Preliminary Method Statement
Transcript of Preliminary Method Statement
Luanda Oil Service Base Expansion Contract for Tender Submission
Quay Wall between Heavy Lift Dock and TCT Area Method Statement
Preliminary Method Statement for
Quay Wall between Heavy Lift Dock and TCT Area
1 / 36
Luanda Oil Service Base Expansion Contract for Tender Submission
Quay Wall between Heavy Lift Dock and TCT Area Method Statement
Table of Contents
1 General.............................................................................................................................3
1.1 Site Location............................................................................................................3
1.2 Scope of Work..........................................................................................................4
1.3 General Construction Flowchart..............................................................................5
2 Temporary Facilities.......................................................................................................7
3 Construction...................................................................................................................7
3.1 Dredging...................................................................................................................8
3.2 Rubble Bedding for Foundation Trench.................................................................10
3.3 Precast Counterfort units.......................................................................................15
3.4 Installation of Counterfort Units..............................................................................19
3.5 Backfilling Sand and Vibro-compaction.................................................................23
3.6 Demolition Works...................................................................................................24
3.7 Cast In-situ Capping Beam....................................................................................25
3.8 Drainage Culvert....................................................................................................28
3.9 Construction of Apron including Trench.................................................................28
3.10 Installation of Auxiliary Facilities............................................................................32
3.11 Placement of Anti-scour Protection........................................................................33
3.12 Fender Replacement and Concrete Repairs.........................................................35
2 / 36
Luanda Oil Service Base Expansion Contract for Tender Submission
Quay Wall between Heavy Lift Dock and TCT Area Method Statement
1 General
It is intended to construct a new quay wall at the Port of Luanda, Angola, currently
known as the Luanda Oil Service Centre. The project comprises the construction of
442.9m long quay wall identified on the drawings referred to in the Employer’s
Requirements, with cope at 3.35 m CD, having a design depth of -12.5m CD
including foundation works and anti-scour protection below -12.5m CD level, tying-
in with the existing quay walls and complete with navigation, berthing and mooring
equipment and provision of spare berthing equipment.
1.1 Site Location
The Project Site is located at the Port of Luanda, Angola, currently known as the
Luanda Oil Service Centre, as indicated in the following figures:
3 / 36
Luanda Oil Service Base Expansion Contract for Tender Submission
Quay Wall between Heavy Lift Dock and TCT Area Method Statement
Site Location
1.2 Scope of Work
The scope of the work required includes the following:
A. Construction of a new quay wall extension comprising:
A new 442.9m long quay wall identified on the drawings referred to in the
Employer’s Requirements, with cope at 3.35 m CD, having a design depth of -
12.5m CD including foundation works and anti-scour protection below -12.5m
CD level, tying-in with the existing quay walls and complete with navigation,
berthing and mooring equipment and provision of spare berthing equipment.
Dredging to lower the seabed in front of the quay wall to –12.5m CD and
disposal of spoil to a location to be agreed with the Employer within Luanda
Bay.
Removal of an existing pipe spooling jetty, piles along shoreline, small craft
quay and disposal of materials off site.
Such temporary works as may be required to maintain the integrity of the
existing quay walls, edge of TCT container yard, outfall channels and any other
structures earthworks during construction for the new quay wall.
Backfilling behind the quay wall using dredged sand material provided by the
Contractor. The Contractor shall be responsible to determine where sand
material can be obtained for the backfilling and shall obtain the necessary
approvals from the relevant authorities for the removal of sand. Backfilling shall
4 / 36
Luanda Oil Service Base Expansion Contract for Tender Submission
Quay Wall between Heavy Lift Dock and TCT Area Method Statement
follow the removal of slope protection material including piles and concrete
blocks along the shoreline close to the Contractor`s construction yard. The
slope protection rock material may be used in the works if suitable or elsewhere
at a price agreed with Sonils. This will be deducted from the Contractors
payment claims.
A paved quay apron 30 m wide behind the new quay wall and the ends of the
existing walls.
Pipe trenches in the quay wall and apron.
Surface water drainage installations including extensions of 3no. existing outfall
culverts and incorporation of 2no. into the new quay wall extension.
B. Supply and installation of replacement fenders and repair of concrete along the
existing quay wall.
1.3 General Construction Flowchart
To ensure the achievement of schedule of the project, the construction of each
phase/section should be started as early as possible. As the dredging of foundation
trench gets started, the construction of precast concrete counterforts should be
initially performed, so as to proceed the following construction as soon as possible.
