POINTS TO BE COVERED IN THE POINTS TO BE COVERED IN THE PROJECT REPORTPROJECT REPORT
Techno Feasibility ReportTechno Feasibility Report IntroductionIntroduction Executive SummaryExecutive Summary Complete details of all aspect of Complete details of all aspect of
projectproject ConclusionConclusion
TECHNO FEASIBILITY REPORTTECHNO FEASIBILITY REPORT
It is a summary of complete It is a summary of complete project, that provide information project, that provide information about the project in a glance.about the project in a glance.
It should cover all the major and It should cover all the major and vital information of the project.vital information of the project.
It should’nt cover more than 2 It should’nt cover more than 2 pages. pages.
INTRODUCTIONINTRODUCTION
The part of project constitutes of:The part of project constitutes of: PreamblePreamble Brief background of companyBrief background of company Background of entrepreneursBackground of entrepreneurs Location details of the projectLocation details of the project
EXECUTIVE SUMMARYEXECUTIVE SUMMARY
Executive summary is a important and Executive summary is a important and necessary part of a project report. It necessary part of a project report. It includes all the details which will includes all the details which will become part of a detailed project become part of a detailed project report but in summary form. It covers:report but in summary form. It covers: LocationLocation Proposed capacityProposed capacity Product mixProduct mix Technological arrangementTechnological arrangement Layout of Factory / plantLayout of Factory / plant
EXECUTIVE SUMMARY…EXECUTIVE SUMMARY…
Raw material requirement, storage Raw material requirement, storage and handlingand handling
Present and Future demand of end Present and Future demand of end productproduct
Plant and MachineryPlant and Machinery Pollution Control equipmentsPollution Control equipments Power and water supplyPower and water supply Capital CostingCapital Costing Other subsidiary requirements and Other subsidiary requirements and
ancillary facilitiesancillary facilities
ENTERPRENUER DETAILSENTERPRENUER DETAILS
QualificationQualification
Work experience in detailWork experience in detail
PRODUCT MIXPRODUCT MIX
Complete details ofComplete details of
End productEnd product Proposed productionProposed production
are to be given. are to be given.
TECHNOLOGICAL TECHNOLOGICAL CONSIDERATIONSCONSIDERATIONS
Technology used in domestic and Technology used in domestic and international market to produce international market to produce the end productthe end product
Merits and demerits of various Merits and demerits of various technology usedtechnology used
Technology proposed to be used in Technology proposed to be used in our project and reason for the our project and reason for the samesame
Details of complete process cycle Details of complete process cycle with process chartwith process chart
SITE DESCRIPTIONSITE DESCRIPTION
Site DetailsSite Details LocationLocation Connectivity through road, train, air Connectivity through road, train, air
etc.etc. Proximity of raw material sources and Proximity of raw material sources and
other vital facilitiesother vital facilities Reason to chosen the site.Reason to chosen the site.
PLANT LAYOUTPLANT LAYOUT
The part of the project report will The part of the project report will include the complete layout, include the complete layout, structure and various facilities to structure and various facilities to cater with the production.cater with the production.
The part must cover the layout The part must cover the layout map.map.
RAW MATERIALRAW MATERIAL
Name and chemical configuration, if Name and chemical configuration, if anyany
Physical RequirementsPhysical Requirements Chemical RequirementsChemical Requirements Availability in the marketAvailability in the market
RECEIPT, STORAGE & RECEIPT, STORAGE & HANDLING OF RAW MATERIALHANDLING OF RAW MATERIAL
Handling systemHandling system Feed systemFeed system Storage arrangements Storage arrangements
At godownsAt godowns At plantAt plant
Transportation arrangments Transportation arrangments
APPLICATION OF END APPLICATION OF END PRODUCTPRODUCT
Whether will be used in own plantWhether will be used in own plant Target marketTarget market
DomesticDomestic ExportExport
Industry details, where it is usedIndustry details, where it is used
ENVIRONMENTAL ASPECTSENVIRONMENTAL ASPECTS
Whether all environmental Whether all environmental clearance certificates required for clearance certificates required for the specific industry has been taken the specific industry has been taken and details of the same.and details of the same.
