Prefeasibility Report For Facility Augmentation at Vijayawada ...
-
Upload
truongdung -
Category
Documents
-
view
269 -
download
12
Transcript of Prefeasibility Report For Facility Augmentation at Vijayawada ...
Prefeasibility Report For
Facility Augmentation at Vijayawada Terminal
At
Kadimipothavaram Village, Pinapaka (PO), G. Konduru
Mandal, Krishna District, Andhra Pradesh
Prepared by
Indian Oil Corporation Ltd.
&
M/s Ultra Tech
(Environment Consultancy & Laboratory)
Table of Contents
1. Executive Summary ................................................................................................................. 1
2. Introduction ............................................................................................................................. 2
3. Site Information ....................................................................................................................... 3
4. Project Description .................................................................................................................. 7
5. Need for Project Activity ......................................................................................................... 8
6. Environment Control Measures ............................................................................................... 7
7. Fire & Safety Measures ........................................................................................................... 8
8. Project Justification, Schedule and Cost ................................................................................ 12
1
1. Executive Summary
Indian Oil Corporation Ltd. was commissioned on 1st September, 1964. Indian oil and its subsidiaries
account for approximately 48% petroleum products market share, 34% national refining capacity and
71% downstream sector pipeline capacity in India. It is India’s flagship national oil company and
downstream petroleum major thus being India’s largest commercial enterprise.
M/s Indian Oil Corporation Limited proposes to facility augmentation at Vijayawada terminal with the
additional storage facilities: Mild steel cone roof tank (60,952 m3), floating roof storage tank (64,340 m3),
Mild steel Horizontal Tanks (148 m3), Additional 8 Bay TLF Gantry, internal product pipelines, railway
siding and pipeline receipt facility from HPCL refinery and white terminal to Vijayawada terminal and
pipeline receipt facility IOCL Paradip Refinery through Paradip-Visakhapatnam-Vijayawada- Hyderabad
Pipeline.
Existing terminal was set up at Kadimipothavaram, Pinapaka P.O, Kondapalli, Krishna district, Andhra
Pradesh. The Terminal was commissioned in the year 2002 in an area of about 85.11 acres of land,
located 29 km from Vijayawada city. The site is well connected by road.
The main activities of the Terminal are Receipt, Storage and Delivery. The Terminal receives stores and
distributes Petroleum Products like Motor Spirit (MS) BS-III, High Speed Diesel (HSD) BSIII, Superior
Kerosene Oil (SKO), Hexane. The Terminal also handles Ethanol, which is mixed in a proportion of 10%
by volume with MS before dispatch.
The land use is industrial and no new land acquisition is required for the project. The land required for the
expansion of the terminal facilities is already in possession of IOCL. Layout of the Existing Plant and
Proposed facilities is shown in Figure 1, below:
FIGURE-1 PLANT LAYOUT
2
Water will not be required for operation of the facilities since no processing/ production is involved. The
total water requirement for mock drills, gardening and domestic use will be around 20 m3 sourced from
bore wells. The estimated power requirement for the proposed project will be met from the state
electricity board/alternatively DG set will be utilized
Insignificant emissions are anticipated from the DG sets (CPCB specifications) which are used during
emergencies. Emissions from the DG sets shall be vented out through exhaust as per statutory norms and
will be monitored. Fugitive emissions from project activity are envisaged and adequate control measures
will be in place. Solid waste viz. Hazardous solid waste and non hazardous solid waste generated in
terminal will collected, segregated and disposed of through authorized agency as per Hazardous waste
rule. The proposed terminal has adequate safety & fire fighting systems in place to control any toward
incidents. These systems are in line with the requirements of OISD.
The proposed project will lead to additional employment during operation phase. Technical manpower
required for proposed expansion shall be sourced from IOC. Local manpower will be preferred during
construction phase. The proposed project will be completed in approximately 24 months from the date of
approval, environmental and other statutory clearances. The total cost of the proposed project is around
Rs 372 Crores.
2. Introduction
Indian Oil Corporation Ltd. was commissioned on 1st September, 1964. Indian oil and its subsidiaries
account for approximately 48% petroleum products market share, 34% national refining capacity and
71% downstream sector pipeline capacity in India. It is India’s flagship national oil company and
downstream petroleum major thus being India’s largest commercial enterprise.
