ZORROTZAURREPublic-private partnership
for a new flood-proof district
2008
FutureNew opportunity space for the city
From an industrial peninsula to a creative island
839.000 m2 of surface.
A great city project
Public 51%Basque Government
40,4%
City Council 10,6%
Private 49%
Property
Social Housing Economical activities
Social Housing (higher price)
Productive
Free housing Private facility
Public facility
Mixed usesresidential, economical activities and public facilities
Residential 74 %5.473 housing units
50% socials
Economical activities 26 %
Looking to the future, but preserving our past
Memory
Mitigation of climate change
Decontamination Accessibility
Investment attraction
Mixture of uses
Preserving the memory Restoration of 320 houses Rehabilitation of 20 industrial buildings Relocation of previous existing activities
‘Downtown’of Zorrotzaurre
Preserving the memory
6,6 M€ invested in public subsidies for the restoration of the existing houses (56% of the real cost). 164 houses have already been benefited of this program.
Preserving the memory
Different elements of the dock lands and of the factorieswill be preserved in the urbanization of the promenades and parks, to maintain the industrial memory of the area.
A sustainable islandDecontamination and mitigation of climate change
Decontamination of 285.000m2 of polluted soils
1,3M€ financed by the European Union for this purpose.
The works have already started Decontamination
Mitigation of climate change
Zorrotzaurre is being transformed in an island (flood risk reduction)
100% electric public transport system Sustainable mobility. The buildings will be emission free as we
are proposing solutions based on geothermic and heat pumps.
A liveable island Accessible and attractive place to live
4 tram stations along the island, connecting with the central ring of the city
7,5km of driveways transformed in promenades 5.500 housing units, half of them social 12 spaces for facilities Job-training and university buildings Spaces for leisure and sports Green areas
An island conceived for pedestrians and public transport
An island where there is always something to do
An attractive island for investmentGreat space of opportunity for the city of Bilbao
It will be focused on priority sectors of Smart specialization for the city
Urban SolutionsKnowledge Intensive
Business Services(KIBS)
Tourism & Business Conventions
Digital Economy Technologies for health
Cultural and Creative Industries
CONSOLIDATE IT BASED ON
INNOVATION
BOOST A MORE ENTREPRENEURIAL
FOCUS
SUPPORT GROWTH AND THE CREATION OF A NEW BUSSINES
NET
Priority sectors to be developed intensively during the period 2017-2020
Urban Techno Park
Northern Techno Park
Southern Techno Park
Two different spaces are defined for an Urban Techno Park:
Southern Techno Park: 103.157 m2 to be built.
Northern Techno Park: 47.533 m2 to be built.
6.000 new jobs expected
SOUTHERN TECHNO PARK
NORTHERN TECHNO PARK
There will be 19 buildings.
Zone New Buildings Existing buildings
SOUTHERN TP 8 0
NORTHERN TP 7 4
TOTAL 15 4
20 industrial buildings for new uses
Currently 6 buildings have already the final use defined.
Papelera(University school)
Tarabusi (offices)
Beta 2(AS Fabrik European Project)
Lancor-Consonni(Business relocation)
IDOM Engineering Company
Beta 1(DigiPen University)
IMQ Zorrotzaurre, the biggest private clinic of the city (designed by the architect Carlos Ferrater)
New buildings
Urbanization project(1st stage)
New bridges
The Frank Gehrybridge is already built (Arenas and Asociates Eng.) and the bridge of San Ignacio (LKS Eng.) will be finished in 2019
Promenade between Elorrieta and Idom(right river bank of the canal)
• Pedestrian area: 520m long and 10m wide.
• Includes a pipe of 1,5 m of diameter and 350 m long to gather rain water while the tide is up
Actual situation of the river bank
Idom Engineering Company
New bridge
San Ignacio square
Playground
San Ignacio square (section)
Covered playground
Promenade in Ibarrekolanda(right river bank of the canal, middle part)
A promenade of 20 m wide will be built along the river bank.
It will be divided in two different levels. The second level will be 1,5m over the other, to preserve the houses from floods. New trees will be planted in the upper level
Actual situation of the river bank
Flood protection wallfor the Downtown of the island (1 m high)
• All the new buildings will be built at least 1,5 m over actual level of the island.
• Because of the length of the island (2,5 Km) and that all land is flat, a complex pumping system has been designed for the sewerage.
• To avoid the cross of the trash trucks along the island a pneumatic gathering system will be developed.
Rain water tanks (2.100 m3 each) with pumping and cleaning systems.The rain water will be used to water the gardens and clean the streets, and will protect the Downtown when the tide is up