Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project...

121
FY2018 Study on overseas business development of Japanese high-quality energy infrastructure Pre-Feasibility study on improvement of grid operation by introducing secure power system operation technology in Asia Final Report March 2019 Prepared for: Ministry of Economy, Trade and Industry Prerared by: TEPCO IEC, Inc.

Transcript of Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project...

Page 1: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

FY2018 Study on overseas business development of Japanese high-quality energy infrastructure

Pre-Feasibility study on improvement of grid

operation by introducing secure power system

operation technology in Asia

Final Report

March 2019

Prepared for:

Ministry of Economy, Trade and Industry

Prerared by:

TEPCO IEC, Inc.

Page 2: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

Bangladesh

Page 3: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

i

Contents

Contents .................................................................................................................................................................................. i

Abbreviation ........................................................................................................................................................................ iii

1 Project Description ...................................................................................................................................................1-1

1.1 Project Objective...........................................................................................................................................1-1

1.2 Project Description.......................................................................................................................................1-1

1.3 Project Implementation Structure ..........................................................................................................1-3

1.4 Project Implementation Schedule ..........................................................................................................1-3

2 Current Status of the Country Surveyed ..........................................................................................................2-1

2.1 Basic Information about the Country ...................................................................................................2-1

Economic Conditions .........................................................................................................................2-1

(1) GDP ...........................................................................................................................................................2-1

(2) Industrial Structure .............................................................................................................................2-1

Economic Growth Policy ...................................................................................................................2-3

2.2 Electricity Policy .............................................................................................................................................2-3

Overview of Electricity Sector of Bangladesh ...........................................................................2-3

(1) Power Division ......................................................................................................................................2-4

(2) Power Cell ..............................................................................................................................................2-4

(3) Bangladesh Power Development Board (BPDB)......................................................................2-4

(4) Bangladesh Rural Electrification Board (BREB) ........................................................................2-4

(5) Sustainable and Renewable Energy Development Authority (SREDA) ...........................2-5

(6) Power Grid Company of Bangladesh Ltd. (PGCB) ...................................................................2-5

Electricity Sector Policy .....................................................................................................................2-5

Grid Code ...............................................................................................................................................2-6

3 Current Status and Future Outlook of Electricity Supply ..........................................................................3-1

3.1 Existing Substations, Power Stations ....................................................................................................3-1

3.2 Ongoing, Planned Substations ............................................................................................................. 3-10

3.3 Revisiting PSMP2016 Plan ...................................................................................................................... 3-10

3.4 Data for Verification ................................................................................................................................. 3-10

4 Current Status of Power Control Operation and Power Control Facilities .........................................4-1

4.1 Power Control Operation ..........................................................................................................................4-1

Supervisory Control System ............................................................................................................4-1

Operation ...............................................................................................................................................4-2

(1) Supervisory Operation ......................................................................................................................4-2

(2) Switching Operation ..........................................................................................................................4-3

(3) Data Recording ....................................................................................................................................4-4

(4) Voltage Regulation .............................................................................................................................4-6

(5) Data Maintenance ............................................................................................................................ 4-13

Training ................................................................................................................................................ 4-13

(1) Training Policy ................................................................................................................................... 4-13

(2) Training Resources........................................................................................................................... 4-13

(3) Training for operators .................................................................................................................... 4-14

(4) Other Programs ................................................................................................................................ 4-14

4.2 Facilities ......................................................................................................................................................... 4-14

SCADA/EMS ........................................................................................................................................ 4-14

(1) Hardware Configuration ................................................................................................................ 4-15

(2) Applications ........................................................................................................................................ 4-15

Communication Network .............................................................................................................. 4-15

Page 4: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

ii

5 Issues of Power Control Operation and Control Facilities Based on Future Facility Expansion .5-1

5.1 Power Control Operation ..........................................................................................................................5-1

Supervisory Control System ............................................................................................................5-1

(1) Division of Roles ..................................................................................................................................5-1

(2) Workload ................................................................................................................................................5-1

Operation ...............................................................................................................................................5-1

(1) Supervisory Operation ......................................................................................................................5-1

(2) Switching Operation ..........................................................................................................................5-1

(3) Data Recording ....................................................................................................................................5-2

(4) Voltage Regulation .............................................................................................................................5-2

(5) Data Maintenance ...............................................................................................................................5-3

Training ...................................................................................................................................................5-3

5.2 Facilities ............................................................................................................................................................5-3

SCADA/EMS ...........................................................................................................................................5-3

(1) Hardware Configuration ...................................................................................................................5-3

(2) Applications ...........................................................................................................................................5-4

Communication network ..................................................................................................................5-4

6 Improvements in Project Schemes ....................................................................................................................6-1

6.1 Operation ........................................................................................................................................................6-1

Supervisory Control System ............................................................................................................6-1

(1) Delegation of Authority ....................................................................................................................6-1

(2) Organizational Configuration .........................................................................................................6-1

Operation ...............................................................................................................................................6-3

(1) Supervisory Operation ......................................................................................................................6-3

(2) Switching Operation ..........................................................................................................................6-3

(3) Data Recording ....................................................................................................................................6-4

(4) Voltage Regulation .............................................................................................................................6-4

(5) Data Maintenance ...............................................................................................................................6-4

Training ...................................................................................................................................................6-5

6.2 Facilities ............................................................................................................................................................6-6

SCADA .....................................................................................................................................................6-6

(1) Hardware Configuration ...................................................................................................................6-6

(2) Application Configuration................................................................................................................6-6

Communication Network .................................................................................................................6-7

6.3 Project Implementation Structure and Schedule .............................................................................6-7

6.4 Result of Pre-Feasibility Study .................................................................................................................6-7

7 Benefits from Improvements in the Project ...................................................................................................7-1

7.1 Expected Benefits for the Partner Country .........................................................................................7-1

Minimizing the Increase in Personnel Expenses .....................................................................7-1

Reductions in Economic Losses by Shortening Power Outages .......................................7-2

Reducing Loss in Leased Transmission Fees .............................................................................7-3

7.2 Estimating CO2 Emission Reductions ...................................................................................................7-3

7.3 Expected Benefits for Japan .....................................................................................................................7-4

7.4 Assessing Japanese Companies' Competitive Advantages ..........................................................7-5

7.5 Possible Utilization of Financing and Government Support ........................................................7-5

7.6 Promoting this Approach to Other Countries ...................................................................................7-5

Page 5: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

iii

Abbreviations

ABBREVIATION FULL TYTLE

ALDC Area Load Dispatching Center

BLDC Bulk Load Dispatch Center

BPDB Bangladesh Power Development Board

BPDP Bangladesh Power Development Board

BREB Bangladesh Rural Electrification Board

E/O Emergency Outage

EMS Energy Management System

HRM Human Resource Management Department

IPP Independent Power Producer

MPEMR Ministry of Power, Energy and Mineral Resources

NLDC National Load Dispatching Center

ODA Official Development Assistance

OPGW Optical Ground Wire

PGCB Power Grid Company of Bangladesh Limited

PLC Power Line Carrier

PSMP Power System Master Plan

S/O Scheduled Outage

SCADA Supervisory Control And Data Acquisition

SREDA Sustainable and Renewable Energy Development Authority

Page 6: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

1-1

1 Project Description

1.1 Project Objective

Electricity Network of Bangladesh consists of only one national grid system which is wholly owned,

operated and maintained by Power Grid Company of Bangladesh Ltd (PGCB). The power generation

capacity of Bangladesh presently reached at about 15,000MW. Bangladesh, being a developing

country, power demand is increasing rapidly. To meet up the continuously increasing demand of

electricity, Government of Bangladesh (GoB) is encouraging as well as giving permission to establish

new power plants both in public and private sector. . Presently, grid system of Bangladesh is running

with 132kV, 230kV and 400kV transmission lines along with corresponding 132/33kV, 230/132kV,

400/230kV and 400/132kV grid substations. According to Power System Master Plan (PSMP)

generation capacity of Bangladesh will reach to approximately 40,000 MW by 2030. To transmit and

distribute evacuate this huge amount of generated electricity power, power grid must be expanded.

Figure 1-1 shows the grid network of PGCB in 2010 and 2018.

PGCB is presently using EMS/SCADA for National Load Dispatch Center (NLDC). NLDC is monitoring

and controlling (by using phone communication) all sub-stations in actual. As the reinforcement of

power generation and expansion of grid, it is estimable that the current organization of NLDC will

be reached to the limit. The capacity of power stations will be increased and NLDC will be involved

more on generation and demand management. So, the organizational structure of NLDC should be

reformed and a new setup should be established for grid monitoring and controlling. At present

only 2 National Load Dispatch Centers (ALDCs) are functioning, but for the future system with large

number of substations more ALDCs must be established.

This project aims to carry out a feasibility study on introduction of Japanese high-quality power

system operation technology by investigating and analyzing of organization, operation and SCADA

of PGCB.

1.2 Project Description

This project is intended to survey the following items.

i. Background survey

a. The partner country's policy trends

b. The partner company's strategic trends

ii. Collecting the information needed to introduce power system operation technology

a. Assessing the current status of electricity infrastructure

b. Assessing the partner company's needs and challenges

c. Current and future trends in supervisory control systems

d. Human resource development framework

iii. Survey on energy-derived CO2 emission reductions

a. Assessing current CO2 emissions

b. Estimating CO2 emission reductions achieved by the introduction of power

system operation technology

iv. Checking Japanese companies' competitive advantages

a. Assessing competitive advantages in power system operation

Page 7: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

1-2

(Source: PGCB Annual report 2009-2010) (Source: PGCB Website https://www.pgcb.org.bd/PGCB/?a=user/home.php)

Figure 1-1 Grid network of PGCB in 2010(left) and 2018(right)

Page 8: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

1-3

1.3 Project Implementation Structure

The following is the implementation structure for this project.

The responsible operator of this project is TEPCO IEC, Inc. The current status analysis and project

scheme study on the cybersecurity field were conducted with the cooperation of McAfee Co., Ltd.

SCADA survey and analysis were performed in collaboration with Toshiba Energy Systems &

Solutions Corporation.

1.4 Project Implementation Schedule

These surveys were conducted on the schedule shown in Figure 1-2.

Figure 1-2 Schedule of Pre-Feasibility Study

Page 9: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-1

2 Current Status of the Country Surveyed

2.1 Basic Information about the Country

Economic Conditions

(1) GDP

In the past ten years, Bangladesh has been maintaining sustainable high economic growth with an

average GDP growth rate of 6% or more. According to the Bangladesh Bureau of Statistics (BBS),

the country's GDP growth rate increased to 7.11% in 2015-16, exceeding the level of 7% for the

first time, then rose to 7.28% in 2016-17.

The country’s GDP growth rates are estimated for three sectors: agriculture, industry, and service.

Figure 2-1 shows the real GDP growth rates by sector.

(Source: Finance Division, Ministry of Finance, Bangladesh Economic Review 2017)

Figure 2-1 Growth of GDP by Sectors

(2) Industrial Structure

The agriculture, industry, and service sectors are divided further into 15 sectors. Figure 2-2 shows

the share of each of these sectors in the real GDP in 2016-17.

6.1

5

4.4

6

3.0

1

2.4

6

4.3

7

3.3

3

2.7

9

2.9

7

7.0

3

9.0

2

9.4

4

9.6

4

8.1

6

9.6

7

11.0

9

10.2

2

5.5

3

6.2

2

6.5

8

5.5

1

5.6

2

5.8

6.2

5

6.6

9

5.57

6.46 6.526.01 6.06

6.557.11 7.28

0

2

4

6

8

10

12

2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17

[%]

Agriculture Industry Service GDP

Page 10: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-2

(Source: Finance Division, Ministry of Finance, Bangladesh Economic Review 2017)

Figure 2-2 Sectoral Share of GDP at Constant Prices (2016-17)

Figure 2-3 shows the changes in the percentage of each sector in the GDP. Since the 1980s, the

share of the service sector has remained at around 50%. This figure shows that a gradual

structural change is occurring from the industry sector to the agriculture sector.

(Source: Finance Division, Ministry of Finance, Bangladesh Economic Review 2017)

Figure 2-3 Trend of Structural Transformation of Sectoral Shares in GDP

11%

3%

2%

18%

1%

8%

13%1%

10%

4%

8%

4%

3%

2%

12%

Agriculture and Forestry

Fishing

Mining and Quarrying

Manufacturing

Electricity, Gas and Water Supply

Construction

Wholesale and Retail Trade

Hotel and Restaurants

Transport, Storage & Communication

Financial Intermediations

Real Estate, Renting and Business Activities

Public Administration and Defence

Education

Health and Social Works

Community, Social and Personal Services

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

1980-81 1985-86 1990-91 1995-96 2000-01 2005-06 2010-11 2013-14 2014-15 2015-16 2016-17

Agriculture Industry Service

Page 11: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-3

Economic Growth Policy

Bangladesh will celebrate the 50th Anniversary of its Independence in 2021. Under the leadership

of Prime Minister Sheikh Hasina, the Government of Bangladesh adopted Vision2021 as the

country's top-priority national program. In order to realize Vision2021, the General Economics

Division formulated the Perspective Plan of Bangladesh (2010-2021), one of the country's most

fundamental long-term plans. If Vision2021 is realized, the socioeconomic environment of

Bangladesh is expected to change from a low income economy to a medium income economy.

The following nine items are listed as top priority challenges of Vision2021.

Ensuring broad-based growth and reducing poverty

Ensuring effective governance and sound institutions but creating a caring society

Addressing globalization and regional cooperation

Providing energy security for development and welfare

Building a sound infrastructure and managing the urban challenge

Bitigating the impacts of climate change

Promoting innovation in a knowledge-based society

2.2 Electricity Policy

Overview of Electricity Sector of Bangladesh

In the electricity sector of Bangladesh, the Bangladesh Power Development Board (BPDB) has

been consistently operating electricity generation, transmission, and distribution divisions over

many years. In 1996, the BPDB started to spin off its electricity generation, transmission and

distribution units one after another. Figure 2-4 shows the BPDB's current structure.

Under the BPDB, there are several electricity producers including independent power producers

(IPPs). In addition, there are several electricity distributors operating in each area of the country.

All power grid networks are operated by the PGCB.

(Source: The Study Team)

Figure 2-4 Overview of Energy Sector of Bangladesh

Page 12: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-4

The following is the overview of individual organizations.

(1) Power Division

The main functions of Power Division are as follows.

All activities related to power generation, transmission and distribution;

Manage all matters and policies related to the Power sector;

Expand, rehabilitate and modernize power generation, transmission and distribution

services in line with the increasing national demand and prepare action plans and

programs accordingly;

Encourage private and joint venture investment in the Power sector in addition to the

government investment;

Improve the standard of living of the rural poor through rural electrification and the

introduction of renewable energy;

Monitor revenue earnings and commercial activities of the utilities ;

Promotion of renewable energy and energy efficiency through formulation of

policy/regulation, different incentive mechanism and R&D.

(2) Power Cell

Aiming to reform the electricity sector of Bangladesh and encourage private-sector companies to

enter the electricity business, Power Cell was established in 1995 under the Ministry of Power,

Energy and Mineral Resources (MPEMR).

(3) Bangladesh Power Development Board (BPDB)

BPDB is mainly responsible for most of the power generation and distribution in Dhaka and the

western part of Bangladesh. This Board is positioned under the Power Division of the Ministry of

Power, Energy and Mineral Resources and the Government of Bangladesh. As a result of a series

of reforms and reorganizations, BPDB has changed in organizational form and is now operating

the following companies as its subsidiaries.

Ashuganj Power Station Company Ltd. (APSCL)

Electricity Generation Company of Bangladesh (EGCB)

North West Power Generation Company Ltd. (NWPGCL)

West Zone Power Distribution Company Ltd. (WZPDCL)

(4) Bangladesh Rural Electrification Board (BREB)

This Board was established when the Rural Electrification Board Act was enacted in 2013 replacing

the Rural Electrification Board Ordinance, which was enacted in 1977. This Board was established

with the aim of utilizing electricity as a means to improve the efficiency of agricultural production

in rural areas.

Page 13: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-5

At present, BREB is operating 76 rural electric cooperatives called Palli Bidyuit Samity (PBS).

(5) Sustainable and Renewable Energy Development Authority (SREDA)

Because its primary energy sources are gradually depleting, Bangladesh needs to ensure long-

term energy security and sustainable economic growth. SREDA was established in 2012 aimed at

driving the development of sustainable and renewable energy. The major roles of SREDA are

described below.

Coordinate renewable energy and energy efficiency issues of the government.

Promote sustainable energy.

Standardize and labialize the products for RE and EE.

Pilot new technologies, and take initiatives for its expansion.

Create congenial environment for the investors.

Research and development on RE and EE.

Capacity development.

Create awareness for RE and EE and

Establish linkage with regional and international organizations .

(6) Power Grid Company of Bangladesh Ltd. (PGCB)

PGCB was established in 1996 in the course of reorganization of the electricity sector of

Bangladesh. PGCB is responsible for the operation and expansion of all power grid networks

throughout the country. The Government of Bangladesh made the decision that all the country's

power transmission-related assets would be transferred to PGCB from BPDP and the Dhaka

Electric Supply Authority (DESA). In accordance with the government decision, PGCB took over

these assets in 2002 and started transmission operations throughout the country.

Electricity Sector Policy

As described in "2.1.2 Economic Growth Policy" Bangladesh formulated Vision2021 to change its

socioeconomic environment to a medium income economy. In addition to Vision2021, the

Government of Bangladesh announced a new growth policy called Vision2041 with the aim of

becoming one of the leading industrialized countries by 2041. Today, Bangladesh depends mainly

on domestically produced natural gas for energy supply. Because the supply of natural gas is

expected to decrease in the future, the Government of Bangladesh formulated Power System

Master Plan 2010 (PSMP2010) with the aim of diversifying energy sources on a long-term basis.

However, PSMP2010 did not progress as expected, which required a review of the plan. In order

to re-look at the energy sector strategy by assessing medium- and long-term challenges and

risks, the Government of Bangladesh formulated another plan called Power System Master Plan

2016 (PSMP2016). In addition, Bangladesh would not be able to become a leading industrialized

country without industry sophistication, and achieving this goal would require the country to at

least improve the quality of electricity supply. For this reason, the revision of PSMP included

reviews of the power development plan and electricity supply plan in order to study the

Page 14: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-6

possibility of improvement in the quality of electricity supply. Five viewpoints emphasized in

PSMP2016 are described below.

i. Enhancement of imported energy infrastructure and its flexible operation

ii. Efficient development and utilization of domestic natural resources (gas and coal)

iii. Construction of a robust, high-quality power network

iv. Maximization of green energy and promotion of its introduction

v. Improvement of human resources and mechanisms related to the stable supply of

energy

In the meanwhile, some power stations in Bangladesh are unable to generate electricity to meet

specified requirements such as output and efficiency. Furthermore, some power stations are

unable to even continue commercial operation as contracted for a number of reasons. Under such

a situation, the supply of electricity is always lacking throughout Bangladesh, making it difficult to

conduct scheduled power shut-downs for inspection. To solve these problems, the Government

of Bangladesh reviewed PSMP2016 then launched "Revisiting PSMP2016" in 2018.

Grid Code

ELECTRICITY GRID CODE 2012 was enacted by Bangladesh Energy Regulatory Commission at 02

January, 2012.

The Grid Code is a document that governs the boundary between the Licensee and Users and

establishes procedures for operations of facilities that will use the Transmission System. It lays down

both the information requirements and the procedures governing the relationship between the

Licensee and Users.

Summary of Grid Code related to the grid operation and SCADA system is shown in Table 2-1.

Table 2-2 describes the definition of terms which appear in boldface in Table 2-1.

Page 15: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-7

Table 2-1 Summary of Grid Code

SUBJECT Details

TRANSMISSION

SYSTEM PLANNING This identifies the method for data submissions by Users to the

Licensee for the planning and development of the Transmission

System.

Transmission System planning and security standards;

- Voltage limits at 132 kV, 230 kV and 400 kV Bus: +/-

10% during emergencies. +/-5% during normal

operations.

- Line outages: single contingency of a permanent

three-phase outage of any one circuit element or

transformer.

- Stability: to be maintained stable during a temporary

fault clearance by three-phase trip within 5 cycles

and followed by successful reclosure within 15 cycles.

- Power factor: on 400 kV side of 400/230/132 kV

substation 0.95 lagging on 230 kV side of 230/132 kV

substation 0.95 lagging on 132 kV side of 132/33 kV

substation 0.9 lagging

CONNECTION

CONDITIONS Connection Conditions specify the technical, design and

operational criteria that must be complied with by any User

connected to the Transmission System.

OUTAGE PLANNING This describes the process by which the Licensee carries out the

planning of Transmission System Outages, including interface

coordination with Users.

SCHEDULE AND

DESPATCH This specifies the procedure to be adopted for the scheduling

and dispatch of Generating Units to meet system demand.

FREQUENCY AND

VOLTAGE

MANAGEMENT

This describes the method by which all Users of the

Transmission System shall cooperate with the Licensee in

contributing towards effective control of the system frequency

and managing the EHV voltage of the Transmission System.

VOLTAGE MANAGEMENT;

The NLDC and the Licensee shall jointly take appropriate

measures to control Transmission System voltages that may

include but not be limited to transformer tap changing and use

of MVAR reserves with Generating units within technical limits

agreed to between the NLDC, Licensee and Generating units.

CONTINGENCY

PLANNING This describes the recovery process to be followed by the

Licensee and all Users in the event of Transmission System

total or partial blackouts.

CROSS BOUNDARY

SAFETY This sets down the requirements for maintaining safe working

practices associated with cross boundary operations.

