Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY...

28
PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED FOR SALUJA STEELS & POWER PRIVATE LIMITED [DRI (600 TPD), Induction Furnace (600 TPD), Rolling Mill (100,000 TPA), Power Generation – 15 MW (8 MW through Waste Heat Recovery Boiler (WHRB) and 7 MW through Fluidized bed combustion (FBC) Boiler)] at Village: Mohanpur, Tehsil: Giridih, District: Giridih, State: Jharkhand Prepared by PECS, Nagpur

Transcript of Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY...

Page 1: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

PRE-FEASIBILITY REPORT

SUBMISSION TO

MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE,

NEW DELHI.

PREPARED FOR

SALUJA STEELS & POWER PRIVATE LIMITED

[DRI (600 TPD), Induction Furnace (600 TPD), Rolling Mill (100,000 TPA), Power Generation –

15 MW (8 MW through Waste Heat Recovery Boiler (WHRB) and 7 MW through Fluidized bed

combustion (FBC) Boiler)]

at

Village: Mohanpur, Tehsil: Giridih,

District: Giridih, State: Jharkhand

Prepared by PECS, Nagpur

Page 2: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Prefeasibility Report Saluja Steels & Power Private Limited

Table of Contents

Chapter –1: EXECUTIVE SUMMARY ....................................................................................3

Chapter – 2: INTRODUCTION OF THE PROJECT ……........................................................5

Chapter – 3: PROJECT DESCRIPTION....................................................................................7

Chapter – 4: SITE ANALYSIS ................................................................................................22

Chapter – 5: PLANNING BRIEF.............................................................................................24

Chapter – 6: PROPOSED INFRASTRUCTURE.....................................................................26

Chapter – 7: REHABILITATION & RESETTLEMENT (R & R) PLAN ..............................28

Chapter – 8: PROJECT SCHEDULE & COST ESTIMATES ................................................29

Chapter – 9: ANALYSIS OF PROPOSAL ..............................................................................30

Page 3: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Chapter –1: EXECUTIVE SUMMARY

1.1 SALIENT FEATURES OF THE PROJECT

Saluja Steels & Power Private Limited (SSPPL), have proposed to expand the existing DRI

Plant at Village Mohanpur, Tundi Road, Tehsil Giridih, District Giridih, State Jharkhand.

Following shall be the plant configuration and production capacity after expansion of the

unit:

Sl.

NO.

UNIT PROJECT CONFIGURATION PRODUCTION

CAPACITY

Existing Proposal

1. DRI Kilns

(Sponge Iron)

2 X100 TPD 2 X200 TPD 600 TPD

2. Induction Furnace with

Concast (MS Billets)

- 2 X 20 +2x10t

(2+2 Cell Standby)

600 TPD

3.

Power

Plant

WHRB - 2x11 tph+2x22 tph 8 MW

AFBC/CFBC - 1 X 30tph 7 MW

4. Rolling Mill (TMT bar) - 100,000 tpa 100,000 tpa

1.2 PROJECT PROPONENT

Rapid industrialization leads to all-round development and improvement in quality of people in the

area. Jharkhand is a very congenial state for industrial growth due to availability of manpower, raw

materials and other infrastructural facilities

About the Group:

Saluja Steels & Power Private Limited (SSPPL), is Private limited registered company under

company act in the year 2006.

List of directors / Background / Experience:

i) Mr Amarjeet Singh Saluja – a graduate having 25 years of experience in steel manufacturing

and presently Chairman and Managing Director of M/s Saluja Steels & Power Private Ltd.,

Giridih having turnover of over Rs.200 Cr.

Page 4: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

ii) Mr. Taranjeet Singh Saluja, an MBA having 12 years of experience in steel melting and

structural manufacturing and presently Director in SSPPL, Giridih having a group turnover of

over Rs.200 Crores.

iii) Mr. Satwinder Singh Saluja, an MBA having 10 years of experience in manufacturers of TMT

bars presently Director of SSPPL having turnover of over Rs.200 Crores.