The general construction flowchart of the Project is shown as follows:
5 / 36
Luanda Oil Service Base Expansion Contract for Tender Submission
Quay Wall between Heavy Lift Dock and TCT Area Method Statement
Construction Flowchart
6 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
2 Temporary Facilities
Referring to the following figure, the existing temporary facilities, including the
living camp, precast yard, batching plant, etc., will be reused after decoration
and repairs. Site office may be established within the living camp or by precast
yard site whose area to be provided by the Employer.
General Layout of Temporary Facilities
3 Construction
After the contract has been awarded, the manpower mobilization will be started
immediately. Most of the manpower will be mobilized, so that the Project can be
started as soon as possible. Normally, the senior staffs will be initially mobilized
to the site within four week to start the preparation works. Part of skilled workers
will be mobilized initially to start the construction of temporary facilities within
three month. Other skilled labors and semi labors will be mobilized subsequently
basing on the construction schedule. Part of skilled workers, semi labors and
7 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
unskilled labors will be recruited locally in Luanda, Angola.
The mobilization of the Equipment, such as grab dredger, flat top barge, floating
crane, etc., will also be commenced early. After obtaining the construction
permission and consents, the dredging construction will be executed
immediately.
3.1 Dredging
3.1.1 General
The works comprises the execution of dredging works required for foundation
trench and leveling of the berth pocket in front of the new quay wall to -12.5 m
CD as indicated on the drawings in Employer’s Requirements.
3.1.2 Dredging Method
For this terminal, the grab dredger will be allocated to the dredging works with
the assistance of the split hopper barge. All dredging work will be carried out
vertically in layers and horizontally bays. The sketch of dredging construction by
grab dredger is shown as below:
Grab
Dredger
Hopper
Barge Grab DredgerWater Level
Original level
Design level
Section of DredgingPlan of Dredging
The Sketch of Dredging
8 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Dredging by Grab Dredger
The procedure for dredging construction is shown as below:
The dredger will be positioned by GPS system. During the dredging, the level of
dredging will be measured by lead. One hydrographic measuring station will be
also set on the existing quay.
The dredging sample will be checked and compared with borehole data in time
when it is carried out to each layer. The width and depth of the dredging area will
be controlled in a tolerance of Employer’s Requirement. If the sample is different
with the design, it should be reported to the Employer to make further decision.
Significant data and information of the dredging will be recorded.
The dredging works will be monitored by regular hydrographic progress survey in
order to verify that works are being executed in accordance with the scope of
design. The survey will be carried by echo sounder and GPS positioning device.
The post-dredging survey must be carried out immediately after the dredging of
the bay is finished.
9 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
3.1.3 Construction Sequence and Schedule
The dredging sequence will be executed from dredging of foundation trench to
dredging of berth pocket in front of quay wall. Considering the site condition,
disposal distance and vessels’ maintenance, about 1,200m3 materials per day
will be executed by grab dredger.
3.1.4 Disposal of Dredging Materials
The disposal areas are not yet identified exactly but it is assumed that dredged
materials will be dumped offshore to a location to be agreed with the Employer
within Luanda Bay.
3.1.5 Dredging Equipment
Major intended equipment resources for dredging are listed as below:
S/N Description Qty. Remark
1 Grab Dredger, 13m3 1
2 Split Hopper Barge, 500m3 2
3 Tug Boat, 1000Hp 1
4 Traffic Boat 1
5 GPS Positioning Device 1
6 Echo Sounder 1
3.2 Rubble Bedding for Foundation Trench
3.2.1 Rockfilling
The sketch of rockfilling for foundation trench is shown as follows and the
rockfilling quantity is about 55,000m³ .The stone will be supplied from the land
and transported to the temporary quay. The excavator will be used to load the
stone onto the 15m3 hoppers. When hoppers are fully loaded, they will be
transported to the specified position for rockfilling. For accurate positioning for
hoppers, flat top barge will be used for positioning by GPS. The method of
plumbing will be adopted to control the rockfilling height accurately.
10 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Sketch of Rockfilling for Foundation Trench
Before the rockfilling starts, the foundation trench, which has been accepted but
is not yet covered with rockfilling, shall be surveyed again. If the thickness of
back silting is above specified profile, it shall be reported to the site Engineer,
and the work for clearance of silt shall be organized.
Trial rockfilling shall be performed prior to determine the location of the hopper
and thickness of stone dumped at a time. Through different trial rockfilling with
different loads of stone, the load for a certain rockfilling thickness can be
determined. Thereby, proper methods for loading and positioning can also be
acquired.
First, the hopper will be used for the coarse-rockfilling, and then the flat top
barge loaded with stone will be accurately positioned for supplementary
rockfilling. During the rockfilling process, frequent plumbing and mark aiming will
be performed to avoid under-rockfilling or over-rockfilling.