Page 16: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-8

OPERATIONAL

EVENT/ACCIDENT

REPORTING

This describes the requirements for reporting, in writing,

incidents that were initially reported orally by/to other Users.

REPORTABLE INCIDENTS;

i. Exceptionally high/low system voltage or frequency. ii. Serious

equipment problem, e.g. major circuit, transformer or bus-bar. iii.

Loss of major Generating Unit. iv. Falling of Transmission line /

Tower due to natural calamity. v. System split, Transmission

System breakaway or Black Start. vi. Major fire incidents. vii.

Major failure of protection. viii. Equipment and transmission line

overload. ix. Minor equipment alarms.

PROTECTION In order to safeguard a User’s system from faults that may occur

on another User’s system, it is essential that certain minimum

standards of protection be adopted.

METERING,

COMMUNICATION

ANDDATA

ACQUISITION

This specifies the minimum operational and commercial

metering, communication and data acquisition requirements to

be provided by each User at the inter-connection points and

also at the cross boundary circuits.

DATA ACQUISITION for Transmission System;

i. MW generated in each Power Station. ii. MW consumed at

each Grid substation. iii. MVAR generated or absorbed in each

Power Station. iv. MVAR consumed at each Grid substation. v.

Voltage at all system buses. vi. Frequency in Transmission

System. vii. MW & MVAR flow in each transmission line.

TESTING This specifies the responsibilities and procedures for arranging

and carrying out Tests which have (or may have) an effect on the

Transmission System or the Generator’s or Distributor’s

systems.

PERFORMANCE

STANDARDS FOR

TRANSMISSION

(a) To ensure the quality of electric power in the Grid;

(b) To ensure that the Grid will be operated in a safe and

efficient manner and with a high degree of reliability; and

(c) (c) To specify safety standards for the protection of

personnel in the work environment. (Source: Bangladesh Energy Regulatory Commission, Electricity Grid Code 2012)

Page 17: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-9

Table 2-2 Definitions

Defined Term Definition

Connection

Conditions The technical conditions to be complied with by any User having

a Connection to the Transmission System

Generating Unit The combination of an alternator and a turbine set (whether

steam, gas, water or wind driven) or a reciprocating engine and

all of its associated equipment, which together represents a

single electricity generating machine.

Generator An organization that has a License to generate electricity and

who is subject to the Grid Code.

Licensee The holder of the Transmission License for the bulk

transmission of electricity between Generators and

Distributors.

Outage The reduction of capacity or taking out of service of a

Generating Unit, Power Station or part of the Transmission

System or Distribution System

Transmission System The system of EHV electric lines and electrical equipment owned

and/or operated by the Licensee for the purpose of the

transmission of electricity between Power Stations, External

Interconnections and the Distribution System.

User A person or establishment, including the Licensee, Buyer,

Generator and the Supplier, who uses the Transmission

System and who must comply with the provisions of the Grid

Code. (Source: Bangladesh Energy Regulatory Commission, Electricity Grid Code 2012)

Page 18: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-1

3 Current Status and Future Outlook of Electricity Supply

3.1 Existing Substations, Power Stations

The existing substations and power stations subject to this study are shown below by area. PGCB

is managing electricity demand, etc., with its operation area divided into nine sections.

As PGCB is operating not only its own substations but also other companies' substations, the

following table includes other companies' facilities. Therefore, this study will be based on the use

of facilities including other companies' facilities.

Table 3-1 Existing substations in Dhaka area

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

1 Ashuganj (N) 650 APSCL 400/230kV

2 Bhulta 1040 PGCB 400/230kV

3 Kaliakoir 650 PGCB 400/132kV

4 Kaliakoir 230 520 PGCB 400/230kV

5 Agargaon 600 PGCB 230/132kV

6 Aminbazar 675 PGCB 230/132kV

7 Ashuganj 300 APSCL 230/132kV

8 Ghorasal 250 BPDB 230/132kV

9 Haripur 675 PGCB 230/132kV

10 Hasnabad 675 PGCB 230/132kV

11 Maniknagar 600 PGCB 230/132kV

12 Meghnaghat Switching - PGCB 230/132kV

13 Rampura 675 PGCB 230/132kV

14 Siddhirganj 600 PGCB 230/132kV

15 Shyampur 600 PGCB 230/132kV

16 Tongi 675 PGCB 230/132kV

17 Agargaon 240 PGCB 230/132kV

18 Ashuganj 116 APSCL 132/33kV

19 Bangabhaban 70 DPDC 132/33kV

20 Bashundhara 225 DESCO 132/33kV

21 Bhasantek 240 PGCB 132/33kV

22 Bhulta 240 PGCB 132/33kV

23 BMPIL 75 Private 132/33kV

24 Dhamrai 150 PGCB 132/33kV

25 Dhanmondi 345 DPDC 132/33kV

26 Ghorasal 126 BPDB 132/33kV

27 Gulshan 240 PGCB 132/33kV

28 Haripur 240 REB 132/33kV

29 Hasnabad 300 PGCB 132/33kV

30 Joydevpur 270 PGCB 132/33kV

31 Kabirpur 360 PGCB 132/33kV

32 Kallayanpur 225 PGCB 132/33kV

33 Kamrangirchar 225 DPDC 132/33kV

34 Kodda 300 PGCB 132/33kV

35 Lalbagh 150 DPDC 132/33kV

Page 19: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-2

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

36 Madanganj 100 DPDC 132/33kV

37 Madartek 150 DPDC 132/33kV

38 Manikganj 150 PGCB 132/33kV

39 Maniknagar 150 PGCB 132/33kV

40 Matuail 150 DPDC 132/33kV

41 MI Cement 28 Private 132/33kV

42 Mirpur 200 PGCB 132/33kV

43 Moghbazar 225 DPDC 132/33kV

44 Munshiganj 240 PGCB 132/33kV

45 Narinda 150 DPDC 132/33kV

46 Narsingdi 150 PGCB 132/33kV

47 New Tongi 240 PGCB 132/33kV

48 RSRM 25 Private 132/33kV

49 Satmasjid 240 PGCB 132/33kV

50 Savar 150 PGCB 132/33kV

51 Shyampur 300 PGCB 132/33kV

52 Siddhirganj 240 PGCB 132/33kV

53 Sitalakhya 225 DPDC 132/33kV

54 Sonargaon 150 PGCB 132/33kV

55 Tongi 225 PGCB 132/33kV

56 Ullon 150 PGCB 132/33kV

57 Uttara 3P 240 DESCO 132/33kV

58 Uttara 150 DESCO 132/33kV (Source: The Study Team)

Table 3-2 Existing substations in Chittagong area

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

1 AKSPL 380 Private 230/33kV

2 BSRM 280 Private 230/33kV

3 Hathazari 600 PGCB 230/132kV

4 Sikalbaha 300 PGCB 230/132kV

5 AKSML 80 Private 132/33kV

6 Bakulia 203 PGCB 132/33kV

7 Baroaulia 184 PGCB 132/33kV

8 Baroirhat 75 PGCB 132/33kV

9 BSRM 80 Private 132/33kV

10 Chandraghona 61 PGCB 132/33kV

11 Cox's Bazar 157 PGCB 132/33kV

12 Dohazari 150 PGCB 132/33kV

13 Halishahar 190 PGCB 132/33kV

14 Hathazari 195 PGCB 132/33kV

15 Juldah 64 PGCB 132/33kV

16 Kaptai 20 BPDB 132/33kV

17 Khagrachari 78 PGCB 132/33kV

18 Khulshi 240 PGCB 132/33kV

Page 20: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-3

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

19 KSRM 100 Private 132/33kV

20 KYCR 20 Private 132/33kV

21 Madunaghat 82 PGCB 132/33kV

22 Matarbari 82 PGCB 132/33kV

23 MSML 30 Private 132/33kV

24 Shahmirpur 128 PGCB 132/33kV

25 Sikalbaha 116.6 BPDB 132/33kV

26 SSML 30 Private 132/33kV

27 TKCCL 75 Private 132/33kV (Source: The Study Team)

Table 3-3 Existing substations in Khulna area

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

1 Bheramara HVDC 500 PGCB HVDC 400kV

2 Bheramara 2nd HVDC 500 PGCB HVDC 400kV

3 Bheramara 450 PGCB 230/132kV

4 Khulna (S) 450 PGCB 230/132kV

5 Bagerhat 157 PGCB 132/33kV

6 Bheramara PGCB 102 PGCB 132/33kV

7 Chuadanga 150 PGCB 132/33kV

8 Faridpur 240 PGCB 132/33kV

9 Gallamari 82 PGCB 132/33kV

10 Goalpara 82 PGCB 132/33kV

11 Gopalganj 161 PGCB 132/33kV

12 Jashore 323.3 PGCB 132/33kV

13 Jhenaidah 240 PGCB 132/33kV

14 Khulna (C) 192 PGCB 132/33kV

15 Kushtia 240 PGCB 132/33kV

16 Madaripur 191 PGCB 132/33kV

17 Magura 82 PGCB 132/33kV

18 Mongla 82 PGCB 132/33kV

19 Noapara 143 PGCB 132/33kV

20 Patuakhali 191 PGCB 132/33kV

21 Satkhira 161 PGCB 132/33kV (Source: The Study Team)

Table 3-4 Existing substations in Rajshahi area

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

1 Baghabari 225 PGCB 230/132kV

2 Bogura 750 PGCB 230/132kV

3 Ishurdi 675 PGCB 230/132kV

4 Sirajganj Switching PGCB 230/132kV

5 Amnura 100 PGCB 132/33kV

6 Bogura 390 PGCB 132/33kV

7 Chapai Nawabganj 135 PGCB 132/33kV

Page 21: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-4

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

8 Ishurdi 115 PGCB 132/33kV

9 Joypurhat 164 PGCB 132/33kV

10 Naogaon 225 PGCB 132/33kV

11 Natore 206 PGCB 132/33kV

12 Niyamatpur 141 PGCB 132/33kV

13 Pabna 150 PGCB 132/33kV

14 Rajshahi 245 PGCB 132/33kV

15 Rooppur 41 PGCB 132/33kV

16 Shahjadpur 191 PGCB 132/33kV

17 Sirajganj 207 PGCB 132/33kV (Source: The Study Team)

Table 3-5 Existing substations in Comilla area

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

1 Cumilla (N) 450 PGCB 230/132kV

2 Brahmanbaria 202 PGCB 132/33kV

3 Chandpur 150 PGCB 132/33kV

4 Chowmuhani 270 PGCB 132/33kV

5 Cumilla (N) 150 PGCB 132/33kV

6 Cumilla (S) 300 PGCB 132/33kV

7 Daudkandi 150 PGCB 132/33kV

8 Feni 195 PGCB 132/33kV

9 Ramganj 150 PGCB 132/33kV (Source: The Study Team)

Table 3-6 Existing substations in Mymensingh area

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

1 Jamalpur 232 PGCB 132/33kV

2 Kishoreganj 207.6 PGCB 132/33kV

3 Mymensingh 360 PGCB 132/33kV

4 Netrokona 157 PGCB 132/33kV

5 Sherpur 100 PGCB 132/33kV

6 Tangail 225 PGCB 132/33kV (Source: The Study Team)

Table 3-7 Existing substations in Sylhet area

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

1 Bibiyana 1040 PGCB 400/230kV

2 Fenchuganj 300 PGCB 230/132kV

3 Beanibazar 150 PGCB 132/33kV

4 Chhatak 81 PGCB 132/33kV

5 Fenchuganj 81 PGCB 132/33kV

6 Kulaura 82 PGCB 132/33kV

7 Shahjibazar 157 PGCB 132/33kV

Page 22: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-5

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

8 Srimangal 60 PGCB 132/33kV

9 Sunamganj 78 PGCB 132/33kV

10 Sylhet 244 PGCB 132/33kV (Source: The Study Team)

Table 3-8 Existing substations in Barisal area

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

1 Barishal (N) 600 PGCB 230/132kV

2 Barishal 150 PGCB 132/33kV

3 Barishal(N) 240 PGCB 132/33kV

4 Bhandaria 82 PGCB 132/33kV

5 Bhola 60 BPDB 132/33kV (Source: The Study Team)

Table 3-9 Existing substations in Rangpur area

NO. NAME CAPACITY [MVA] O&M ENTITY VOLTAGE LEVEL

1 Barapukuria 750 PGCB 230/132kV

2 Barapukuria 122 PGCB 132/33kV

3 Lalmonirhat 168 PGCB 132/33kV

4 Palashbari 197 PGCB 132/33kV

5 Panchagarh 82 PGCB 132/33kV

6 Purbasadipur 211 PGCB 132/33kV

7 Rangpur 176.6 PGCB 132/33kV

8 Saidpur 207 PGCB 132/33kV

9 Thakurgaon 750 PGCB 230/132kV (Source: The Study Team)

Table 3-10 Existing Power Stations in Dhaka area

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

1 a) Ghorasal ST Unit-1 55 40

2 b) Ghorasal ST 2 55 45

3 Ghorasal ST :Unit-3 210 170

4 Ghorashal ST Unit-4 210 180

5 Ghorashal ST Unit-5 210 190

6 Ghorashal CCPP Unit -7 365 365

7 Ghorashal Regent 108 108

8 Ghorashal 78.5MW (MAX) 78 78

9 Tongi GT 105 105

10 Horipur GT:Unit 1,2 64 40

11 Horipur NEPC (HFO) 110 110

12 Horippur Power CCPP 360 360

13 Meghnaghat CCPP 450 450

14 Shiddirganj ST 210 115

Page 23: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-6

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

15 Horipur 412 MW CCPP 412 412

16 Siddirganj GT Unit- 1,2 210 210

17 Siddhirganj CCPP 335 MW GT 217 217

18 Siddirgonj (Desh) 100 100

19 Siddhirganj (Dutch Bangla) 100 100

20 Pagla (DPA) 50 50

21 Meghnaghat CCPP (Summit) 305 305

22 Meghnaghat IEL 100 100

23 Madanganj (Summit) 102 100

24 Madanganj-55 55 55

25 Keraniganj (Powerpac) 100 MW 100 100

26 Gagnagar (Orion) 102 102

27 Narshingdi (Doreen) 22 22

28 Summit Power (Madhbdi+ Ashulia) 80 80

29 Summit Power (Maona) 33 33

30 Summit Power, Rupgonj 33 33

31 Gazipur RPCL 52 52

32 Kodda Gazipur 149 149

33 Kathpotti 52 mw 51 51

34 Kamalaghat Munshigonj

(Banco Energy 54 MW) 54 54

35 Summit Gazipur-2 300 300

36 APR Energy, Keranigonj 300 300

37 Aggreco Bramhangoan 100 100

38 Aggrako aurahati 100 mw 100 100

39 Southern Power 55 55

40 Northen 55 MW 55 55

41 Bosila 108 CLCPC Keranigonj 108 108 (Source: BPDB Website, http://www.bpdb.gov.bd/bpdb_new/)

Table 3-11 Existing Power Stations in Chittagong area

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

1 Kaptai Hydro:Unit-1,2,3,4,5 230 230

2 Chittagong RaozanST(Gas):Unit-1 210 180

3 Chittagong RaozanST(Gas):Unit-2 210 180

4 Raozan 25MW 25 25

5 Shikalbaha ST 60 40

6 Patenga 50 MW 50 50

7 b) Shikalbaha Peaking (GT) 150 150

8 Shikalbaha 225 MW GT 225 225

9 Shikalbaha(Energis) 51 51

10 Julda 100 100

11 Dohazari Sangu 102 102

Page 24: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-7

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

12 Hathazari 98 98

13 Barabkunda (Regent) 22 22

14 Malancha, Ctg.EPZ (United) 0 0

15 Chittagong ECPV 108 108 (Source: BPDB Website, http://www.bpdb.gov.bd/bpdb_new/)

Table 3-12 Existing Power Stations in Khulna area

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

1 Bheramara GT (Unit-1,2,3) 60 46

2 Bherama 360 MW 410 410

3 Faridpur 54 54

4 Gopalganj Peaking 109 109

5 Khulna CCPP 230 230

6 Khulna (KPCL-2) 115 115

7 Bangla Track (Noapara) 100 100

8 Noapara (khanjahan ali) 40 40

9 Bheramara HVDC Interconnector 1000 1000 (Source: BPDB Website, http://www.bpdb.gov.bd/bpdb_new/)

Table 3-13 Existing Power Stations in Rajshahi area

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

1 a)Baghabari GT 1 71 71

2 a)Baghabari GT2 100 100

3 Baghabari Peaking 52 52

4 Bera Peaking 71 71

5 Amnura 50 50

6 Chapainawabgonj 100 MW 104 104

7 Katakhali (Peaking) 50 50

8 Khtakhali (Northern) 50 50

9 Santahar Peaking 50 50

10 Sirajganj CCPP1 210 210

11 Sirajgonj CCPP 2 220 220

12 Sirajganj unit 3 141 141

13 Bogra GBB 22 22

14 Bogra(Energyprima) 20 10

15 Ullapara (Summit) 11 11

16 Rajlanka 52 MW 52 52 (Source: BPDB Website, http://www.bpdb.gov.bd/bpdb_new/)

Page 25: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-8

Table 3-14 Existing Power Stations in Comilla area

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

1 c) Ashuganj ST 3 150 135

2 Ashugonj ST 4 150 129

3 Ashugonj ST 5 150 134

4 ASHUGONJ ENGINES 53 45

5 c) Ashuganj CCPP-225MW 221 221

6 Asuganj CCPP South 360 360

7 Asugonj CCPP NORTH 360 360

8 Ashuganj (Precision) 55 55

9 d) Ashuganj (United) 53 53

10 Ashuganj (Modular) 195MW 195 195

11 Ashuganj (Midland) 51 51

12 Brahmanbaria (Agrico) (Gas) 85 85

13 Titas(Dautkandi) 52 52

14 Chandpur 163 163

15 Feni (Doreen) 22 22

16 Feni, Mahipal (Doreen) 11 11

17 Jangalia (Summit) 33 33

18 Jangalia(Lakdamavi) 52 52

19 Summit Power, Comilla 25 25

20 Daudkandi 200 MW 200 200

21 Tripura 160 160 (Source: BPDB Website, http://www.bpdb.gov.bd/bpdb_new/)

Table 3-15 Existing Power Stations in Mymensingh area

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

1 RPCL,CCPP, Mymensingh 210 202

2 Tangail (Doreen) 22 22

3 Jamalpur RPP 95 95

4 United Mymensingh PPL 200 200

5 Sarishabari Solar Plant 3 3 (Source: BPDB Website, http://www.bpdb.gov.bd/bpdb_new/)

Table 3-16 Existing Power Stations in Sylhet area

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

1 Fenchuganj CCPP-1 (Gas) 97 70

2 Fenchuganj CCPP-2(New) 104 90

3 Fenchuganj (Barakatullah) 51 51

4 Fenchuganj (Energyprima) 44 44

5 Kushiara 163 MW Fenchugonj 163 163

6 Hobiganj (Confidence-EP) 11 11

7 Shajibazar GT Unit-8, 9 70 66

Page 26: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-9

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

8 Shahjibazar 330 MW 330 330

9 Shajibazar (Shajibazar ) 86 86

10 Shajibazar(ENERGYPRIMA) 50 50

11 Sylhet 150MW GT 142 142

12 Sylhet 20MW GT 20 20

13 Sylhet (Energyprima) 50 50

14 Sylhet(Desh) 10 10

15 Shahjahanulla 25mw 25 25

16 Summit Bibiana-2 341 341 (Source: BPDB Website, http://www.bpdb.gov.bd/bpdb_new/)

Table 3-17 Existing Power Stations in Barisal area

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

1 Barishal GT-unit-1,2 40 30

2 Summit Barisal 110MW 110 110

3 Bhola Venture 33 33

4 Bhola CCPP GT-1,2,ST 194 194

5 Bhola Agreeco 95 mw 95 95 (Source: BPDB Website, http://www.bpdb.gov.bd/bpdb_new/)

Table 3-18 Existing Power Stations in Rangpur area

NO. NAME INSTALLED

CAPACITY [MVA]

DERATED

CAPACITY [MVA]

1 Barupukuria ST 1 125 85

2 Barupukuria ST 2 125 85

3 Barapukuria ST Unit-3 274 274

4 Rangpur GT 20 20

5 Syedpur GT 20 20 (Source: BPDB Website, http://www.bpdb.gov.bd/bpdb_new/)

Page 27: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-10

3.2 Ongoing, Planned Substations

PGCB has specific plans for substations to be constructed till 2023 as shown in Figure 3-1.

(Source: The Study Team)

Figure 3-1 Substation construction plan of PGCB until 2023

3.3 Revisiting PSMP2016 Plan

Figure 3-2 shows the plans of Revisiting PSMP2016 for substations to be constructed.

(Source: Revisiting PSMP2016)

Figure 3-2 Year-wise the number of substations up to 2041 in Revisiting PSMP2016

3.4 Data for Verification

Because near-future plans are laid out with PSMP2016 Plan modified on an as-needed basis, there

are differences in the plans up to 2023 between "3.2 Ongoing, Planned Substations" and "3.3

Revisiting PSMP2016 Plan." PGCB Plan is based on a significant increase in facility expansion in

preparation for a large-scale coal-fired power station whose operation is scheduled to start

around 2023 and 2024.

Because "3.2Ongoing, Planned Substations" is the latest plan available for the study of this project

0

100

200

300

2018 2019 2020 2021 2022 2023

Nu

mb

er

Year

400/230 kV

400/132 kV

230/132 kV

230/33 kV

132/33 kV

0

100

200

300

400

500

2018 2023 2028 2033 2038

Nu

mb

er

Year

765/400kV

400/230kV

400/132kV

230/132kV

132/33kV

Page 28: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-11

scheme, this data will be used as base data till 2023. After 2023, this project scheme will be

verified using data adjusted to eventually fit with "3.3 Revisiting PSMP2016 Plan" in 2041. Figure

3-3 shows the data for verification.