Brief Summary

Project name Expansion of existing DRI 60,000tpa to 180,000tpa, &

manufacturing 138,700 steel billets in SMS, rolling into

100,000tpa TMT Rods and adding 15 MW Power

generation from waste heat recovery from DRI

kiln(2x11+2x22 tph WHRB) and converting waste

dolochar and fine rejected coal( through 1x30tph

AFBC/CFBC boiler) At Mouza Mohanpur, PS

Mahtodih, District Giridih(JHK)

Project proponent Saluja Steel & Power Private Limited (SSPPL)

Location

Village Mohanpur, Tundi Road, Tehsil Giridih, District

Giridih, State Jharkhand

Latitude

Longitude

Total Area Total Project Area is 30.29343 acres (12.26 hectares).

The proposed expansion will be within the unutilized area

within the existing premises of plant.

Present Land use break up Pre-establishment land use = Industrial

Post-establishment land use = Industrial

Product Sponge Iron, Billets ,TMT Bars and Electrical Energy

Rated capacity 15 MW CPP

Working days 300

Manpower 135

Implementation Schedule 24 Months from approval

Expected cost of the projectRs, 96 Crores

Elevation 320 m MSL

Topography Flat

Latitude & longitude of existing plant

24° 8'37.10"N 86°20'21.32"E

24° 8'36.39"N 86°20'25.96"E

24° 8'26.56"N 86°20'27.07"E

24° 8'29.13"N 86°20'13.75"E

Page 5: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Water requirement 1096 KLD

Source of water Water will be drawn from the pond made on Water

Harvesting Principle by the company in the existing Plant

premises and ground water,

Power description Project will generate 15 MW electric power from the

proposed CPP and will utilize the total power generated in

its existing Sponge Iron plant,

Power source Captive Power Plant, Currently from DVC

Page 6: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Chapter – 2: INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION

2.1 BRIEF DESCRIPTION OF THE NATURE OF THE PROJECT

Saluja Steels & Power Private Limited (SSPPL), have proposed to expand the existing DRI

plant at Village Mohanpur, Tehsil Giridih, District Giridih, State Jharkhand. The Company

intends to convert the unit into a steel plant with final unit product shall be TMT rods.

• Manufacturing of 600 TPD of Sponge Iron by installing 2 x 200 TPD DRI Kilns in addition

to existing 2x100tpd DRI Kilns.

• Manufacturing of 600 TPD of MS Billets by installing 2 x 20+2x10 T (2+2 cell standby)

capacity Induction furnace with matching Concast for manufacturing Cast Billets.

• Manufacturing of 100,000 tpa TMT bars in hot Rolling Mill

• Power generation of 8 MW through Waste Heat Recovery from DRI Kilns and 7 MW

through AFBC/CFBC based boilers converting waste dolochar generated from DRI Kiln to

power.

2.2 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND/

OR REGION

India’s economic growth is contingent upon the growth of the Indian steel industry.

Consumption of steel is taken to be an indicator of economic development. While

steel continues to have a stronghold in traditional sectors such as construction,

housing and ground transportation, special steels are increasingly used in engineering

industries such as power generation, petrochemicals and fertilizers. India occupies a

central position on the global steel map, with the establishment of new state-of-the-art

steel mills, acquisition of global scale capacities by players, continuous modernization

and up gradation of older plants, improving energy efficiency and backward

integration into global raw material sources. Steel production in India has increased

by a compounded annual growth rate (CAGR) of 8 percent over the period 2002-03 to

2006-07. Going forward, growth in India is projected to be higher than the world

average, as the per capita consumption of steel in India, at around 52 kg, is well below

the world average (170 kg) and that of developed countries (400 kg). Indian demand

is projected to rise to 300 million tonnes by 2030. Given the strong demand scenario,

most global steel players are in a massive capacity expansion mode, either through

brownfield or Greenfield route. Steel production capacity in India is expected to touch

120 million tonnes by 2020. While Greenfield projects are slated to add 30 million

Page 7: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

tonnes, brownfield expansions are estimated to add 50 million tonnes to the existing

capacity of 90 million tonnes. Steel is manufactured as a globally tradable product

with no major trade barriers across national boundaries to be seen currently. There are

also no inherent resource related constraints which may significantly affect production

of the same or its capacity creation to respond to demand increases in the global

market. Even the government policy restrictions have been negligible worldwide and

even if there are any the same to respond to specific conditions in the market and have

always been temporary. Therefore, the industry in general and at a global level is

unlikely to throw up substantive competition issues in any national policy framework.