Settlement shall be taken into consideration for the rockfilling of foundation bed.
The preserved amount of settlement shall be determined by design requirement.
3.2.2 Ramming
One crawler crane 70t will be fixed on the flat top barge for foundation trench
compaction. The foundation trench shall be compacted by ramming in layers
according to thickness; and the thickness of the layer is not advisable to be
greater than 3m after compaction. Adjacent ramming rounds with half
overlapped with each other longitudinally and transversely will be adopted for
11 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
compaction.
The rammer will be planned to use 5 t in weight with 1.0m diameter circular
bottom. When the buoyant force and resistance is not taken into account, the
impact energy of each ramming is not advisable to be less than 120KJ/m2. The
compact energy can be obtained when lifted height is up to 2.5m. The rammer
shall be lifted up to 3 m to achieve compact energy of 130kJ/m2 for each
ramming.
The ramming for rockfilling bed shall proceed from one point to another, with
adjacent ramming circles half overlapped with each other longitudinally and
transversely as shown in the sketch, and will be carried out in two rounds, with
the initial ramming followed by the recurrence, four times ramming at each point
for each round, and 8 times ramming in total for each point.
Sketch of Layout of Rammer’s Falling Points
12 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Sketch of Ramming for Trench
The foundation trench shall be divided into 2 sections, with 2 m overlapped
length, and 3m in thickness for each layer.
The plane of each rockfilling layer shall be checked before starting the ramming,
and leveling shall be executed if height difference between adjacent locations is
more than 0.3m.
Typical area, with 1m exceeding each side of counterfort and length of 10m,
shall be chose as the trial section.
The initial ramming and recurrence will be executed by the same means of
adjacent ramming rounds half overlapped with each other longitudinally and
transversely to prevent local heave of foundation bed or flaw of ramming. 1 m
exceeding front/back side line of the counterfort will be taken for rammed width.
The reserved settlement value will be adjusted according to the trial ramming
properly.
3.2.3 Leveling
The area of foundation trench to be leveled is about 6700m². When the rockfilling
for foundation trench is completed and accepted, the work of leveling will be
commenced at once.
The survey rod will be controlled by the total station for rails placement of the
13 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
leveling work, while the survey rod will be controlled by the water level to obtain
the elevations. For the placement of rails, the control points shall be set on the
temporary survey station.
Please refer to the following sketch for leveling of foundation trech:
Sketch of Foundation Trench Leveling
One leveling barge and some divers will be involved for foundation leveling. The
amount of rubble stone and crushed stone shall be estimated beforehand
according to the as-built section of the rockfilling works, and the stone needed
shall be prepared.
Flat top barge will be served for leveling, which can be loaded with the stone for
14 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
leveling. Crushed stone will be used at the last step for fine leveling. Via the
woven bag which will be raised and put down by manpower, the crushed stone
will be transited to the location controlled by the diver for leveling.
Divers will be employed to lay the steel rails underwater, and a leveler will be
equipped on the rails to level the crushed stone within reach. Surveyors shall
erect the total station at the survey station and direct the divers to place the steel
rails by observing the instruments. The divers shall place concrete blocks
underwater to support the steel rails. Elevation of the rails shall be controlled by
the water level and survey rod. When the steel rails are ready, two teams of
divers shall dive into water at the same time, and push the leveler forward along
the steel rails.
During the process for fine leveling, rubble stone shall be used to fill the uneven
position among rock blocks, while crushed stone shall be used to fill the uneven
position among rubble stone. The crushed stone is allowed to form a layer with
thickness less than 5cm. Only those crushed stone of 2~4cm shall be used. Via
the bamboo basket which will be raised and put down by manpower, the crushed
stone will be transferred to the position required through underwater wire
telephone communication between the diver and surveyor. The divers shall push
the leveler (such straight hard material as channel steel) along the rails to level
the stone. And the completion of leveling for a section of foundation bed shall be
followed by the operation for the next section.
Elevation and position of rails shall be rechecked at the time after the fine
leveling. If any deviation beyond allowable is found, the rails shall be adjusted.
Life buoys connected with concrete block through nylon rope shall be placed for
each corner of the leveled section of foundation bed. And those area completely
leveled shall be kept away from anchoring of vessels.
3.3 Precast Counterfort units
3.3.1 General
There are 53 units of counterfort (CF) to be precast in this project, with 51 units
of standard and 2 special. All of the CFs will be prefabricated at the precast yard,
with 9130m3 concrete involved. The precast sequence will in accordance with
the requirement of site installation.