(Source: The Study Team)

Figure 3-3 Data used in this Pre-FS

In the meantime, studying this supervisory control organization would require data on the number

of substations in each area. It is considered that the number of 230/132kV and 132/33kV

substations required to supply electricity to each area is roughly proportional to the area’s electricity

demand. For this reason, the total number of substations is prorated in accordance with the

electricity demand in each area based on the 2041 data of Revisiting PSMP.

The number of substations in each area till 2023 is based on the respective data of "3.2 Ongoing,

Planned Substations". After 2023, this project scheme will be verified using data adjusted to

eventually fit with "3.3 Revisiting PSMP2016 Plan" in 2041.

Additionally, because the operation of transmission control includes the switching operation at

power stations, the number of power stations is also included in this study. Some of these power

stations are connected to bulk power systems and the other power stations are connected to

local supply systems. These two types of power stations need to be studied separately, but there

are some power stations that are connected to power systems whose voltage class is unknown. In

such a case, this study assumes that power stations with a generation capacity exceeding a certain

level are connected to bulk power systems.

In the meanwhile, as these plans may be revised at some points in the future, this study will be

verified on the assumption of a 20% increase in the current facility expansion plan. Figure 3-4

shows the case in which the number of substations and power stations is increased by 20%. From

this point forward, this study will be verified based on this data.

0

100

200

300

400

500

600

2018 2023 2028 2033 2038

Nu

mb

er

Year

PGCB Plan

Revisiting PSMP2016

Page 29: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-12

(Source: The Study Team)

Figure 3-4 The case where the number of substations and power stations increased by 20%

0

50

100

150

200

250

300

2018 2023 2028 2033 2038

Nu

mb

er

Year

BulkDhakaChittagongKhulnaRajshahiComillaMymensinghSylhetBarisal

Page 30: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-1

4 Current Status of Power Control Operation and Power Control

Facilities

4.1 Power Control Operation

Supervisory Control System

As shown in Figure 4-1, PGCB, under the control of the Managing Director, consists mainly of four

major units – Finance, Human Resource Management, Planning & Development, and Operation &

Maintenance. Operation & Maintenance is divided further into three groups – Transmission-1,

Transmission-2, and System Operation. Load Dispatch Team in charge of supervisory control

belongs to System Operation.

(Source: The Study Team)

Figure 4-1 Company Structure of PGCB

Under Load Dispatch, there are a National Load Dispatch Center (NLDC), a Backup Control Center

(BCC), and three Area Load Dispatch Centers (ALDCs). As shown in Figure 4-2, NLDC is controlling

power output in response to the changes in electricity consumption. NLDC is also steadily

operating electric power systems depending on the amount of electricity that flows into each

facility, including appropriate network configuration, voltage maintenance, and power flow

management. ALDCs are conducting the routine operation of supply systems within their territory.

But because NLDC has the authority to operate supply systems, ALDCs are operating under the

instructions of NLDC.

Some operators reside at BCC as well so that they can respond to emergency situations until

NLDC operators move in. These operators at BCC usually conduct part of NLDC operations with

the aim of technical skill transfer. PGCB substations – all manned substations – are operated in

close contact with NLDC and ALDCs.

Page 31: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-2

(Source: The Study Team)

Figure 4-2 The monitoring and control organization of PGCB

The standard number of operators at each supervisory control center is shown in Table 4-1. These

operators are working on a three-shift rotation.

Table 4-1 Standard personnel at each control center

CONTROL CENTER THE NUMBER OF OPERATORS

NLDC 25

ALDC 7

BACKUP CONTROL CENTER 5

SUBSTATION 8 (Source: The Study Team)

At NLDC, five crews of five operators are working on a three-shift rotation, and the division of

roles between the five operators is as described below.

A supervisor who makes decisions on emergency shutdowns, etc.

A person in charge of controlling electricity frequencies

A person in charge of operating transmission systems

A person in charge of collecting data

A person in charge of reporting data

At each of three ALDCs, BCC, and each substation, three crews of one or two operators are

working, with no particular division of roles specified within each crew.

Operation

(1) Supervisory Operation

With the exception of some substations that cannot be remotely supervised, power systems are

supervised by each ALDC for substations within its territory and by NLDC for other substations.

Page 32: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-3

(2) Switching Operation

The work flow of switching operation for a scheduled stop operation is shown in Figure 4-3. The

substation prepares a procedure in accordance with the format shown in Figure 4-4 and sends it

to NLDC in advance, and NLDC confirms and approves the procedure. At the scheduled time for

switching, NLDC orders the substation to conduct the switching operation. After completing the

operation, the substation reports the completion of the order to NLDC. Instead of ordering the

processes of switching line by line, the order for switching is given to deliver only the purpose of

switching as shown in Figure 4-4. Following the order, the substation conducts the detailed

processes described in the switching order form.

A substation in the territory of an ALDC conducts a switching operation after checking the

details of the order among three concerned parties – the substation, the ALDC, and NLDC.

Several days before the date of switching operation, NLDC prepares a procedure and stores it in

SCADA. In preparing a procedure, NLDC may reuse a similar procedure prepared in the past.

(Source: The Study Team)

Figure 4-3 Work flow of preparation of procedure and operation

Page 33: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-4

(Source: PGCB Web site https://www.pgcb.org.bd/PGCB/)

Figure 4-4 Switching Order Form of PGCB

(3) Data Recording

NLDC is collecting the following data on substations.

i) Bus (Primary & Secondary)

a) Voltage

ii) Transformer (Primary & Secondary)

a) MW

b) MVAR

c) Power Factor

d) Current

e) TAP

f) Winding Temp

g) Oil Temp

iii) Transmission line

a) MW

Page 34: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-5

b) MVAR

c) Current

d) Voltage

iv) Other information on outages and emergency shutdowns

The substation side writes only numerical records in log sheets every hour and reports them to

NLDC or ALDC by phone. Each ALDC reports a summary of data on substations in its territory to

NLDC. The need of collecting these numerical records is specified in the grid code.

At the same time, similar numerical records are collected from generators. The data on

generators is entered on the PGCB Intranet so that NLDC can check the data.

Assuming the number of transformers at each substation as shown in Table 4-2, the number of

numerical records required for each substation is between 16 and 30. In addition to these

numerical records, each ALDC reports the numerical records of transmission lines connected to

substations.

Table 4-2 Number of model case logs

765/

400KV

765/

400KV

400/

230KV

400/

132KV

230/

132KV

230/

33KV

132/

33KV

TRANSMISSION

LINE

Tr×4 Tr×2 Tr×3 Tr×2 Tr×2 Tr×2 Tr×2

VOLTAGE 2 2 2 2 2 2 2 1

MW 4 2 3 2 2 2 2 1

MVAR 4 2 3 2 2 2 2 1

POWER

FACTOR 4 2 3 2 2 2 2 -

CURRENT 4 2 3 2 2 2 2 1

TAP 4 2 3 2 2 2 2 -

WINDING

TEMP 4 2 3 2 2 2 2 -

OIL TEMP 4 2 3 2 2 2 2 -

TOTAL 30 16 23 16 16 16 16 4 (Source: The Study Team)

The data NLDC collected will be provided to other PGCB departments. Summarized as daily

reports and monthly reports along with information on outages and emergency shutdowns, the

data will be made public on the PGCB webpage. In addition to key data such as electricity

demand and electricity generated, these reports provide detailed information as shown in the

example of a monthly report below.

i) Outage of Sub-Station equipment due to tripping/emergency maintenance

ii) Outage of Transmission lines due to tripping/emergency maintenance

iii) Outage of Sub-Station equipment due to schedule maintenance/project work

iv) Outage of Transmission lines due to schedule maintenance/project work

v) Summary of tripping and outage (Emergency / scheduled )

vi) Summary of unserved Energy

Page 35: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-6

vii) Consolidated Statement of Sub-Station performance

viii) Consolidated Statement of Transmission line's performance

ix) Power Interruption due to trouble in Transmission/Generation System

x) Over all Power interruption report of the system

xi) Maximum Load recorded at different Sub-Station

xii) Area & Zone wise maximum load served during peak hour

xiii) Maximum & Minimum Voltages of Grid Sub-Stations

xiv) Maximum load of 230/132KV Auto transformer

xv) Report on load shedding

The disclosure of this information is obligated by the government.

(4) Voltage Regulation

a. Maximum Voltages

Table 4-3, Table 4-4, and Table 4-5 show the records of maximum voltages at each substation

from July 2017 through June 2018. The fluctuation of maximum voltages is specified in the grid

code as an indicator that shows the level of power quality maintenance: within ±5% of the

reference voltage in normal times and within ±10% of the reference voltage in emergency,

both in all voltage classes.

In each table, the cells colored in light brown contain a maximum voltage that deviates from

the reference voltage +5%, and the cells colored in dark brown contain a maximum voltage

that deviates from the reference voltage +10%. One of the reasons why maximum voltages

exceed the upper limit indicator is that in the northeastern regions of Bangladesh, there are a

large number of generators despite their low electricity demand. In this situation, excessive

reactive power tends to be generated, causing voltages to increase.

Table 4-3 MAX Voltage of 400kV Grid Sub-Station (2017-2018)

No. Name Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May. Jan.

1 Bibiyana 424 425 428 413 417 413 425 416 397

2 Bheramara 424 395 425 425 422 417 418 419 495

3 Kaliakoir 396 399 403 409 410 396 428 416 384 (Source: The Study Team)

Page 36: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-7

Table 4-4 MAX Voltage of 230kV Grid Sub-Station (2017-2018)

No. Name Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May. Jan.

1 Ghorasal 230 230 230 230 235 240 242 240 232 235 240

2 Ishurdi 236 236 240 236 241 243 242 250 237 238 243

3 Ashuganj 242 240 240 238 245 245 247 244 240 240 245

4 Serajganj 225 224 235 225 230 231 232 248 234 232 231

5 Baghabari 228 227 235 230 232 237 232 253 239 232 237

6 Barapukuria 230 227 238 230 231 232 240 240 245 246 232

7 Bogra 229 226 236 230 233 234 231 264 240 237 234

8 Khulna South 242 242 244 241 244 244 244 238 241 239 244

9 Rampura 221 220 221 236 230 233 231 233 228 228 233

10 Haripur 219 227 219 221 226 232 232 235 230 228 232

11 Hasnabad 223 224 223 225 230 236 236 236 233 232 236

12 Aminbazar 222 222 223 224 244 235 237 242 234 231 235

13 Tongi 231 222 227 226 242 235 234 232 233 230 235

14 Comilla (N) 229 227 230 232 237 241 242 236 236 235 241

15 Hathazari 222 222 227 222 230 233 232 230 230 230 233

16 Megnaghat 224 225 224 228 240 238 240 242 235 232 238

17 Fenchuganj 239 240 243 243 248 245 245 240 248 240 245

18 Siddhirganj 234 237 244 242 241 242 242 240 237 228 242

19 Maniknagar 231 236 243 240 243 240 242 239 236 230 240

20 Old Airport 221 221 220 224 229 233 236 241 240 231 233

21 Barisal 238 241 246 239 244 241 240 248 243 244 241

22 AKSML 220 220 224 224 227 233 233 228 227 227 233

23 BSRM 221 223 226 226 230 236 236 230 235 232 236

24 Bibiyana 236 240 244 243 245 247 236 247 238 245 (Source: The Study Team)

Page 37: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-8

Table 4-5 MAX Voltage of 132kV Grid Sub-Station (2017-2018)

No. Name Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May. Jan.

1 Siddhirganj 138 139 141 140 138 140 141 140 138 139 140

2 Munsiganj 138 139 141 140 138 140 141 140 138 140 140

3 Megnaghat 137 134 136 138 137 139 140 145 134 138 139

4 Shyampur 132 135 134 134 135 138 137 139 137 136 138

5 Bhulta 127 130 130 129 132 139 143 145 140 142 139

6 Madanganj 135 134 137 138 137 140 140 140 142 139 140

7 Shitalakhya 137 139 136 138 141 140 141 146 144 140 140

8 Rahim Steal 136 137 138 138 139 140 140 138 138 138 140

9 Matuail 136 136 138 138 137 139 139 140 138 137 139

10 Ghorasal 140 140 140 140 140 144 142 145 144 145 144

11 Narsinghdi 139 137 138 139 137 136 142 138 141 136 136

12 Haripur (SBU) 136 137 139 138 138 141 140 138 137 138 141

13 Ullon 134 135 136 137 136 137 138 139 139 140 137

14 Hasnabad 135 136 136 136 138 138 138 143 140 138 138

15 Magbazar 134 135 137 135 135 138 138 134 149 141 138

16 Maniknagar 136 138 143 139 139 135 142 140 144 139 135

17 Bangabhaban 132 136 135 135 139 138 142 144 140 140 138

18 Narinda 134 135 136 136 135 136 136 140 139 141 136

19 Dhanmondi 135 135 138 138 136 137 139 140 144 140 137

20 Lalbag 132 136 134 135 139 138 142 145 140 140 138

21 Madartek 134 135 136 136 135 137 136 140 139 141 137

22 Mirpur 131 132 132 135 139 139 138 140 141 138 139

23 Kalyanpur 135 135 136 137 140 140 138 142 141 137 140

24 Gulshan 134 135 136 136 135 137 136 139 139 140 137

25 Uttara 133 132 134 140 137 138 136 143 138 136 138

26 Kamrangirchar 134 136 135 136 139 139 142 145 141 138 139

27 Savar 133 134 134 135 137 137 135 141 139 136 137

28 Bhasantec 132 134 136 138 138 136 136 144 136 136 136

29 Agargaon 132 135 137 139 138 136 136 144 137 135 136

30 Satmosjid 136 134 136 138 138 136 136 144 136 134 136

31 Tongi 138 138 141 141 140 140 140 142 146 142 140

32 Kabirpur 139 138 140 138 138 141 140 140 139 142 141

33 Basundhara 138 135 137 137 137 137 137 138 135 137 137

34 Manikganj 141 141 146 145 146 145 144 145 145 144 145

35 Joydevpur 140 143 147 142 143 143 144 145 145 144 143

36 New Tongi 138 139 141 141 141 141 140 144 140 142 141

37 Kodda 138 140 140 142 140 144 144 140

38 Tangail 137 140 143 140 140 140 140 140 145 145 140

39 Mymensing 136 138 144 137 140 140 138 144 140 142 140

40 Kishorganj 137 136 140 138 137 138 138 143 142 140 138

41 Netrokona 134 140 142 137 140 140 140 142 144 140 140

42 Jamalpur 134 137 141 135 135 140 138 147 138 142 140

43 Sherpur 136 138 143 138 141 141 145 145 140 143 141

44 Srimongal 140 140 141 142 142 144 145 143 145 142 144

45 Shahjibazar 138 139 141 142 142 143 143 144 140 141 143

46 Fenchuganj 137 137 139 140 140 143 142 141 141 138 143

47 Khulawara 136 137 138 139 140 144 141 140 140 136 144

48 Sylhet 136 135 137 139 138 142 141 139 140 142 142

49 Chattak 135 135 138 137 138 142 142 139 139 139 142

50 Comilla(South) 133 133 135 136 133 134 135 138 138 139 134

51 Comilla (North) 136 137 138 138 140 145 144 145 142 140 145

52 Chandpur 131 138 140 138 138 140 140 139 142 138 140

53 Feni 137 124 127 135 137 131 130 128 135 130 131

54 Chowmuhani 128 129 136 133 133 137 136 136 136 137 137

55 Ashuganj 140 140 144 143 145 145 145 146 142 143 145

Page 38: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-9

56 Daudkandi 137 135 138 140 138 141 141 141 141 142 141

57 Brahminbaria 138 139 141 141 142 143 144 146 142 142 143

58 Madanhat 134 135 138 136 138 140 140 138 136 141 140

59 Hathazari 132 132 137 132 136 138 140 135 135 134 138

60 Khulshi 133 129 137 130 138 136 137 133 134 137 136

61 Halishahar 131 131 134 132 136 140 140 135 136 140 140

62 Baraulia 130 130 134 132 135 137 138 134 133 133 137

63 Sikalbaha 131 132 134 133 136 139 139 136 134 138 139

64 Dohazari 130 133 135 132 136 139 140 134 136 135 139

65 Cox'sbazar 128 131 132 129 133 136 136 132 132 135 136

66 Chandraghona 131 131 135 135 136 138 139 134 135 139 138

67 Kaptai 134 132 135 134 136 140 140 135 136 135 140

68 A. Khaer Stl. 130 130 134 130 134 136 136 132 136 133 136

69 Bakulia 129 131 132 131 134 137 138 132 134 137 137

70 Julda 130 132 134 134 135 138 139 133 133 135 138

71 TK Chemical 133 134 136 135 138 141 142 137 138 137 141

72 Modern Steel 130 131 134 133 136 137 137 132 134 133 137

73 Shahmirpur 129 131 134 132 135 138 137 132 135 134 138

74 Goalpara 139 138 138 138 139 140 142 140 140 141 140

75 Khulna Central 139 139 139 139 139 139 141 140 140 139 139

76 Noapara 138 137 138 137 137 137 140 137 140 139 137

77 Jessore 133 136 136 130 132 133 135 134 138 136 133

78 Jhenida 135 134 135 136 136 135 140 139 140 139 135

79 Bottail 135 135 138 137 140 140 144 141 142 144 140

80 G.K.Project 137 137 140 138 144 142 146 145 144 144 142

81 Faridpur 136 134 138 133 135 135 140 139 140 141 135

82 Madaripur 136 135 140 135 136 136 140 142 142 142 136

83 Gopalganj 141 138 143 138 139 139 142 145 146 146 139

84 Bagerhat 138 141 140 138 140 140 140 140 141 141 140

85 Mongla 137 136 136 135 137 136 138 135 140 138 136

86 Satkhira 138 137 138 137 138 139 141 139 141 141 139

87 Gallamari 139 139 139 139 139 140 140 140 141 141 140

88 Magura 134 130 138 135 137 138 142 140 142 140 138

89 Chuadanga 130 129 136 134 136 136 137 139 138 139 136

90 Barisal 140 142 140 138 139 141 140 142 142 142 141

91 Patuakhali 140 142 140 138 139 141 140 142 142 142 141

92 Bhandaria 137 135 140 136 137 140 137 140 140 140 140

93 Ishurdi 136 135 139 136 139 140 145 160 144 145 140

94 Ruppur Paromanobik 134 138 134 134 141 142 138

95 Natore 137 137 140 137 140 140 144 160 144 141 140

96 Bogra 137 136 143 138 139 140 142 160 142 143 140

97 Noagaon 135 132 141 134 134 136 142 150 140 146 136

98 Rajshahi 138 137 138 136 137 136 140 146 142 138 136

99 C.Nawabganj 135 138 138 135 137 134 138 144 140 138 134

100 Amnura 140 140 140 140 139 142 140 140 142 140 142

101 Pabna 138 131 135 132 135 135 135 152 140 140 135

102 Shahjadpur 140 139 142 139 140 142 145 150 145 145 142

103 Serajganj 136 134 140 136 137 138 143 150 142 142 138

104 Niyamatpur 135 135 143 134 135 137 143 150 143 142 137

105 Joypurhat 136 136 142 135 137 137 144 150 144 144 137

106 Rangpur 129 127 133 129 136 130 134 141 136 138 130

107 Lalmonirhat 127 128 137 130 130 130 135 143 141 143 130

108 Saidpur 129 125 135 130 130 130 134 138 138 140 130

109 Purbasadipur 132 132 135 130 132 132 134 140 143 145 132

110 Thakurgaon 130 121 132 124 130 126 130 138 140 145 126

111 Palashbari 127 127 135 130 131 131 136 142 140 140 131

112 Barapukuria 130 127 135 130 131 132 140 140 145 146 132

113 Panchagar 125 119 130 124 130 125 129 137 138 147 125 (Source: The Study Team)

Page 39: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-10

b. Minimum Voltages

Table 4-6, Table 4-7, and Table 4-8 show the records of minimum voltages at each substation

from July 2017 through June 2018. In these tables, the cells colored in light blue contain a

minimum voltage that deviates from the reference voltage -5%, and the cells colored in dark

blue contain a minimum voltage that deviates from the reference voltage -10%.

There are more substations whose minimum voltages deviate from the reference voltage -10%

than those whose maximum voltages deviate from the reference voltage +10%. There are not a

sufficient number of generators near the regions where electricity demand is high such as Dhaka

and Chittagong. In such regions, voltages tend to decrease due to a shortage of reactive power.

Table 4-6 min Voltage of 400kV Grid Sub-Station (2017-2018)

No. Name Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May. Jan.

1 Bibiyana 371 400 365 393 379 368 374 380 376

2 Bheramara 362 357 373 401 396 393 379 388 384

3 Kaliakoir 347 269 365 383 363 344 340 353 353 (Source: The Study Team)

Table 4-7 min Voltage of 230kV Grid Sub-Station (2017-2018)

No. Name Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May. Jan.