As the flagship national oil company in the downstream sector, Indian Oil reaches precious petroleum
products to millions of people every day through a countrywide network of about 35,000 sales points.
They are backed for supplies by 167 bulk storage terminals and depots, 101 aviation fuel stations and 89
Indane (LPG) bottling plants.
The Indian Oil Group of companies owns and operates 10 of India's 20 refineries with a combined
refining capacity of 60.2 million metric tons per annum (MMTPA, .i.e. 1.2 million barrels per day). These
include two refineries of subsidiary Chennai Petroleum Corporation Ltd.
The Corporation's cross-country network of crude oil and product pipelines, spanning over 10,000 km and
the largest in the country, meets the vital energy needs of the consumers in an efficient, economical and
environment-friendly manner.
As a leading public sector enterprise of India, Indian Oil has successfully combined its corporate social
responsibility agenda with its business offerings, meeting the energy needs of millions of people every
day across the length and breadth of the country, traversing a diversity of cultures, difficult terrains and
harsh climatic conditions.
Existing Terminal: Existing terminal is set up at Kadimipothavaram, Pinapaka P.O, Kondapalli, Krishna district, Andhra
Pradesh. The Terminal was commissioned in the year 2002 in an area of about 85.11 acres of land,
located 29 km from Vijayawada city. The site is well connected by road.
3
Nature of Project The main activities of the Terminal are Receipt, Storage and Delivery. The Terminal receives stores and
distributes Petroleum Products like Motor Spirit (MS) BS-III, High Speed Diesel (HSD) BS-III, Superior
Kerosene Oil (SKO), and Hexane. The Terminal also handles Ethanol, which is mixed in a proportion of
10% by volume with MS before dispatch.
No by-products / additional products are generated / manufactured during the operations. Hence, the
present proposal is classified under Schedule 6(b) & Category ‘B’ according to EIA Notification 2006 &
subsequent amendments.
3. Site Information M/s Indian Oil Corporation Limited proposes to facility augmentation at Vijayawada terminal with the
mentioned facilities: 5 Internal Floating Roof Vertical Tank (64340 m3); 5 Conical Roof Vertical Tanks
(60952 m3) and 2 Horizontal Tanks (148 m3), Additional 8 Bay TLF Gantry, internal product pipelines,
railway siding and pipeline receipt facility from HPCL refinery and white terminal to Vijayawada
terminal Pipeline receipt facility IOCL Paradip Refinery through Paradip-Visakhapatnam-Vijayawada-
Hyderabad Pipeline.
However, since this is an expansion project, there are total of 12 existing tanks, being used to store- MS,
HSD, SKO and Ethanol.
• Infrastructure For establishment and successful operation of terminal, it is imperative to ensure availability of the
following infrastructure:
o Rail/ road accessibility;
o Availability of water and proximity to source;
o Availability of land;
o No populated city in vicinity;
o Power evacuation plan; and
o Environmental consideration.
• Connectivity
The project site is located at distance of 3.5 km in South direction from the Kondapalli railway station.
The site is well connected to Vijayawada by road through NH-221 / NH-9. The nearest Airport
Gannavaram is located at 28 km in Southeast direction.
• Environmental Setting The Environmental Setting in 10 km radius of project site is presented in Table-1.