15 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
3.3.2 Existing Temporary Works
The existing temporary works, including precast yard, batching plant, etc., will
be used after decoration and repairs. The sketch layout of temporary works is
shown as followings:
Sketch of General Layout of Temporary Works
3.3.3 Construction Method
A. General arrangement
Two precast lines will be arranged for CF prefabrication. 8 CF units will be
completed every month. Ballonet method will be used for transporting the
precast unit.
16 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
B. Bottom Formwork Preparation
For the convenience of ballonet loading out, 5 groups of I-Steels (32#) and one
group channel steel shall be placed transversally on the floor to form 5
interspaces, at the ends of the interspaces, built-up type steel formwork shall be
placed transversally to connect with the longitudinal I-bars. Thus the outline of
the bottom formwork can be formed. Sand shall then be filled into the 5
interspaces, which shall later be watered and compacted until the surface of
sand is the same level as that of the I-bars and channel steel. Afterwards, 20mm
thick wooden board and paper shall be placed onto the sand form the bottom
formwork. To transport the components, remove the transversal steel formwork
at the ends of the I-bars, clear away the sand in the interspaces, then insert the
ballonets into the interspaces, when the component is lifted by the ballonets filled
with air, the I-bars shall then be removed, and the component can be loaded out
to the temporary quay by revolving the ballonets in shift.
As there 2 special counterfort in this project, one set of the formworks should be
changed correspondingly. These special will be planed to be produced finally, so
that the formwork will not have to be changed for tow times.
C. Processing and Erecting of Rebar
After processing in the shed, the rebar shall be transported to the site by trucks
and then be erected on the bottom formwork. Auxiliary steel frame for rebar
erection between rib slab and the upright slab shall consist of 7 layers, each
layer 2.0m in height.
The auxiliary framework mentioned shall be welded into an integer by profile
steel and fixed with the bottom formwork. The erecting of rebar shall be kept
stable and fasten. In order to hang the vertical rebar of upright slab and rib slab,
movable profile steel and horizontal hanger rod shall be set up on top of the steel
framework. Vertical rebar shall be hanged onto the horizontal hanger rob
according to the design space, a certain numbers of horizontal rebar shall be
fastened on the top, middle and bottom of the vertical rebar to form a frame
structure, afterwards, from the upper to the down. The inner rebar shall be
erected first, then the outer horizontal rebar, and finally the rebar for bottom slab.
When the bar erection work is completed, concrete cover spacer shall be placed
on the surface of the rebar cage, outer formwork can be installed then.
Supported by the outer formwork, the rebar of the counterfort shall keep stable,
17 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
afterwards, the frame for bar erection will be hoisted out, and the working
procedure for fixing and erection of rebar has been fully finished.
D. Side Formwork
CHEC has rich experience in precasting the same counterfort in the Quay Wall
and GRN project. The gantry crane 20t will be used for formwork installation/
removal, while the inner formwork shall be installed layer by layer, concrete
casting shall be performed continuously until it is completed, so that the
concreting can go on smoothly, and the quality of the counterfort units can be
well ensured.
Formwork for one side of bottom slab shall be installed as a whole according to
the setting-out location. Large formwork with a weight of 15t will be used as outer
formwork. Outside the steel plate surface, horizontal trusses shall be erected at
the height of 1.2m. The adjacent trusses at both ends of the upright wall of
counterfort will be connected into a whole to form a bearing grid. Bolts that can
be fastened at both ends will be equipped in each rib of the horizontal trusses of
the upright wall. Therefore, a bearing structure of multi-span continuous beam is
formed. The bolts that can be fastened at both ends shall then be connected with
the frame of inner formwork.
Both the counterfort rib slabs and the inner formwork of the upright wall consist
of 7 layers with 2m layer height. Position for erecting of formwork shall be set out
on the bottom formwork, and the marks shall be made at the place where
supporting concrete block need to place. Place concrete column block at the
right place, where steel formwork for bottom slab shall be installed. The inner
formwork for each layer shall be hanged to the corresponding steel truss. And
removable formwork chamfered for the convenience of formwork removal shall
be installed at the corner. Bolts shall be installed between inner formwork and
outer formwork. The support column for inner formwork of each layer shall be
connected by bolts end to end. And sealing strip shall be used for joints between
formwork. A platform with bevel will be erected with the inner formwork to
facilitate the concrete casting. The weight for each section of inner formwork and
the support frame is about 10t, and it will be hoisted and installed by gantry
crane.
As there are 2 special counterfort is this project, one set of the formworks should
be changed correspondingly. These special ones will be produced last, so that
18 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
the formwork won’t have to be changed two times.
E. Concrete Casting
With reference to the design of formwork, the outer formwork installation shall be
completed at the beginning for concrete casting. The inner formwork between
two ribs shall be divided into 7 layers. They shall be assembled section after
section, and then be installed layer by layer along with the concrete casting
process.