1 Ghorasal 220 220 220 220 220 225 226 220 220 222 225

2 Ishurdi 226 223 225 226 215 227 218 213 211 220 227

3 Ashuganj 229 225 227 228 228 234 228 225 214 225 234

4 Serajganj 210 210 206 212 208 214 212 202 208 210 214

5 Baghabari 216 212 214 200 213 219 217 208 202 200 219

6 Barapukuria 214 210 208 213 215 216 212 220 214 220 216

7 Bogra 210 204 200 209 206 212 208 200 203 207 212

8 Khulna South 138 229 228 222 211 218 211 214 215 206 218

9 Rampura 210 206 209 208 214 214 217 212 205 216 214

10 Haripur 211 205 206 208 213 213 218 215 215 215 213

11 Hasnabad 212 206 201 206 215 215 220 214 215 212 215

12 Aminbazar 211 203 205 206 215 215 219 215 210 213 215

13 Tongi 202 200 200 203 212 220 212 203 204 205 220

14 Comilla (N) 220 216 216 218 220 228 225 215 215 220 228

15 Hathazari 208 205 200 205 206 205 210 203 205 202 205

16 Megnaghat 217 208 210 210 217 221 218 218 220 219 221

17 Fenchuganj 229 227 227 224 210 235 224 218 211 225 235

18 Siddhirganj 213 211 208 217 212 209 213 212 208 207 209

19 Maniknagar 210 208 206 215 212 210 211 209 208 205 210

20 Old Airport 210 202 202 204 211 216 218 213 212 210 216

21 Barisal 218 200 219 221 219 226 224 224 213 218 226

22 AKSML 203 202 197 201 205 206 205 201 203 202 206

23 BSRM 206 204 203 207 208 211 210 207 206 206 211

24 Bibiyana #N/A 215 227 231 231 233 227 217 218 223 233 (Source: The Study Team)

Page 40: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-11

Table 4-8 min Voltage of 132kV Grid Sub-Station (2017-2018)

No. Name Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May. Jan.

1 Siddhirganj 128 127 125 127 128 131 124 124 123 125 131

2 Munsiganj 127 126 125 127 128 130 124 125 124 126 130

3 Megnaghat 126 126 126 127 128 130 124 125 122 126 130

4 Shyampur 119 122 114 117 120 125 120 120 119 120 125

5 Bhulta 118 117 115 114 119 120 120 126 124 118 120

6 Madanganj 124 124 125 122 126 130 123 125 125 124 130

7 Shitalakhya 123 124 123 122 125 126 124 126 126 125 126

8 Rahim Steal 127 126 124 126 129 132 126 125 123 126 132

9 Matuail 125 124 124 126 119 118 118 123 122 124 118

10 Ghorasal 130 128 130 130 135 135 133 125 130 130 135

11 Narsinghdi 123 122 119 125 127 134 120 121 119 122 134

12 Haripur (SBU) 128 126 124 129 129 130 127 125 124 125 130

13 Ullon 124 120 121 122 123 125 122 120 120 126 125

14 Hasnabad 125 124 125 123 125 126 125 124 127 126 126

15 Magbazar 122 120 121 120 115 125 122 110 120 125 125

16 Maniknagar 123 120 122 126 118 119 120 124 125 123 119

17 Bangabhaban 123 120 122 126 118 119 120 124 125 123 119

18 Narinda 123 121 122 127 118 116 120 126 125 128 116

19 Dhanmondi 123 120 122 122 118 120 122 120 120 126 120

20 Lalbag 120 118 118 118 122 121 120 124 124 119 121

21 Madartek 123 120 121 121 124 126 122 120 121 126 126

22 Mirpur 121 116 119 116 124 126 120 125 122 123 126

23 Kalyanpur 123 124 123 123 129 128 120 125 123 125 128

24 Gulshan 124 120 121 121 123 126 121 120 120 119 126

25 Uttara 119 114 120 118 125 126 122 118 120 113 126

26 Kamrangirchar 122 119 120 117 124 123 122 124 121 123 123

27 Savar 123 118 120 119 125 126 122 121 120 119 126

28 Bhasantec 122 120 120 123 124 126 121 120 121 118 126

29 Agargaon 123 121 123 123 126 127 124 121 119 120 127

30 Satmosjid 120 120 121 124 125 125 123 121 120 119 125

31 Tongi 124 121 122 124 126 128 125 120 124 122 128

32 Kabirpur 120 118 120 122 125 127 120 118 120 120 127

33 Basundhara 122 119 120 122 120 127 122 118 117 120 127

34 Manikganj 96 120 123 126 130 134 124 123 128 126 134

35 Joydevpur 113 124 124 127 132 129 129 127 124 125 129

36 New Tongi 123 120 122 124 128 130 123 118 123 121 130

37 Kodda #N/A #N/A #N/A 127 131 130 130 124 121 126 130

38 Tangail 116 115 115 119 121 125 120 112 118 120 125

39 Mymensing 111 112 117 120 124 119 107 109 111 107 119

40 Kishorganj 115 120 123 125 127 126 115 114 115 113 126

41 Netrokona 104 110 117 121 120 115 113 108 110 105 115

42 Jamalpur 111 108 113 117 114 115 107 108 107 108 115

43 Sherpur 110 109 111 116 115 115 108 105 110 107 115

44 Srimongal 132 133 134 127 137 137 136 125 129 127 137

45 Shahjibazar 130 130 124 131 136 137 134 125 127 127 137

46 Fenchuganj 131 131 131 133 135 133 133 128 126 126 133

47 Khulawara 130 131 130 133 132 132 130 127 125 122 132

48 Sylhet 128 127 126 131 133 131 129 122 123 120 131

49 Chattak 124 123 120 129 132 125 127 121 122 124 125

50 Comilla(South) 117 110 118 119 122 123 122 118 119 117 123

51 Comilla (North) 129 121 128 124 133 126 133 128 120 125 126

52 Chandpur 120 112 120 120 125 122 128 115 116 119 122

53 Feni 115 110 115 118 120 120 118 114 113 113 120

54 Chowmuhani 115 110 109 118 122 111 117 114 111 116 111

55 Ashuganj 131 131 135 122 137 138 135 121 127 125 138

Page 41: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-12

56 Daudkandi 125 123 124 127 129 121 129 108 126 125 121

57 Brahminbaria 128 129 132 128 134 136 125 120 127 123 136

58 Madanhat 126 125 121 126 127 126 126 120 126 123 126

59 Hathazari 124 121 120 124 125 125 124 119 107 120 125

60 Khulshi 120 119 116 119 122 119 121 109 120 118 119

61 Halishahar 121 119 118 121 122 122 118 110 122 121 122

62 Baraulia 120 119 118 110 121 120 123 113 115 107 120

63 Sikalbaha 121 119 118 120 120 121 123 117 123 122 121

64 Dohazari 122 120 119 119 122 122 122 120 115 118 122

65 Cox'sbazar 115 109 111 115 119 116 113 112 110 111 116

66 Chandraghona 123 122 120 124 125 122 125 114 107 115 122

67 Kaptai 125 125 125 124 126 124 126 125 125 122 124

68 A. Khaer Stl. 119 121 120 120 122 124 124 116 121 120 124

69 Bakulia 119 119 116 119 121 120 122 118 121 120 120

70 Julda 121 117 118 120 121 121 123 110 122 120 121

71 TK Chemical 124 123 121 124 123 125 127 125 123 124 125

72 Modern Steel 120 119 117 119 121 122 108 115 120 119 122

73 Shahmirpur 121 117 118 121 121 120 123 115 122 121 120

74 Goalpara 127 131 130 128 120 122 119 124 120 118 122

75 Khulna Central 127 124 132 128 121 121 120 125 125 120 121

76 Noapara 125 127 127 125 120 118 120 121 120 118 118

77 Jessore 118 119 120 120 115 111 110 114 117 117 111

78 Jhenida 116 117 115 117 113 106 107 113 110 109 106

79 Bottail 120 117 124 125 125 125 110 120 112 120 125

80 G.K.Project 131 125 123 128 129 130 127 116 122 130 130

81 Faridpur 123 118 122 120 123 125 123 122 121 120 125

82 Madaripur 122 121 123 123 124 123 122 120 120 122 123

83 Gopalganj 121 116 118 118 119 120 119 118 118 118 120

84 Bagerhat 129 130 130 121 120 121 120 121 122 120 121

85 Mongla 124 127 127 118 120 118 117 121 120 113 118

86 Satkhira 127 129 130 128 121 123 121 125 122 121 123

87 Gallamari 129 119 132 127 123 122 121 121 122 122 122

88 Magura 115 115 115 115 119 110 106 112 108 107 110

89 Chuadanga 109 109 109 115 115 101 104 106 104 105 101

90 Barisal 125 128 130 130 126 130 123 127 125 126 130

91 Patuakhali 125 128 130 130 126 130 123 127 125 126 130

92 Bhandaria 124 122 125 120 125 120 125 124 120 120 120

93 Ishurdi 129 127 128 127 124 129 124 124 122 130 129

94 Ruppur Paromanobik #N/A #N/A #N/A #N/A 130 130 129 129 121 131 130

95 Natore 126 125 122 125 123 127 119 120 121 126 127

96 Bogra 122 118 118 124 123 124 113 111 106 119 124

97 Noagaon 118 115 114 121 119 120 111 110 113 115 120

98 Rajshahi 123 124 123 124 123 123 121 119 121 125 123

99 C.Nawabganj 121 116 122 120 120 120 119 116 118 120 120

100 Amnura 120 120 120 122 120 120 120 119 115 118 120

101 Pabna 124 122 106 124 122 120 120 120 118 124 120

102 Shahjadpur 130 124 117 131 129 131 125 130 115 131 131

103 Serajganj 120 123 119 125 125 123 122 114 115 123 123

104 Niyamatpur 112 111 113 118 117 113 105 107 108 111 113

105 Joypurhat 116 113 114 120 118 117 111 111 110 111 117

106 Rangpur 106 109 107 109 112 109 104 105 100 108 109

107 Lalmonirhat 100 100 100 104 103 102 97 104 105 100 102

108 Saidpur 104 105 104 108 108 106 101 103 108 104 106

109 Purbasadipur 107 108 103 110 110 112 105 104 118 112 112

110 Thakurgaon 98 95 95 100 100 104 95 103 103 105 104

111 Palashbari 110 103 110 115 114 112 110 108 105 110 112

112 Barapukuria 114 110 108 113 115 116 112 108 122 120 116

113 Panchagar 93 90 94 95 96 99 92 98 100 98 99 (Source: The Study Team)

Page 42: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-13

c. Voltage Supervision and Control

With respect to voltage supervision, the grid code stipulates that "strategic substations" must be

continuously supervised. In each table, the substations whose names are shown in red are

"strategic substations."

(5) Data Maintenance

With respect to the maintenance of facility data stored in SCADA upon installation of a new

facility, because the construction of a new substation or new transmission line is ordered on a

full-turnkey basis, the maintenance of SCADA data is covered by the construction work contract.

The contractor for construction work commissions the data maintenance work to an SCADA

vendor so that the electric power system including the new facility will be reflected in SCADA.

In many cases, the maintenance of SCADA data is conducted about one or two months after the

completion of a new facility, but there are cases where this procedure is taken later than that.

Training

(1) Training Policy

Figure 4-5 shows the types of training available at PGCB. There are two types of off-the-job

training: one is training received in foreign countries or at external institutions, and the other is

training received in Bangladesh. The type of training received in Bangladesh is classified further

into two types: one conducted in a training center for a group of operators and the other

conducted in each region. All PGCB employees are required to receive this training for a total of

70 hours each year.

The training programs offered by facility manufacturers and external institutions are included in

the training for 70 hours a year. The contents of these 70-hour training programs range from

general administration to special training specific to the employee's post and responsibility.

(Source: The Study Team)

Figure 4-5 Types of training

(2) Training Resources

PGCB is conducting programs to provide in-house training to its operators. As the first step,

PGCB is launching a program to develop a team of 5 to 7 operators as the trainers of a

maintenance unit of steel towers and transmission lines called "Training of Trainers." Once this

Page 43: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-14

program is completed successfully, PGCB will conduct similar programs for other types of

workers and develop about 30 trainers in the next three years.

(3) Training for operators

PGCB is currently focusing on on-the-job training for operators rather than off-the-job training

for them. The operators at BCC are sent to NLDC once or twice a month to work face-to-face

with NLDC operators, experience NLDC operations, and maintain their skills at a high level. On

the other hand, there are some ALDCs and substations where only one operator is working due

to the shortage of operators. In such a case, a supervisor in these workplaces is providing on-

the-job training, or NLDC is providing on-the-job training over the phone.

(4) Other Programs

In the past, training conducted outside Bangladesh was intended only for management-level

employees. However, as a new initiative directed at staff-level employees, PGCB has a plan to

send about 30 engineers to an Indian electric power company for a month.

Unable to communicate well in English, PGCB engineers will have to break the language barrier

before receiving training programs conducted in foreign countries. But because its engineers

can communicate in Bengali in the western part of India, PGCB decided to plan this exchange

program. Once this program is completed successfully, PGCB will continue this relationship with

the Indian Electric Power Company.

4.2 Facilities

SCADA/EMS

Since the start of its operation in 2010, the existing SCADA/EMS has been in service for about

eight years. Although the service life of the hardware is already over, the policy on next-

generation SCADA/EMS has yet to be determined. Furthermore, considering the facility

expansion plans in the future, PGCB also has many problems with its supervisory control system.

Not having developed its specific policy on the supervisory control system, PGCB is unable to

work out a facility replacement plan. Given this background, PGCB already planned and

authorized the replacement of SCADA/EMS hardware this year or next year. It is expected that

the service life of the existing SCADA/EMS will be extended by about 5 to 8 years because of

this hardware replacement.

Page 44: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-15

(1) Hardware Configuration

The equipment connected to RTU LAN is the RTUs of substations. The equipment connected to

SCADA LAN includes each function server of SCADA, workstations for operational use,

workstations for maintenance use, and a supervisory control terminal.

(2) Applications

The function for adjusting electricity supply and demand is currently disabled due to a

connection problem with other pieces of equipment. However, this function will be enabled

through the upcoming "Bangladesh Power System Reliability and Efficiency Improvement

Project of the World Bank."

Communication Network

Figure 4-6 shows the configuration of the optical fiber network PGCB owns.

PGCB sets up optical ground wires (OPGW), a type of cable that mounts optical fiber cable inside

the overhead ground wire designed to protect high-voltage transmission lines from direct

lightning strokes. PGCB has its proprietary power line carrier (PLC) communication system in

place. However, because the speed of its existing PLC communication equipment is not at a

satisfactory level, PGCB is trying to improve its communication system by installing high speed

optical fibers using multiplexers.

As a result, the total length of the OPGW became 4,300km as of June 2012, and over 5,000km

today (according to our hearing survey), covering most of the land of Bangladesh. Not just for

PGCB itself, the optical fiber network has expanded rapidly enough to lease it to local

telecommunications carriers and grow the country's communication infrastructure.

Page 45: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-16

(Source: PGCB Web site https://www.pgcb.org.bd/PGCB/)

Figure 4-6 PGCB Optical Fiber Network

Page 46: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

5-1

5 Issues of Power Control Operation and Control Facilities Based on

Future Facility Expansion

5.1 Power Control Operation

Supervisory Control System

If the number of substations increases in the future as forecasted in "3 Current Status and Future

Outlook of Electricity Supply," the system of PGCB described in "4.1.1 Supervisory Control System"

is expected to lose control. The following are the reasons.

(1) Division of Roles

In normal times, NLDC orders each substation to conduct specific operations over the phone. But

only when the balance between supply and demand becomes strained, NLDC will control load

interruption at the substation by remote operation. Ordering all substations to conduct operations

over the phone will increase the workload of NLDC if the number of substations increases in future.

(2) Workload

It is expected that the workload of NLDC will build up with the increasing number of new facilities.

While the details will be described in "5.1.2 Operation," workload related to power system control

will increase in proportion to the number of new facilities. Furthermore, it is also expected that the

existing plans for new generators will increase the complexity of electricity supply and demand

control. This situation would not only increase the workload of staff-level employees but also

increase the time supervisors must spend making decisions, possibly affecting PGCB's overall

performance.

Operation

(1) Supervisory Operation

At present, alarm supervision for each equipment at substation is conducted by the substation.

Equipment failures that affect the operation of the power system need to be reported to NLDC. It

is considered that the number of facility problem reports from each substation will increase with

the growing number of new facilities. Because only one operator is involved in transmission system

control at NLDC, there is concern that necessary actions may not be taken when multiple problems

occur at the same time.

(2) Switching Operation

Scheduled outages are concentrated in the winter in Bangladesh because of high electricity

demand and frequent cyclones in other seasons. According to our surveys, it was learned that

each facility needs to be shut down for inspection and maintenance once a year. This means that

the number of scheduled outages will increase with the growing number of new facilities.

Page 47: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

5-2

In this case, there may be a problem in which some facilities cannot be shut down due to

limitations of power system operation. There is concern that NLDC operators will become busy

with multiple operations, which may lead to erroneous operations and delayed operations. They

may not be able to spend sufficient time for inspection, paying less attention to operation safety.

(3) Data Recording

Based on the number of numerical records prepared at each substation that was assumed in

"4.1.2(3) Data Recording" and "3.4 Data for Verification," the workload needed to prepare records

and reports in the future is estimated as follows. However, the records of generators are excluded

from these log points because they are reported using the PGCB Intranet.

(Source: The Study Team)

Figure 5-1 Rough estimation of the log point of substations and transmission lines

The work needed to prepare these records and reports are burdensome even today. If this work

must be continued into the future, the workload will double in 2022 and triple in 2033 compared

to today's levels. Unless the number of operators is increased or how to conduct operations is

changed, the total workload is expected to go beyond what ALDC and NLDC can possibly deal

with.

(4) Voltage Regulation

Being aware that voltages at each substation deviate from the maximum and minimum indicators,

PGCB is faced with the problem of not knowing how to regulate these voltages within the range.

It seems that this problem can be solved by introducing an application that simulates voltages in

its power systems and offers appropriate solutions. At a glance, however, there are many

0

4000

8000

12000

16000

20000

24000

2018 2023 2028 2033 2038

Total Substation Transmission line

Page 48: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

5-3

substations where voltages deviate from the maximum and minimum indicators. It is a concern

that the workload of voltage regulating operation will increase over time.

(5) Data Maintenance

It seems that the timing of SCADA data maintenance lags because PGCB is not outsourcing

SCADA data maintenance to an SCADA vendor. Furthermore, there is concern that as the number

of new facilities will increase at a rapid pace, PGCB will lose track of what equipment will be added

to SCADA and when.

Training

At present, internal and external training programs are clearly classified in accordance with the

"Training Policy." In addition, all employees are required to receive introductory training and

develop an annual training plan, with a person in charge of training clearly indicated for each

department. PGCB is well organized in its training system. Further, PGCB employees appear to be

proactively receiving external and overseas training programs.

However, all of these are desktop training, and all skill coaching training is conducted as on-the-

job training. Additionally, there is the problem that staff-level employees have limited

opportunities to receive external training programs due to the language barrier.

Currently, trainer development programs are under way, albeit in a limited number of areas. It is

necessary to expand the scope of such programs to other areas. It is also necessary to create an

environment in which skill coaching training programs will be conducted as off-the-job training.

5.2 Facilities

SCADA/EMS

(1) Hardware Configuration

First, concerning the internal configuration of SCADA, signals to be processed in real time are

flowing through SCADA LAN, including switch ON/OFF data collected from on-site facilities,

signals that transmit measurement data to operators, and signals that transmit control signals to

on-site facilities.

In addition, other types of signals are also flowing through SCADA LAN, such as signals that do

not require real-time processing as much as the above-mentioned signals, which include the

preparation, storage, and invocation of operating procedures, the storage of records in archives,

and the processing of power system simulation. In the existing architecture, all signals are

transmitted through SCADA LAN. In the future, the number of signals flowing through the inside

of SCADA will increase with the growing number of substations, which may increase the level of

data traffic. It is therefore necessary to create a mechanism to separately process signals that

must be processed in real time and other signals.

Page 49: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

5-4

(2) Applications

As described earlier, the functions required for electricity supply and demand control will be

developed through the "Bangladesh Power System Reliability and Efficiency Improvement Project

of the World Bank." One of the kinds of issues that PGCB must solve is that the company

introduced its SCADA/EMS with full functions built in despite the inability to connect it to some

pieces of the existing equipment. In introducing SCADA/EMS, PGCB should design the

SCADA/EMS on its own and introduce the best system.

In the meanwhile, PGCB is using almost all the functions required for power system control, but

they are all conventional functions. These functions are not enough to solve the issues described

in "5.1.2 Operation."

Communication network

The current communication network equipment is enough to lease it to local telecommunications

carriers, and there is no problem in particular. It is necessary to prepare for data traffic between the

field device and SCADA with the growing number of field devices in the future.

Page 50: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

6-1

6 Improvements in Project Schemes

6.1 Operation

Supervisory Control System

(1) Delegation of Authority

As a first step, it would be best to delegate the responsibility and authority for power system

control NLDC holds to somewhere else in order to solve the issues described in "5.1.1(1) Division

of Roles."

It seems that NLDC has been responding to more urgent problems first in both power system

control and supply and demand control. If the authority of NLDC for power system control is

delegated to somewhere else as shown in Figure 6-1, NLDC will be able to focus more on supply

and demand control including less urgent problems. This setting would provide the benefit of

realizing high-value-added operations.

The organization that can operate this type of function today is ALDCs. The details will be

described in the next paragraph.

(Source: The Study Team)

Figure 6-1 Advantage of empowerment

(2) Organizational Configuration

In order to delegate NLDC's authority for power system supervision control, new Load Dispatch

Centres need to be set up at several locations so that all areas of Bangladesh will be covered.

After ALDCs are set up to cover all Bangladeshi areas, the authority and responsibility for power

system supervision control will be given to ALDCs. But because the electric power system is

connected to all regions of the country, any operation conducted in one region in normal times

or at the event of an outage will affect other regions. For this reason, these Load Dispatch Centres

must be interconnected. Especially bulk power transmission lines, which are designed to transmit

generated electric power throughout Bangladesh, require wide-area tidal current supervision

capabilities. It is therefore difficult for supervisory control centers across the country to conduct

the supervisory control of these bulk power transmission lines.

