Preparation for Circulating Beam - Part II
Collimators (40') Oliver Aberleo Breakdown of tests foreseen in preparation for beam
o Equipment folder: tests results, handling of non-conformities, performance below specs, machine as commissioned vs. machine as specified
o Piquet/Experts availability
With help and input from the members of the collimation team, especially fromAB / ATB: A. Masi, R. Chamizo,
ABP: T. Weiler, R. Assmann,OP: S. Redaelli,CO: M. Jonkers
TS/ ICC: J. CoupardTuesday 04 March 2008 1LTC Extended meeting
Tuesday 04 March 2008 2LTC Extended meeting
Related talks:
Session 3 - Possible injection into part of the machine, preparation for beam
Stopping the beam in a possible sector test (S. Redaelli)
Session 4 - Beam Plans for Accelerator Physics Systems
Collimators (R. Assmann)
Machine Protection (J. Uythoven)
Session 6 - Readiness of Controls
Collimator control (M. Jonker)
TCTVA.4R5.B2
Tuesday 04 March 2008 3LTC Extended meeting
Overview:
1. Status Production and Installation
2. Hardware Commissioning & Cold Checkout
3. HWC Procedure Defined and in MTF
4. Machine Protection Commissioning
5. Piquet/Experts availability
6. Summary
Tuesday 04 March 2008 4LTC Extended meeting
Overview:
1. Status Production and Installation
2. Hardware Commissioning & Cold Checkout
3. HWC Procedure Defined and in MTF
4. Machine Protection Commissioning
5. Piquet/Experts availability
6. Summary
Tuesday 04 March 2008 5
CERCA Production• All TCP and TCS collimators received, tested and installed.• All TCDI collimators received, tested and installed. Spares already received.• All TCT collimators received and tested. 9 (out of 30) collimators still to be installed.• Remaining production for 2008 installation (TCLP and TCS) or spares (TCP, TCS, TCT and TCLP).
LTC Extended meeting
Tuesday 04 March 2008 6
CERN Production• In total 15 special collimators produced at CERN.• Last for initial installation will arrive in week 11.
Collimator Quantity AvailabilityTCDD #1 1 week 39TCAPA 4 week51TCAPB 2 week 5TCAPC 2 week 8TCTVB #1 1 week 5TCTVB #2 1 week 7TCTVB #3 1 week 9TCTVB #4 1 week 11TCLIA #1 1 week 13TCLIA #2 1 week 15Two-beam collimator
Passive Absorber(TCAPA)
LTC Extended meeting
Tuesday 04 March 2008 7
Installation
LTC Extended meeting
• TCP, TCS and TCDI done.
• TCT and passive absorbers ready, last installation in week 12.
• First TCTVB in final bake-out, 3 more to finish.
• TDI in bake-out
• TCDD bake out launched.
Tuesday 04 March 2008 8LTC Extended meeting
Overview:
1. Status Production and Installation
2. Hardware Commissioning & Cold Checkout
3. HWC Procedure Defined and in MTF
4. Machine Protection Commissioning
5. Piquet/Experts availability
6. Summary
Tuesday 04 March 2008 9
Hardware Commissioning & Cold Checkout
Collaborative effort between several teams and groups. RWA, LHC MAC 12/07
LTC Extended meeting
Tuesday 04 March 2008 11
Deliverables• Outcome of the collimator hardware commissioning:
– Validation of single collimator, all relevant functionality– Settings and sensor readouts (position, temperature, switches,...) verified– Control of each collimator from CCC is declared “safe”– Machine protection functionality (without beam) partially established
• Cold checkout focused on:– Control an ensemble of collimators– Address timing and synchronization issues– Function-driven motion, “tracking” tests with other equipment– Establish full machine protection functionality without beam– Verify interfaces to other accelerator systems
• Beam loss monitors: configuration/acquisition of distributed system• Sequencer driven commands, machine modes• Verify logging of distributed systems (big data sets!)
– Consistency and sanity checks; global system status
LTC Extended meeting
Tuesday 04 March 2008 12LTC Extended meeting
Validation of single collimator, all relevant functionality
Tuesday 04 March 2008 13LTC Extended meeting
Validation of single collimator, acceptance up to installation
Tuesday 04 March 2008 14LTC Extended meeting
Validation of single collimator, manufacturing and operational data
The hardware commissioning of the collimators include all the tests that will be performed once the collimator is installed in the tunnel in order to validate their correct functioning. These include tests on infrastructure up to the base support, tests of the tunnel equipment, on the full system and with the collimator under vacuum.
Systems:TCL, TCLIA, TCLIB, TCLIM, TCT, TCTVB, TCLP, TCHSH, TCHSS, TCHSV, TCLA, TCAPx, TCP, TCSGRequirements:Commissioning 1 (C1, access needed): Collimator installed, cabling finished. Tests with cross check in tunnel (two teams).Commissioning 2 (C2, no access required): C1 + bake out terminated, under vacuum, water flow nominal. Remote tests (one team)Infrastructure:Power, light, Water cooling, Vacuum, Cabling, Collimator installed, Ethernet, GSM.