When the installation of formwork is completed and concreting has been
approved by the Engineer, the concrete casting may be commenced at once.
The gantry crane with the concrete bucket or concrete pump truck will be used
for the casting operation. Concrete will be supplied by the batching plant on site,
and be delivered to site by concrete truck. Later, the concrete will be released
into the concrete bucket, hoisted to the formwork by the gantry crane or directly
cast by pump truck. Labors shall then be employed to release the concrete into
the formwork and compact it by the internal vibrator.
The bottom slab and the first layer of 2m high wall and rib shall be cast first, and
then the inner formwork for each layer shall be installed along with the increasing
concrete. Each layer for concrete casting shall be 2m in height. About 2 hours
(less time for the smaller upper section) will be taken for the casting of each
layer. About 1 hour for formwork installation of one layer. So 3 hours will be taken
on average for completion of one layer. Taken other factors into consideration,
the 7 layers including the bottom slab, can be completed within 21 hours.
Meanwhile retarder shall be added into the concrete to ensure the initial setting
time prolonged to 4.5-5 hours.
In the case of heavy rain during casting concrete, the casting can make a pause
temporary, and be better to cover the concrete with plastic sheet for a while. If
the casting cannot be stopped or resumed after pausing, the mix of the concrete
should be adjusted appropriately.
F. Curing
When the required strength of the concrete is obtained and approved by the
Engineer, side formwork can be removed. The concrete shall then be marked
and be cured continuously with fresh water. The water for concrete curing shall
comply with the design requirement. The unit shall be cured with water for 7
19 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
days.
When the component reaches the 100% of the design strength, it can be moved
to the temporary quay by ballonets, and then be hoisted to the barge for
installation by barge crane.
3.4 Installation of Counterfort Units
3.4.1 General
There are 53 pieces counterfort (CF) units weigh about 432t for each. They will
be transported from the precast area to the temporary quay by ballonets, loaded
on flat top barge 1000t and installed by floating crane with maximal hoisting
capability of 800t.
3.4.2 Construction Method
Ballonet will be used to transport the CF from precast area to temporary quay for
installation. Structure of ballonet is shown as follows:
A ballonet consists of its body, head and nozzle, etc. Its auxiliary parts include
safety valve, pressure meter and pipe joints, referring to the following sketch:
20 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Sketch of Ballonet Structure
The ballonet to be used in this project is made up of 6 layers. The allowable
working pressure is 0.2MPa; and the extreme pressure is 0.5MPa. One piece of
φ1000mm*9m ballonet weighs about 250kg; and generally the mass of the air
charged can be omitted.
In order to ensure horizontal load for the CF at the beginning of lifting up the unit,
the ballonets shall be set regularly along the moving direction of the CF. As per
the level load principle:
21 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
CF Transported by Ballonet
Leveling for foundation trench rockfill must be inspected and accepted before
installation. The CF units will be hoisted and loaded on barge in sequence after
the concrete compressive strength of the units reach the designed strength. The
CF units will be hoisted about 50cm above the ground at first, and it will be lifted
up again when the floating crane becomes steady. The barycenter lines of the
CF unit and 2000t barge must be matched together when loading the unit on the
barge in order to avoid inclination of the barge caused by imbalanced load. The
plan for CF units loading on barge is shown as below:
Sketch of CF units Loading
22 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
The floating crane and flat top barge will be moved to the Quay site with the help
of tug boat. The bow direction of floating crane shall be normal to the cope line of
the quay, and two front anchors will be connected with ground anchors buried
onshore or bollard.
Survey stations shall be prepared before installation. The survey stations should
be ensured observation without obstruction during installation, longitudinal
survey station and GPS shall be prepared separately for controlling the
positioning.
The installation sequence will commence from the Heavy Lift Dock to existing
GRN Quay. Timber will be prepared to control joints width in advance.
The positioning for floating crane and survey controlling are shown in the
sketches.
23 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Sketch of CF units Installation
The CF unit can be put on the foundation trench when the positioning is
satisfied, and divers will check width of joint and staggering between neighboring
units separately. The shackles can be released and removed when the checked
items are qualified.
Observation points for settlement and displacement can be set after the
installation, and they will be surveyed regularly or irregularly according to the
requirement.
3.5 Backfilling Sand and Vibro-compaction
3.5.1 Backfilling Sand
Backfilling sand will be executed after the completion of geotextile filter layer.
Dredged sand will be used as backfill material. The quantity of the backfill ing
sand behind the quay wall is about 590,000m3.