Further, there are no natural monopoly characteristics in steel. Therefore, one may not

expect complex competition issues as those witnessed in industries like telecom,

electricity, natural gas, oil, etc.

2.3 DEMAND AND SUPPLY GAP

Demand for steel is high and as soon as they are processed, they will be supplied to nearby

industries.

2.4 EXPORT POSSIBILITY

As the Indian steel industry has entered a new development stage from 2007-08, riding high

on the resurgent economy and rising demand for steel. Rapid rise in production has resulted

in India becoming the 4th largest producer of crude steel and the largest producer of sponge

iron or DRI in the world. As the demand is more the export possibility of Sponge Iron will

also be more. As the demand is more the export possibility will also be more.

2.5 DOMESTIC/EXPORT MARKETS

While the demand for steel will continue to grow in traditional sectors such as infrastructure,

construction, housing automotive, steel tubes and pipes, consumer durables, packaging, and

ground transportation, specialized steel will be increasingly used in hi-tech engineering

industries such as power generation, petrochemicals, fertilizers, etc. The new airports and

railway metro projects will require a large amount of steel. Hence the domestic and export

markets for steel sector will rise.

2.6 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT

The estimated manpower requirement for the proposed project is 135 numbers; the total

manpower requirement for the entire plant is 500 numbers inclusive of staff and security.

Page 8: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

They will comprise of 20 % of skilled labours, 40 % of semi- skilled labours and 40 % of

unskilled labours.

Page 9: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Chapter – 3: PROJECT DESCRIPTION

3.1 TYPE OF THE PROJECT

Saluja Steels Private Limited (SSPPL), have proposed to setup the steel plant at Village

Mohanpur, Tehsil Giridih, District Giridih, State Jharkhand.

Company intends to:

• Manufacturing of 600 TPD of Sponge Iron by installing additional 2 x 200 TPD DRI Kilns.

• Manufacturing of 600 TPD of MS Billets by installing 2 x 20 + 2x10 T (2+2 cell standby)

capacity Induction furnace with matching CONCAST.

• Manufacturing of 100,000 TPA of bars/rods by installing 100,000 capacity Rolling mill.

• Power generation of 8 MW through Waste Heat Recovery from 2 x 100+2x200 TPD DRI

Kiln. Power generation of 7 MW through FBC based boiler.

3.2 LOCATION OF THE PROJECT

• Project location is at Village Mohanpur, Tehsil Giridih, District Giridih, State

Jharkhand.

• 30.29343 acres of land is under possession of the company for the proposed expansion

project.

• The entire project area will fall in the Survey of India topo sheet no. G45U8

3.3 DETAILS OF THE ALTERNATE SITES

This is an existing plant therefore there is no question of alternative site as sufficient land is

under possession of company for this expansion for the proposed Steel plant:

Sl.

No. Particulars Site # 1

1. Location (Village) Mohanpur

2. Geographical Coordinates TOPO SHEET NO.: G45U8

Latitude & longitude of existing plant

24° 8'37.10"N 86°20'21.32"E

24° 8'36.39"N 86°20'25.96"E

24° 8'26.56"N 86°20'27.07"E

24° 8'29.13"N 86°20'13.75"E

Page 10: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

3. Areas falling under the critically polluted

areas (within 10 Kms. Radius) No

4. National Parks / Wild life Sanctuaries / Bird

Sanctuaries/ Tiger reserve/ Elephant

corridors / Migratory routes for Birds / Forest

(within 10 Kms. of the project site)

