Predicting Project Completion Date Using EVM · Using Earned Value Management Predicting Project...
Transcript of Predicting Project Completion Date Using EVM · Using Earned Value Management Predicting Project...
© MMVI, Management Technologies© MMVI, Management Technologies11
Predicting Project Completion Date Using Earned Value Management
Predicting Project Completion Date Predicting Project Completion Date Using Earned Value ManagementUsing Earned Value Management
NASA PM Challenge 2006
March 21-22
Galveston
Ray W. Stratton, PMP, EVP
714-318-2231
raystratton@ mgmt-technologies.com
© MMVI, Management Technologies© MMVI, Management Technologies22
Presentation OutlinePresentation Outline
�� Refresher on EVM conceptsRefresher on EVM concepts
�� The Problem with SPIThe Problem with SPI
�� The Earned Schedule ConceptThe Earned Schedule Concept
�� Comprehensive ExampleComprehensive Example
�� Research ResultsResearch Results
�� Earned Schedule MaturityEarned Schedule Maturity
�� ConclusionsConclusions
�� References and Contact InformationReferences and Contact Information
© MMVI, Management Technologies© MMVI, Management Technologies33
WhatWhat Could be New Could be New AboutAbout EVM?EVM?
�� In the 1900’s.....In the 1900’s.....
�� EVM used in DoD, NASA, DoE, DoT, elsewhereEVM used in DoD, NASA, DoE, DoT, elsewhere
�� Provided Cost and Schedule Variances (CV, SV)Provided Cost and Schedule Variances (CV, SV)
�� Computed Cost and Schedule Performance Indices Computed Cost and Schedule Performance Indices
(CPI, SPI(CPI, SPI$$))
�� Produced “Estimated Produced “Estimated CostCost at Complete” (EAC)at Complete” (EAC)
�� 2121stst Century Improvements to EVMCentury Improvements to EVM
�� Provides SV in Provides SV in timetime unitsunits
�� Computes SPIComputes SPItt based on based on timetime unitsunits
�� Produces “Estimated Produces “Estimated DateDate of Completion”of Completion”
© MMVI, Management Technologies© MMVI, Management Technologies44
RefresherRefresher ononEarned Value ConceptsEarned Value Concepts
How earned value management is different from cost reports and schedule updates.
••Refresher on EVM conceptsRefresher on EVM concepts••The Problem with SPIThe Problem with SPI••The Earned Schedule ConceptThe Earned Schedule Concept••Comprehensive ExampleComprehensive Example••Research ResultsResearch Results••Earned Schedule MaturityEarned Schedule Maturity••ConclusionsConclusions••References and Contact InformationReferences and Contact Information
© MMVI, Management Technologies© MMVI, Management Technologies55
Basic EVM ConceptsBasic EVM Concepts
�� Relate the money spent to the work doneRelate the money spent to the work done
�� Combines schedule status with cost informationCombines schedule status with cost information
�� Requires common “units” of measureRequires common “units” of measure
�� Fundamental conceptsFundamental concepts
�� The work has value equal to its budget The work has value equal to its budget
�� The project “equity” is the sum of The project “equity” is the sum of the value of the value of all all
work done towork done to--datedate
�� Building the equity (Earned Value) should equal the Building the equity (Earned Value) should equal the
budget planned for the work done (budget planned for the work done (spend spend appropriately)appropriately)
�� The equity should accumulate at the rate planned The equity should accumulate at the rate planned
(stay on schedule)(stay on schedule)
© MMVI, Management Technologies© MMVI, Management Technologies66
The Three Key Elements of EVMThe Three Key Elements of EVM
�� Only three terms (two we already Only three terms (two we already have)have)
�� Planned Value (PV)Planned Value (PV)
�� Actual Cost (AC)Actual Cost (AC)
�� Earned Value (EV)Earned Value (EV)
© MMVI, Management Technologies© MMVI, Management Technologies77
The Planned Value (PV)The Planned Value (PV)
�� The The scheduleschedule (plan) to build project equity from zero to (plan) to build project equity from zero to
the total project valuethe total project value
�� The expected gain in project equity as each piece of The expected gain in project equity as each piece of
work is completedwork is completed
�� Previously “budgeted cost of work scheduled” (BCWS)Previously “budgeted cost of work scheduled” (BCWS)
Time
Value ($ or hours) Planned
Value
Performance Measurement
Baseline (PMB)
© MMVI, Management Technologies© MMVI, Management Technologies88
The Earned Value (EV)The Earned Value (EV)
�� The project equity gained, The project equity gained, regardless of the cost to regardless of the cost to accomplish the workaccomplish the work..