Arrangements to avoid pollution Arrangements to avoid pollution from the government specified from the government specified limits.limits.
WATER, POWER AND WATER, POWER AND AUXILLARY SERVICESAUXILLARY SERVICES
RequirementRequirement
Arrangement through government or Arrangement through government or private sourcesprivate sources
Alternative arrangementsAlternative arrangements
SUPPLEMENTARY FACILITIESSUPPLEMENTARY FACILITIES
Repairs and Maintenance facilitiesRepairs and Maintenance facilities Ventilation and air conditioning Ventilation and air conditioning
systemsystem Instrumentation & telecommunication Instrumentation & telecommunication Automation and Computer ControlAutomation and Computer Control Safety and fire protection Safety and fire protection
arrangementarrangement Hydrant SystemHydrant System
MARKET ARRANGEMNTSMARKET ARRANGEMNTS
This part of project report covers This part of project report covers complete market analysis of your end complete market analysis of your end product.product. in present in present in futurein future
It also covers the marketing strategy It also covers the marketing strategy customer is going to adopt in future, customer is going to adopt in future, to sell its products. to sell its products.
POLLUTION CONTROLPOLLUTION CONTROL
Arrangements to avoidArrangements to avoid Air PollutionAir Pollution Water PollutionWater Pollution Noise PollutionNoise Pollution
Arrangements for effluent disposalArrangements for effluent disposal
MANPOWER PALNNINGMANPOWER PALNNING
Category wise break up needs to be Category wise break up needs to be given:given: Senior ManagementSenior Management Technical staffTechnical staff Marketing StaffMarketing Staff Maintenance StaffMaintenance Staff Production staffProduction staff Quality Control StaffQuality Control Staff
MANPOWER PALNNING…MANPOWER PALNNING…
Estimated requirementEstimated requirement
Cost InvolvedCost Involved
Training arrangementTraining arrangement
Employee welfare arrangementsEmployee welfare arrangements
CONSTRUCTION PLANNINGCONSTRUCTION PLANNING
Month wise target is to be given for Month wise target is to be given for Each construction phaseEach construction phase
Erection of plant and machineryErection of plant and machinery
Commencement of commercial Commencement of commercial productionproduction
CAPITAL COSTCAPITAL COSTEstimated cost is to be given for each Estimated cost is to be given for each capital expenditure planned up.capital expenditure planned up. LandLand
Cost of landCost of landCost of site developmentCost of site development
Building Building construction costconstruction costInternal designing costInternal designing cost
Plant and MachineryPlant and MachineryCost of purchaseCost of purchaseErection and Commissioning Erection and Commissioning
chargescharges
CAPITAL COST…CAPITAL COST…
Other costOther costFurniture and FixturesFurniture and FixturesOffice EquipmentsOffice EquipmentsVehicles and Mobile equipmentsVehicles and Mobile equipmentsTechnical Know howTechnical Know howPreoperative expenditurePreoperative expenditureInterest during constructionInterest during constructionMargin for contingencies, etc.Margin for contingencies, etc.
MEANS OF FINANCEMEANS OF FINANCE
Equity ContributionEquity Contribution Existing Existing ProposedProposed
Borrowed FundsBorrowed Funds ExistingExisting ProposedProposed
FINANCIAL APPRAISALFINANCIAL APPRAISAL
Need to provide 8 years’Need to provide 8 years’ Capacity UtilisationCapacity Utilisation Balance SheetBalance Sheet Profit and Loss AccountProfit and Loss Account Cash Flow StatementCash Flow Statement
Break Even Point (BEP that means Break Even Point (BEP that means no profit no loss)no profit no loss)
FINANCIAL APPRAISAL…FINANCIAL APPRAISAL…
Calculation of Internal Rate of Calculation of Internal Rate of Return (IRR) on the basis of Return (IRR) on the basis of projected profitabilityprojected profitability
Calculation of Debt Service Calculation of Debt Service Coverage Ratio (DSCR)Coverage Ratio (DSCR)
Details of assumptions made to Details of assumptions made to prepare projected financialsprepare projected financials
Sensitivity Analysis – It is done to Sensitivity Analysis – It is done to check the profitability if any check the profitability if any projected targets not achieved.projected targets not achieved.