No

5. Sensitive Areas with 10 Kms. radius of the

site No

6. Type of Land Industrial

7. Distance of nearest Habitation Mohanpur – 2.7 Kms

8. Nearest Water body Ushri River –7.0 Kms

3.4 SIZE OR MAGNITUDE OF OPERATION

S.NO. Units Existing

Configuration

Proposed

Configuration

Production Capacity

1. DRI Kilns (Sponge

Iron)

2 X100 TPD 2x200 TPD 600 TPD

(180,000TPA)

2. SMS

Induction Furnace with

CONCAST (MS

Billets)

- 2 X 20+2x10 T 600 TPD

(138,700 TPA

MS Billets)

Billets for sale

33,437 TPA

3. Rolling Mill (TMT

Mill)

- 100,000 T TMT

Rods

100,000 T TMT

Rods

4. Power Plant

(Electricity)

WHRB - 2x11+2x22 tph 8 MW

FBC - 1x30tph 7 MW

Page 11: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

3.5 MANUFACTURING PROCESS

3.5.1 DRI KILN BASED SPONGE IRON PLANT

The Direct Reduced Iron (DRI) plant will comprise of 2 x 100 TPD Kiln existing while

2x200 TPD Dri Kiln proposed and related accessories including Waste Heat Recovery

power generating unit. The major plant facilities for the Sponge Iron plant envisaged are

as follows:

Day bins

Rotary Kiln & Cooler

Central Control Room

Product processing and product storage

Off gas system including waste heat recovery power generation

The day bin building will have bins for meeting raw material required for kiln. This bin will

have the storage facility for pellets, feed coal, dolomite etc.

A refractory lined rotary kiln will be used for reduction of Iron ore in solid state. A central

Burner located at the discharge end will be used for initial heating of the kiln. Sized Iron ore

will be continuously fed into the kiln along with coal which has dual role of fuel as well as

reductant. Dolomite will be added to scavenge the Sulphur from the coal. A number of air

tubes will be provided along the length of the kiln. The desired temperature profile will be

maintained by controlling the volume of the combustion air through these tubes. The

Carbon monoxide generated due to the combustion of coal, reduces the iron ore and

converts it into sponge iron. The rotary kiln is primarily divided into two zones viz. the pre

heating zone and the reduction zone. The preheating zone extends over 30 to 50 % of the

length of the kiln and in this the moisture in the charge will be driven off and the volatile

matter in the coal will be burnt with the combustion air supplied through the air tubes. Heat

from the combustion rises the temperature of the lining and the bed surface. As the kiln

rotates, the lining transfers the heat to the charge. Charge material, pre-heated to about

1000oC enters the reduction zone. Temperature of the order of 1050oC will be maintained in

the reduction zone, which is the appropriate temperature for solid state reduction of iron

oxide to metallic iron. This hot material will be transferred to rotary cooler. In rotary cooler

the material will cool from 1000oC to 100oC in cooler by spraying water. The cooler

Page 12: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

discharge material consists of sponge iron lumps, sponge iron fines and char. Magnetic and

non-magnetic material will be separated through magnetic separators and stored in separate

bins

3.5.2 STEEL MELTING SHOP (SMS)

In Steel Melting Shop (SMS), Sponge Iron will be melted along with melting scrap and

fluxes to make pure liquid steel and then to mould it in required size billets. The SMS

will consist of following equipment and subassemblies:

Induction Furnace: Induction Furnaces is a device to melt the charge material using

electrical power. It consists of Crucible consisting of water-cooled induction coils lined

with refractory material lined with water cooled induction coils, Electrical system to give

controlled power to induction coil, Hydraulic tilting system, Heat exchanger to cool the

circulating water, water softener for generating soft water, furnace transformer, Power

Factor improvement system and surge suppressor.

Page 13: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Ladles: Ladles are pots with refractory lining inside to withstand 17500C temperature. It

has side arms so that can be lifted with the help of crane. Ladles are used to stores the

liquid steel from Induction Furnace and take it for further processing. Ladles are with

bottom nozzle and pneumatically operated gate for discharge of liquid.

