Things to look for and remember while preparing FD05 Estimates
Preparing an Estimate
![Page 2: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/2.jpg)
The views expressed during this presentation do not necessarily reflect the views of KYTC.
This message is intended only for the use of the individual or entity to which it is addressed and may contain confidential information that is legally privileged and exempt from disclosure under applicable law. If the reader of this message is not the intended recipient, you are notified that any dissemination, distribution or copying of this communication is strictly prohibited. If you have received this communication in error, please notify this office by telephone and return this message to the original sender. Under Kentucky Rule of Evidence 503 this communication is confidential and not intended to be disclosed to third persons other than those to whom disclosure is made in furtherance of the rendition of professional legal services to the client, Kentucky Transportation Cabinet.
Legal Disclaimer
![Page 3: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/3.jpg)
http://transportation.ky.gov/Maintenance/Pages/Intranet/Roadway-Preservation.aspx
Drive the Project
Where to Start
![Page 4: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/4.jpg)
Print out a copy of the estimate sheet and summary sheets (most current version).
Make sure you have a measuring wheel.
Take your updated Route Log.
Has your DMI been calibrated recently?
Before You Hit the Road
![Page 5: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/5.jpg)
Measure the width in several locations per mile.
Don’t measure in curves, at mailboxes, or at entrances.
Note changes in Typical Section.
Drive the Project
![Page 6: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/6.jpg)
Is there striping? Centerline, Edgelines, etc.
Are there manholes, and who are the owners?
Are there pavement markers to be removed?Only replace on Interstates, Parkways, and
TWLTL’s
Are there bridges or culverts?Check with bridge section.
Things to look for
![Page 7: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/7.jpg)
EDGELINE RUMBLE STRIPS
![Page 8: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/8.jpg)
CENTERLINE RUMBLE STRIPS
![Page 9: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/9.jpg)
What types of shoulders are there?Are there drop-off that need correctingCan it be paved monolithic or separate
pavement wedge?
Is there curb and gutter?
Are there any RR Crossings?
Are there ADA compliant sidewalk ramps?
Things to look for
![Page 10: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/10.jpg)
Does the project have thermo to be replaced?Include quantities on summary sheets.
Are there traffic or planning loops affected?Include quantities on summary sheets.
Are there base failures that need repaired?Include quantities on summary sheets.
Things to look for
![Page 11: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/11.jpg)
![Page 12: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/12.jpg)
How do you know if it’s a base failure?
Deep crackingRutting / pumpingWater / mud coming out of cracksUsually located near edge of pavement
Base Failures
![Page 13: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/13.jpg)
What is this?
![Page 14: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/14.jpg)
What to do here?
![Page 15: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/15.jpg)
Used to correct out of section pavement.Correcting cross slopes, dips, etc.
Not a Scratch Course.
How much do you need?
Level and Wedging
![Page 16: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/16.jpg)
Ride the project
Visual survey
Usually calculated as a percentage of surface quantity.
Calculating Leveling and Wedging
![Page 17: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/17.jpg)
If the route needs more than 50% leveling and wedging, consider milling the entire route.
Helps to reduce pavement edge drop-offs.
Corrects existing rutting.
Re-defines pavement section.
How much is too much
![Page 18: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/18.jpg)
At Bridge ends and RR crossings.Usually 100 feet per 1 inch.
Curb and Gutter sections
Alternative to leveling and wedging.
Make sure milling depth is appropriate.
Milling
![Page 19: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/19.jpg)
TOO MUCH MILLING
![Page 20: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/20.jpg)
Cross slope problems
![Page 21: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/21.jpg)
Check intersections to see if needed.
Not for commercial entrances.
Include all bid items.
Is it technically feasible?If not, include documentation and pictures.
Sidewalk / Handicap Ramps
![Page 22: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/22.jpg)
ADA ramp, what to do here?
![Page 23: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/23.jpg)
![Page 24: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/24.jpg)
Do you see anything wrong?
![Page 25: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/25.jpg)
What to do here?
![Page 26: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/26.jpg)
What do you see?
![Page 27: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/27.jpg)
Input project data into estimate program.
Check all quantities for errors.
Verify pavement type against Warrants.
Pavement depth1.0”, 1.25” or 1.5” (District 1, 2, 3 only or SMA)
Back in the Office
![Page 28: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/28.jpg)
Complete typical sectionsOne typical for each pavement section.Use common sense.
Show detailsPavement typeDepthType of shouldersMilling if required
Typical Section
![Page 29: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/29.jpg)
![Page 30: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/30.jpg)
![Page 31: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/31.jpg)
What type is needed for this project?
Will night work or restricted hours be needed?
Are there dates where no lane closures will be allowed?Holidays, festivals, etc.
Will it be a significant project?Include Public Information Plan.Complete documents for TMP.
Traffic Control Plan
![Page 32: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/32.jpg)
Check Diana’s “commonly made mistakes” email.Did you need flashing arrows or message
boards?
Did you include Fuel and Asphalt adjustments?
Use comments section.
Don’t forget!
![Page 33: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/33.jpg)
Use Traffic Engineer to help with Thermo and Loop quantities and locations.
Check with Permits, Project Development, and HSIP Coordinator for conflicting projects.
Check with Bridge section if bridges are on the project.
Did you include all applicable notes?
Things to Remember
![Page 34: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/34.jpg)
Did you miss anything?
See it from a contractor’s view?
What will the inspector see?
Is there anything unexpected that you may have missed?
Drive the project again
![Page 35: Preparing an Estimate](https://reader035.fdocuments.us/reader035/viewer/2022062323/56816570550346895dd805be/html5/thumbnails/35.jpg)
Questions???