TABLE–1
ENVIRONMENTAL SETTING
Sr. No. Particulars Details
1 Plant location Located in IDA Kondapalli, Krishna district,
Andhra Pradesh State
2 Topo sheet No. 65 D/10
3 Site Coordinates Latitude : 16039’29.22” N
Longitude : 80033’14.46” E
Climatic conditions at Gannavaram IMD station (1971-2000)
4 Maximum temperature 44.6 0C
5 Minimum temperature 15.4 0C
4
Sr. No. Particulars Details
6 Annual rainfall (total) 921.5 mm
7 Relative humidity Maximum- 82 % (August)
Minimum- 45 % (May)
8 Predominant wind directions Annual:- SE and S
9 Plant site elevation above MSL 40 m
10 Plant site topography Plain
11 Present land use at the site Land use pattern is notified for industrial use
12 Nearest highway NH-221- 0.8 km, E
NH-9 - 7.5 km, SW
13 Nearest railway station Kondapalli RS- 3.5 km, South
14 Nearest Airport Gannavaram 28 km, SE
15 Nearest major water bodies • Budameru – 2.8 km, SSE
• Krishna River- 9.2 km, SSW
16 Nearest town/City Vijayawada, 15 km, SSE
17 Nearest village Kattubadipalem, 0.2 km, W
18 Archaeologically important places Kondapalli Fort, 3.6 km, SW
19 Protected areas as per Wildlife
Protection Act, 1972 (Tiger reserve,
Elephant reserve, Biospheres, National
parks, Wildlife sanctuaries, community
reserves and conservation reserves)
Nil
20 Reserved / Protected Forests • Kondapalli RF – 1.9 km, W
• Konduru RF - 3.8 km, N
• Duggiralapadu RF – 3.7 km, NW
• Gaddamanugu konduru RF – 5.8 km, NNE
• Kotturu RF - 8.8 km, E
21 Defence Installations Nil
22 List of major Industries in 10 km radius
• Nagarjuna Cement Factory – 0.5 km, W
• Inchem Labs Pvt Ltd - 0.6 km, South
• HPCL POL TERMINAL-0.6km, East
• HPCL LPG BP – 0.9km, SE
• Nifty Labs Pvt Ltd – 1.1 km, South
• Lanco Power Plant – 1.6 km, South
• GAIL – 2.3 km, NNE
• Vijayawada Thermal Power Station – 5.4
km, S
• Railway Wagon Workshop – 7.0 km, South
23 Seismicity Seismic Zone-III as per IS 1893 (Part I): 2002
Land Use and Land Ownership The proposed modification & augmentation will be carried out in the vacant land of existing terminal.
Hence, no alternate sites were considered for the project. The land use is industrial and no new land
acquisition is required for the project. The land required for the expansion of the terminal facilities is
already in possession of IOCL.
The total land allotted for IOCL is approximately 85 Acres; the proposed modernization / augmentation
will be within the premises of existing terminal. Clearance of vegetation is expected during construction /
installation phases. There are three LPG bottling plants for storage and filling of LPG viz of M/s. Indian
5
Oil Corporation Limited (IOCL), M/s. Hindustan Petroleum Corporation Limited (HPCL), Bharat
Petroleum Corporation Limited (BPCL). There are two other industries storing POL. Products, viz M/s.
Hindustan Petroleum Corporation Limited (HPCL) and M/s. Bharat Petroleum Corporation Limited
(BPCL) in surrounding area. There are no infrastructural facilities in the vicinity
Water requirement Ground water, as is being used by already installed plant, will be used for human consumption during
expansion of terminal. Water will not be required for operation of the facilities since no processing/
production is involved. The total water requirement for mock drills, gardening and domestic use will be
nearly 20 m3/day sourced from bore-wells.
Power requirement: The estimated power requirement of 2780KVA for the proposed project will be met from the state
electricity board/alternatively DG set will be utilized
4. Project Description The main activities of the Terminal are Receipt, Storage and Delivery. The Terminal receives stores
and distributes Petroleum Products like Motor Spirit (MS) BS-III, High Speed Diesel (HSD) BS-III,
Superior Kerosene Oil (SKO), and Hexane (at present); The Terminal also handles Ethanol, which is
mixed in a proportion of 10% by volume with MS for dispatches. Proposed products are Motor
Spirit (MS), High Speed Diesel (HSD), TRANSMIX Tank for MS and TRANSMIX Tank for HSD
and Bio Diesel.
• Receipt: IOCL Vijayawada Terminal Receives product by Pipe Line from HPCL Oil Terminal
and from paradip.
• Storage: The products handled by the Terminal are MS, HSD, SKO, Ethanol, Hexane and Bio
Diesel is stored in Vertical Storage Tanks.
• Delivery: IOCL Vijayawada Terminal plays a crucial role in the distribution of petroleum oils to
Krishna, Guntur, Khammam, Nalgonda, Warangal and Karimnagar districts by Tank Trucks. It
occupies an important place in the Indian Oil distribution network.
As the Petroleum Products are flammable and can catch fire if exposed to ignition, facilities and
Operations of the Terminal are designed and maintained to prevent any incidence of fire. All internal
electrical facilities in the Terminal are designed to prevent generation of spark.
Tank Trucks are allowed to enter the Terminal with spark arrestors only so that sparks do not come
out with exhaust from the trucks. Earthing system is provided to dissipate static electrical charges to
eliminate the chances of spark during product handling. Precautions are taken during execution of
maintenance and project works involving welding, cutting, grinding or any other action that can
generate spark.