Cranes: Electric Over-head (EOT) cranes of various capacities are used to carry the

ladles/materials at different places. Cranes are used in Melting hall to charge melting

scrap, remove the ladles to the LRF, further, to place it over the Tundish of the

Continuous Caster, to remove billets from the cooling bed and store at designated places,

and for other petty use. Accordingly, the sizes, capacity and numbers of cranes are

decided.

Continuous Casting Machine (CCM): CCM is used to continuously cast the liquid steel in

required cross section and in length. It consists of Tundish, Mould, Bow with Withdrawal

mechanism, straightening mechanism and cooling bed, hydraulic system for withdrawal

mechanism, water pumps and cooling towers for water spray on the withdrawn section as

well as on the cooling bed. Dummy bar is provided to start the casting. Tundish is a

rectangular vessel, lined with refractory and having discharge nozzle with pneumatically

operated gate. A stand is erected over it where the ladle is stationed for discharging the

liquid in it. Mould is of copper with water cooled jacked. Its cross-section in the bottom is

of the size of which billet is to be drawn. Initially the dummy for of the same size is kept

inserted. When the liquid steel is poured in the mould, the dummy bar is drawn slowly, so

that the liquid steel in partially frozen state comes out of the mould. Water spray nozzles

are installed to spray water over the just drawn billet to cool it further and to harden the

skin of the drawn billet.

There will be 2 nos. of 20 T and 2no 10 T Induction Furnaces in the SMS plant. MS

Billets will be produced in Continuous Casting Machine.

Page 14: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED
Page 15: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

3.5.3 ROLLING MILL

TMT or Thermo Mechanically Treated bars are high-strength reinforcement bars having a

hardened outer core and a soft inner core. They are manufactured under a process called

Thermo Mechanical Treatment, after which they are named. Thermo Mechanical Treatment

(TMT) processes combines mechanical or plastic deformation processes like compression or

forging, rolling etc. with thermal processes like heat-treatment, water quenching, and heating

and cooling at various rates into a single process.

The production quality of TMT bar depends on three major factors:

• Quality of raw materials.

• A properly designed and automated rolling mill stand.

• A well-designed quenching and tempering technology.TMT bars, having a uniform and concentrated hardened periphery and a considerably softercore, will have the desired tensile strength coupled with high elongation as required in theconstruction of buildings located in areas with regular seismic activity.

3.5.4 POWER PLANT

It is proposed to install 8 MW WHRB & 7 MW FBC based power plant to meet the

power requirement for various processes of integrated plant including auxiliaries of

power plant.

WHRB Power Plant:

Page 16: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Production of sponge iron in DRI kiln generates huge quantities of hot flue gases carrying

considerable sensible heat. The energy content of these gases can effectively be used to

generate electric power as well as steam for meeting various process requirements. Thus,

a WHRB (Waste Heat Recovery Boiler) power plant would be an ideally suited

proposition to effectively make use of this waste gas. This WHRB Power plant would not

only make the plant independent of external source of electric power to some extent but

would also result in energy conservation and environment protection.

Steam Turbo-generators (STGs) envisaged for the Power plant will be single cylinder,

multistage, extraction – cum – condensing type complete with condenser, air evacuation

system, 2 x 100% condensate extraction pumps, electronic governing system, lubricating

oil system, regenerative feed heating system etc. The turbine will be fed with steam

generated from HRSG in DR kiln. The STGs will be in the machine hall of the power

plant.