LIST OF DOCUMENTS NEED TO LIST OF DOCUMENTS NEED TO BE SUBMITTED WITH PROJECT BE SUBMITTED WITH PROJECT
REPORTREPORT Prescribe application form in Duplicate Prescribe application form in Duplicate Project Report in Duplicate Project Report in Duplicate List of total movable and immovable Assets of the List of total movable and immovable Assets of the
promoters. promoters. Income Tax and Wealth Tax details of last three Income Tax and Wealth Tax details of last three
years, with copies of Assessment / Return if years, with copies of Assessment / Return if applicable. applicable.
Provisional Registration Certificate from the Provisional Registration Certificate from the concerned District Industries Centre. concerned District Industries Centre.
Memorandum of Articles of Association and Memorandum of Articles of Association and Certificate of in corporation (in case of Company). Certificate of in corporation (in case of Company).
Certified copy of Registration Certificate issued by Certified copy of Registration Certificate issued by the Registrar of firms ( if partnership concern) if the Registrar of firms ( if partnership concern) if forms 'A' and 'C'. forms 'A' and 'C'.
LIST OF DOCUMENTS NEED TO BE LIST OF DOCUMENTS NEED TO BE SUBMITTED WITH PROJECT SUBMITTED WITH PROJECT
REPORT…REPORT… Registration with the Tourism Department, and Registration with the Tourism Department, and
the licence for eating house in case of Hotel the licence for eating house in case of Hotel Industry. Industry.
Permission/licence from Competent Authority (in Permission/licence from Competent Authority (in case of Textile, Drugs, Foods etc.). case of Textile, Drugs, Foods etc.).
Certified copy of sale deed in respect of land. Certified copy of sale deed in respect of land. (The land should be in the name of sole proprietor (The land should be in the name of sole proprietor / partner / company whichever applicable/ partner / company whichever applicable
OR OR Rent agreement in case of rented premises. Rent agreement in case of rented premises. Three quotation in respect of each item of plant Three quotation in respect of each item of plant
and machinery and raw material, proposed to be and machinery and raw material, proposed to be purchased. purchased.
LIST OF DOCUMENTS NEED TO BE LIST OF DOCUMENTS NEED TO BE SUBMITTED WITH PROJECT SUBMITTED WITH PROJECT
REPORT…REPORT… Details of power requirement and tie-up with Details of power requirement and tie-up with
State Electricity Board. State Electricity Board. Copy of instructions to your Bankers to give full Copy of instructions to your Bankers to give full
information about the concern on request to State information about the concern on request to State Financial Corporation. Financial Corporation.
Permission from Water Pollution Control Board. Permission from Water Pollution Control Board. Approved Building plan from Competent Authority Approved Building plan from Competent Authority
with cost estimates with cost estimates
SOME IMPORTANT FORMULASSOME IMPORTANT FORMULAS
Working CapitalWorking Capital
= Current assets – Current Liabilities= Current assets – Current Liabilities
Current Assets are Accounts Receivables, Current Assets are Accounts Receivables, inventory and cash bank balancesinventory and cash bank balances
Current Liabilities are Account payablesCurrent Liabilities are Account payables
SOME IMPORTANT FORMULASSOME IMPORTANT FORMULAS
Internal Rate of Return (IRR)Internal Rate of Return (IRR)
It is an annualised rate of return that It is an annualised rate of return that can be earned on invested capital.can be earned on invested capital.
IRR is calculated on the basis of IRR is calculated on the basis of Discounted Cash Flow MethodDiscounted Cash Flow Method
SOME IMPORTANT FORMULASSOME IMPORTANT FORMULAS
Debt Service Coverage Ratio (DSCR)Debt Service Coverage Ratio (DSCR)
= (Profit before Tax + Interest)/ = (Profit before Tax + Interest)/ (Principal repayment + interest)(Principal repayment + interest)
As a standard it should be two.As a standard it should be two.