Variance Analysis
Chapter 7
![Page 2: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/2.jpg)
Variance Analysis Often performed separately for each of
the four manufacturing costs Direct labor variances Direct materials variances Variable manufacturing overhead variances Fixed manufacturing overhead variances
actual cost > standardUnfavorable Variance
actual cost < standardFavorable Variance
Are all favorable variances good?
![Page 3: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/3.jpg)
Causes of Labor Variances• Two causes
–Price (P)• Paid too much per hour or
paid less than expected per hour
–Quantity (Q)• Used too many DL hours
or used fewer DL hours than expected
![Page 4: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/4.jpg)
Labor VariancesP
Q
A S S
A A S
Labor Price (Rate) Variance
Labor Quantity (Efficiency) Variance
Rate per hour is more or less than
allowed.
Incurred too many or less than allowed
hours.
Total Labor Variance
Labor Price Variance +
Labor Quantity Variance
![Page 5: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/5.jpg)
Responsibility for Labor VariancesProduction supervisors
make work assignments, monitor the efficiency of
employees, authorize pay raises, and
terminate employees.
I am responsible for the labor rate and labor
efficiency variances.
![Page 6: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/6.jpg)
Causes of Material Variances• Two causes
–Price (P)• Paid too much or paid less
than expected for material per unit
–Quantity (Q)• Used too much or used
less than expected
![Page 7: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/7.jpg)
Isolation of Material Variances
I need to know as early as possible to make
product pricing or quantity changes
The material price variance is isolated at
the purchase date. Why?
As a purchasing manager,I need the price variance
sooner so that I can better identify purchasing problems.
Price Variance
Computed on the entire quantity purchased
Quantity Variance Computed only on the
quantity used
![Page 8: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/8.jpg)
Material VariancesPQ
A S S SA A A Sp up
Material Price Variance
Material Quantity Variance
Indicates if materials cost more or less per material
unit than allowed.
Indicates if more or less materials were
used.
Material Price Variance +
Material Quantity Variance
Total Material Variance
![Page 9: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/9.jpg)
Responsibility for Material Variances
I am not responsible for this unfavorable material
quantity variance. You purchased cheapmaterial, so my peoplehad to use more of it.
You used too much material because of poorly trained
workers and shoddy equipment maintenance,
and you are a lousy scheduler! You make me overnight the material
making it cost more, causing unfavorable price variances.
![Page 10: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/10.jpg)
Variable Overhead Variances
VOH Spending Variance
VOH Efficiency Variance
Actual VOH Cost
Actual DLH x
Std Rate
VOH Flexible Budget
Applied VOH
VOH Production Volume Variance
VOH Flexible Budget Variance
Total VOH Variance
VOH Production Volume Variance
This is the underapplied or overapplied variable overhead amount.
![Page 11: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/11.jpg)
Fixed Overhead Variances
FOH Spending Variance
FOH Efficiency Variance
Actual FOH Cost
FOH Static
Budget
FOH Flexible Budget
Applied FOH
FOH Production Volume Variance
FOH Flexible Budget Variance
Total FOH Variance
FOH Production Volume Variance
This is the underapplied or overapplied fixed overhead amount.
![Page 12: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/12.jpg)
Applied OverheadOverhead costs are applied to products and services
using a predetermined overhead rate (POHR).
Applied VOH = [VOHR × Actual Activity]
Applied FOH = [FOHR × Actual Activity]
Estimated VOHVariable OH rate = Estimated Activity Estimated FOHFixed OH rate = Estimated Activity
![Page 13: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/13.jpg)
Overhead Variance Responsibility
• Spending variances– Production supervisor – if he selects specific OH items– Purchasing manager – if he works with supplier on cost
• Efficiency variances– Production supervisor – controls use of overhead items
• Production volume variance– No one is responsible We know why it exists.– Exists because the volume of production/sales is
less/more than budgeted
![Page 14: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/14.jpg)
14
Predictable Variances Variances that always have zero balances
VOH production volume variance Amount allowed per activity on the flexible
budget is the same as the VOH applied FOH efficiency variance
It is not possible to reduce a FOH cost simply by being more efficient.
![Page 15: Prepared by Diane Tanner University of North Florida](https://reader035.fdocuments.us/reader035/viewer/2022062302/568164db550346895dd733fa/html5/thumbnails/15.jpg)
Behavioral ConsiderationsStandard costs and variance analysis can1) Provide very useful control
measures 2) Aid in performance
evaluations3) Cause dysfunctional
behavior among employees and managers