FBC Power Plant:

The unit will have one FBC boiler connected to 7 MW Steam Turbine Generator. The

boiler will be designed for continuous operation at Turbine Maximum Continuous Rating

(TMCR). A margin of 10% over TMCR shall be considered to arrive at Boiler rated

capacity. The boiler will be natural circulation, fluidized bed combustion, two passes,

non-reheat, single drum, balanced draft, semi-outdoor type. The boiler will have

continuous evaporation rating of approx. 360 tonnes/hr. (BMCR shall not be less than

110% of TMCR) with steam parameters at super heater outlet as 98 kg/cm2 and 5400C (±

50C). The feed water temperature at MCR at inlet to economizer is expected to be around

230-degree C. Steam parameter are to be fine-tuned at Boiler outlet based on actual plant

layout and piping arrangement. The boiler will be complete with ash /solid separator,

economizer, air heater, ducting, FD fans, ID fans and PA fans. Air cooled condensers

envisaged for Power plant to conserve water.

Page 17: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Process Flow Diagram

Page 18: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

3.6 RAW MATERIAL REQUIREMENT

The following will be the raw material requirement for the proposed project:

Raw Material Quantity (TPA) Source Mode of Transport

For DRI (Sponge Iron)

Sized Iron Ore 297,000 Internal Through covered conveyors

Non-Coking Coal 260,000 South African By road Piperwar

Sized Dolomite 10,800 Local/Jharkhand By road(through covered trucks)

For Steel Melting Shop (MS Billets)

Sponge Iron 180,000 Internal Through covered conveyors

MS Scrap 38,557 Nearby market By road(through covered trucks)

Ferro alloys 173.8 Local /Jharkhand By road(through covered trucks)

For Rolling Mill (TMT Bars/Rods)

Billets 105,263 Internal Through Transfer

For FBC Boiler [Power Generation 7MW]+ 8 MW WHRB

Char/Dolochar 21,294 Internal Generation through covered conveyors

Coal Fines 48,890 Internal Generation By road

3.7 WATER REQUIREMENT AND ITS SOURCE

Water required for the existing and proposed expansion project will be 1096 KLD and

same will be sourced from Ground Water source. Following is the break-up of water

requirement:

S.NO. WATER REQUIREMENT FOR QUANTITY IN KLD

1 DRI kilns 432

2 Steel Melting Shops 209

3 Rolling Mills 76

4 Power Plant 358

5 Domestic 20

Total 1096

Page 19: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

3.8 WASTEWATER GENERATION & ITS MANAGEMENT

• There will be no effluent generation in the DRI plant, SMS, Rolling Mill and power

generating unit as closed-circuit cooling system will be adopted. There will be no

discharge of waste water from plant boundary

• Effluent from power plant will be treated and after ensuring compliance with SPSB

norms, it will be utilized for dust suppression, ash conditioning and for greenbelt

development.

• Sanitary waste water will be treated in septic tank followed by sub-surface dispersion

trench.

3.9 SOLID WASTE GENERATION AND ITS MANAGEMENT

The following will be the solid waste generation & disposal method from the proposed project.

Sl.NO WASTE QUANTITY

(TPD)

METHOD OF DISPOSAL

Sponge Iron plant:

1 Char/ Dolochar 240 Will be used in FBC power plant as fuel/ brick

manufacturing.

Induction Furnace:

3 Slag 46 sub base material in road construction/brick

manufacturing

4 Ash from Power Plant 2339 Ash generated will be given to Cement Plants/

Bricks manufacturers etc.

4 Rolling Mill- Mill scale

& Mill scrap

17.52 Scrap recycle to SMS, slag is sold

3.10 POWER REQUIREMENT

Power requirement for the existing & proposed project will be met from DVC during

construction phase. Power required for proposed project will be met from proposed

15MW WHRB and FBC based power plant during operation. Following is break up of

power requirement:

Page 20: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Chapter – 4: SITE ANALYSIS

4.1 INFRASTRUCTURE

For establishment and successful operation of plant, it is imperative to ensure

availability of the following infrastructure:

Availability of raw coal & iron ore and its proximity to the plant to reduce cost of

transportation.

Road / Rail head connection so that the raw materials and products can be easily and

economically transported.

Availability of water.

Permanent and reliable source of power.

Adequate land for the plant, storage of raw material and products & disposal of waste

material.

4.2 CONNECTIVITY

The proposed site is well connected with Road network. The following table gives brief

regarding connectivity of the proposed site:

Component Description

Road :Tundi Road Giridih – 0.8 to 1 Kms.