The Terminal takes adequate care and precautions in its Operations, however in an unlikely event of
fire the Terminal is equipped with fire fighting facilities which include water storage tanks of 8898
m3 filled with water, Auto Fire Hydrant System, Monitors, and dry chemical powder extinguishers.
Foam required to fight Petroleum fires is kept ready in the Terminal for instant use in case of
emergency. Facilities to cool the Tanks, Tank Trucks, and Tank Lorry Filling Shed have also been
provided. Mock Fire Drills are conducted on regular basis to assess the preparedness of the Terminal
employees in handling situations of exigencies and regular training for the same is imparted to them.
6
� Storage tank details& quantities are given in table below:
Sr. No. Product Flammability Class Capacity (m3) Type
1 MS A 12868 IFRVT
2 MS A 12868 IFRVT
3 MS A 12868 IFRVT
4 MS A 12868 IFRVT
5 MS A 12868 IFRVT
6 HSD B 21211 CRVT
7 HSD B 21211 CRVT
8 HSD B 17530 CRVT
8 Transmix Tank for MS 500 CRVT
9 Transmix Tank for HSD 500 CRVT
10 Bio Diesel C 74 Horizontal
Tank
11 Bio Diesel C 74 Horizontal
Tank
5. Need for Project Activity
The proposed Project will help to mitigate:
• Any disruption in supplies or any operational reasons in pumping, there can be dry-out situations
and may also lead to procure bulk POL from non-economical sources.
• With small size vessels and dead stocks (un-pumpable), the effective transfer/receipt quantity is
even less which calls for frequent, switch-over.
• Existing facilities are limited. Any further reduction in storage would lead to severe constraint in
day-to-day operation and a crisis situation.
7
FIGURE-2 LAYOUT DRAWING
6. Environment Control Measures
• During construction phase there will be fugitive emissions due to movement of equipment at site,
dust emitted during the leveling, grading, earthworks, foundation works and other construction
related activities. These impacts will however, be marginal and temporary in nature.
• Periodic LDAR survey shall be carried out to detect & control such measures.
• Sewage generation is envisaged during operation phase and hence STP along with soak pit is
proposed to cater the sewage load. Sewage from the administration building will be routed to the
septic tanks followed by soak pits and the sludge generated from the septic tank will be dried and
used as manure for green belt area.
• Storm water drains are provided at Terminal. These drains carry storm water from Tank
dykes/other areas outside the terminal premises in a controlled manner.
8
• The DG sets shall be acoustically insulated resulting in reduction of noise as per limits prescribed
by State Pollution Control Board. The exhaust pipe from DG sets shall be taken above the
building as per State Pollution Control norms.
• No process / manufacturing involved. There is no hazardous waste as well as solid waste is
generated from process. The waste oil generated from DG sets and fire engines will be collected
in barrel and stored in a closed shed until its disposal and the same will be disposed to Gem
lubricants.
• All conditions & pre-requisites of water and air consents together with certificate to handle
hazardous products issued by State Pollution Control Board shall be strictly adhered to.
7. Fire & Safety Measures
Fire Prevention system-
The Hydrocarbon detection, fire prevention and control system at Vijayawada terminal are the latest and
comply with the OISD norms. The following systems are provided at existing terminal:-
� HYDROCARBON DETECTION SYSTEM AND ANNUNCIATION SYSTEM: Hydrocarbon detectors are installed near all potential leak sources i.e., near MS tank dykes, tank
manifolds, pump house manifold for detection of buildup of explosive vapour concentration.
Hydro Carbon detection system consists of gas detecting sensors linked to a computerized
processing unit and with alarm panels at control room which gives warning annunciation in case
of to explosive vapour build up alert the terminal personnel to take timely corrective action.
� REMOTE SHUT OFF VALVES These are pneumatically operated quick shut off valves provided on pipelines with actuating
points located both remotely and nearer to operating facilities in Terminal. When actuated, the
valves will close within 25 seconds, stopping the flow of pipelines. In case of leakage through
flange joint or rupture of pipeline, the remote operated shut off valves are operated restricting the
leakage of oil to the sections between two ROVs only and in upstream area and the storage area is
cut off from the leaking point, thereby preventing major leakage or fire.