�� The gain in project equity as a result of completed workThe gain in project equity as a result of completed work
�� Previously “budgeted cost of work performed” (BCWP)Previously “budgeted cost of work performed” (BCWP)
Value ($ or hours) Planned
Value
Earned Value
Time
Now
© MMVI, Management Technologies© MMVI, Management Technologies99
The Actual Cost (AC)The Actual Cost (AC)
�� The total cost of the completed workThe total cost of the completed work
�� Previously “actual cost of work performed” (ACWP)Previously “actual cost of work performed” (ACWP)
Value ($ or hours)
Planned Value
Earned Value
Time
Now
Actual Costs
© MMVI, Management Technologies© MMVI, Management Technologies1010
Analyzing Variances From the PlanAnalyzing Variances From the Plan
Value ($ or hours)
Time
Now
PlannedValue
Earned Value
Actual Costs
{ } Cost Variance
ScheduleVariance
© MMVI, Management Technologies© MMVI, Management Technologies1111
Cost Performance Index (CPI)Cost Performance Index (CPI)
�� ““Did the cost of Did the cost of adding “equity”adding “equity” equal the equal the “equity” “equity”
added?”added?”
�� CPI = progress/costCPI = progress/cost
�� CPI = EV/ACCPI = EV/AC
�� Greater than 1.0 is good, less than 1.0 is badGreater than 1.0 is good, less than 1.0 is bad
�� ExampleExample
66.01500
1000
___
_ ====hrs
hrs
DONEWORKOFCOST
DONEWORK
AC
EVCPI
(this is not good)
© MMVI, Management Technologies© MMVI, Management Technologies1212
Schedule Performance Index (SPI$)Schedule Performance Index (SPI$)
�� ““Did a month’s of schedule produce a month of Did a month’s of schedule produce a month of
progress?”progress?”
�� SPI$ = progress/planSPI$ = progress/plan
�� SPI$ = EV/PVSPI$ = EV/PV
�� Greater than 1.0 is good, less than 1.0 is badGreater than 1.0 is good, less than 1.0 is bad
�� ExampleExample
2.11000
1200
_
_$ ====
hrs
hrs
PLANNEDWORK
DONEWORK
PV
EVSPI
(this is good)
© MMVI, Management Technologies© MMVI, Management Technologies1313
TheThe Problem with SPIProblem with SPI
We’ve been using SPI for 30+ Years,What could be wrong with it?
••Refresher on EVM conceptsRefresher on EVM concepts••The Problem with SPIThe Problem with SPI••The Earned Schedule ConceptThe Earned Schedule Concept••Comprehensive ExampleComprehensive Example••Research ResultsResearch Results••Earned Schedule MaturityEarned Schedule Maturity••ConclusionsConclusions••References and Contact InformationReferences and Contact Information
© MMVI, Management Technologies© MMVI, Management Technologies1414
Two Serious Problems with SPITwo Serious Problems with SPI$$
�� SPISPI$$ fails in the endfails in the end
�� SPISPI$$ = EV/PV= EV/PV
�� At project completion EV = PVAt project completion EV = PV
�� SPISPI$$ = EV/PV = PV/PV = 1.0 at project end= EV/PV = PV/PV = 1.0 at project end
�� Implications:Implications:
�� At project start SPI is reliableAt project start SPI is reliable
�� At some point SPI accuracy diminishesAt some point SPI accuracy diminishes
�� Toward the project end it is Toward the project end it is uselessuseless
�� SPISPI$$ does not show weeks or months of schedule does not show weeks or months of schedule
variancevariance
�� What most people want to know and understandWhat most people want to know and understand
© MMVI, Management Technologies© MMVI, Management Technologies1515
Graphing the Problem with SPIGraphing the Problem with SPI$$
1.0
.9
1.1
1.2
.8
SPI$
TIME
ActualProjectFinish
OriginalProjectFinish
3 months
SPI$
Project schedule improvement or false indications
due to SPI?
