May 2018
El Dorado International Airport.El DoradoAeropuerto Internacional El Dorado
ABOUT ODINSA
We are a Colombian concession company that belongs to Grupo Argos, dedicated to the structuring, promotion, management and development of
roadway and airport infrastructure projects, having a presence in Colombia, Ecuador, Aruba and Dominican Republic, which has become a vehicle for
regional connectivity and a source of development.
• Balance, support and
standards of corporate
governance.
• We are Grupo Argos’ mid-
term growth commitment.
• Structural position of the
industry in Colombia and
timely stake in profitable
assets abroad.
• Proper mix of mature assets
and projects that provide
stability.
• Assets majority stakes.
• Privileged position to benefit
from the potential growth of
the infrastructure sector.
• Counter-cyclical industry and
promoter of economic
growth, with institutional
structure and state support.
• Revenue amounted to COP
813 thousand million as of
December 2017.
• EBITDA margin of 63.38% as
of December 2017.
• Net leverage2: 2.99x as of
December 2017.
COMPANY OF GRUPO ARGOS ROBUST AND DIVERSIFIED
PORTFOLIO OF ASSETS AND
PROJECTS
LEADER IN ROADWAY AND
AIRPORTS CONCESSIONS IN
COLOMBIA1
FINANCIAL STRENGTH
TO MANAGE
RISKS AND TO GROW
1 Revista Dinero (Colombian Economic Journal), July 2017, leader in profits in the concessions sector. 2 Net leverage = net debt/EBITDA
HIGHWAYS AND
AIRPORTS ROBUST
PORTFOLIO
ROADWAY CONCESSIONS
Odinsa Grupo Argos Other
AIRPORT CONCESSIONS
Aeropuerto Internacional El Dorado Aeropuerto Internacional Mariscal Sucre
Autopistas del Café Conexión Pacífico 2 Boulevard Turístico del Atlántico Malla Vial del Meta
Green Corridor Autopistas del Nordeste
Colombia Colombia Colombia
Colombia Aruba
Dominican Republic
Dominican Republic Ecuador
Non-controlling interests in Mariscal Sucre (Quito) and El Dorado (Bogota) airports.
OUR CONCESSIONS
Roadway concessions in operation3
Concessions under construction3
Airport concessions2
FINANCIAL STRENGTH
- Change
(Margin)
Income Costs, expenses,
and other incomeOperating profit Ebitda Controlling net
income
Net margin
✓ Fraud, bribery and corruption risk management policy
✓ Self-regulation and money laundering and financing of terrorism risk management policy
✓ Policy for relations between related companies
✓ Data protection policy
✓ Gifts and tokens of appreciation policy
POLICIES
CODES
✓ Code of Good Governance
✓ Code of Business Conduct.
COMMUNICATION CHANNELS
✓ Transparency line
✓ Annual statement of potential sources of conflict of
interest
CORPORATEGOVERNANCE
Annual statement ofpotential sources ofconflicts of interest
Code of Good Governance
Code ofConduct
Transparencyline
HIGH STANDARDS OF CORPORATE
GOVERNANCE
We aim at generating shared value for our stakeholders, responsibly managing our impacts,fostering development, competitiveness and people’s connection; and managing risks andbuilding on opportunities for the business.
• Measurement of the carbon and water footprints in Odinsa and its concessions• We conducted materiality analysis, giving priority to economic, environmental and social
issues in which we must work with greater focus.• We structured our sustainability plan for the 2017-2019 period.
Highlights of 2017 management
GOOD SUSTAINABILITY PRACTICES
Opinion-makers:
Media /Opinion leaders
/ Academia
Business and social
associations
Unions / companies
from the sector /
Associations / NGO
Employees:
Odinsa and
Concessionaires
Authorities
Investors:
Long-term funders / Banking
/ Financial sectorSuppliers Communities Users
Leadership that inspires and motivates people to achieve the major business challenges and to experience values.
Collaborative work as the main source of knowledge strengthening.