To prevent the foundation being silted, the sand will be backfilled when 30 CF
units (about 255m) are installed. And the method of backfilling is hydraulic
backfilling. The bathymetric survey should be carried out by GPS echo sounder
or hand-lead survey before backfilling, and then topographic map will be made to
calculate the quantity for hydraulic backfilling. Hydraulic backfilling shall be
executed by reclamation dredger and be assisted to fill by bulldozer, dumpers
and excavator. Meanwhile the settlement and displacement of CF units will be
24 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
monitored by surveyor during backfilling. The diver will check the geotextile filter
layer to ensure its stability during construction. Backfilling will be executed with
the sequence of CF installation.
The outlet of the hydraulic backfilling pipe will be laid in the location which is
about 40m from the copy line. Dredged sand will be used as the material, and
backfilled sand will be transported, loaded and leveled by excavator and
bulldozer to the front, Manpower will be used for partially trimming.
The Level of the quay apron after backfilling between 3 and 30m from the cope
line is about +3.0m, so the level after vibroflotation is about +2.0m, which is
above water level and is convenient for the subsequence construction. And the
level of the remainder is about +3.5m which should comply with the Employer
requirement.
3.5.2 Vibro-compaction
The backfilled sand will be treated (vibro-compacted) which is between 3m and
30m from the cope line.
Vibro-flotation lifted by crawler crane will be allocated to carry out this
construction, referring to the following sketch:
Compaction by Vibro-flotation
3.6 Demolition Works
The existing pipe spooling jetty, piles along shoreline, slope protection material
and emergency small craft quay shall be demolished and removed from site,
25 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
specified in Employer’s Requirements.
The hydraulic breaker and excavator will be mainly used for the demolition
works. If agreed with the Engineer, the piles may be cut off at sea bed level,
provided they do not interfere with the quay wall works.
Acceptance of demolition works will be granted following the acceptance of the
surface by the Engineer and receipt of all required documentation.
The disposal areas are not yet identified exactly but it is assumed that demolition
materials will be dumped offsite at a distance, in a legal manner and with the
approval of local Authorities.
Demolition by Hydraulic Breaker
3.7 Cast In-situ Capping Beam
There is 442.9m cast-in-situ capping beam for the quay wall, which is divided
into 26 segments. The design compressive strength of the concrete is 40 MPa,
and the quantity of concrete involved is about 2861m³. The standard section of
quay wall is shown as below:
26 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Typical Section of Quay
Take the entire segment divided in accordance with the design as a construction
unit (17m as a segment), concrete will be cast in place every other segment from
Heavy Lift Dock to GRN Quay, and concrete casting for each segment shall be
finished at a time. The flow chart of cast in-situ process is as follows:
27 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Flow Chart of Cast in-situ Process
Triangle bracket will be installed at first; and then 100*100mm timber and
plywood for bottom formwork. Side formwork structure shall be 8mm thick steel
plate integrated with enclosing purlins. Formwork includes outside part, inner
part, and end-sealing part. Side formwork will be installed after the rebar erection
is inspected and accepted by the Engineer.
Sketch of Triangle Bracket for Bottom Formwork
28 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Side formwork will be installed by crawler crane, and the shape, straightness,
and dimension of the formwork shall conform to stipulations set forth in relevant
codes. The embedded bolts such as the rubber fender’s, bollard’s and ladder’s
should be fixed accurately and firmly at the same time.
The concrete will be produced by batching plant on site; it will be transported to
the quay wall site by mixer truck and will be cast by concrete pump.
Internal vibrator will be used for compacting concrete. Vibration quality shall be
ensured during casting, defects as honeycomb on concrete surface and air voids
should be avoided.
Finishing shall be performed with trowel when top elevation reaches, and screed
by manpower shall be used for leveling before initial setting of concrete.
When concrete compressive strength reaches 10N/mm2, side formwork can be
removed according to BS 8110 part 1. Side formwork will be removed by labors
with the help of crane. Attentions to safety and integrality of formwork should be
paid during the removal of formwork, don not prize and hammer here and there
so as to avoid deformation of formwork. Bottom formwork will be removed at last
when compressive strength conforms to relevant stipulation. The structure shall
be covered immediately and cured with fresh water or by applying curing agent,
and moist curing period shall not be less than 7 days.
3.8 Drainage Culvert
Surface water drainage installations, including extensions of 3 no. existing outfall
culverts and incorporation of 2 no. into the new quay wall extension, will be cast
on site. The concrete will be provided by the batching plant.