Page 51: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

6-2

Given this background, this study proposes the establishment of a Load Dispatch Centre that

plays the roles of conducting the supervisory control of bulk power transmission lines and

organizing the operations of all ALDCs. Figure 6-2 shows the best organizational configuration of

the Load Dispatch Centre this study recommends.

(Source: The Study Team)

Figure 6-2 Suitable monitoring and control organization

A new organization called the Bulk Load Dispatch Centre (BLDC) will be established. The

following are the roles that BLDC should play.

Supervision and control of the bulk power system network

Information sharing with NLDC that controls electricity supply and demand in normal

times and emergency situations

Cooperation with ALDCs for organized operations in power system supervision control

Providing support to ALDCs in human resources development

Based on this proposal, NLDC can concentrate on the most important supply and demand

control operations, allowing itself to strive for high-quality operations. When the balance

between supply and demand is strained or in the event of an outage, NLDC needs to interact

only with BLDC, which minimizes the workload of NLDC.

As one idea about the division of roles between BLDC and ALDCs, it is recommended that BLDC

conducts the supervisory control of 400/230kV and 400/132kV substations and 400kV and

230kV transmission lines, and that ALDCs conduct the supervisory control of 230/132kV and

132/33kV substations and 132kV transmission lines.

In this setting, BLDC will conduct the supervisory control of 230kV-or-higher bulk power systems

Page 52: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

6-3

throughout Bangladesh, and each ALDC will conduct the supervisory control of 132kV area

power systems in its territory. However, there is the need to set rules for the authority for the

132kV side of 400/132kV substations and the 230kV side of 230/132kV substations, including

the need of close interaction between concerned BLDC and ALDC.

It is desirable that BLDC will eventually delegate its authority for 132kV-or-lower power systems

to ALDCs. When considering the delegation of authority, it is necessary to make sure the

facilities to which the authority will be delegated have qualified human resources. However, it is

realistically impossible to find such human resources at ALDCs at the starting point. It is

therefore desirable that BLDC will deploy human resources with experience of conducting power

system supervision control at NLDC, and that BLDC will support ALDC in developing qualified

operators and gradually developing an ideal form of organization.

In the meantime, new BLDC can be set up at any location. If there is enough space, establishing

BLDC right next to NLDC makes a lot of sense in terms of effective interaction between the two.

Alternatively, establishing BLDC right next to the Backup Control Center (BCC) of NLDC would

allow BLDC to back up NLDC when it becomes unable to conduct supervisory control.

Operation

In this section, the opportunities for automating ongoing operations using SCADA will be studied

in order to solve the problem of operator shortage.

(1) Supervisory Operation

One supervisory control center is supervising several dozen of substations at the same time. For

this reason, there is the need for computer screens designed to classify incoming information into

those that require alarming and those that do not and to help grasp necessary information

quickly.

(2) Switching Operation

PGCB can prepare and store procedures for switching operations in advance. PGCB also can refer

to the procedures used in the past in preparing new procedures. These facts make us believe that

PGCB's switching operations are streamlined to a certain degree. Further efficiency improvements

might be possible by automating the preparation of procedures for switching operations. It seems

possible to automatically prepare procedures for simple processes such as for stopping a single

facility, which can be ordered using a typical procedure.

At present, NLDC or each ALDC is instructing substations over the phone to follow "Purpose of

Switching" as shown in Figure 4-4, and the substations are implementing the procedures line by

line. In this case, the use of remote operation directly from SCADA would be more efficient. If

specifications are designed to automatically implement procedures for each piece of equipment

line by line simply by executing the command of "Purpose of Switching," virtually nothing will

change from the previous procedures, resulting in smooth transition.

Page 53: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

6-4

(3) Data Recording

PGCB should pursue the automation of data recording as well. The need of reporting data over

the phone every hour is burdensome for substations, NLDC, and ALDCs. PGCB is currently using a

predetermined format for data reporting. If there is a function that can automatically output data

collected by SCADA into that format, the efficiency of data reporting is expected to improve

significantly.

But there is the need to set rules before changing this procedure for data reporting. The reasons

why PGCB is not using data collected by SCADA today include missing pieces of data and

measurement errors.

With respect to missing pieces of data, it is necessary to set up rules for some functions of

SCADA. For example, when finding an apparently strange data point, SCADA must remove it and

adopt a value estimated from the previous and next data points.

As to measurement errors, at the start of operation of a piece of equipment, the values displayed

at the substation and NLDC must be carefully checked to see whether they are identical. If there

are any discrepancies in measurements, a calibration test must be conducted. In addition, the

equipment in operation must be checked regularly to see whether there are any discrepancies in

measurements between the substation and NLDC.

(4) Voltage Regulation

With respect to voltage regulation, there is the need for a function that can judge whether the

transformer tap must be stepped up or down, or whether the switch of the phase modifying

equipment must be turned ON or OFF, when voltages deviate from the target level and must be

brought back into an adequate range.

At present, the shape of daily electrical load curves of Bangladesh is moderate. It is unknown how

this shape will change with increasing electricity demand in the future. Furthermore, when the use

of renewable energy increases in the future, changes in the weather may affect electricity demand

and voltages.

It is likely that voltages need to be regulated frequently in the future, and the introduction of a

function that can automatically adjust voltages to SCADA is recommended. As described in

"5.1.2(2) Switching Operation," the number of scheduled outages is expected to increase in the

future and the number of operations will increase accordingly. This is why the automated

regulation of voltages is recommended.

(5) Data Maintenance

Upon new facility installation, it is recommended that PGCB outsource SCADA data maintenance

directly to an SCADA vendor. For example, if PGCB itself controls the schedule of SCADA data

Page 54: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

6-5

maintenance by conducting the data maintenance of multiple facilities every month, it will

prevent data maintenance from lagging behind the start of operation of a new facility.

(Source: The Study Team)

Figure 6-3 Proposal of SCADA data maintenance ordering method

Training

At present, PGCB is having its operators receive external training programs proactively, and this

approach should be continued. However, most of these external training programs are one-time

events, which are not suited for long-term practical training. Even if PGCB plans long-term

operator training programs with the help of external programs, it would cost the company a lot,

and all operators may not be able to receive such training programs. Moreover, the number of

operators who can receive such training programs is limited because of the language barrier.

Given this background, the introduction of in-house training is necessary to improve the skills of

all operators. In this case, practical skill training by internal trainers familiar with internal rules

would enable coaching reflecting the company's actual conditions. This type of internal training

would allow operators to learn practical skills in their workplaces. This approach also makes it

easy to benchmark the level of skills acquired, and the company can foster its operators on an

ongoing basis, while checking the pace of their growth at the same time.

However, conducting in-house practical skill training for all operators would involve the

assignment of internal trainers and the creation of a training environment, which requires a lot of

time.

Given this background, this study offers a proposal in which human resources will be brought up

while developing the training environment in incremental steps.

Page 55: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

6-6

6.2 Facilities

SCADA

(1) Hardware Configuration

a. System configuration

The main system configuration of the proposed SCADA remains unchanged from the existing

SCADA, with FEPs and servers installed at Server Base. Thin client terminals are installed at

supervisory control organizations to supervise/control electric power systems. These terminals

are installed at places where display terminals need to be monitored.

b. Service Bus

Information has different levels of priorities. When many types of information are bundled into

one bus, high-priority information may not be processed in real-time due to data traffic caused

by low-priority information. This issue can be solved by using different buses depending on the

priority of information.

c. Gateway

Gateways are installed between substation SAS and RTU and SCADA FEP. The details will be

described in "6.2.2 Communication Network".

(2) Application Configuration

a. Automated procedure preparations, operational functions

When it comes to controlling on-site facilities directly from BLDC or ALDC, BLDC or ALDC needs

to prepare not only the procedure for "Purpose of Switching" but also the procedure for each

piece of equipment. If SCADA has a function that can read in the procedure for each of the

related pieces of equipment when preparing "Purpose of Switching," the streamlining of

procedure preparations may be possible.

If the procedure for each of the related pieces of equipment can be automatically executed

when "Purpose of Switching" is executed, the workload of the operator will be reduced.

b. Data output function

The timing and format of records and reports are predetermined. If SCADA has a function that

can store and output records and reports in these predetermined format and time, a significant

increase in efficiency may be expected.

c. Voltage regulation function

SCADA needs to have a function that informs the details of appropriate operations, or conducts

such operations automatically, when the voltage is found to deviate from an adequate voltage

range during bus bar voltage supervision at each station. If PGCB has a plan to introduce phase

modifying equipment in the future, SCADA needs to have a function that monitors reactive

Page 56: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

6-7

power.

Communication Network

The communication network in Bangladesh is well-organized, and there are few short-term

challenges. However, the level of data traffic may increase with the increasing number of

substations and growing amount of incoming information in the future. For this reason, the need

to introduce more efficient communication methods may arise in the future.

6.3 Project Implementation Structure and Schedule

Our proposal based on the results of this survey would require the construction of a new

supervisory control system and the introduction of a new SCADA for system supervisory control.

At present, PGCB does not have the ability to design the best SCADA specifications on its own.

For this reason, PGCB must start with human resources development.

The electric power system operators PGCB has today are limited to those at NLDC. Although

PGCB has many substation operators, none of them have experience with electric power system

operation. The new supervisory control system would require system operators at BLDC and ALDC

locations, meaning that PGCB will need to have more system operators than the center has today.

However, PGCB has neither training plans nor training programs for developing system operators.

In order to develop the many system operators that will be required in the future, the

implementation of system operator training programs is recommended as a first step. The system

operators developed through such training programs will be able to operate electric power

systems and understand necessary SCADA requirements. The system operators developed in such

a way will become operators at each supervisory control center under a new supervisory control

system, or they are expected to become engineers who design necessary requirements for a new

SCADA.

6.4 Result of Pre-Feasibility Study

It was confirmed that our proposal based on the results of this survey is feasible in all aspects of

supervisory control system, SCADA, operation, and training. The introduction of new operational

practices would require detailed rule setting, and there is the need for our technical assistance.

Page 57: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-1

7 Benefits from Improvements in the Project

7.1 Expected Benefits for the Partner Country

Minimizing the Increase in Personnel Expenses

If facility expansion continues without revising the existing personnel plan, a large number of

operators must be added at substations. However, if operations can be streamlined by

establishing supervisory control systems as described in "6.1.1 Supervisory Control System" by

conducting supervisory control at BLDC and by introducing a new SCADA, the number of

operators at substations could be reduced from the current plan.

If additional personnel are deployed at each supervisory control center to directly

supervise/control substations, the number of substation personnel could be reduced from the

current plan. While it seems possible to introduce unmanned operation, this simulation assumed

the abolition of three-shift rotations at substations and halving the number of substation

personnel to half from the current plan.

Figure 7-1 shows the result of our simulation on the number of personnel.

(Source: The Study Team)

Figure 7-1 Comparison of personnel in each plan

Assuming that a new SCADA will be introduced in 2024 and supervision/control under a new

system will start at the same time, the number of operators required will increase as shown by the

orange solid line in Figure 7-1, about 75% of the number of the current plan as of 2041. However,

given the long-term plan that many facilities will be expanded by 2023, the current personnel

plans should be reviewed earlier. Because the scale of power grids in Bangladesh is not large

today, it seems possible to deal with future facility expansion by building supervisory control

systems as early as possible and by installing the terminals of the existing SCADA at new

0

500

1000

1500

2000

2500

3000

3500

4000

4500

2018 2023 2028 2033 2038

Pers

on

nel

Year

Operator (In current plan)

Operator (In tentative plan from 2024)

Operator (In tentative plan from 2021)

Page 58: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-2

supervisory control centers. In this case, the number of personnel required will change as shown

by the orange dotted line in Figure 7-1, about 80% of the number of the current plan even as of

2023 then about 65% as of 2041.

In order to start building supervisory control systems as early as possible, the installation of

simulators to train operators should be started earlier than the introduction of a new SCADA.

Once the supervisory control systems are put in place, the continuously expanding electric power

system can be operated in an efficient manner by the introduction of a new SCADA and the

expanded scope of training programs.

Reductions in Economic Losses by Shortening Power Outages

It is obvious that even in Bangladesh, the occurrence of power outages interrupts its economic

activities to a certain degree. The cost of such economic losses is estimated here.

First, Figure 7-2 shows the status of power outages in Bangladesh.

(Source: PGCB Web site https://www.pgcb.org.bd/PGCB/)

Figure 7-2 Summary of unserved energy (2017-2018)

According to an estimate by the Central Research Institute for Electric Power Industry1, economic

losses from power outages are considered to be somewhere between 300 and 1,000 yen/kWh,

however this is based on Japanese data. This survey was conducted based on a power outage loss

of 883 yen/kWh, a value estimated using an analysis technique.

Losses from power outages in Japan cannot be applied directly to similar losses in Bangladesh.

For this reason, economic losses from power outages in Bangladesh were estimated based on

Japan's GDP in 2011 and Bangladesh GDP in 2017 and 2018 (estimated): 0.43 dollars/kWh (2017)

and 0.48 dollars/kWh (2018). Based on these economic losses per kWh and the actual unserved

energy shown in Figure 7-2Figure 7-2, total economic losses from power outages in Bangladesh

were estimated as shown in Figure 7-3.

1 Takeo Imanaka, Overview of Electricity Supply-Demand Curve, the Central Research Institute for Electric Power

Industry, 2011

0

500

1000

1500

2000

2500

3000

Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May Jun.

[MW

h]

T E/O S/O

Page 59: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-3

(Source: The Study Team)

Figure 7-3 The economical loss caused by outage

According to this estimate, Bangladesh is losing 12 million dollars every year due to power

outages. If the time needed to recover from power outages can be decreased by 10% by

developing supervisory control systems, upgrading the existing SCADA, and providing training to

operators, economic losses due to power outages can be reduced by more than 1 million dollars.

This estimate was based on economic losses due to power outages in Japan, and it is not known if

Bangladesh will experience similar levels of economic losses. However, it is expected that

Bangladesh will see its economic losses caused by power outages increasing in the future since it

is aiming to become an advanced country by 2041. In this sense, it is important to try to shorten

power outages.

Reducing Loss in Leased Transmission Fees

Figure 7-2 showed the amount of unserved energy due to power outages. This means that

Bangladesh is missing the amount of leased transmission fees equivalent to the length of power

outages. The reduction in power outages will decrease the loss in expected leased transmission

fees.

7.2 Estimating CO2 Emission Reductions

According to the World Bank data, carbon dioxide emissions in Bangladesh were approximately

73,000kt in 2014. In Bangladesh, the power sector accounts for about one-third of the total

energy consumption, which means that the power sector is emitting approximately 24,000kt of

carbon dioxide every year.

Electricity transmission company PGCB can contribute to the reduction of carbon dioxide

emissions by decreasing the transmission loss as shown in Figure 7-4.

0

2

4

6

8

10

12

14

0

1

2

3

4

5

Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May. Jun.

Cu

mu

lati

ve l

oss

[m

illi

on

$]

Mo

nth

ly L

oss

[m

illi

on

$]

T E/O S/O Cumulative

Page 60: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-4

(Source: PGCB Annual Report 2016-2017)

Figure 7-4 Transmission Loss of PGCB

One of the effective measures to reduce transmission loss is proper management of transmission

voltage. As described in "4.1.2(4) Voltage Regulation" transmission voltage deviates from the

standard voltage at many substations. Of these substations, a larger number of substations were

seen operating at a transmission voltage lower than the standard voltage.

Power transmission at a higher voltage helps reduce transmission loss. For this reason,

transmission loss could be reduced by introducing the function proposed in "6.2.1(2)c Voltage

regulation function " and through voltage management improvements. Assuming that the power

sector emits 24,000kt of carbon dioxide, and after correcting the influence of the growth of

electricity demand from 2014 till today, our estimate shows that if transmission loss is reduced by

0.01%, carbon dioxide emissions can be reduced by approximately 33.8kt/year.

7.3 Expected Benefits for Japan

In the world of operational technology (OT), which has been a closed world in the past, the use of

general-purpose products and standard protocols has been promoted for cost reduction, and

connection to data processing systems (IT systems) has been driven for efficiency improvement.

In the industrial arena, products and facilities sit at the center of business. The utilization of such

information is essential and the combination of OT and IT would offer numerous benefits.

Generally, the OT sector collects data from facilities to efficiently supervise/control the facilities

based on this data. The IT sector prepares market forecasts and production schedules utilizing

product sales and manufacturing information.

Electric power companies prepare facility expansion and repair plans based on data of the

operational status of facilities as well as the status of electricity consumption. In other words, OT

data sits at the center of the business of electric power companies, with SCADA sitting at the

center of OT. It is expected that the combination of IT and OT and the introduction of IoT

technology will be promoted in Bangladesh in the future. Introducing Japanese SCADA systems in

Bangladesh would allow Japanese companies to enter into the center of OT in the country. This

approach would help Japanese companies have more business opportunities and gain a

competitive advantage in the country.

2.72% 2.70%2.92% 2.82% 2.77% 2.86%

2.67%

0%

1%

2%

3%

4%

5%

2011 2012 2013 2014 2015 2016 2017

Page 61: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-5

7.4 Assessing Japanese Companies' Competitive Advantages

Today, PGCB is lacking in power system operation technology and SCADA design technology.

This is where Japan can find its business opportunity. By providing PGCB with technical assistance

through training programs concerning the power system operation technology and SCADA

design technology, which are demonstrating Japan’s high electric power quality, Japan will be

able to get PGCB to fully recognize the competitive advantage of Japanese power system

operation technology and the importance of cybersecurity measures. If PGCB reflects input from

Japan in its SCADA procurement requirements and specifications, Japan can favorably promote

Japanese market-oriented SCADA developed to satisfy the needs of partner countries, vs.

overseas vendors that insist on product-oriented SCADA procurement.

7.5 Possible Utilization of Financing and Government Support

From a financial standpoint, it is difficult for PGCB to implement this project on its own. Therefore,

it is considered appropriate that Phase 1 and Phase 2, which were described in "6.3 Project

Implementation Structure and Schedule" will be covered by ODA funds in a framework of

technical cooperation, with Phase 3 covered by project loans.

7.6 Promoting this Approach to Other Countries

It was confirmed that our proposal for this project is technically applicable to PGCB. With respect

to the possibility of promoting this approach to other countries similar in economic growth to

Bangladesh, another round of surveys for each country will be required, because the type of

electric power system, scale, supervisory control system, electric power facilities, etc. vary

depending on the country, and because the best supervisory control system and SCADA also vary

depending on each country.