Innovation as differentiator to leave an imprint wherever we have operations.
HIGHLY QUALIFIED AND
COMMITTED TALENT
ROBUST AND DIVERSIFIEDPORTFOLIO OF ASSETS
Autopistas del Café
Relevant Figures
First generation concession, with a rating of 4.59 in a 5-scale in the evaluation of the status index of roads given on concession.
General information
✓ Concession with guaranteed minimum income.✓ Beginning and end of activities: January 1999 to January 2027.✓ Road corridor of 270.2 km.✓ 7 toll stations, 3 customer care centers, 1 operational control center
and 1 weighing station.✓ The project currently has no long-term debt.
Project location
EBITDAMillion of COP
2015 2016 2017
46,788
62,491
80,351
Total TrafficThousands of Vehicles
2012 2013 2014 2015 2016 2017
9,77710,580
11,32812,147 12,544 12,770
Roadway concession in operation: Autopistas del Café
Relevant Figures
During 2017, the first disbursement of the structured funding was achieved under the "project finance” mode. Currently, the work progress is close to 30%. The estimated date for the commissioning of all UF is October 10 of 2020.
General information
✓ 98Km; Construction: La Pintada - Bolombolo (44 km) and maintenance: La Pintada - Primavera (54 km).
✓ PPP of public initiative(4G - with forecast budgets and collecting rights). ✓ Contractual milestones: (i) Awarded May 22, 2014; (ii) Certificate of
commencement: November 11, 2014. ✓ 100% of environmental licenses approved, certificate of non-presence of
communities, 30% of the project execution. ✓ Financial closure was completed and the first disbursement of the senior
debt was carried out in 2017.
Project locationEBITDA
Million of COP
2015 2016 2017
307
9,677
27,684
Total TrafficThousands of Vehicles
2015 2016 2017
2,2222,276
2,489
Roadway concession under construction: Conexión Pacífico 2
Relevant Figures
The project has not begun yet because of substantial changes in the traffic forecast. The arbitration court with ANI is under way, which is expected to be solved in the third quarter of 2018.
General information
✓ PPP of Private Initiative (without government resources). ✓ Awarding April 9 2015, signing of the contract: May 5 and the
certificate of commencement on June 9, 2015. ✓ Subject of the Contract: (i) Granada corridor - Villavicencio - Puerto
López - Puerto Gaitán - Arimena Bridge. ii) Ring Road of Villavicencio and accesses to the city - Meta Road Network.
✓ 354 km, 6 toll stations (5 existing toll stations, plus a new one).✓ Financial closure is scheduled for January 2019.
Project location EBITDAMillion of COP
2015 2016 2017
4,154
1,665
(1,782)
Total TrafficThousands of Vehicles
2015* 2016 2017
4,240
6,7506,570
* Only 7 months are taken into account, since the concession starts in June 2015
Roadway concession under construction: Malla Vial del Meta
Relevant Figures
ADN is a roadway concession located in the Dominican Republic that is currently in operation and maintenance phase. The scope of the contract is design, financing, construction, operation and maintenance for a term of 33 years.
General information
✓ Contract Law, approved by the Legislative Chambers and ratified by the President.
✓ Guaranteed minimum income. ✓ Awarded on July 18, 2001. The works were completed on June 30, 2008.
Concession will end in 2041.✓ Contract to 30 years of operation, 107 km, 3 tolls.✓ Financed through issuing bonds for USD162 million, under Regulation
144-A of the US. The debt balance is USD147 million and ends in April of 2024.
Project location EBITDAMillion USD
2015 2016 2017
26 25
49
Total TrafficThousands of Vehicles
2013 2014 2015 2016 2017
2,754 2,959
3,906
3,5153,754
Roadway concession in operation: Autopistas del Nordeste
Relevant Figures
BTA is a roadway concession in the Dominican Republic that is in operation and maintenance phase. It was awarded in 2001, with second stage in 2009, and works were completed in 2011.