© MMVI, Management Technologies© MMVI, Management Technologies1616
Using CPI and SPIUsing CPI and SPI$$ ininEstimating the Final CostEstimating the Final Cost
�� Simple extrapolationSimple extrapolation
�� Final cost = cost of work done + (work left/past Final cost = cost of work done + (work left/past
performance)performance)
�� Assumes future performance is same as past (generally Assumes future performance is same as past (generally
true)true)
�� EAC (CPI) = AC+(BACEAC (CPI) = AC+(BAC--EV)/CPI = BAC/CPIEV)/CPI = BAC/CPI
�� EAC (CPI, SPIEAC (CPI, SPI$$) = AC+(BAC) = AC+(BAC--EV)/(CPI*SPIEV)/(CPI*SPI$$))
Toward the end of the project how accurate
can this term be?
© MMVI, Management Technologies© MMVI, Management Technologies1717
TheThe Earned Schedule ConceptEarned Schedule Concept
Creating a Schedule Performance Index that is accurate to the end of the project.
••Refresher on EVM conceptsRefresher on EVM concepts••The Problem with SPIThe Problem with SPI••The Earned Schedule ConceptThe Earned Schedule Concept••Comprehensive ExampleComprehensive Example••Research ResultsResearch Results••Earned Schedule MaturityEarned Schedule Maturity••ConclusionsConclusions••References and Contact InformationReferences and Contact Information
© MMVI, Management Technologies© MMVI, Management Technologies1818
At What Point Did I Expect to Attain my At What Point Did I Expect to Attain my Current Earned Value?Current Earned Value?
Budget
or
staff hours
Time
Work done (EV)
When work was to be
done (PV)!
Actual Time (AT) i.e., NOW
Earned Schedule (ES) i.e.,How much have you accomplished and
when were supposed to?
10 months6 months
AC is not shown in this example since this is
about Earned Schedule!
© MMVI, Management Technologies© MMVI, Management Technologies1919
Some New TermsSome New Terms
�� AT = Actual Time (now, or data date)AT = Actual Time (now, or data date)
�� ES = Earned Schedule (Point in time when ES = Earned Schedule (Point in time when currentcurrentprogress was progress was plannedplanned to occur)to occur)
�� PD = Planned Duration (planned project duration)PD = Planned Duration (planned project duration)
�� ED = Estimated Duration (estimated project duration)ED = Estimated Duration (estimated project duration)
�� PCD = Planned Completion Date (Planned project end PCD = Planned Completion Date (Planned project end
date)date)
�� ECD = Estimated Completion Date (Estimated project ECD = Estimated Completion Date (Estimated project
end date)end date)
© MMVI, Management Technologies© MMVI, Management Technologies2020
Some New FormulasSome New Formulas
�� SVSVtt = ES = ES -- AT (Schedule Variance in time units, note AT (Schedule Variance in time units, note
subscript versus SVsubscript versus SV$$))
�� SVSVtt = 6 months = 6 months –– 10 months = 10 months = --4 months4 months
�� SPISPItt = ES/AT (SPI in time units)= ES/AT (SPI in time units)
�� SPISPItt = 6/10 = 0.6= 6/10 = 0.6
© MMVI, Management Technologies© MMVI, Management Technologies2121
The Traditional and the NewThe Traditional and the New
Planned Budget (BAC)
Work done (EV)
Planned work (PV)
Actual Time (AT)
Earned Schedule (ES)
Planned Duration (PD)
ScheduleVariance (SVt)
BAC
Funds spent (AC)
Budget Spent
Work Done
Cost Variance
(CV)
ScheduleVariance (SV$)
PlannedCompletion
Date
© MMVI, Management Technologies© MMVI, Management Technologies2222
Traditional and New EVM Analysis ToolsTraditional and New EVM Analysis Tools
PV
EVSPI =$
AC
EVCPI =
CPI
BACEAC =
AT
ESSPI t =
tSPI
PDED =
Traditional New
ACEVCV −=
PVEVSV −=$ ATESSVt −=
EDdatestartECD += _
© MMVI, Management Technologies© MMVI, Management Technologies2323
Comprehensive ExampleComprehensive Example
Putting all the pieces together.
