumption Auxiliary % % DM Make-up Unit Outages Combustibles in Ash

    Heat Rate Cost of Unit

    Fuel and Fuel Handling Plant Maintenance Philosophy Spares Management Environment Administration

  • 8/13/2019 Presentation on Benchmarking

    11/39

    KEY FINDINGS Both the plants are having enviable records of performance

    PLF is high in both plants as the demand for power in Andhra Pradeshis more than supply. Seasonal effect is also absent.

    PAF is high in both plants (> 95%) because of tight overhaul schedule(12 15 days)

    Annual overhaul of units is totally outsourced and is done on job- contract basis

    Demurrage paid to railways is almost zero

    Combustibles in Fly Ash is less than 0.7% and that in Bottom Ash isless than 4%

    Steam Leak Detectors are installed in the boilers of both plants

  • 8/13/2019 Presentation on Benchmarking

    12/39

    Visit to Bakreswar,WBPDCL Visit was also undertaken to Bakreswar Power Plant(3x210 MW) of WBPDCL in West Bengal.Although PAF is greater than 90%, PLF is comparativelylow (78.36% in 2003-04) because of low system demand

    The plant has paid zero demurrage to the railways sinceinception in 1999

    Combustibles in Fly Ash is between 0.5 to 0.7% and thatin Bottom Ash is between 1 to 2%Steam Leak Detectors are installed in all the boilers ofthe plant

  • 8/13/2019 Presentation on Benchmarking

    13/39

    Visit to Tata Power, Trombay

    We next selected Tata Power (Trombay)(150+180+2x500MW) Thermal Power Station

    The units run in coal, gas and oil

    Unit 5 (500 MW) runs mainly on imported coal but can be runwith oil and gas too

  • 8/13/2019 Presentation on Benchmarking

    14/39

    KEY FINDINGS

    Turbine overhaul is carried out wholly byM/s Siemens while M/s UCC carries out theboiler overhaul. The parties themselves hire

    all the contract personnel engaged in the job Improvised forced cooling method to reduceoutage hours

    Coal is imported from Indonesia

  • 8/13/2019 Presentation on Benchmarking

    15/39

    Improvised forced cooling method

    After a forced shutdown (e.g. tube leakage of boiler), the boiler isvented to atmosphere and the drum metal temperature comes downto maximum 110 deg C within 5 hours. This is achieved by keeping theHP & LP bypass of the turbine open while forced cooling by draughtfans is also being carried out. Maximum difference that occurs

    between top and bottom drum metal temperature is 70 deg C After about 12 hours of shutdown, when turbine inner casingtemperature is about 370 deg C, the barring gear is stopped,lubricating oil pumps are stopped, jacking oil pump continues to run

    and blanking of pipelines to the generator bearings is carried out(process takes about 15 min).The generator is now decoupled from the turbine. During thedecoupling process, hand barring is being done regularly. By this

    process, the generator overhauling job can be start from the second

    day itself, thereby saving time.

  • 8/13/2019 Presentation on Benchmarking

    16/39

    Outstanding practices After the visits, following actions were aimed to beimplemented in Budge Budge Generating Station :

    Reduction in Demurrage paid to the railways

    Reduction in Combustibles in Fly and Bottom Ash Installation of Tube Leak Detection System

  • 8/13/2019 Presentation on Benchmarking

    17/39

    REDUCTION IN DEMURRAGE STEPS TAKEN

    A time study of the coal unloading operation

    National Productivity Council was entrusted with the job.SUBSEQUENTLY

    For BOBR rakes : Tare weighment discontinued in line with the loading end.Manpower for unloading was increased

    2 shunting engines hired to decrease time for shunting of wagons

    Coal flow during unloading was increased by running two chains

    Incentive scheme introduced for unloading of BOX N rakes

  • 8/13/2019 Presentation on Benchmarking

    18/39

    IMPROVEMENTS

    BOBR BOX N BOBR BOX N 2003 - 04 265 348 3.75 13.42 2004 - 05 313 340 4.06 13.63 2005 - 06 411 334 2.79 10.70

    Number of Rakes Average Unloading

    Time (Hrs)

  • 8/13/2019 Presentation on Benchmarking

    19/39

    IMPROVEMENTS

    BOBR BOX N BOBR BOX N 2003 - 04 265 348 3.75 13.42 2004 - 05 313 340 4.06 13.63 2005 - 06 411 334 2.79 10.70

    Number of Rakes Average Unloading

    Time (Hrs)

    Real decrease in Average Unloading Time observed in 2005-06when all the steps discussed before were implemented

  • 8/13/2019 Presentation on Benchmarking

    20/39

    REDUCTION OF COMBUSTIBLES IN

    ASH

    The average figures for combustibles in Fly and Bottom Ash in ourbenchmarked stations was 0.7 & 4% respectively But this was for Tangential firing boilers

    No data was available for Double Down Shot type boilers

    So it was decided to benchmark the Design Heat Loss figure of2.5% as stated by OEM in their design considerations

  • 8/13/2019 Presentation on Benchmarking

    21/39

    REDUCTION OF COMBUSTIBLES IN

    ASH

    STEPS TAKEN

    Optimisation of Boiler Total Air Flow for maximum

    efficiency

    Implementation of Boiler Auto Combustion Control for proper distribution of Primary & Secondary Air

  • 8/13/2019 Presentation on Benchmarking

    22/39

    IMPROVEMENTS

    Fly Ash Bottom Ash 2003 - 04 3.96 8.91 2004 - 05

    2.65 8.79 2005 - 06 2.13 6.26

    Combustible % in

  • 8/13/2019 Presentation on Benchmarking

    23/39

    IMPROVEMENTS

    Fly Ash Bottom Ash 2003 - 04 3.96 8.91 2004 - 05 2.65 8.79 2005 - 06 2.13 6.26

    Combustible % in

  • 8/13/2019 Presentation on Benchmarking

    24/39

    INSTALLATION OF TUBE LEAK

    DETECTION SYSTEM

    Boiler Tube leak detection system based on Acoustictechnology have been installed in one unit of BudgeBudge Generating Station. Installation in the otherwill be done after checking the effectiveness of thisone.