Page 62: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

Vietnam

Page 63: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

i

Contents

List of abbreviations ................................................................. iv

1 Project Details .................................................................. 1-1

1.1 Objectives of Project ........................................................ 1-1

1.2 Project Details .............................................................. 1-1

1.3 Project Implementation Method .............................................. 1-2

1.3.1 Project Implementation Structure ......................................... 1-2

1.3.2 Implementation Schedule ................................................ 1-3

2 Actual State of Investigated Country............................................... 2-1

2.1 Basic Information about the Country .......................................... 2-1

2.1.1 Economic Situation ..................................................... 2-1

2.1.2 Economic Development Policies .......................................... 2-3

2.2 Power Overview ............................................................ 2-3

2.2.1 Power Overview ........................................................ 2-3

2.2.2 Power Policies .......................................................... 2-4

2.3 Regarding Electric Power Circular ............................................. 2-5

2.3.1 Basic Structure of the Vietnamese Law ..................................... 2-5

2.3.2 Circular 25/2016/TT-BCT ................................................. 2-7

(1) Scope ................................................................. 2-7

(2) Subjects of application .................................................. 2-7

(3) Main contents .......................................................... 2-7

2.3.3 Circular 28/2016/TT-BCT ................................................. 2-9

(1) Scope ................................................................. 2-9

(2) Subjects of application .................................................. 2-9

(3) Main contents .......................................................... 2-9

2.3.4 Circular 39/2015/TT-BCT ................................................ 2-11

(1) Scope ................................................................ 2-11

(2) Subjects of application ................................................. 2-11

(3) Main contents ......................................................... 2-11

2.3.5 Circular 40/2014/TT-BCT ................................................ 2-14

(1) Scope ................................................................ 2-14

(2) Subjects of application ................................................. 2-14

(3) Main contents ......................................................... 2-14

2.3.6 Circular 44/2014/TT-BCT ................................................ 2-18

(1) Scope ................................................................ 2-18

(2) Subjects of application ................................................. 2-18

(3) Main contents ......................................................... 2-18

2.3.7 Circular 55/2017/QD-DTDL .............................................. 2-20

(1) Scope ................................................................ 2-20

(2) Subjects of application ................................................. 2-20

(3) Main contents ......................................................... 2-20

2.3.8 Circular 69/2018/QD-DTDL .............................................. 2-23

(1) Scope ................................................................ 2-23

(2) Subjects of application ................................................. 2-23

(3) Main contents ......................................................... 2-23

Page 64: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

ii

2.3.9 Circular 03/2017/TT-BTTTT .............................................. 2-25

(1) Scope ................................................................ 2-25

(2) Regulated entities ..................................................... 2-25

(3) Main contents ......................................................... 2-25

3 Current Situation and Prospects for Power Supply ................................... 3-1

3.1 Power Supply Structure ...................................................... 3-1

3.2 Overview of EVN SMART GRID PLAN .......................................... 3-2

3.3 Facility Enhancement Plan ................................................... 3-4

3.3.1 Plan of Total Installs Generation Capacity .................................. 3-4

3.3.2 Plan of Transmission and Transformer ..................................... 3-5

4 Current situations of Power Control Operation and Control Facilities ................... 4-1

4.1 Operation ................................................................. 4-1

4.1.1 Monitoring Control Organization ......................................... 4-1

4.1.2 Responsibility Border of Power System .................................... 4-4

4.1.3 Operation ............................................................. 4-6

(1) Monitoring Work ....................................................... 4-6

(2) Operation work ........................................................ 4-6

(3) Recording work ........................................................ 4-8

(4) Data maintenance in SCADA ............................................. 4-8

4.2 Facility .................................................................... 4-9

4.2.1 SCADA/EMS ........................................................... 4-9

(1) Function configuration .................................................. 4-9

(2) Hardware configuration ................................................. 4-9

(3) Backup SCADA ........................................................ 4-10

4.2.2 Communication Network ............................................... 4-10

5 Issues of Power Control Operation and Control Facilities Considering Future Facility

Reinforcement ..................................................................... 5-9

5.1 Operation ................................................................. 5-9

5.1.1 Monitoring Control Organization ......................................... 5-9

(1) Role sharing ........................................................... 5-9

(2) Workload .............................................................. 5-9

5.1.2 Operation ............................................................. 5-9

(1) Operation work ........................................................ 5-9

(2) Estimate of issues in EVN by comparison with TEPCO Power Grid ............. 5-10

(3) Recording work ....................................................... 5-11

5.2 Facility ................................................................... 5-11

5.2.1 SCADA/EMS .......................................................... 5-11

(1) Hardware configuration ................................................ 5-11

(2) Application ........................................................... 5-12

6 Investigation for Improving Work Schemes ......................................... 6-1

6.1 Operation ................................................................. 6-1

6.1.1 Monitoring Control System .............................................. 6-1

(1) Review of Organization .................................................. 6-1

6.1.2 Operation ............................................................. 6-2

(1) Creation of operation procedure .......................................... 6-2

Page 65: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

iii

7 Benefits from Improvements in the Project ......................................... 7-1

7.1 Expected Benefits for the Partner Country ...................................... 7-1

7.1.1 Reducing in Transmission Loss............................................ 7-1

(1) transmission loss ....................................................... 7-1

(2) Increase in transmission loss due to transmission line stoppage ............... 7-1

(3) Reduction of transmission loss by automating NLDC operation ............... 7-3

(4) Estimation of transmission loss reduction .................................. 7-3

7.1.2 Reduction of Limitation for High-efficiency Thermal Power Plant .............. 7-4

7.1.3 Reduction of Power Outage Recovery Time ................................. 7-4

7.2 Estimation of CO2 Emissions Reduction Amount ................................ 7-5

7.3 Expected Benefits for Japan .................................................. 7-5

7.4 Assessing Japanese Companies’ Competitive Advantages ........................ 7-5

7.5 Possible Utilization of Financing and Government Support ....................... 7-6

7.6 Promoting this Approach to Other Countries ................................... 7-6

Page 66: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

iv

Abbreviations

ABBREVIATION SIGNIFICANCE

EVN Electricity of Vietnam

MOIT Ministry of Industry and Trade of the Socialist

republic of Vietnam

NLDC National Load Dispatching Center

RLDC Regional Load Dispatching Center

HRM Human Resource Management Department

SCADA Supervisory Control and Data Acquisition

EMS Energy Management System

E/O Emergency Outage

S/O Scheduled Outage

PLC Power Line Carrier

OPGW Optical Ground Wire

BSLDC Bulk System Load Dispatching Center

PDP7 Power Development Plan 7

Page 67: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

1-1

1 Project Details

1.1 Objectives of Project

Vietnam’s entire power grid, including all power generation, transmission, and distribution, has

been owned, operated, and maintained by Electricity of Vietnam (EVN), which is a state-run power

company. Its recent power generation area is in a competitive power generation market based on

03/2013/TT-BCT and 79/QD-DTDL.

At present, Vietnam’s voltage classes are divided into three ranges: high voltages of 500kV, 220kV,

and 110kV, medium voltages of 1kV to 35kV, and low voltages below 1kV. 500kV and 220kV are

used for power transmission systems that connect the North, Middle, and South of Vietnam. 110kV

is applied to power transmission/distribution systems in main supply areas, whereas 1kV to 35kV

are applied to subordinate distribution systems.

The total electricity generated in Vietnam is approximately 182,000GWh and its power facility

capacity has reached approximately 40,000MW. Such figures are increasing year by year in Vietnam,

which is a developing country. Vietnam’s power development plan is currently being implemented

based on the 7th Power Development Plan (PDP7), which was reviewed by the government in March

2016. PDP7 describes the power development plan from 2011 to 2020 with an eye to 2030 and its

objective is to achieve a total generated electricity of 572,000GWh and a power facility capacity of

129,500MW by 2030. The current power grid must be expanded in order to transmit and distribute

such enormous amounts of electricity.

At present, EVN uses EMS/SCADA at a National Load Dispatch Center (NLDC) to monitor and

control all of its substations (by telephone). As the power plants are enhanced and the systems are

expanded, the current NLDC is expected to reach its organizational limits due to operational

pressure, personnel shortage, etc. If the power plant capacity increases toward 2030, NLDC will be

involved more deeply into the demand and supply management. Therefore, it is necessary to reform

NLDC’s organization structure and establish a new mechanism for monitoring and controlling the

power grid.

In addition, regional load dispatching centers exist under LNDC and they are abbreviated as RLDCs.

At present, there are three RLDCs in the North, Middle, and South. Although only these three are

currently in operation, more RLDCs will need to be built for the power systems, as the power plants

are enhanced and the number of substations increases in the future.

The purpose of this project is to investigate and analyze the monitoring and control organizations,

operations, and SCADA of NLDC under EVN, and then further investigate the feasibility of

introducing Japan’s high-quality operational technologies for power systems.

1.2 Project Details

This project investigates the following items.

i. Background investigation

a. Policy trends in the target country

b. Strategy trends by the target company

ii. Collection of information required to introduce operational technologies for power

Page 68: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

1-2

systems

a. Identification of the actual current state of the power infrastructure

b. Identification of the needs and issues of the target company

c. Current and future trends in the monitoring and control structure

d. Personnel development structure

iii. Reduction/regulation of energy-originated CO2 emissions

a. Identification of the current emissions

b. Tentative calculation of the reductions achieved by introducing operational

technologies for power systems

iv. Superiority check of Japanese companies

a. Operational superiority evaluation

1.3 Project Implementation Method

1.3.1 Project Implementation Structure

Figure 1-1 shows the structure used to implement this project.

Figure 1-1 Pre-FS Implementation Structure

The main entity that implements this project is TEPCO IEC, Inc. In addition, McAfee Co., Ltd. has

cooperated in the present state analysis of the cyber security field and the business scheme

examination, whereas NTT DATA Corporation has cooperated in the network investigation and

analysis.

Page 69: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

1-3

1.3.2 Implementation Schedule

Figure 1-2 shows the schedule for implementing this project.

Figure 1-2 Pre-FS Implementation Schedule

Page 70: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-1

2 Actual State of Investigated Country

2.1 Basic Information about the Country

2.1.1 Economic Situation

Vietnam’s economy maintains continuous growth. As shown in Figure 2-1, the country’s GDP

growth rate for the past 10 years is approximately 6.01% in average. It rose to 6.8% in 2017.

According to a report released by the World Bank, it is expected to slow down to 6.6% in 2019, and

then 6.5% in 2020. However, this will be part of the global trend. While such economic slowdown

is predicted globally, Vietnam’s expected GDP growth rate exceeds 6.3%, which is the average level

in the East Asia and Pacific Areas, and Vietnam is also expected to maintain a +4% rise by 2020.

Figure 2-1 GDP growth rate of Vietnam

Figure 2-2 shows the sectoral share of GDP in Agriculture, Industry, and Service in 2017, and Figure

2-3 shows the trends in the share of Agriculture, Industry, and Service sectors in GDP. According

to Figure 2-3, although the dramatic change has not been seen in each of the three sectors since

2010, Agriculture is gradually decreasing, indicating that the Service sector is increasing little by

little.

GDP is closely related to electricity demand. Even in Japan, electricity demand was also increasing

during the rapid growth period of GDP. Electricity demand is expected to grow in Vietnam as GDP

growth can be expected in the future as well. Future forecast of electricity demand by MOIT is

shown in Figure 2-4.

References:JETRO Report

https://www.jetro.go.jp/ext_images/world/asia/vn/data/vn_overview201811.pdf

Page 71: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-2

Figure 2-2 Sectoral Share of GDP at Constant Prices (2017)

Figure 2-3 Trend of Structural Transformation of Sectoral Shares in GDP

References:VIET NAM ENERGY POLICY

MINISTYR OF INDUSTRY AND TRADE General Directorate of Energy

https://eneken.ieej.or.jp/data/6238.pdf#search='Vietnam+GWh

References:VIET NAM ENERGY POLICY

MINISTYR OF INDUSTRY AND TRADE General Directorate of Energy

https://eneken.ieej.or.jp/data/6238.pdf#search='Vietnam+GWh

Page 72: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-3

Figure 2-4 Power consumption forecast

2.1.2 Economic Development Policies

Vietnam maintains a high GDP growth rate of 6.01% in average over the past 10 years. Such

economic growth was derived from the policies of "doi moi", which were declared in 1986. The

policies of "doi moi” are based on the following four policies:

1. Introduction of capitalist economy

2. Cooperation with the international community

3. Investments into industries required for lives of the people

4. Mitigation of socialist policies

Based on the policies of “doi moi”, Vietnam extended the autonomy of companies, opened its

economy to the world and introduced a market economy. In 2000, the country revised its foreign

investment act to increase direct foreign investments into Vietnam in the fields of development and

infrastructure improvement in Vietnam, sponsored by investment institutions and foreign-owned

companies.

2.2 Power Overview

2.2.1 Power Overview

As for power business operations in Vietnam, the Ministry of Industry and Trade (MOIT) is

responsible for the power and energy field, the Ministry of Planning and Investment (MPI) is

responsible for the national development planning and investment field, and the Ministry of Natural

References:VIET NAM ENERGY POLICY

MINISTYR OF INDUSTRY AND TRADE General Directorate of Energy

https://eneken.ieej.or.jp/data/6238.pdf#search='Vietnam+GWh

Page 73: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-4

Resources and Environment (MONRE) is responsible for the environmental regulation field.

Regulations on the electricity market and electricity charges are controlled by the Electricity

Regulatory Authority of Vietnam (ERAV) immediately under MOIT.

In addition, the Institute of Energy (IE) immediately under MOIT formulates energy policies,

establishes power development plans and conducts power-related investigations and research.

According to an investigation on EVN, EVN used to dominate the electricity market in Vietnam as

the state-owned corporation, but the Ministry of Commerce and Industry officially decided to

liberalize the electricity wholesale market. Currently, power generation business operators,

including foreign-owned companies, are allowed to enter the market as Independent Power

Producers (IPPs). While non-power generation businesses are vertically integrated by EVN,

company split-up is taking place for liberalization. Figure 2-5 shows the power business structure

of Vietnam.

The EVN group companies include companies that are wholly owned and directly controlled by

EVN, self-financing companies, and JSCs (Joint Stock Companies) whose stocks are partially owned

by EVN.

Regarding the power generation businesses operated by the EVN group, its power plants were

divided into GENCO1, GENCO2, and GENCO3 due to the impact of the competitive power

generation market in June 2012. The directly-controlled companies, self-financing companies, and

JSCs are under these three companies. VINACOMIN (Vietnam National Coal Mineral Industries

Group) and PVN (Vietnam Oil and Gas Group) are operating power generation businesses as IPPs,

for example.

2.2.2 Power Policies

Vietnam’s power policies are described in the Power Development Plan (PDP). The PDP is a

medium-term power development plan and reviewed once every five years or so. The PDP is

prepared by MOIT as the main entity, in cooperation with IE, EVN, and other parties. Then, the

prepared PDP is filed with the government/prime minister, and finally issued upon approval. The

Figure 2-5 Power Business Structure of Vietnam

Page 74: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-5

PDP contains a power master plan and vision along with their planning periods. The currently-

issued PDP is PDP7, which is a revised version.

PDP7 was originally issued in July 2011, and then revised in December 2013 and March 2016. The

planning periods in the current PDP7 are as follows:

1. Planning periods:

Power master plan: 2011 to 2020

Vision: Until 2030

2.3 Regarding Electric Power Circular

2.3.1 Basic Structure of the Vietnamese Law

In Vietnam, the Constitution is a fundamental law and has the highest legal force. All legal norms

must be in compliance with this law. In addition to the constitution and laws that the National

Assembly of Vietnam has the right to establish, the main legal norms and the government

organizations that have the right to establish those norms are in the following order.

(i) Constitution

(ii) Law

(iii) Resolution (Resolution of a national assembly)

(iv) Ordinance (Ordinance of Standing Committee of the National Assembly)

(v) Decree (Agreement of Government)

(vi) Decision (Decision of Prime Minister)

(vii) Circular (Circular of Ministries)

Basic structure of the Vietnamese law is shown in Figure 2-6. Among these, what has a relation to

LNDC is Circular created by MOIT and the following eight Circulars exist.

(i) Circular 25/2016/TT-BCT

(ii) Circular 28/2016/TT-BCT

(iii) Circular 39/2015/TT-BCT

(iv) Circular 40/2014/TT-BCT

(v) Circular 44/2014/TT-BCT

(vi) Circular 55/2017/QD-DTDL

(vii) Circular 69/2018/QD-DTDL

(viii) Circular 03/2017/TT-BTTTT

Page 75: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-6

Figure 2-6 Basic structure of law

Page 76: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-7

2.3.2 Circular 25/2016/TT-BCT

Circular 25/2016/TT-BCT provides regulation of technical requirements and operation

management of SCADA system.

(1) Scope

The scope of the regulation of this circular (Circular 25/2016/TT-BCT) is shown below.

1. Requirements of operation of the electricity transmission system

2. Load forecasts

3. Transmission grid development plan

4. Technical requirements and procedures for connection to transmission grid

5. Assessment of electricity system security

6. Operation of electricity transmission system

(2) Subjects of application

Subjects of application of this circular (Circular 25/2016/TT-BCT) are shown below.

1. Transmission network operator;

2. Electricity system and market operator;

3. Electricity wholesalers;

4. Electricity distribution units;

5. Electricity retailers;

6. Generating units;

7. Electricity customers receiving electricity from transmission grid (hereinafter referred to as

“electricity customers”);

8. Vietnam Electricity;

9. Other organizations, individuals.

Note that Generating sets of a power plant with total installed capacity greater than 30 MW

connected to distribution grid must meet technical requirements of equipment connected to

transmission grid and other relevant requirements prescribed herein.

(3) Main contents

a. Requirements in operation of transmission power system

1. Frequency

2. Voltage

3. Voltage fluctuation

4. Reliability of transmission network

5. Power loss of transmission network

b. Load forecast

1. General provisions on forecasting electricity demand for the national electricity system

2. Monthly load forecast

Page 77: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-8

3. Weekly load forecast

4. Daily load forecast

c. Development plan of transmission system

1. General principle

2. Details of development plan of transmission system

d. Operation of power transmission system

1. Principle of power transmission system operation

- Operation mode of the power transmission system

- Operation of power transmission system

- Troubleshooting handling

- Security of the transmission system

2. Responsibility for the operation of power transmission system

– Responsible for transmission system and market management

– Responsibility of the power transmission unit

- Responsibility of the power distribution unit

3. Maintenance of the power transmission system

– General provisions on maintenance and repair of power transmission system

– Maintenance and repair plan of transmission system

4. Adjustment, communication and reporting of operations

– Communication in case of trouble

Page 78: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-9

2.3.3 Circular 28/2016/TT-BCT

Circular 28/2014/TT-BCT provides the regulations on troubleshooting process in the national

electricity system.

(1) Scope

This circular provides principles and procedures of handling incidents to restore the country's

power system to a normal operative system.

(2) Subjects of application

Subjects of application of this circular (Circular 28/2016/TT-BCT) are shown below.

1. The national electricity system moderation unit (the national electricity system regulation

center).

2. Generator unit.

3. Power transmission unit.

4. Power distribution unit.

5. Electricity distribution and retail unit.

6. Customers using electricity receive electricity directly from transmission grid, customers

use distribution grid with own station.

7. Operators of units.

8. Other related organizations and individuals.

(3) Main contents

a. Requirements and principles of handling national electric system incidents

1. Setting up the line of electric system

- Principles for making basic wiring diagrams in the electricity system

2. Protection and automatic

- Protection relay requirements when operating equipment

3. Requirements, principles and distribution of national electricity system treatment

- General requirements for troubleshooting national electricity system

- Principles of troubleshooting national electricity system

4. Handling wired incidents

b. Handling wired incidents

1. Handling of troubleshooting on 500kV lines

- Transmission limits on 500 kV lines

2. Handling of troubleshooting on lines over 35kV to 220kV

- Handling of overloaded overhead lines, supplying voltage over 35 kV to 220 kV

3. Handling of troubleshooting on 35kV or lower lines

– Handling of incidents on overhead lines supplying voltage at 35kV or less

4. Handling of troubleshooting power cables

Page 79: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-10

c. Handling of troubleshooting such as at power stations

1. Handling troubleshooting at a power station

2. Handling troubleshooting of transformers

- Restoration of transformers

1. Handling of troubleshooting of other devices

2. Full shutdown of the power station

- Response by staff

d. Handling of the warning, emergency and extreme emergency policy

1. Handling the warning mode

- Warning regime

2. Handling the emergency mode

- Emergency regime

3. Handling the extreme emergency mode

- Extreme emergency regime

e. Organization of implementation

1. Organization of implementation

2. Implementation effect

Page 80: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-11

2.3.4 Circular 39/2015/TT-BCT

Circular 39/2015/TT-BCT provides regulation of technical requirements and operation

management of SCADA system.

(1) Scope

The scope of the regulation of this circular (Circular 39/2015/TT-BCT) is shown below.

1. Requirements in operating power distribution systems.

2. Forecast of electricity load demand.

3. Plan for investment in distribution grid development.

4. Technical conditions and requirements and procedures for connection to distribution grids.

5. Operating distribution electricity system.

(2) Subjects of application

Subjects of application of this circular (Circular 39/2015/TT-BCT) are shown below.

1. Power distribution unit.

2. Electricity distribution and retail unit.

3. National electricity system regulation unit.

4. Power transmission unit.

5. Customers use distribution grid.

6. Vietnam Electricity Group.

7. Other relevant organizations and individuals.

(3) Main contents

a. Operational requirements of power distribution

1. Technical requirements

– Frequency

- Voltage

- Allowable current

2. Reliability of the power supply and power loss

b. Load forecast of power distribution systems

c. Plan for investment in power distribution systems

1. General provisions on planning for investment in power distribution systems

2. Details of plan for investment

3. Approval order of plan for investment

d. Connection to power distribution systems

1. Principles

– Information system requirements

Page 81: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-12

- Requirements for connecting SCADA system

- Technical requirements of control center

e. Operation of power distribution systems

1. Responsibilities for operation

– Responsibilities for power distribution systems

– Responsibilities for power distribution units

2. Operation plan

– Operation of power distribution systems

- Operation of power distribution systems in remote islands

3. Emergency operation

- Operation in a case where a major accident occurred in 110kV power distribution system

– Restoration of power distribution systems

4. Voltage control

– Load control

– Load reduction measures

– Performing voltage adjustment

- Monitoring and remote operation

- Contact during operation

- Notification when an incident occurs

5. Report on operation of power distribution systems

f. Operation requirements for distribution

1. Technical requirements

– Frequency

- Voltage

- Allowable current

2. Reliability of power supply and power loss

g. Load prediction of distribution system

h. Investment plan of distribution system

1. General provisions on investment planning of distribution system

2. Contents of investment plan

3. Approval process of investment plan

i. Connection to the distribution system

1. Principle

– Information system requirements

- Requirements for connecting SCADA systems

- Technical requirements of the control center

j. Operation of distribution system

1. Responsibility in operation

Page 82: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-13

– Responsibility of the power distribution unit

2. Operation plan

– Operation of distribution system

- Operation of distribution system of remote island

3. Operation of Emergency

- Operation when a serious accident occurs in 110 kV distribution system

– Restoration of distribution system

4. Voltage control

– Load control

– Load mitigation measures

– Voltage adjustment

- Monitoring and Remote Operation

- Contact in operation

- Notification when an incident occurs

5. Report on operation of distribution system

Page 83: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-14

2.3.5 Circular 40/2014/TT-BCT

Circular 40/2014/TT-BCT provides provisions on dispatching of the national power system.

National power system is a power system uniformly directed nationwide. Dispatching is an output

control of each power station by load dispatching or load-dispatching instruction.

(1) Scope

The scope of the regulation of this circular (Circular 40/2014/TT-BCT) is shown below.

1. Dispatching hierarchy of the national power system;

2. Responsibilities of organizations and individuals involved in dispatching and operation

activities of the national power system.

3. Planning and approval of operation mode of the national power system.

4. Dispatching and operation of the national power system in real-time.

5. Duties of divisions involved in dispatching of the national power system. Operation of the

power plant, power station, power network, and control center.

6. Training of titles directly involved in dispatching and operation of the national power

system

(2) Subjects of application

Subjects of application of this circular (Circular 40/2014/TT-BCT) are shown below.

1. Vietnam Electricity Group.

2. National power system dispatching unit.

3. Power generating unit.

4. Power transmitting unit.

5. Power distributing unit.

6. Power retailing and distributing unit.

7. Customers receiving power directly from the transmission power network, customers using

distribution power network with separate substation.