••Refresher on EVM conceptsRefresher on EVM concepts••The Problem with SPIThe Problem with SPI••The Earned Schedule ConceptThe Earned Schedule Concept••Comprehensive ExampleComprehensive Example••Research ResultsResearch Results••Earned Schedule MaturityEarned Schedule Maturity••ConclusionsConclusions••References and Contact InformationReferences and Contact Information
© MMVI, Management Technologies© MMVI, Management Technologies2424
Comprehensive ExampleComprehensive Example
Planned Budget (BAC)
Actual Time (AT)
Earned Schedule (ES)
Planned Duration (PD)
ScheduleVariance (SVt)
Budget Spent
Work Done
Cost Variance
(CV)
18 PD10 AT6 ES
4 EV
7 PV
5 AC
12 BAC
Work done (EV)
Planned work (PV)
Funds spent (AC)
© MMVI, Management Technologies© MMVI, Management Technologies2525
Comparing EVComparing EV and and ES Schedule AnalysisES Schedule Analysis
57.07$
4$$ ===
PV
EVSPI 6.0
10
6 ===months
months
AT
ESSPI t
monthsmonths
SPI
PDED
t
306.0
18 ===
Traditional New
3$7$4$$ −=−=−= PVEVSVmonthsSV
monthsmonthsATESSV
t
t
4
106
−=
−=−=
?=ED
© MMVI, Management Technologies© MMVI, Management Technologies2626
New Analysis ProductsNew Analysis Products
�� Schedule performance index {SPI(t) or SPISchedule performance index {SPI(t) or SPItt}}
�� Schedule Variance {SV(t) or SVSchedule Variance {SV(t) or SVtt}}
�� Estimated Duration (ED)Estimated Duration (ED)
�� Estimated Completion Date (ECD)Estimated Completion Date (ECD)
© MMVI, Management Technologies© MMVI, Management Technologies2727
Research ResultsResearch Results
Does Earned Schedule really work?
••Refresher on EVM conceptsRefresher on EVM concepts••The Problem with SPIThe Problem with SPI••The Earned Schedule ConceptThe Earned Schedule Concept••Comprehensive ExampleComprehensive Example••Research ResultsResearch Results••Earned Schedule MaturityEarned Schedule Maturity••ConclusionsConclusions••References and Contact InformationReferences and Contact Information
© MMVI, Management Technologies© MMVI, Management Technologies2828
Empirical EvidenceEmpirical Evidence((Henderson)Henderson)
�� Findings derived from a small set of real life project dataFindings derived from a small set of real life project data
Commercial IT Infrastructure Expansion Project Phas e 1
Earned Schedule, Independent Estimate At Completion (time) - IEAC(t)as at Project Completion: Week Starting 15th July x x
0
5
10
15
20
25
30
35
40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Actual Time (Weeks)
Dur
atio
n (W
eeks
)
Planned Schedule Earned Schedule cum IEAC(t) PD/SPI(t)
Henderson, K., 2003, “Earned schedule: a breakthrough extension to earned value theory? A retrospectiveanalysis of real project data”, The Measurable News, Summer 2003, 21, 13-17
© MMVI, Management Technologies© MMVI, Management Technologies2929
Academic ResearchAcademic Research(Vanhoucke)(Vanhoucke)
�� Created 3,100 project activity networksCreated 3,100 project activity networks
�� Constructed a schedule for each networkConstructed a schedule for each network
�� Simulated (executed) activity duration and cost in a Simulated (executed) activity duration and cost in a
controlled way (9 execution scenarios, each schedule controlled way (9 execution scenarios, each schedule
subjected to each scenario 100 times)subjected to each scenario 100 times)
�� Monitored and forecasted at each reporting periodMonitored and forecasted at each reporting period
�� Analysed the data (3.100 x 9 x 100 = 2.790.000 project Analysed the data (3.100 x 9 x 100 = 2.790.000 project
data sets)data sets)
Vanhoucke M., Vandevoorde St., Vanhoucke M., Vandevoorde St., A Simulation and Evaluation of Earned Value A Simulation and Evaluation of Earned Value Metrics to Forecast the Project Duration,Metrics to Forecast the Project Duration, Ghent University, Working Paper Ghent University, Working Paper
2005/312, June 20052005/312, June 2005
© MMVI, Management Technologies© MMVI, Management Technologies3030
The Nine Simulation ScenariosThe Nine Simulation Scenarios
�� Critical Path ActivitiesCritical Path Activities
�� Real Duration < Planned Real Duration < Planned
DurationDuration
�� Real Duration = Planned Real Duration = Planned
DurationDuration
�� Real Duration > Planned Real Duration > Planned
DurationDuration
�� NonNon--Critical Path ActivitiesCritical Path Activities
�� Real Duration < Planned Real Duration < Planned
DurationDuration
�� Real Duration = Planned Real Duration = Planned
DurationDuration
�� Real Duration > Planned Real Duration > Planned
DurationDuration
© MMVI, Management Technologies© MMVI, Management Technologies3131
Research ProcessResearch Process
© MMVI, Management Technologies© MMVI, Management Technologies3232
Academic Research ResultsAcademic Research Results
� “The results reveal that the Earned Schedule method outperforms, on the average, all other forecasting methods.”