� HIGH LEVEL ALARM This kind of alarm is installed in storage tanks. In case of filling of storage tanks more than safe
capacity of tanks, the alarm will be actuated at control room and leads to closure of REMOTE
OPERATED SHUT OFF VALVES. For this purpose an independent hardwired level switch has
been provided on the storage tanks and is interlocked with alarm and actuation of REMOTE
OPERATED SHUT OFF VALVES.
� DYKE DRAIN VALVE ANNUNCIATION SYSTEM All the dyke valves are fitted with a proximity switch / sensor for indication of the position of the
valve. The valves of the product storage tank dyke shall remain in closed position. In case any
valve is open then Audio alarm and visual indication shall come at control panel for suitable
corrective measures.
� MUTUAL AID Mutual Aid agreement is available with other oil sector units in and around KONDAPALLI and
also larger units in Industrial Area, KONDAPALLI –like IOCL, HPCL & BPCL Terminal and
Pipeline division, LANCO, NIFTY Labs, VTPS.
� EMERGENCY SHUTDOWN BUTTONS & MANUAL CALL POINTS These emergency shutdown push buttons are provided at strategic places in the terminal. In case
of emergency, when the emergency shutdown button is actuated action takes place as specified in
the clause 9.3 of OISD 244 which involves power shut down i.e., tripping of electricity to all the
9
operating equipment in the hazardous area of the terminal and process shutdown which includes
tripping of loading pumps, opening of barrier gates for evacuation of tank trucks from loading
gantry, closure of all remote operated valves on the pipelines, stopping of Tank Lorry filling
operations through batch controllers and sounding of siren. Operation of manual call point will
denote abnormal situation alerting the plant personnel and will involve the sounding of siren only.
These points are provided at strategic locations in the plant.
� FIRE HYDRANT SYSTEM
The main components of the fire water system are:
Fire Water Storage
Fire Water Pumps
Water Sprinkler system
Foam pourer system
Fire Hydrant/ Monitor distribution piping network.
� FIRE WATER STORAGE The terminal is provided with three numbers of above ground vertical cone roof tanks of
capacities 2 X 2413 KL & 1 X 4072 KL each for fire water storage for combating double
contingencies in line with OISD 117 & 244.
� FIRE WATER PUMPS
The terminal is equipped with 4 No’s main & 2 No’s standby diesel engine driven Fire water
pumps of flow rate 410 m3/hr .The 6 No’s Fire Engines are The fire water pumps are provided
with auto start facility which shall function with pressure drop in hydrant line and specified logic
even if initial pump does not start or having started, fails to build up the required pressure in the
fire water ring main system the next pump shall start and so on.
The terminal is also equipped with 1 No main & 1 No standby electric driven jockey pump for
keeping the hydrant system /line pressurized at all times. And also Auto cut-in / cut-off facility is
provided for jockey pumps to maintain the line pressure of 7Kg/cm2 at the farthest point in line
with OISD 244.
� FIXED WATER SPRAY SYSTEM This sprinkler system which is fixed pipe system equipped with open spray nozzles for cooling of
class A & class B storage tanks as per the specifications given in OISD 244.
� FOAM SYSTEM Foam pourers are provided on Class A & Class B storage tanks which are usaed for extinguishing
fire in flammable liquid hazards by discharging foam over the liquid surface in line with OISD
244.
Medium expansion foam generators are also provided to arrest vapour cloud formation from
spilled volatile hydrocarbons
� FIRE HYDRANT SYSTEM/ FIRE WATER RING MAINS The terminal is provided with well laid out hydrant system with alternate double headed hydrant
post and water or water cum foam monitors covering tank farm and other vital facilities.
The fire water system in the terminal is designed to meet the highest fire water flow requirement
of two largest scenarios i.e., Class A & Class B storage tanks on fire plus 144 m3/h for operating
2 Nos. Fire water Monitors/ Supplementary Hose requirements.
10
The water hydrant is hooked up with HPCL, POL terminal hydrant under mutual in case of
emergency. In addition to this there are first aid fire fighting like fire extinguishers of various
type.
Layout of fire water system is shown in Figure-3.
FIGURE-3 FIRE WATER SYSTEM LAYOUT MAP
FIRE ALARM SYSTEM: MAJOR FIRE: A wailing siren for two minutes. Siren will be sounded 3 times for thirty seconds
with an interval of fifteen second in between.