Tuesday 04 March 2008 15LTC Extended meeting
Hardware commissioning (HWC) COLLIMATORS
(ATB and Collimation project)
Tuesday 04 March 2008 16LTC Extended meeting
Planning provided by J. Coupard:
Related to:
-Bake out of sectors
-Access restrictions
-Water cooling
HWC
Tuesday 04 March 2008 17LTC Extended meeting
Planning provided by J. Coupard:
Commissioning 1 with access, commissioning 2 without access (if there are no problems)
HWC
Tuesday 04 March 2008 18LTC Extended meeting
HWC - Commissioning 1 (with access): 2 collimators per day / 2 teams- -Commissioning 2 (remote): 3 collimators per day / 1 teamsLast date: End of week 21
Tuesday 04 March 2008 19LTC Extended meeting
Overview:
1. Status Production and Installation
2. Hardware Commissioning & Cold Checkout
3. HWC Procedure Defined and in MTF
4. Machine Protection Commissioning
5. Piquet/Experts availability
6. Summary
Tuesday 04 March 2008 21
HWC Procedure Defined and in MTF
LTC Extended meeting
Support commissioning without collimator (Later installations, plug and play design)
Files created during the commissioning:
Annex 1Test Summary Low Level Control System Collimators
Annex 2 LVDTs calibration messages list
Annex 3LVDTs Calibration Report
Annex 4LVDTs Calibration file
Annex 5LVDTs noise measurements
Annex 6Auto retraction Report
Annex 7Mechanical Play report
Annex 8Gap-Axes LVDTs comparison report
Annex 9Errors on the execution of a typical LHC motion profile
Tuesday 04 March 2008 22
HWC Procedure Defined and in MTF
LTC Extended meeting
1.46 1.48 1.5 1.52 1.54 1.56 1.58 1.6 1.62 1.64 1.66
x 104
-10
-5
0Right Downstream Error (LVDT-Reference)
time(s)
mm
1.46 1.48 1.5 1.52 1.54 1.56 1.58 1.6 1.62 1.64 1.66
x 104
-0.05
0
0.05Reference Right Downstream
LHC Collimator 20 minutes Profiles Test Report
RWA, LHC MAC 12/07 23
HWC: Tracking Jaw PositionsSetting
Reading
50 mm
20 s
20 s
50 mm
Setting
Reading
10 mm
20 s
S. Redaelli
Tuesday 04 March 2008 24
Results in Collimation Project Web
LTC Extended meeting
E. Veyrunes (web page) and R. Billen and C. Roderick (DB support)
Tuesday 04 March 2008 25LTC Extended meeting
Overview:
1. Status Production and Installation
2. Hardware Commissioning & Cold Checkout
3. HWC Procedure Defined and in MTF
4. Machine Protection Commissioning
5. Piquet/Experts availability
6. Summary
Tuesday 04 March 2008 26
Machine Protection Commissioning
All machine protection functionality based on interlocks on position readings (redundancy).
Can be commissioned without beam.
Foreseen for March/April.
LTC Extended meeting
Tuesday 04 March 2008 27LTC Extended meeting
Overview:
1. Status Production and Installation
2. Hardware Commissioning & Cold Checkout
3. HWC Procedure Defined and in MTF
4. Machine Protection Commissioning
5. Piquet/Experts availability
6. Summary
Tuesday 04 March 2008 28
Piquet/Experts availability
LTC Extended meeting
• No piquet service foreseen
• Expert telephone list
• Depending on problem:
1. Disable collimator
2. Minor intervention (remotely, expert tool)
3. Intervention in tunnel (Failure: Stepping motors, Read-out (switches, LVDT), roller screw;limited intervention, preventive maintenance and monitoring;Impact: Few hours up to 2 days)
4. Collimator exchange (Failure: Important vacuum or water leak, mechanical damage;exchange collimator; Impact: Several weeks downtime, RP, transport, vacuum and bake out involved)
Tuesday 04 March 2008 29LTC Extended meeting
Overview:
1. Status Production and Installation
2. Hardware Commissioning & Cold Checkout
3. HWC Procedure Defined and in MTF
4. Machine Protection Commissioning
5. Piquet/Experts availability
6. Summary
Tuesday 04 March 2008 30
Summary
LTC Extended meeting
• Final installation in Week 17
• Transfer lines commissioned, to be finalized
• Point 5R commissioned (C1) with final procedure, special setup in Point 6 this week.
• Commissioning of sectors one by one is still feasible, but very tight
• Performance of phase 1 collimation system will by only assessed after the completion of the installation during the shut down 2008/09
• Piquet/Experts:-No Piquet service foreseen, first years of LHC operation will tell more-Experts phone list
More details: R. Assmann, Plan for Collimator Commissioning7/12/2007 - LHC MAC