Vanhoucke M., Vandevoorde St., Vanhoucke M., Vandevoorde St., A Simulation and Evaluation of Earned Value A Simulation and Evaluation of Earned Value Metrics to Forecast the Project Duration,Metrics to Forecast the Project Duration, Ghent University, Working Paper Ghent University, Working Paper
2005/312, June 20052005/312, June 2005
© MMVI, Management Technologies© MMVI, Management Technologies3333
EarnedEarned Schedule Maturity Schedule Maturity
Current state of Earned Schedule development and deployment
••Refresher on EVM conceptsRefresher on EVM concepts••The Problem with SPIThe Problem with SPI••The Earned Schedule ConceptThe Earned Schedule Concept••Comprehensive ExampleComprehensive Example••Research ResultsResearch Results••Earned Schedule MaturityEarned Schedule Maturity••ConclusionsConclusions••References and Contact InformationReferences and Contact Information
© MMVI, Management Technologies© MMVI, Management Technologies3434
Earned Schedule MaturityEarned Schedule Maturity
�� First paper: March 2003, PMIFirst paper: March 2003, PMI--CPM Measurable NewsCPM Measurable News
�� Over twenty presentations and publicationsOver twenty presentations and publications
�� A growing trend and management expectationA growing trend and management expectation
�� Yet to appear in commercial EVM software productsYet to appear in commercial EVM software products
�� Early AdoptersEarly Adopters
�� USAFUSAF
�� Lockheed MartinLockheed Martin
�� BoeingBoeing
�� BelgiumBelgium
�� Management Technologies (education, processes)Management Technologies (education, processes)
© MMVI, Management Technologies© MMVI, Management Technologies3535
USAF PlanningUSAF Planning
�� Air Force understands the potential of Earned ScheduleAir Force understands the potential of Earned Schedule
�� Demonstrate Earned Schedule on a sample set of Demonstrate Earned Schedule on a sample set of
programsprograms
�� Build a body of evidence on a larger set of programsBuild a body of evidence on a larger set of programs
�� Validate the Earned Schedule as a value added program Validate the Earned Schedule as a value added program
management toolmanagement tool
�� Integrate Earned Schedule as a tool in Air Force Integrate Earned Schedule as a tool in Air Force
AcquisitionAcquisition
© MMVI, Management Technologies© MMVI, Management Technologies3636
Lockheed Martin, Program #1Lockheed Martin, Program #1
45
50
55
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
PD IEAC(t) Linear (IEAC(t))
45
50
55
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
PD IEAC(t) Linear (IEAC(t))
IEAC(t) = (PD ÷ SPIt)
PD = 48 PD = 54
© MMVI, Management Technologies© MMVI, Management Technologies3737
Lockheed Martin, Program #2Lockheed Martin, Program #2
35
40
45
50
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41
IEAC(t) Linear (IEAC(t))
PD = 39 AD = 42
IEAC(t) = (PD ÷ SPIt)
© MMVI, Management Technologies© MMVI, Management Technologies3838
The Good News!The Good News!