Rail :Nearest station – Giridih Railway Station – 6.0 Kms.

Air :Ranchi Airport – 200.0 Kms.

Page 21: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

4.3 TOPOGRAPHY

Giridih is headquarters of the Giridih district of Jharkhand state, India. The literal

meaning of Giridih is the land of hills and hillocks. The topography of the area is rugged

with undulations. The area is situated on the Chota Nagpur Plateau and is diverse in

nature. It is bounded by Jamui district and part of Nawada District of Bihar in the North,

by Dhanbad & Bokaro on the South, by the district of Deoghar and Jamtara on the east,

and by Hazaribagh & Koderma on the West.

4.4 EXISTING LAND USE PATTERN

Present land use pf project site is mostly converted to industrial purpose. The area is

industrial hub for many industries.

4.5 EXISTING INFRASTRUCTURE

Many infrastructure facilities are available at the project site. Project is well connected

with road network very well

4.6 CLIMATIC DATA FROM SECONDARY SOURCES

The normal climate of Giridih is dry. The summer brings very hot temperature like rest of

the Jharkhand State. The summer season starts in the month of April however May-June

are considered hottest months in the region with temperature soaring almost up-to 42° C.

The highest temperature in the city was recorded 47° C. The temperature in the hills

however, reduces due to the height factor. The humidity level of the area increases during

the rainy season. The month of June brings Pre Monsoon rains in the city. However, from

July to August the amount of monsoon rains increases and the rain even continues till the

month of September. The winter season is very pleasant and the temperature remains on

the moderate line. The time between October to March is best time to visit the city.

Page 22: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Chapter – 5: PLANNING BRIEF

5.1 PLANNING CONCEPT

Saluja Steels & Power Private Limited (SSPPL), have proposed to setup the steel plant at

Village Mohanpur, Tehsil Giridih, District Giridih, State Jharkhand. Following is the

plant configuration and production capacity:

Sl.

NO.

UNIT PROJECT CONFIGURATION PRODUCTION

CAPACITY

Existing Proposal

1. DRI Kilns

(Sponge Iron)

2 X100 TPD 2 X200 TPD 600 TPD

2. Induction Furnace with

CONCAST (MS Billets)

- 2 X 20 +2x10t

(2+2 Cell Standby)

600 TPD

3.

Power

Plant

WHRB - 2x11 tph+2x22 tph 8 MW

AFBC/CFBC - 1 X 30tph 7 MW

4. Rolling Mill (TMT bar) - 100,000 tpa 100,000 tpa

5.2 POPULATION PROJECTION

Mohanpur is a large village located in tundi road of Giridih district, Jharkhand with total

1040 families residing. The Mohanpur village has population of 5088 of which 2596 are

males while 2492 are females as per Population Census 2011.

In Mohanpur village population of children with age 0-6 is 761 which makes up 14.96 %

of total population of village. Average Sex Ratio of Mohanpur village is 960 which is

higher than Jharkhand state average of 919. Child Sex Ratio for the Mohanpur as per

census is 987, higher than Jharkhand average of 890.

Mohanpur village has lower literacy rate compared to Jharkhand. In 2011, literacy rate of

Mohanpur village was 70.95 % compared to 78.03 % of Jharkhand. In Mohanpur Male

literacy stands at 84.23 % while female literacy rate was 57.05 %.

Page 23: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

5.3 LAND USE PLANNING

The following is the Land use planning of the proposed project area.

ITEM EXTENT OF LAND (ACRES)

Built up area 40%

Internal roads 08%

Storage yard 13%

Greenbelt 33%

Paking area 2%

Open land 4%

Total land 30.2935(100%)

5.4 AMENITIES / FACILITIES

Facilities like canteen, rest rooms will be provided in the existing plant as basic facilities

to workers. No other additional facilities are proposed.

Page 24: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Chapter – 6: PROPOSED INFRASTRUCTURE

6.1 INDUSTRIAL AREA (PROCESSING AREA)

The main plant area comprises of DRI Kilns, Furnace sheds, Rolling mill area, raw

material storage and product storage etc.