8. Operators of units.

9. Other relevant organizations and individuals.

(3) Main contents

a. Dispatching hierarchy and right of dispatching level

1. Hierarchy, control authority, and inspection authority of the national power system as well

as hierarchy of information grasping right

- Dispatching hierarchy of the national power system

- Principles of hierarchy of the control and inspection authority

2. CONTROL AUTHORITY, INSPECTION AUTHORITY AND INFORMATION GRASPING RIGHT

- Control authority

- Inspection authority of the superior dispatching level

3. Right of the national dispatching level

- Control authority of the national dispatching Level

Page 84: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-15

- Inspection authority of the national dispatching Level

4. Right of the Regional dispatching level

- Control authority of the regional dispatching level

- Inspection authority of the regional dispatching level

5. Right of the provincial dispatching level

- Control authority of the provincial dispatching level

- Inspection authority of the provincial dispatching level

6. Right of the district distribution dispatching level

- Control authority of the district distribution dispatching level

- Inspection authority of the district distribution dispatching level

7. Right of the unit managing and operating power plant, power station and control center

- Control authority of the power plant, power station and control center

b. Levels of and responsibilities for the national power system

1. Responsibility of the dispatching levels

- Responsibility of the national dispatching Level

- Responsibility of the regional dispatching level

- Responsibility of the provincial distribution dispatching level

- Responsibility of the district distribution dispatching level

2. Responsibility of the district distribution dispatching level

- Responsibility of the power generating units

- Responsibility of the power transmission units

- Responsibility of the power distributing units

- Responsibility of the power retailing and distributing units

- Responsibility of the telecommunications services providers

- Responsibility of the gas suppliers for power generation

c. Operation mode of the power system

1. Registration and approval of the operation mode of the power system

- Main contents of the operation mode of the power system

- Approval of the operation mode of the power system

2. Development of the operation mode of the power system

- Basic one-line diagram of the power system

- Forecasting of the power load demand

d. Dispatching and operation of the national power system in real time

1. General provisions

- Contents of the dispatching instructions

- Form of the dispatching instructions

- Requirements for compliance with dispatching instructions

- National dispatching Level

- Regional dispatching level

- Provincial distribution dispatching level

- District distribution dispatching level

- Working relationship in dispatching and operation of the power system

Page 85: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-16

- Report on daily operation and breakdown

2. Operation shift regulation

- Regulation on shift handover and acceptance

- Regulations for operator during shift duty

3. Frequency control

- Measures of frequency

- Limit of voltage

- Regulation on voltage adjustment

4. Power network control

- Automatic power network control

- Outage of lines and electrical equipment

5. Power source control

6. Load control

- Notification of the control of non-emergency usable capacity

- Dispatching instructions on control of the emergency usable capacity

- Breakdown load switching due to shortage of the power source as per dispatching

instruction

- Automatic load shedding under low frequency

- Load switching due to overloading or low voltage

7. Breakdown troubleshooting

- Breakdown troubleshooting of the power system

e. Duties of divisions directly involved in dispatching and operation activities of the national

power system

1. National dispatching level

- Divisions directly involved in dispatching activities of the national power system

- Duties, powers and responsibilities of the national dispatcher

2. Regional dispatching level

- Divisions directly involved in dispatching activities of the regional power system

- Regulations on employees of the regional dispatching division on duty

- Duties, powers and responsibilities of the regional dispatchers

3. Provincial distribution level

- Divisions directly involved in dispatching activities of the distribution power

system

- Responsibilities, powers and responsibilities of the provincial distributing

dispatchers

4. District distribution dispatching level

5. Operators at the power plants, power stations and control centers

f. Training of the titles directly involved in dispatching and operation of the national power

system

1. General provisions

- Training of the operator at dispatching levels

2. Training at national power system

- Regulation on new training for the national dispatchers

- Regulation on re-training for the national dispatcher

Page 86: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-17

- Regulation on training of the power system planning and analysis engineer for

the national power system

- Regulation on training for the SCADA/EMS engineer of the national power system

3. Training at the regional dispatching level

- Regulations on new training for the regional dispatcher

- Regulation on re-training for the regional dispatcher

- Regulation on training for the power system planning and analysis engineer of

the regional power system

- Regulation on training for the SCADA/EMS engineer of the regional power system

4. Training at provincial distribution dispatching level

- Regulation on re-training for the provincial distributing dispatcher

- Regulation on training for the engineer of the distribution power system

- Regulation on training for the SCADA/DMS engineer of the distribution power system

5. Training at district distribution dispatching level

- Regulation on new training of the district distributing dispatcher

- Regulation on re-training for the district distributing dispatcher

6. Training at the power plant, power station and control center

g. Implementation organization

1. Implementation organization

2. Effect

Page 87: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-18

2.3.6 Circular 44/2014/TT-BCT

Circular 44/2014/TT-BCT provides the regulations of working process in the National electric

system.

(1) Scope

The regulation of this circular (Circular 40/2014/TT-BCT) describes the order in which work is

conducted.

(2) Subjects of application

Subjects of application of this circular (Circular 44/2014/TT-BCT) are shown below.

1. National electricity system regulation unit.

2. Generator unit.

3. Power transmission unit.

4. Power distribution unit.

5. Electricity distribution and retail unit.

6. Customers using electricity receive electricity directly from the transmission grid, customers

use the distribution grid with their own station.

7. Operators of the units.

8. Other related organizations and individuals.

(3) Main contents

a. Order to work

1. Action organization

- General requirements on manipulating electrical equipment in the national

electricity system

- Verbal manipulation order (order by phone)

- Operation procedure table

- Creation and approval of stop plan

- Creation and approval of unexpected operation procedure

- Operation records

2. Execute action

- Requirements for the manipulation commanders

- Performing operations involving secondary circuits

- Manipulation during high demand for the electricity and shift delivery

- Manipulate in bad weather conditions

- Suspend operation

3. Action

- General provisions of remote operation

- Conditions of remote operation

b. Regulation of basic activities

Page 88: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-19

1. Action device close cut

– Disconnection operation

2. Workshop transformer

- Power cut operation of the transformers

- Operation of the transformers

3. Line working

- Operation of the power cut off lines

4. Bars action

– Operation of the busbar

5. Working other electrical devices

c. Number of devices in the national electric system

1. General principles

- Rules on naming and numbering of devices

Page 89: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-20

2.3.7 Circular 55/2017/QD-DTDL

Circular 55/2017/QD-DTDL provides technical requirements and operation management of SCADA

system.

(1) Scope

The regulation of this circular (Circular 55/2017/QD-DTDL) covers technical requirements, signal

connection, and operation management of SCADA system in electrical system.

(2) Subjects of application

Subjects of application of this circular (Circular 55/2017/QD-DTDL) are shown below.

1. The electricity system and market operating unit (National Electricity Moderation Center).

2. Power transmission unit.

3. Power distribution unit.

4. Electricity distribution and retail unit.

5. Power generation unit.

6. The channel operator.

7. Customers use electricity to receive electricity directly from the transmission grid.

8. Customers use distribution grid with separate transformer station.

9. Vietnam Electricity Corporation.

10. Other relevant organizations and individuals. Other related organizations and individuals.

(3) Main contents

a. General technical requirements of the SCADA/EMS/DMS system

1. Technical requirements of the SCADA system

- General requirements for manipulating electrical equipment in the national electricity

system.

- Technical requirements of the SCADA system

- Basic components of the SCADA system in electrical system

- Configuration and function of the central SCADA system

- Requirements for connection, data sharing and network security

2. Technical request of the SCADA/EMS system

- System structure of the SCADA/EMS

- Application of the EMS system

3. Technical requirements of the SCADA/DMS system

- Configuration of the SCADA / DMS system

- Application of the DMS system

4. Request engineering communication channel system

- General requirement

- Speed of the data transmission channel

- Interface for connecting channels

- Communication protocol

Page 90: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-21

5. Technical requirements for the RTU terminals/Gateway

- General technical requirements

- Technical requirements for the RTU equipment

- Technical requirements for the Gateway equipment

- Technical requirements for the converters A

b. SCADA system connection in electric system

1. Register to the SCADA system connection for electric factory and transformers

- Registration of the connection

- Technical design agreement

- Registration of the End-to-End inspection

- Examination and acceptance of the End-to-End

2. Register SCADA connections for the power plant and improved pressure palaces

- Registration for the renovation or expansion of the RTU / Gateway terminals

- Technical design agreement for cases of renovation or expansion of the RTU/Gateway

terminals

- End-to-End inspection registration for cases of renovation or expansion of

the RTU/Gateway terminals

- Checking End-to-End for cases of improving or extending the RTU/Gateway terminals

3. Content test point-to-point and end-to-end testing

- Contents of checking and acceptance of Point-to-Point from the RTU to the electrical

equipment

- Contents of acceptance testing of Point-to-Point from the SAS/DCS system to the

Gateway computers

- Contents of checking and acceptance of the transmission channels

- Contents of checking and acceptance of the End-to-End

c. MANAGEMENT OF OPERATION OF THE SCADA/EMS/DMS

1. Responsibilities of participants and operation system of the SCADA/EMS/DMS

- The responsibility of the Regime has control

- Responsibilities of the operation management units

- Responsibilities of the channel operator

2. SCADA DATA LIST

- Requesting the SCADA data list of the power plant

- Requesting the SCADA data list of the substation

- Request for the SCADA data list of the Control Center

3. Handling of incidents in the SCADA system operation

- General principles

- Troubleshooting central SCADA system

- Troubleshooting RTU / Gateway terminals and transmission channels

d. Appendix

1. Chart for connecting and registering a new power station and transformer.

2. Table of the SCADA data list

3. Testing into channel

Page 91: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-22

4. Test of the point-to-point

5. Collection test of the end-to-end

Page 92: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-23

2.3.8 Circular 69/2018/QD-DTDL

Circular 69/2018/QD-DTDL provides procedures for issuance of certificates of regulations on and

operations of the national power system and inspection thereof by the electricity regulatory

authority.

(1) Scope

The regulation of this circular (Circular 69/2018/QD-DTDL) covers training, inspection, and issuance

of certificates for operators at all levels at power stations, transformer stations, and control centers

and includes the following.

1. Conditions for people appointed to training positions to directly participate in the work of

moderation and operation.

2. Content of training for the titles to directly participate in moderation, operation at all levels

and operating management units.

3. Procedures for inspection and certification of operation certificates.

4. Managing and using Operation Certificates.

(2) Subjects of application

Subjects of application of this circular (Circular 69/2018/QD-DTDL) are shown below.

1. Vietnam Electricity Corporation.

2. National electricity system regulation unit.

3. Generator unit.

4. Power transmission unit.

5. Power distribution unit.

6. Electricity distribution and retail unit.

7. Customers using electricity receive electricity directly from the transmission grid, customers

use the distribution grid with their own power station.

8. Operating staff. The channel operator.

9. Electric project investor.

(3) Main contents

a. Training conditions and contents/Direct participles/National electricity control and operation

1. Training participatory lists/Direct conditions at the national level

- Conditions for participating in trainings at the national level.

- Outline of training types

- Content of training for engineers of the national electricity system.

- Content of training for SCADA/EMS engineers of the national electricity system.

- Training programs at the national level.

2. Training list

- Conditions for participating in trainings at the domain level.

- Content of training for engineers of the regional power system.

- Training programs at the domain level.

Page 93: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-24

3. Training distribution district

- Conditions for participating in trainings at the district power distribution level.

- Content of training concerning the district power distribution companies.

- Content of training for engineers of the district power distribution system.

- Content of training concerning SCADA/DMS of the district power distribution system.

- Training programs at the district power distribution level.

b. Inspection and grant of the operation certification

1. Responsibilities of the units

- Responsibilities during test period

2. To get a certificate of operation

- Items of certificate

- Conditions of inspection

3. Content, form and assessment of the test results

- Content of test

- Form of test

- Assessment of test results

4. Organization of inspection and granting of the operation certification

- Organization of inspection

- Announcement of results and issuance of the operation certificates

c. Management, classification and use of the operation certification

1. Types of operation certificates

- Operation certificate form

- Grant of certificate

2. Management and use of operation certificate

- Usage term of operation certificate

- New level of operation certificate

- Re-issuance of operation certificates

- Management and use of operation certificates

d. Appendix

1. Form of operation certification

Page 94: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

2-25

2.3.9 Circular 03/2017/TT-BTTTT

Circular 03/2017/TT-BTTTT provides regulation of technical requirements and operation

management of SCADA system.

(1) Scope

This Circular regulates the security of information system by classification, including: guide the

classification of information system by class; request the security of information system by

classification; inspect and evaluate the security of information; keep and verify the proposal for the

classification; report and share information.

(2) Regulated entities

The entities regulated by this Circular are specified in Article 2 of the Government’s Decree No.

85/2016/ND-CP dated July 01, 2016 on the security of information system by classification

(hereinafter referred to as Decree No. 85/2016/ND-CP)

(3) Main contents

a. Guideline for the determination and classification of information system

- Determination of specific information system

b. Requirements for security of information systems by classification

- General requirements

c. Inspection and assessment of information security

- Contents and forms of inspection and assessment

d. Receipt and verification of the classification proposal

- Submission and receipt of the classification proposal

Page 95: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-1

3 Current Situation and Prospects for Power Supply

3.1 Power Supply Structure

EVN’s organization is structured as shown in Figure 3-1.

Figure 3-1 Organization Chart

References : EVN annual report 2017

Page 96: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-2

3.2 Overview of EVN SMART GRID PLAN

1. Objectives

Objectives of Smart grid development

- Enhancing the stability and reliability of power system

- Increasing the productivities

- Reduction of the technical and commercial loss

- Reduction of the peak load

- Reduction of electric system reliability indices (10-20% per year)

- Better information for management

- Improvement of customer satisfaction

2. Dispatching section

1. New SCADA/EMS project

- Scope of project: modernizing National Load dispatching centre and 3 Regional load

dispatching centers and 1 backup center in order to implement EMS at 2016

- Bidder: OSI – USA

- The project implementation period: 12/2012 – 3/2015

- Status: ongoing

2. Fault recorder and PMU project (2 phases)

- Scope: Purchasing and installing Fault recording equipment at 73 substations

(500/220kV substations and power stations)

- The project implementation period: 2014 – 2015

- Status: Project initiation document has been submitted

3. International Consulting Services

- Scope: Evaluation, analysis and propose solution for enhancing the stability and

reliability of Vietnamese power system

- The project implementation period: 2014 – 2015

- Status: Project initiation document has been submitted

3. Transmission section

1. Upgrading substation control system projects

- Scope of projects: Replace the traditional substation control panels by Computerized

control system at the 500/220kV substations

- The project implementation period: 2014 – 2016

- Status: PDO submitted to WB (TEP – Transmission Efficiency Project)

2. Remote control center projects

- Scope: Set up remote control systems at substations and from there can control

remotely about 5 – 10 substations around (without operators)

- The project implementation period: 2014 – 2016

- Status: TEP

- Scope of projects: Replace the traditional substation control panels by Computerized

control system at the 500/220kV substations

Page 97: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-3

4. Distribution section

1. SCADA/DMS and 110kV substations without operators in EVNSPC

- Scope of projects: Scope of projects: Replace the traditional substation control panels

by Computerized control system at the 500/220kV substations

- The project implementation period: 2012 – 2015

- Status: Bid document submitted to WB (DEP – Distribution Efficiency Project)

2. Upgrading SCADA/DMS in EVNHCMC

- Scope: Upgrade the existing SCADA/DMS system in Ho Chi Minh City

- The project implementation period: 2014 – 2015

3. Status: Project initiation – DEP Upgrading SCADA/DMS in EVNHCMC

- MiniSCADA/DMS in Gia Lai and Quang Nam province (EVNCPC)

- The project implementation period: 2014 – 2015

- Status: PDO submitted to Finland ODA

4. DAS Pilot project in Ho Chi Minh City

- Scope of projects: Installing DAS for 2-4 MV lines (including many MV/LV substations,

Recloses)

- The project implementation period: 2013 – 2015

- Status: Japanese sponsor - TEPCO

5. AMI Pilot project in Ho Chi Minh City

- Scope: AMI system with 48.000 smart meters in Ho Chi Minh City

- The project implementation period: 2014 – 2015

- Consultant: AF Mercados – Spain

- Status: Project initiation – DEP

6. AMR projects

- Scope: Power companies invest many AMR projects (many phases) in order to install

millions of electronic meters (PLC, GPRS, RF…)

- The project implementation period: 2011 – 2017

- Status: ongoing

5. Renewable energy integration

- Scope of projects: installing a solar and wind generation (4,500 W) in a smart building

connected to LV network in Da Nang (EVNCPC – Central Power Corporation)

- The project implementation period: 2013 – 2014

- Status: Project initiation submitted

6. Challenges

- Lack of experiences

- Choosing “Right” Smart Grid solutions

- Integrating multi vendors’ products into unique system

- Integration AMR and AMI

- New jobs and retraining reduced employees

- Enterprise change: Organization restructure, Rules, Business procedures…

- Project Budgeting: Estimated cost for Smart Grid is about 2 bil. USD (exclude AMI

investment: 4 bil. USD)

Page 98: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-4

3.3 Facility Enhancement Plan

3.3.1 Plan of Total Installs Generation Capacity

Figure 3-2 and Table 3-1 show target increases in EVN’s power generation capacity by power plant

type toward 2030, based on PDP7.

Figure 3-2 Graph of Total installs capacity to 2030

Table 3-1 Table of Total installs capacity to 2030

References:Ministry of Industry and Trade General Directorate of Energy

Viet Nam’s Power Development Plan

References:Ministry of Industry and Trade General Directorate of Energy

Viet Nam’s Power Development Plan

Page 99: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

3-5

3.3.2 Plan of Transmission and Transformer

Figure 3-3 shows EVN’s enhancement plan for the length of transmission lines and capacity of

transformers 500/220kV toward 2030.

Figure 3-3 Transmission Network Investment Plan

References:Ministry of Industry and Trade General Directorate of Energy

Viet Nam’s Power Development Plan

Page 100: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-1

4 Current situations of Power Control Operation and Control Facilities

4.1 Operation

4.1.1 Monitoring Control Organization

EVN NLDC is a subsidiary of Vietnam Electricity and has eight divisions with Board of Directors as

well as the Division Center located in the northern, southern, and central areas in Vietnam as shown

in Figure 4-1 and Figure 4-2.

Figure 4-1 Company Structure of NLDC(Reference:EVN NLDC Webpage)

Figure 4-2 Load Dispatching Organization Structure (Reference:EVN NLDC Webpage)

Page 101: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-2

Also, EVN NLDC has an organization called Load Dispatching Center (LDC) responsible for control

of power generation and monitoring control of power system, which is decentralized and operated

into four groups as separate organizations from the business organization structure of EVN NLDC.

National Load Dispatching Center (NLDC) has control over the bulk system (500kW) throughout

Vietnam. Regional Load Dispatching Center (RLDC) is divided and placed into three areas: northern

area, southern area, and central area in Vietnam.

Responsibilities of each hierarchy are shown in Table 4-1.

Table 4-1 the Roles of Each Load Dispatching Center

Division Responsibility

National Load

Dispatching

Center

1. Control of frequency of national power system

2. Control of voltage on 500 kV

3. Control of capacity of generating units of large power plant

4. Switching and handling of breakdowns of 500 kV

5. Black start and restoration of 500 kV

6. Control of load of national power system

7. manage of breakdown of large power plant

8. reservoir of hydroelectric sources

9. Sets up the basic operation mode

10. Performs calculation and inspection upon requirement for operation

(operation modes, setting form of automatic and protective relay on

500kV, parameters (short circuit power, short circuit currents), stability,

load shedding)

11. Analysis and identification of cause of breakdowns on 500 kV

12. Management of operation of SCADA/EMS system

13. Aggregation of actual operation and report

North

Regional Load

Dispatching

Center

1. Complies with the direction of the national dispatching Level

2. Control of voltage

3. Control of frequency in case of separation

4. Control of capacity of generating units

5. -Switching and handling of breakdowns

South

Regional Load

Dispatching

Center

Page 102: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-3

Central

Regional Load

Dispatching

Center

6. Black start and restoration

7. Coordination with the relevant regional dispatching level upon switching

and handling of breakdown of inter-region transmission lines

8. Notification regarding affecting the normal operation mode

9. Control of load

10. Registers the estimated operation mode with the national dispatching

Level

11. calculation and inspection as per the operational requirement (operation

modes, setting form of protective relay (220 kV, 110 kV), parameters

(short circuit power, short circuit currents), automatic relays on

distribution power network, protective and automatic relays of equipment

on distribution power network)

12. evaluating the effect of connection of new power works

13. -setting and operation of automatic load shedding system under the

frequency and voltage

14. analysis and identification of cause of breakdowns

15. Manages the operation of SCADA/EMS system

16. Makes the prescribed aggregation of regional power system and report

Page 103: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-4

Provincial

Load

Dispatching

Center

1. Complies with the direction of regional dispatching level

2. Control of voltage

3. Control of frequency in case of separation

4. Control of capacity of generating units

5. Switching and handling of breakdowns

6. Restoration of distribution power system

7. Control of load

8. Coordination with relevant provincial distribution dispatching level upon

switching of lines

9. Notification regarding affecting the normal operation mode

10. Notification of cause of breakdown to customers

11. Registers the estimated operation mode with the regional dispatching

level

12. calculation and inspection as per the operational requirement (operation

modes, setting form of protective and automatic relay, calculation,

inspection and approval for setting values for protective equipment of

relay)

13. power loss and recommendation of measures to reduce the power loss

14. setting and operation of automatic load shedding system under the

frequency

15. Analysis and identification of cause of breakdowns

16. Management of operation of SCADA/DMS system, automation system

17. Aggregation, report and provision of data as required by the regional

dispatching level

4.1.2 Responsibility Border of Power System

EVN NLDC shares roles of system operation by voltage level and region.