  • 8/13/2019 Presentation on Benchmarking

    25/39

    Visit to Dahanu,Reliance Energy

    Dahanu (2x250MW) Thermal Power Station of RelianceEnergy Ltd

    Dahanu was selected as one of the Top Plants of the World 2004 by platts Power, USA amongst 12 short listed power

    plants

    For FY 2004-05, its PLF was 101.35% (a feat unequalled till

    date), Loading Factor 104.61% and Auxiliary 7.53%

  • 8/13/2019 Presentation on Benchmarking

    26/39

    KEY FINDINGS Plant Load Factor greater than 100%

    Loading Factor more than 100% (achieved by running the T/Aat 262 MW with name plate capacity of 250 MW)

    Auxiliary % was only 7.53

    Statutory Overhaul of Boiler carried out in 12 15 days,Turbine overhaul is contracted out to BHEL

    Coal stock maintained > 3.5 lakh Te (1.8 lakh Te washed coalfrom Korba and 1.7 lakh Te imported coal)

  • 8/13/2019 Presentation on Benchmarking

    27/39

    Benchmarking BBGS, CESC Limited and Dahanu, Reliance Energy

    BENCHMARKED PERFORMANCE FIGURES

    PLF to be 100% PAF to be > 95 %Auxiliary power consumption to be 7.5%

    Statutory Overhaul period for boiler to be completedwithin 11 days in phases Minimum ground coal stock 1.0 Lakh tonnes

  • 8/13/2019 Presentation on Benchmarking

    28/39

    INCREASE OF BBGS PLF TO 100%

    To achieve this, BBGS units have to be operated at a loadmore than its rated capacity of 250 MW 262 MW wasdecided as all technical parameters remained within limits

    at that load Statutory overhaul period will have to be limited to 1215days

    Seasonal as well as daily variation of load in CESCs system will have to be flattened out through increasedexport of power

  • 8/13/2019 Presentation on Benchmarking

    29/39

    INCREASE OF BBGS PAF

    Forced outages of units have to be minimum

    Statutory overhaul period will have to be limited to 1215days Necessary planning of survey activities from freshangle and procurement of sky-climber may facilitate this

  • 8/13/2019 Presentation on Benchmarking

    30/39

    IMPROVEMENTS IN PLF & PAF

    PLF (%) PAF (%)

    2003 - 04 79.85 91.73

    2004 - 05 86.40 92.74

    2005 - 06 99.61 97.47

  • 8/13/2019 Presentation on Benchmarking

    31/39

    IMPROVEMENTS IN PLF & PAF

    PLF (%) PAF (%)

    2003 - 04 79.85 91.73

    2004 - 05 86.40 92.74

    2005 - 06 99.61 97.47

  • 8/13/2019 Presentation on Benchmarking

    32/39

  • 8/13/2019 Presentation on Benchmarking

    33/39

    IMPROVEMENTS IN PERIOD OF

    OVERHAUL

    PERIOD OF STATUTORYOVERHAUL (DAYS)

    2003 - 04 30.6 2004 - 05 30.7

    2005 - 06 11.3

  • 8/13/2019 Presentation on Benchmarking

    34/39

    REDUCTION OF BBGS AUXILIARY% PLF will have to be increased to 100%

    Forced outages of units have to be minimum Dahanu has open circuit cooling system whereas BBGS havecooling towers.

    Dahanu has wet Fly Ash Conveying System whereas BBGS havedry Fly Ash Conveying System

    these inherent differences in design restricts BBGS from

    reaching Dahanus level of Auxiliary% Various options to reduce auxiliary will have to be explored

  • 8/13/2019 Presentation on Benchmarking

    35/39

    REDUCTION OF BBGS AUXILIARY% STEPS TAKEN

    Reduction in Differential pressure across Feed ControlStation led to lower BFP discharge pressure and lowerspeed. Hence a reduction in power consumed is effected.

    Logic modification carried out in ID Fan Vane Controlwith speed. The suction vane now opens more in the sameload thus causing lower speed and lower powerconsumption.

    Service Air pressure is reduced from 7 kg/sq cm to 6kg/sq cm. As a result one compressor is now enough tosupply the whole requirement compared to two before

  • 8/13/2019 Presentation on Benchmarking

    36/39

    IMPROVEMENTS IN AUXILIARY %

    Auxiliary (%)

    2003 - 04 9.04 2004 - 05 8.69 2005 - 06 8.32

  • 8/13/2019 Presentation on Benchmarking

    37/39

    IMPROVEMENTS IN AUXILIARY %

    Auxiliary (%)

    2003 - 04 9.04 2004 - 05 8.69 2005 - 06 8.32

  • 8/13/2019 Presentation on Benchmarking

    38/39

  • 8/13/2019 Presentation on Benchmarking

    39/39

    Indian Thermal Power Plants (Source CEA)