�� PreviouslyPreviously
�� EVM was great at cost managementEVM was great at cost management
�� EVM was “ok” at schedule management, EVM was “ok” at schedule management, sometimessometimes
�� NowNow
�� EVM can address both cost and schedule wellEVM can address both cost and schedule well
�� EVM can estimateEVM can estimate
�� Cost at completionCost at completion
�� Completion date!Completion date!
�� SPISPItt can record project outcome in lessons learnedcan record project outcome in lessons learned
© MMVI, Management Technologies© MMVI, Management Technologies3939
Credit to Discoverers, Advocates, & Credit to Discoverers, Advocates, & ResearchersResearchers
�� Henderson Kym, Henderson Kym, Earned Schedule: A Breakthrough Extension to Earned Schedule: A Breakthrough Extension to
Earned Value Theory? A Retrospective Analysis of Real Project Earned Value Theory? A Retrospective Analysis of Real Project
Data,Data,The Measurable News, Summer 2003The Measurable News, Summer 2003
�� Robert Handshuh, New Concept in Earned Value Robert Handshuh, New Concept in Earned Value -- Earned Earned
Schedule, PMI Southeast Regional Conference USA, June 2005Schedule, PMI Southeast Regional Conference USA, June 2005
�� Walt Lipke & Kym Henderson, Earned Schedule Status Update Walt Lipke & Kym Henderson, Earned Schedule Status Update
and Early Adaptor Applications Feedback, 17th IPMC November and Early Adaptor Applications Feedback, 17th IPMC November
20052005
�� Vandevoorde St., Vanhoucke M., A Comparison of different Vandevoorde St., Vanhoucke M., A Comparison of different
project duration forecasting methods using earned value project duration forecasting methods using earned value
metrics, Ghent University, working paper 2005/312, June 2005metrics, Ghent University, working paper 2005/312, June 2005
�� Approved for Publishing in “International Journal of Project Approved for Publishing in “International Journal of Project
Management”Management”
�� State of the Art Report on Forecasting Duration MethodsState of the Art Report on Forecasting Duration Methods
© MMVI, Management Technologies© MMVI, Management Technologies4040
ConclusionsConclusions
So What?
••Refresher on EVM conceptsRefresher on EVM concepts••The Problem with SPIThe Problem with SPI••The Earned Schedule ConceptThe Earned Schedule Concept••Comprehensive ExampleComprehensive Example••Research ResultsResearch Results••Earned Schedule MaturityEarned Schedule Maturity••ConclusionsConclusions••References and Contact InformationReferences and Contact Information
© MMVI, Management Technologies© MMVI, Management Technologies4141
What We Know About Earned ScheduleWhat We Know About Earned Schedule
�� Faithful to the project’s endFaithful to the project’s end
�� Provides a reliable means to calculate an estimated Provides a reliable means to calculate an estimated
completion datecompletion date
�� Provides Provides a useful schedulea useful schedule performance metricperformance metric for for
project history andproject history and lessons learnedlessons learned
�� May provide a better estimated completion date than May provide a better estimated completion date than
critical path critical path methods!methods!
© MMVI, Management Technologies© MMVI, Management Technologies4242
Why use ES?Why use ES?
�� More intuitive schedule informationMore intuitive schedule information
�� Schedule variance Schedule variance in in timetime units (intuitive to most people)units (intuitive to most people)
�� Cost variance in Cost variance in resource ($$) resource ($$) unitsunits
�� SPISPItt retains utility to project end retains utility to project end
�� SPISPItt does not automatically creep toward 1.0 near does not automatically creep toward 1.0 near
project endproject end
�� SPISPItt captures the final project captures the final project schedule performance schedule performance
datadata
�� Can finallyCan finally estimate estimate Project Completion DateProject Completion Date
© MMVI, Management Technologies© MMVI, Management Technologies4343
Reference and Contact InformationReference and Contact Information
Tell me more!