6.2 RESIDENTIAL AREA (NON-PROCESSING AREA)

No colonization is proposed; however, facilities like canteen, rest room and indoor games

facilities will be provided in the proposed plant and one Admin building is also proposed.

6.3 GREEN BELT

More than 1/3rd of total land availability is reserved for plantation i.e. greenery.

Greenbelt development plan

• Local DFO will be consulted in developing the green belt.

• Greenbelt of 33% of the area will be developed in the plant premises as per CPCB

guidelines.

• 5 m wide greenbelt is being maintained all around the plant.

• The tree species to be selected for the plantation are pollutant tolerant, fast growing,

wind firm, deep rooted. A three-tier plantation is proposed comprising of an outer most

belt of taller trees which will act as barrier, middle core acting as air cleaner and the

innermost core which may be termed as absorptive layer consisting of trees which are

known to be particularly tolerant to pollutants.

6.4 SOCIAL INFRASTRUCTURE

Social infrastructure will be developed as per need based in the Villages of the close

vicinity of the project.

6.5 CONNECTIVITY

Page 25: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

The proposed site is well connected with Road network. The following table gives brief

regarding connectivity of the proposed site:

Component Description

Road : SH- (Giridih – Dhanbad) – 0.14 Kms.

Rail : Nearest station – Giridih Railway Station – 6.0 Kms.

Air : Ranchi Airport – 200 Kms.

6.6 DRINKING WATER MANAGEMENT

The required amount of drinking water will be suppled from ground water sources.

6.7 WASTEWATER GENERATION & ITS MANAGEMENT

• There will be no waste water generation in the DRI plant, SMS & Rolling Mill as closed-

circuit cooling system will be adopted.

• Effluent from power plant will be treated and after ensuring compliance with JSPCB

norms, it will be utilized for dust suppression, ash conditioning and for greenbelt

development.

• Sanitary waste water will be treated in septic tank followed by sub-surface dispersion

trench.

Page 26: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Chapter – 7: REHABILITATION & RESETTLEMENT (R & R) PLAN

No rehabilitation and resettlement are required for the proposed project did not have any

habitation.

Page 27: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Chapter – 8: PROJECT SCHEDULE & COST ESTIMATES

8.1 PROJECT SCHEDULE

Proposed expansion Project will be implemented in 24 months from the date of receipt of

Environmental Clearance from the MoEF&CC, New Delhi & Consent from JSPCB.

PROJECT COST

The estimated cost for the proposed project for will be Rs. 96.0 Crores. The following is the

breakup of the proposed project cost.

Particulars Rs. in Crores

1 Sponge Iron 20.0

3 Induction Furnace with CCM 21.0

4 Rolling mill 10.0

5 Power plant 45.0

Total Investment 96.0

6 Land Already in possession

Grand Total 96.0

Means of Finance Rs. in Crores

Particulars

i. Promoters contribution 26.0

ii. Financial institutions 70.0

Total Investment 96.0

Page 28: Pre Feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/TOR/27...PRE-FEASIBILITY REPORT SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI. PREPARED

Chapter – 9: ANALYSIS OF PROPOSAL

9.1 FINANCIAL AND SOCIAL BENEFITS

With the implementation of the proposed project, the socio-economic status of the local

people will improve substantially. The land rates in the area will improve in the nearby

areas due to the proposed activity. This will help in upliftment of the social status of the

people in the area. Educational institutions will also come-up and will lead to

improvement of educational status of the people in the area. Primary health centre will

also be developed by us and the medical facilities will certainly improve due to the

proposed project.

9.2 SOCIO-ECONOMIC DEVELOPMENTAL ACTIVITIES

The management is committed to uplift the standards of living of the villagers by

undertaking following activities / responsibilities as the part of Corporate Environmental

Responsibility.

Infrastructure creation for Health & hygiene

Infrastructure creation for drinking water

Training centre for surrounding people