3.9 Construction of Apron including Trench
3.9.1 General
The quay has an apron of 30m wide. The section covers capping beam and
concrete pavement (service trench). As for the 25.1m wide pavement, it consists
of a 200mm thick graded crushed rock sub-base, a 250 thick lean concrete C15
base course and a 430mm thick reinforced concrete C40 surface course. The
total thickness is 880mm, and the section of apron is as follows:
29 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
3.9.2 Service Trench
Service trenches are situated longitudinally and transversely in the quay. The
dimension of the trench situated transversely is 1.87m in height and 2.2m in
width, it is a single box with two cells. The dimension of the longitudinal trench is
1.65~1.87m in height and 1.9m in width, which is a single box with one cell.
Cover slabs will be precast and installed for the trenches. The compressive
strength of the concrete for the trench is 40MPa. There is about 1684m3
concrete involved in service trenches.
The cover slab prefabrication is prior to the principle part of trench construction.
The trench construction procedure is as follows:
Foundation excavation → graded crushed rock sub-base → C15 lean
concrete base course → rebar assembling → side formwork installing →
concreting → curing → cover slab installing
Steel side formwork will be used for service trench, which will be installed and
removed with the help of the crawler crane.
Concrete placing shall be divided into three times. Firstly, concrete of bottom
slab and side walls is to be cast; secondly, the pedestal for cover slabs is to be
cast to ensure its straightness; the central partition (only transverse trench) is to
be cast finally. The casting sequence is shown as below:
30 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Sketch of Sequence of Trench Concreting
After side formwork removal, concrete shall be cured timely in accordance with
relevant requirements, and it shall be kept damp not less than 7 days.
Qualified Cover slab will be installed by 65t auto crane after the pavement is
finished.
3.9.3 Sub-base
200mm thick graded crushed rock which lies on backfilled sand sub-grade after
compaction will serve as unbound sub-base for pavement; and 3084m3 graded
crushed rock will be involved in sub-base.
Construction for sub-base will be executed form west to east in section and in
one layer. And the procedure is as follows:
Prepare → graded crushed rock spreading → compacting
When the compactness of sub-grade has been accepted, setting out for graded
crushed rock sub-base can be executed, whilst graded crushed rock can be
stored and tested in accordance with design requirement or relevant codes.
Type SD23 bulldozer will be used for spreading for crushed rock; and partial
trimming and leveling shall be executed by manpower to ensure thickness and
level of the sub-base.
31 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Compaction should be carried out as soon as possible after crushed rock has
been spread according to the requirements and relevant codes.
Type LSS218B vibratory roller with static linear load 415N/cm will be used for
compaction. Basing on the design thickness of the sub-base is 200mm, 7 passes
will be executed for compaction in accordance with requirement.
Special care should be taken to obtain full compaction in the vicinity of both
longitudinal and transverse joints.
A minimum width of 2m of properly compacted sub-base beyond the edge of the
lean concrete should be prepared before actually placing the lean concrete.
3.9.4 Base Course
250mm thick lean concrete C15 which lies on the sub-base will serve as base
course for pavement; and the quantity of lean concrete is about 3855m3.
The construction sequence for lean concrete is stated as below:
Site prepare → formwork installation → concreting → curing
Setting out for lean concrete base can be executed after sub-base has been
accepted. Lean concrete will be constructed longitudinally in about 5m strips.
The staggered distance between longitudinal joints of lean concrete base and
upper layer pavement slab shall be more than 300mm; whilst the staggered
distance between transverse joints of lean concrete base and upper layer
pavement slab shall be more than 1m.
Concrete for base will be produced by our batching plant. And the slump
constant of lean concrete shall be met with the design requirement. Lean
concrete will be transported by mixer truck. It shall be constructed in one layer
and in strip along longitudinal direction of quay wall. Hand guided method shall
be adopted for concreting in a continuous process. Internal vibrator will be used
for compaction.
The side formwork shall be removed by labors. Curing liquid or fresh water shall
be involved in curing. Lean concrete shall be cured in accordance with relevant
requirements.
32 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
3.9.5 Surface Course
430mm thick reinforced concrete C40 which lies on the base course will serve as
surface course for pavement, with the quantity of about 6631m3.
Construction for reinforced concrete will be executed transversely segment by
segment; and every segment of the reinforced concrete slab, which is in accord
with the design plan, will be cast in one layer. Its procedure is as follows:
Prepare → rebar prepare and erection → formwork installation →
concreting→ curing
When the lean concrete base has been accepted, setting out for reinforced
concrete slab can be executed, whilst reinforcement cages can be prepared.
Steel side formwork with reserved holes for dowel bars will be used for
reinforced slab. Formwork will be installed when reinforcement cages for
pavement slab have been finished. Dowel bars shall be installed after formwork
has been installed.