NLDC (one place) has a responsibility for 500kV system throughout Vietnam and RLDCs (three

places) have responsibilities for each region of 220K to 110kV.

Figure 4-3 shows the division of roles by voltage class and Figure 4-4 shows an overview of the

areas divided by Load Dispatching Center.

Page 104: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-5

Figure 4-3 Assigned roles by voltage class

Figure 4-4 Assigned area of each Load Dispatch Center

Page 105: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-6

4.1.3 Operation

(1) Monitoring Work

Basically, Load Dispatching Centers acquire information of the substation controlled by them and

remotely monitor the state of the facilities through SCADA.

All information of the substations which NLDC and RLDC from A0 to A3 use are linked with each

other by SCADA system, so each of NLDC and RLDC can acquire information of circuit breakers

and switchgears as necessary.

(2) Operation work

Operations can be performed on facilities in the control area divided by voltage class and area

according to each plan and judgment, but since the power systems are electrically connected to

each other, a rule prescribed based on the dispatching hierarchy is applied to planning, creation

of operation procedures, instruction of operations, execution of operations, and use of record

reports.

As a method for performing operations, the procedures are prescribed in Circular strictly. Details

are as follows.

a. Order by phone

a) The commander must clearly state their full name

b) The commander must specify the name and title of the order recipient.

c) Operation orders must be recorded and fully recorded in the operation diary at the units.

d) Operation instructions must be short, clear, accurate and specify the purpose of the

operation.

e) The operator must understand the sequence of all expected operation steps, the

conditions that allow it to follow the actual diagram status and the device operation mode.

f) In case of forecasting, when it is impossible to communicate with mobile operators,

allowing to order and manipulate multiple operational tasks at the same time. Mobile work.

g) When ordering, the commander must ask the receiver to compare and adjust the time

according to the clock of the commander.

h) The order commander must repeat the command, record the operation command, and

the commander's name and the time of the operation request.

i) Only when the commander determines that it is absolutely correct and allows the

operation to be performed, the receiver will then be able to perform the operation.

j) The finishing operation must record the end time and report back to the commander.

b. Remote operation

There are no provisions related to specific operation rules for performing remote operations.

Securing of the soundness of SCADA, communication line, and remote terminal unit which

enables remote operations is prescribed.

c. Creation of operation procedure

The operation procedures have a prescribed format and contain the following subjects. They are

applied through examination and approval processes when operation is implemented.

Page 106: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-7

A) Name of operation card

B) Writer, Examiner, Approver

C) Operator(commander)

D) Purpose of the operation

E) Intended time

F) Conditions required for proceeding

G) Operation item sequence

H) Signature

Page 107: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-8

(3) Recording work

A) Record and report of daily operation result (Report on daily operation)

Reporting of the operation result is performed every day. The report line is in Figure 4-5.

Figure 4-5 Report line (Original)

Report data collected from the whole country is collected at NLDC. A person in charge of the

report in NLDC collects the data by making use of Excel macro with the dedicated personal

computer.

Regular report to general executives at EVN headquarters

- NLDC reports on power generation and a demand forecast to the business meeting

attended by the general executives at EVN headquarters and the top managers of the

subsidiaries which is held every week.

(4) Data maintenance in SCADA

For data maintenance in SCADA, NLDC retains engineers as SCADA Development Team and

performs data change works and tests whenever data maintenance works are required due to such

as construction of a new substation or transmission line.

Page 108: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-9

4.2 Facility

4.2.1 SCADA/EMS

The current SCADA/EMS is called the fourth generation SCADA and adopts the SCADA/EMS made

by the OSI in the United States. NLDC and RLDCs in three areas are introduced at the same time.

(1) Function configuration

Table 4-2 shows the main functions of SCADA.

Table 4-2 Main functions of SCADA(Original)

FUNCTION NAME DESCRIPTION

SCADA Server The real-time applications

Security Server Virus check and extermination for Virus

Historian Server Retrieves real-time data from the front end processor

Development Server Engineering for SCADA data

Front End Processor Scanning, Monitoring & Receiving of field data from RTU

Training Server Training simulation function

Planning Server Generation planning

Data Acquisition Server Acquiring and referring from RTU data

Terminal Server Protocol Converting

(2) Hardware configuration

Servers are arranged in the function unit and each server has dual configuration. Also, the LAN

configuration is grouped by function and consists of System LAN, RTU LAN,

Management/Engineering LAN, SCADA system LAN, Maintenance LAN, and Training LAN. It is also

assumed that all physical units such as Ethernet switch, a firewall, and a network interface of each

server has the dual configuration. It is assumed that a hot standby configuration and a cold

standby configuration are used for the operating state of the dual-redundant servers, Ethernet

switches, and firewalls according to the importance (required reliability).

As for data exchange between servers belonging to different LAN classification, the servers are

connected in a star form by a Layer 3 switch which is installed in the center of the LAN

configuration. Connection among LAN segments are achieved by routing configuration. Thus, the

network is logically divided. Therefore, servers cannot connect to the functionally irrelevant LAN.

When the communication specification adopts a serial protocol, information transmission between

the remote terminal unit installed in the substations/power stations and SCADA is achieved by

establishing a connection via the terminal server in SCADA and converting the serial protocol to

the Internet protocol or inversely converting the Internet protocol to the serial protocol.

When the remote terminal units in the substations/power stations support the Internet protocol,

they are connected directly with SCADA RTU LAN by the Layer 3 switch nearest to SCADA through

Ethernet network called RTU WAN. Information from the the remote terminal units is language-

or format-converted by a server called Front End Processor as data available inside SCADA.

The office side has the Office LAN connected with SCADA and the Management HMI with which

the management and the engineers of NLDC can check the operation state of the power system

and the state of SCADA in real-time.

Page 109: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

4-10

A physically block able unit that can shut down the Ethernet line is installed on the route from the

Management/Engineering LAN, Maintenance LAN, and Training LAN to the Layer 3 switch installed

at the center place. Therefore, the state of a degeneration function operation can be set to protect

SCADA by limiting to the monitoring control function when an incident caused by a cyber-attack

and the like occurs.

(3) Backup SCADA

Each of NLDC and RDLCs in three areas has a backup SCADA in place. The basic specification is

the same except that the simulator function is not implemented.

4.2.2 Communication Network

EVN NLDC connects NLDC, RDLCs and substations/power stations by using a wide area

communication network owned by EVN. The outline is shown in Figure 4-6.

A0

A3

A1

A2RTU

RTU

RTU

A0=National Load Dispatching Center,

A1=North Regional Load Dispatching Center,

A2=South Regional Dispatching Center,

A3=Central Regional Load Dispatching Center

Figure 4-6 Image of connection between RTU and each Load Dispatching center

Page 110: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

5-9

5 Issues of Power Control Operation and Control Facilities Considering Future Facility

Reinforcement

5.1 Operation

5.1.1 Monitoring Control Organization

If the substation increases in future, the Monitoring Control Organization is expected to reach its

limit. The reasons are explained below.

(1) Role sharing

As facilities increase, workload for adjusting the supply/demand (adjusting amount of power

generation) and operating the transmission system in NLDC is expected to increase. The details

are described in later, but operations of system control increase proportionally to the facility

reinforcement. Also, because the generator is planned to be added more, complexity of the supply

and demand adjustment is expected to increase. Therefore, it is assumed that the roles of NLDC

become excessive.

(2) Workload

During day-to-day equipment operation in the substation, operation orders by a telephone are

conducted as described in "4.1.3(2)a" and time to confirm the caller's name, title, and order details

and to mutually repeat them to prevent inconsistency in the operation is required. The operation

order takes much time. When operation amount increases with the expansion of the power system

in future, operations ordered by a telephone become a bottleneck, and there is a possibility that

the required operation amount cannot be handled.

Dispatchers become unable to concentrate by tight situation of operation works, and human

errors are expected to increase due to deterioration of accuracy of the operation order or omission

of the required confirmation work. It may cause a false outage or a fatal accident. As a result, it is

expected to cause deterioration of the electric power quality in the whole Vietnam.

5.1.2 Operation

(1) Operation work

As shown in Power Development Plan 7, there is a plan to further expand the transmission system

in future in Vietnam. Consequently, it is expected that the amount of facilities will increase, and

periodic inspection, facility repair, new facility construction works will rapidly increase.

In that case, it is expected that troubles such as not being able to stop a facility may occur due to

limitations of operation works. There is a concern that inspection time cannot be secured because

the operational error occurs by operational congestion of NLDC operators and the operation is

delayed and securing work safety may be neglected. This is a concern to be linked directly with

deterioration of the electric power quality.

Page 111: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

5-10

(2) Estimate of issues in EVN by comparison with TEPCO Power Grid

a. Estimate of operation amount in EVN based on system operation record in TEPCO PG

Table 5-1 compares the facility scale between EVN and TEPCO Power Grid. The facility scale of

EVN has already exceeded that of TEPCO Power Grid on data as of 2018. It is supposed that this

is due to the difference of geographical conditions and that the transmission line to supply power

to broader area becomes longer and the number of 220kV substations for regional grid systems

increases. EVN is assumed to perform the monitoring control of large-scale transmission systems

equivalent to or larger than TEPCO PG. As such, EVN plans to continue to expand the power

system.

Table 5-1 Basic Quantity Comparison

Basic Quantity EVN (July,2018) TEPCO PG (2017)

500kV Transmission Line 7503km 4520km

220kV (275kV Transmission Line 16920km 2339km

500kV Substation 28 SS 28 SS

220kV(275kV) Substation 114 SS 51 SS

Dispatching Area 331,200 ㎢ 32,420 ㎢

The number of the system operations also increases with expanding the power system. Figure

5-1 estimates the planned outages based on total capacity data of transformers of 220kV or more

in EVN which are installed/planned in Power Development Plan 7. According to Power

Development Plan 7, it is expected that the capacity of the transformer will increase 3.3 times by

2030 compared to that in 2015. The transmission system in Vietnam in the stage of growth is in

a phase where new facilities are installed for the present. In the future, when entering in a phase

where the facilities are maintained, it is expected that inspection, repair, and update works of the

facilities will increase, and operations of the system control will rapidly increase. According to the

simulation result, it is expected that planned outage operations in 2025 will occur 3.3 times

compared to that in 2015 and the number of operations in the system control will rapidly increase.

The actual number is expected to exceed this number because this index does not include

inspections/repairs of transmission lines, control devices, and switchgears.

Page 112: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

5-11

* Calculation of outage index: indexing the number of planned outages occurred, assuming that a life cycle of the transformer

is 40 years, and a stop operation occurred during operation period is one for new construction, two for inspection, one for

repair, and one for update.

Figure 5-1 Estimation of Planned Outages

(3) Recording work

In NLDC, power supply performance is reported to the EVN management weekly based on report

from RLDC and NLDC operator. In the result of a hearing, there is a comment saying that there is

a feeling of work burden. If the work of manual record reporting is continued, the amount of

information to be recorded will increase due to the expansion of the power system. Then, unless

the staff is increased or the operations are reviewed, it is concerned that the amount may exceed

the range that operators in RLDC and NLDC can handle.

5.2 Facility

5.2.1 SCADA/EMS

(1) Hardware configuration

With respect to an inside configuration of SCADA, signals to be processed in real time, such as a

signal for transmitting ON/OFF information of switchgears or the measured values collected from

substations to operators and a signal for transmitting a control signal to local facilities, flow in the

LAN.

In addition, signals that do not require real-time processing as much as those signals described

above, such as a signal for creating, saving, and calling an operation procedure, a signal for saving

record in an archive, and a signal for processing a system calculation, also flow in the LAN. In the

current architecture, all signal is exchanged via SCADA LAN. In the future, as the number of

substations increases, the amount of information to be handled in NLDC will also increase. As such,

the traffic in SCADA LAN also increases and a processing speed may become slow. Therefore, by

0.30

1.00

1.93

3.30

5.15

6.67

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

0

100000

200000

300000

400000

500000

600000

2010 2015 2020 2025 2030 2035

Estimation of Planned Outages

Total Capacity Deploy Outage Index

Page 113: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

5-12

separating the important signals requiring real-time processing from the other signals, it is

necessary to create a mechanism for preventing the delay of such important signals.

(2) Application

According to the estimation of the future workload in the system control in NLDC using TEPCO

PG as an index, in NLDC, their operation works are assumed to become excessive and the required

planned outage cannot be handled. Therefore, measures to automate the operators' works are

required.

Page 114: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

6-1

6 Investigation for Improving Work Schemes

6.1 Operation

6.1.1 Monitoring Control System

(1) Review of Organization

It is optimum to divide NLDC's responsibilities because the future reinforcement of the power

generation and transmission facilities causes increase of the workload in NLDC.

NLDC currently deals with both supply-demand control operation and system control operation.

By separating the system control operation from NLDC, they will be able to focus on the supply-

demand control operation only. Therefore, dividing responsibilities for the system control has an

advantage to achieve a high value-added operation.

Figure 6-1 Advantage of NLDC Reorganization

The role sharing between BSLDC, which is to be newly established, and NLDC is shown in Table 6-1.

They are organized based on the existing role of NLDC.

Page 115: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

6-2

Table 6-1 Role sharing between BSLDC and NLDC

National Load Dispatching Center Bulk System Load Dispatching Center

1. Control of frequency of national power

system

2. Control of capacity of generating units of

large power plant

3. Black start and restoration of 500 kV

4. manage of breakdown of large power

plant

5. reservoir of hydroelectric sources

6. Management of operation of EMS

function

7. Aggregation of actual operation and

report

1. Control of voltage on 500 kV

2. Switching and handling of breakdowns of 500

kV

3. Control of load of national power system

4. Sets up the basic operation mode

5. Performs calculation and inspection upon

requirement for operation (operation modes,

setting form of automatic and protective relay

on 500kV, parameters (short circuit power,

short circuit currents), stability, load shedding)

6. Analysis and identification of cause of

breakdowns on 500 kV

7. Management of operation of SCADA function

8. Aggregation of actual operation and report

6.1.2 Operation

In this section, for solving the operator shortage, possibilities for automating works in operations

by SCADA are considered.

(1) Creation of operation procedure

It is expected that operators' works increase due to progress of future facility reinforcement and

occurrence of periodic inspections and repair works. Since the planned facility outage is a typical

procedure, it is expected to be created automatically in some degree.

Therefore, operators' works can be reduced by automating such a typical procedure using

SCADA/EMS.

Page 116: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-1

7 Benefits from Improvements in the Project

7.1 Expected Benefits for the Partner Country

7.1.1 Reducing in Transmission Loss

(1) transmission loss

Transmission loss refers to loss that occurs mainly when power is transmitted from a power plant

to a demand site. Current flows through a small electric resistance in the conductor of the

transmission line, resulting in thermal energy which is released to the atmosphere and consumed.

The Basic equation is shown in Figure 7-1.

Figure 7-1 The Basic equation

In general, hydropower stations and thermal power plants in bay area are located geographically

far from the places where electricity is consumed. To reduce this transmission loss as much as

possible, the electric power system is formed so that it can be delivered to a point of consumption

with a higher voltage (passing current is reduced).

(2) Increase in transmission loss due to transmission line stoppage

This is for backing up so that power outage does not occur in the demand area when stopping one

transmission line due to inspection. Also, t is for a backup to make it possible to continue

transmission on the remaining lines when equipment has a malfunction.

The basic formula of transmission loss when transmitting two lines at the normal time in parallel is

shown in Figure 7-2.

Page 117: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-2

Figure 7-2 The basic equation of transmission loss (transmitting two lines at the normal time in parallel)

Transmission lines may be stopped for several days, once every several years, for the maintenance

and management of equipment. During this stoppage period, in the case where power is normally

transmitted through two lines, power transmission is performed by one line. The transmission loss

at this time is basically calculated by the formula of Figure 7-3. In that case the transmission loss

will be increased four times compared to normal transmission.

Figure 7-3 Basically calculated by the equation(1 lines is outage)

Page 118: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-3

(3) Reduction of transmission loss by automating NLDC operation

For this reason, it is desirable that the transmission line shutdown period is as short as possible. The

procedure for stopping the transmission line is shown in Figure 7-4.

Figure 7-4 The procedure for outage the transmission

If the time of Outage Operation and Restoration Operation is shortened, there is a possibility that

total stoppage time can be shortened. The following are assumed solutions that shorten downtime.

1. Shorten the time required for operation itself.

2. Move the transmission date forward by shortening the operation time.

Solution 1 is to automate the operation (operation execution, related party contact, equipment

state confirmation, etc.) by the SCADA application and shorten the operation time.

Solution 2 is to shorten the stop period by advancing the power transmission operation by

improving the number of operations and the time period per day as a result of performing solution

1.

This solution 1 and 2 is to implement the application for automation in SCADA, and they can be

realized by the solutions described in 6.1.2.

(4) Estimation of transmission loss reduction

Figure 7-5 is an example of a general 500 kV transmission line specification. This is the assumption

of a 500 kV transmission line in Vietnam.

Page 119: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-4

Figure 7-5 Example of a general 500 kV transmission line specification

The transmission loss in each case of the two-line operation and the one-line operation (one line)

in the form of the above-mentioned power transmission line is as follows.

1 line operation = 51 MW

2 line operation = 13 MW

The transmission loss reduction amount when the transmission line stoppage time is shortened by

1 day (24 hours) by the automation of the above-mentioned operation is as follows.

(51[MW]-13[MW]) × 24[h] = 912[MWh]

7.1.2 Reduction of Limitation for High-efficiency Thermal Power Plant

When a power transmission line connected to a high-efficiency thermal power plant is planned

outage, power plant may be output limitation. At that time, Other power plants are raised output

as a response to that limitation.

If the raised power plant is an inefficient fuel, there is an economic disadvantage and leads to an

increase in CO2 emissions.

7.1.3 Reduction of Power Outage Recovery Time

In the event of an outage due to a facility failure, the fault location is should be specified based on

the information on the system and equipment status pointed to by SCADA, the recovery plan is

determined, and the recovery operation is performed.

However, since a large number of facility information is transmitted at the time of a power failure,

the Load Dispatching Center must properly arrange these pieces of information to grasp the current

state of the power system and issue instructions for restoration. Even under circumstances where

the information is complicated, it is necessary to always respond in a calm and reassuring manner

and judge the exact condition and handle it appropriately so as not to mis-operate.

This FS report proposes to reduce the burden on operators by automating or semi - automating

Page 120: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-5

application of series of restoring operations such as preparation of procedures and execution of

operations. Automation allows operators to concentrate on important tasks such as grasping

recovery situations, so it is possible to shorten the total time of power outage time and reduce the

recovery time. That leads to improvement of power quality.

7.2 Estimation of CO2 Emissions Reduction Amount

CO2 emissions can be reduced by shortening the planned outage period of time when a planned

outage of single transmission line out of two 500kV transmission lines installed in parallel.

CO2 emissions are calculated based on the transmission loss reduction amount calculated

previously. Also, CO2 emission coefficient α was 0.66 kg CO2 / kWh of oil fired power.

The result is as follows.

912 × 103[kWh] × 0.66 ×10-3[α] = 602 [tCO2]

Since the 500 kV power transmission line is operating about 7000 km (2016 PDP 7) throughout

Vietnam, assuming that planned outage occurs every five years.

It is assumed that 1,400 km of power transmission lines are stopped annually, yearly.

The amount of CO2 emission suppression is roughly as follows.

602 × 1400/400 = 2107 [tCO2]

7.3 Expected Benefits for Japan

Since the demand for electricity in Vietnam is expected to increase due to economic growth in the

future, the development of power supply and electric power system will continue for the time being.

However, these developments are not responses to power shortages, but to deal with future

demand increases.

Therefore, it is assumed that the management task of EVN is changing from quantitative goal to

qualitative target.

Regarding qualitative response, it is a field of specialty of Japanese electric utilities and vendors

that achieve world best supply quality.

There is a possibility of securing the advantage from other countries' entrants.

Supporting future activities at EVN together with the public and private sectors without missing this

turning point leads to the creation of business opportunities for Japanese companies.

7.4 Assessing Japanese Companies’ Competitive Advantages

High power quality in Japan is supported by (1) the high level of power system operation

technology and (2) SCADA's design technology realizing it. In other words, it is not vendor-driven

development. If Japan provide EVN with technical assistance with the public and private sectors, it

will be able to get them to fully recognize the competitive advantage of Japanese power system

operation technology and the importance of cybersecurity measures. Also, if NLDC reflects input

from Japan in its SCADA procurement requirements and specifications, Japan can favorably

promote Japanese market-oriented SCADA developed to satisfy the needs of partner countries, vs.

overseas vendors that insist on product-oriented SCADA procurement.

Page 121: Pre-Feasibility study on improvement of grid operation by ...1-1 1 Project Description 1.1 Project Objective Electricity Network of Bangladesh consists of only one national grid system

7-6

7.5 Possible Utilization of Financing and Government Support

In Vietnam, many projects have already been developed with ODA funds, and it will be difficult to

acquire funds for SCADA procurement in the future.

Therefore, while seeking the possibility of procuring ODA funds, it is necessary to propose them to

raise fund on their own by showing the investment effect of SCADA procurement.

7.6 Promoting this Approach to Other Countries

It was confirmed that our proposals for this project is applicable to NLDC both technically and in

terms of business operations.

However, in terms of the structure of the company, it is necessary to appeal to the EVN

headquarters.

With respect to the possibility of promoting this approach to other developing countries, another

round of surveys for each country will be required, because the type of electric power system, scale,

supervisory control system, electric power facilities, etc. vary depending on the country, and

because the best supervisory control system and SCADA also vary depending on each country.