General information
✓ The investment value of the project was USD180 million.✓ The road has 123.51 km, of which 104.81 km correspond to
rehabilitation and 18.7 km to construction. ✓ Guaranteed minimum income.✓ Financial closure with multilateral entities by USD151.1 million to 15
years. ✓ The current debt of the project is USD112.8 million and ends in
November 2024.
Project location EBITDAMillion USD
2015 2016 2017
29 24 29
Total TrafficThousands of Vehicles
2013 2014 2015 2016 2017
1,1131,272
1,3491,355 1,375
Roadway concession in operation: Boulevard Turístico del Atlántico
General information
Green Corridor is a roadway concession in Aruba which is currently in the construction phase. Works are expected to be completed and operation is expected to start in the second quarter of 2018. It would start to receive revenues during the third quarter of 2018.
✓ Contract of DBFM (Spanish acronym that stands for design, construction, financing and maintenance) contract.
✓ Income for the road availability, there are no tolls. ✓ Awarded in July 2015. Term: 18 years from the time of road availability.✓ 95% of progress in the construction of the project.✓ CAPEX of USD58.05 million.✓ Senior debt of USD58.7 million and equity of USD20.03 million. ✓ The availability period is expected to start in the second quarter of
2018, once the documentation related to the project and some landscaping aspects of the work are completed.
✓ The concession holder’s obligations after the beginning of the availability period are as follows:
✓Maintenance of the entire infrastructure.✓ Control of environmental conditions and air quality.✓Monitoring of the quality standards of works.
Project location
Roadway concession under construction: Green Corridor
15.8 17.4 19.1 20.8 21.3 20.6
Passengers who travel through the airportMillion Passengers
2012 2013 2014 2015 2016 2017
22.525.0
27.430.0 31.0 30.9
6.77.6
8.49.2 9.8 10.4
Relevant Figures
El Dorado, operated by Opain, was awarded with Skytrax 4-star rating as the best airport in South America. In 2017, 6 contact positions started and more than 25,000 m2 were commissioned to improve the passenger experience. Capacity increased to 40 million passengers.
General information
✓ The concession contract signed in September 12, 2006 for constant COP1,062 million in 2005 .
✓ Third airport in Latin America by number of passengers and first airport in Latin America by cargo movement. Close to 32 million passengers in 2017.
✓ Purchase of 30% was improved by Grupo Argos in the first quarter of 2017.✓ The expansion works of the National and International terminal were
completed in 2017, increasing the terminal built area to 223,700 m2.✓ Current debt balance is USD368.2 million, plus COP300.8 thousand million.
Aeropuerto Internacional El DoradoBogotá, Colombia
EBITDAMillion of COP
2015 2016 2017
217,693
265,121
280,943
International
National
Airport concession: Opain – Aeropuerto Internacional El Dorado
Relevant Figures
In December 2015, Odinsa Holding completed the acquisition of 50% of the company that owns 93% of the economic rights of Mariscal Sucre Airport concessionaire in Quito (UIO), Ecuador. This concession is valid until 2041.
General information
✓ Operations started on February 20, 2013.✓ Strong domestic travel market with 98% origin-destination of Quito Capital.✓ It is designed with a flexible structure of the runway and in the passengers and
cargo terminal facilities that allow adapting to growth. ✓ The acquisition was made through Marjoram Riverside Company (BVI), a
company controlled by Odinsa Holding Inc, Odinsa subsidiary.✓ The current debt balance is USD100 million and ends in 2020.
Aeropuerto Internacional Mariscal SucreQuito, Ecuador
EBITDAMillions of US$
2015 2016 2017
116 107106
3.5 3.4 3.3 3.0 2.72.2
Passengers who travel through the airportMillion Passengers
2012 2013 2014 2015 2016 2017
5.3 5.4 5.6
2.7
5.4 4.94.9
1.8 2.1 2.32.4
2.1
International
National
Airport Concession: Quiport - Aeropuerto Internacional Mariscal Sucre
Conexión Pacífico 2