The concrete shall be produced by the batching plant in precast yard; it will be
transported to the quay site by mixer truck and will be cast by concrete pump.
Internal vibrator will be used for compacting concrete. Vibration quality shall be
ensured during casting, defects as honeycomb and big air voids should be
avoided. Finishing shall be performed when top elevation reaches, and concrete
finishing machine will be involved in leveling concrete surface. Screed by
manpower shall be used for leveling before initial setting of concrete.
Curing liquid will be sprayed when the concrete sets finally, and geotextile will be
covered subsequently. The damp curing will be applied at least 7 days. The side
formwork will be removed by labors when concrete compressive strength
reaches 10N/mm2. Then the contraction joint will be cut immediately after the
removal of side formwork.
3.10 Installation of Auxiliary Facilities
Auxiliary facilities, including bollard, fender, ladder, etc. will be installed after the
completion of capping beam and apron.
33 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Fender and Bollard Installation
3.11 Placement of Anti-scour Protection
Reno mattress, L*W*H=3000*2000*500mm, is designed for anti-scour protection
in front of quay wall. The construction sequence is as follows:
Site preparation → Mattress assembling → Foundation preparation →
Mattress installation.
A. Site Preparation
Mattresses, stone for mattresses and lifting frame should be prepared before
construction. The size of lifting frame is 6.0m in length and 2.0m in width, the
sketch is shown as follows:
The sketch of Lifting Frame
B. Assembly and Filling
The folded units shall be taken out from the bundle and placed on a flat ground.
Mattresses should be opened, unfolded and pressed out to their original shape.
34 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
Front, back and end panels shall be lifted to a vertical position to form an open
box shape. End flaps shall be folded and overlapped, as appropriate. All edges
of the diaphragms and panels shall be tied or fastened to front and back of the
mattress. The mattresses should be assembled individually, by erecting the
sides, ends and diaphragms, ensuring that all creases are in the correct position
and the tops of all sides are level. Then, the edges of the mattress will be
connected by using lacing wire. When using lacing wire, cut a sufficient length of
wire and first loop and twist the lacing wire to the wire mesh. Proceed with tying
alternate double and single loops through every mesh opening approximately
every 100 mm, and pull each loop tight and finally securing the end of the lacing
wire to the wire mesh by looping or twisting. The lacing wire should be supplied
with the mattresses.
After being assembled, the mattresses shall be filled with rocks. Rocks for
mattresses shall be hard, angular to round, durable and of such quality that they
shall not disintegrate on exposure to water or weathering during the life of the
structure. Care shall be taken when placing the stone to avoid damaging the wire
coating. After a layer of rock has been placed in the cell, sufficient hand
manipulation of the rock shall be performed to minimize voids and achieve a
maximum density of the rock in the units.
To allow for settlement, fill more and level it off above the tip of the mesh. Then
lay the lid down and pull the edges of the panels to be connected. The lids shall
be tightly laced along all edges, ends and diaphragms in the same manner as
described for assembling.
C. Foundation preparation
The foundation on which the mattresses are to be placed shall be level to the
elevations as shown on the project construction drawings and surface
irregularities, loose material and vegetation in accordance with the project
specifications.
D. Installation
Finally, the mattresses shall be placed in their proper location and securely
attached to the adjacent ones. In principle, the mattresses will be installed by the
autocrane on the quay, and probably a few by crane on the barge.
Control for installation: When installing the mattresses, direction of the installing
35 / 36
Luanda Oil Service Base Expansion Contract for Tender SubmissionQuay Wall between Heavy Lift Dock and TCT Area
Method Statement
mattress should be controlled by the following steps. First, before the mattress
lifting underwater by crane with lifting frame, the location should be adjusted by
pulling ropes and moving the crane hook above the water. Then, diver shall dive
under water to adjust the location of the mattress by directing the crane until the
location is right. Finally, take off the hooks and make a mark on the capping
beam to record the installation location.
Placement of Reno Mattress
3.12 Fender Replacement and Concrete Repairs
The scope of this contract includes the installation of a fendering solution for the
following quay walls:
New quay to be constructed;
Existing quay wall of caisson construction (90m) ;
Existing quay wall constructed by Murray and Roberts (401m);
Existing quay walls constructed by CHEC (782 + 305m)
Existing dock quay walls constructed by CHEC either side of the heavy lift
dock (42 + 42m)
No fender repairs are required to the existing GRN quay or in the heavy lift dock.
The old concrete will be demolished by hydraulic breaker and removed from site.
Concrete will then be placed during interval. All these works will be carried out in
accordance with the programme and in such a way as to minimize interference
with the normal business of the Port and the Luanda Oil Service Centre.
36 / 36