••Refresher on EVM conceptsRefresher on EVM concepts••The Problem with SPIThe Problem with SPI••The Earned Schedule ConceptThe Earned Schedule Concept••Comprehensive ExampleComprehensive Example••Research ResultsResearch Results••Earned Schedule MaturityEarned Schedule Maturity••ConclusionsConclusions••References and Contact InformationReferences and Contact Information
© MMVI, Management Technologies© MMVI, Management Technologies4444
Seminal DocumentsSeminal Documents
�� Lipke, Walter, “Schedule is Different”, The Measurable Lipke, Walter, “Schedule is Different”, The Measurable
News, March and Summer 2003News, March and Summer 2003
�� Henderson, Kym, “Further Development in Earned Henderson, Kym, “Further Development in Earned
Schedule”, The Measurable News, Spring 2003Schedule”, The Measurable News, Spring 2003
�� Henderson, Kym, Earned Schedule: A Breakthrough Henderson, Kym, Earned Schedule: A Breakthrough
Extension to Earned Value Theory? A Retrospective Extension to Earned Value Theory? A Retrospective
Analysis of Real Project Data, The Measurable News, Analysis of Real Project Data, The Measurable News,
Summer 2003Summer 2003
The Measurable news is a quarterly publication of the Project Management Institute’s College of Performance Management
www.pmi-cpm.org
© MMVI, Management Technologies© MMVI, Management Technologies4545
Other ReferencesOther References
�� Earned Schedule Status Update and Early Adopter Applications FeeEarned Schedule Status Update and Early Adopter Applications Feedback dback
Presentation facilitated by Walt Lipke and Kym Henderson, 17th IPresentation facilitated by Walt Lipke and Kym Henderson, 17th IPMC PMC
November 2005 November 2005
�� Earned Schedule Leads to Improved Forecasting:Earned Schedule Leads to Improved Forecasting:
Presentation by Walt Lipke, intended for 17th IPMC November 2005Presentation by Walt Lipke, intended for 17th IPMC November 2005
�� Earned Schedule in Action:Paper by Kym Henderson, published PMI Earned Schedule in Action:Paper by Kym Henderson, published PMI CPM CPM
Journal, The Measurable News "Spring" 2005 Journal, The Measurable News "Spring" 2005
�� Forecasting Project Schedule Completion by Using Earned Value MeForecasting Project Schedule Completion by Using Earned Value Metrics, trics,
Presentation by Ing. Stephan Vandevoorde, Senior Project ManagerPresentation by Ing. Stephan Vandevoorde, Senior Project Manager, ,
Fabricom Airport Systems and Prof. Dr. Mario Vanhoucke, Ghent UnFabricom Airport Systems and Prof. Dr. Mario Vanhoucke, Ghent University, iversity,
Belgium, Early Warning Signals Conference, V.U.B. Brussels, JuneBelgium, Early Warning Signals Conference, V.U.B. Brussels, June 2005 2005
�� Not Your Father's Earned Value: Earned Schedule overview paper bNot Your Father's Earned Value: Earned Schedule overview paper by Ray y Ray
Stratton, published on Projects@Work (http://www.projectsatwork.Stratton, published on Projects@Work (http://www.projectsatwork.com) 24 com) 24
Feb 2005 Feb 2005
�� Connecting Earned Value to the Schedule:Paper by Walt Lipke, pubConnecting Earned Value to the Schedule:Paper by Walt Lipke, published lished
PMI CPM Journal, The Measurable News, "Winter" 2004 PMI CPM Journal, The Measurable News, "Winter" 2004
© MMVI, Management Technologies© MMVI, Management Technologies4646
OneOne--Stop ShoppingStop Shopping
�� Comprehensive Library of EVM and Earned ScheduleComprehensive Library of EVM and Earned Schedule
�� PapersPapers
�� PresentationsPresentations
http://sydney.pmichaptershttp://sydney.pmichapters--australia.org.au/australia.org.au/
Click “Education,” then “Presentations and Papers” for .pdf copiClick “Education,” then “Presentations and Papers” for .pdf copieses
© MMVI, Management Technologies© MMVI, Management Technologies4747
In ClosingIn Closing ………………
If you are not practicing Earned Schedule as part of your
Earned Value Management System ………
………you are practicing 20th CenturyEarned Value Management!
© MMVI, Management Technologies© MMVI, Management Technologies4848
Discussion and QuestionsDiscussion and Questions
Ray W. Stratton, EVP, PMP
President, Management Techologies
PMI CPM Vice President, Research and Standards
714-318-2231
www.mgmt-technologies.com