11
DISASTER: Same type of siren as in case of major fire but the same will be sounded for three times
at the interval of 10 seconds in between.
ALL CLEAR (FOR FIRE): Straight run siren for 2 minutes.
PERIODICITY OF VARIOUS TEST/AUDIT: Fire Drill - Monthly
Fire Hose testing –Once in 6 months
Pressure gauge Testing - Once in 6 months
PV Valves calibration – Once in 6 months
Sprinkler Testing – Once in a month
Foam Pourer Testing – Once in a month
Explosive meter –Once in a year
Product Hose Testing – Once in 4 months
Fire Pump log Book – Daily
Fire Extinguisher record – Monthly Visual Check
Fire Extinguisher Servicing Record – Once in 3 months
Strainers of Hydrants and product Lines- Once in 3 months
Hot Work/Cold/Height Work Permits – Immediately
Daily Safety Audit
Self safety Audit - Monthly
Safety Committee Meeting - Once in a month
Safety Circle Meeting - Once in month
ERD- Once in six months
Earth Pit Resistance Testing- Once in six months
Cable Insulation Resistance Testing- Once in six months
Fire Fighting Facilities & Infrastructure: Fire Extinguishers
75 kg dry chemical powders (DCP) - 10 nos.
25 kg dry chemical powders - 22 nos.
10 kg dry chemical powders - 97 nos.
4.5 kg CO2 f.e. - 26 nos.
2.0 kg CO2 f.e. - 27 nos.
A) Dry Chemical Powder
10 kg DCP Fire Extinguishers - 109 Nos.
25 kg DCP Fire Extinguishers - 15 Nos.
75 kg DCP Fire Extinguishers - 6 Nos.
DCP Powder - 950 Kgs
B) CO2 Fire Extinguishers
2 Kg CO2 Fire Extinguishers - 18 Nos
4.5 Kg CO2 Fire Extinguishers - 19 Nos
CO2 cartridges 2 kg – 75 kg DCP - 07 nos.
CO2 cartridges 1 kg – 25 kg DCP - 08 nos.
CO2 cartridges 200 gm – 10 kg DCP - 78 nos.
C) Nozzles
Jet - 28 Nos.
Fog - 04 Nos.
Universal - 8 Nos.
Foam Branching Pipe - 06 Nos.
Water Curtain - 04 NOS.
12
D) FOAM COMPOUND
AFFF - 21 KL
ATC - 1 KL
E) Life Saving Equipment –
Safety Helmets - 71nos.
Strecher With Blanket - 02 Nos.
Explosive Meter - 02 Nos.
Rubber Hand Gloves - 02 Pairs.
First Aid Box - 06 Nos.
Fire Proximity Suit - 02 Nos.
SCABA with Spare Cylinder - 04 Nos.
F) Emergency Spill Control Equipments –
Oil Sorbent Booms - 2 Nos.
G) Electric Siren -3 Km Range - 01 Nos.
Hand Siren - 06 Nos.
H) Water Cum Foam Trolly -
210 Ltrs - 03 Nos.
900 Ltrs - 01 Nos.
I) Hydrant System -
a) Diesel Driven Pumps - 06Nos. X 410KL/HR
b) Jockey Pumps - 2 Nos.
c) Water Cum Foam Monitors - 44Nos
d) Hydrant Points (Double) - 39nos.
e) Fire Hose Box - 31 Nos.
f) Fire Hose - 104Nos.
g) Water Storage
Static Water Sump - 1 X 70 KL
Vertical Conical Roof Water Tank - 2 X 2413 KL + 1 X 4072KL
h) Water Source
Bore Well Pump - 6 Nos.
8. Project Justification, Schedule and Cost
The proposed project shall yield following benefits:
Maintain continuity in supply of products to the consumers through distributors and quality of
services to the consumers.
Ease in availability during crisis period.
Help to overcome the scarcity due to huge gap between demand and supply.
Increase safety measures for hazard detection and prevention system.
Storage is intrinsically and technologically proven safe device
Possibility of BLEVE is ruled out in case of storage.
The terminal augmentation / modernization is estimated to cost Rs. 372 Crores and the proposed
project is estimated to be completed within 24 months from obtaining all the regulatory clearances.