Site- and rainfall-specific runoff coefficients and critical rainfall for ...
PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/... · less rainfall. The...
Transcript of PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/... · less rainfall. The...
1
PRE FEASIBILITY REPORT
“GRANITE BUILDING STONE QUARRYMINING PROJECT”
APPLICANT
Mr. RAJESH ROY
MANAGING PARTNER
UNIVERSAL GRANITES
ALANADU P. O
KOTTAYAM
PIN. 686651
Mob.9447368652
PREPARED BY
KORAH A.G.
ADDITIONAL DIRECTOR, RETIRED,
DPT.OF MINING AND GEOLOGY
LIFE MEMBER
QUALITY COUNCIL OF INDIA,
RQP.REG.NO.RQP/BNG/362/2015/A
STATE : KERALA
DISTRICT : KOTTAYAM
THALUK : MEENACHIL
VILLAGE : BHARANANGANAM
BLOCK NO. : 35
SURVEY NO. : 270
MINERAL : GRANITE BUILDING STONE
APPLICATION STATUS : EXISTING
APPLICATION AREA : 00.9912 Ha.
PRODUCTION COST : 75 LAKH
PRODUCTION CAPACITY : 216975 MT (5YEARS)
YEARLY PRODUCTION : 43395 MT /ANNUALY
LIFE OF MINE : 5 YEARS
2
INDEX
CHAPTER NO. TITLE PAGE
NO.
1. Executive Summary 3
2. Introduction of Project / Background Information 4
3. Project Description 6
4. Site Analysis 8
5. Planning Brief 11
6. Proposed Infrastructure 13
7. Rehabilitation and Resettlement (R & R) Plan 14
8. Project Schedule & Cost Estimates 15
9. Analysis of Proposal 16
3
1. EXECUTIVE SUMMARY
Mr. Rajesh Roy seeking new environmental clearance for mining located at village –
Bharanaganam, Thaluk - Meenachil, District – Kottayam, State- Kerala.
The purpose of this present Pre-Feasibility Study is to evaluate the economic viability of
alternative arrangements for Mr Rajesh Roy.
The total project area is about 4 km. West of Bharanaganam, Has a normal surface
elevation of 100m – 60 m. MSL and an application area of 00.9912 Ha.
The water required for dust suppression of the quarry will be sourced from pit. And the
waste water is processed and allowed to flow to the pit.
There will probably be no extra vigour requirement for brand spanking new production.
Present power is adequate for the proposed project.
Ideally topsoil is collected and dispersed immediately on to prepared rehabilitation areas
and after the course of mine the topsoil is refilled and the vegetation is replaced.
Proper safety will be provided during storage, handling and use of blasting substance.
Portable Fire Extinguishers, first aid facilities shall be provided at key location. Also, the
labour safety is emphasized.
The area is found to have prominent exposures of Granite Building Stone covering most
of application area. Detailed study of the area has been done by the applicant by sampling
exposed blocks of Granite Building Stone and depth of the surrounding area. The mine is
carrying out medium scale quarrying by engaging Semi mechanized Open cast method of
quarrying.
Rain Water Harvesting System proposed within project premises to avoid wastage of rain
fall.
The Quarrying Plan is prepared with main emphasis on Systematic Method of working
with an aim to ensure systematic development & conservation of granite building stone
deposits and protection of environment.
4
2. INTRODUCTION OF PROJECT
2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT
Mr. Rajesh Roy which is of an area of 00.9912 Ha. proposes to mine the new
quarrying area with survey no 270
The quantity of material that comes under the proposed project is given below
SECTION BLOCKED
RESERVE (MT)
MINEABLE
RESERVE (MT)
GEOLOGICAL
RESERVE(MT)
A-A 138795 97125 235920
B-B 121125 119850 240975
TOTAL 259920 216975 476895
PROJECT PROPONENT
Mr. Rajesh Roy is the owner of the mining area.
2.2 NATURE OF THE PROJECT
The rock is transported from the quarry to the others crushing units, construction
purposes, making roads etc.
The site is fully adoptable for mining purposes and the labours are provided with good
working environment. The waste materials produced are processed and dumped in a separate
space and used for various purposes. The waste water generated is filtered and allowed to
flow to the nearby water source.
2.3 NEED FOR THE PROJECT
In order to full fill the huge demand of rock and rock products for various building
works, industrial development, roads, various domestic needs etc. And also as a concern over
the employment of localities settled nearby the proposed area. Rapid industrialization and
growth in infrastructure has made global as well as domestic demand for Granite Building
Stone. So, number of Granite Building Stone manufacturing quarries & industries are coming
up in this sector. Granite Building Stone is the chief material in this sector, for building
constructions, roads and railway ballast materials. The size & quality parameters for supply
of the mineral will be as per the requirements of the user industry. Based on the demand, the
5
applicant intends to produce the required quantum of Granite Building Stone exclusively for
the Domestic purposes, roads etc.
The employees will be assigned job relating to drilling, the handling of the Granite
Building Stone and waste & others routine works in the quarry.
6
3. PROJECT DESCRIPTION
3.1 TYPE OF PROJECT
Based on the demand, the applicant intends to produce the required quantum of
Granite Building Stone exclusively for the Domestic purposes, roads etc, send to the crusher
for crushing purpose.
3.2 LOCATION
The proposed granite building stone quarry is situated in Sy.No.270
village –Bharanaganam, Thaluk - Meenachil, District – Kottayam, State- Kerala.
Geographical location of the site is and boundary pillars of the site is.
Boundary Pillar No. Latitude (N) Longitude (E )
1 09°44'31.6" 76° 43'43.7"
2 09°44'34.1" 76° 43'42.9"
3 09°44'34.5" 76° 43'42.3"
4 09°44'35.7" 76° 43'45.0"
5 09°44'35.2" 76° 43'45.3"
6 09°44'32.8" 76° 43'46.7"
7 09°44'32.4" 76° 43'44.8"
The mine area is located in the topo sheet no. - 58C10 ,New C43Q10,UTM Zone 43.
The field studies it is observed that the Quarry area is falling in uncultivable lands,
non-forest i.e. in Own lands. The area in essence consists of Stone/Rocky ridges and
slope/gradient in all directions.
3.3 DETAILS OF ALTERNATE SITES
Mr. Rajesh Roy, the mining site Located in village – Bharannganam ,Thaluk-
Meenachil, District – kottayam, State- Kerala, proposes to mine the given area so there are no
alternate sites.
3.4 SIZE / MAGNITUDE OF OPERATION
The existing mining area will be used for the proposed project. The method of
working for Building Stone in the Quarry lease area for the proposed plan period is by Semi
7
Mechanized method of opencast quarrying. Considering the technical parameters like surface
topography, quality variations, geo‐technical aspects, required rate of production & available
resources etc, it is proposed to work this deposit by adopting 3m bench height and with an
ultimate pit slope of 45° by Small scale quarrying activity with small dia. jack Hammer
drilling & blasting and use of Hydraulic Rock Breaker. The benches height and the width will
be maintained as specified by DGMS. The width of the working benches, shall not be less
than the height. The Year wise Production & Development plan indicates the workings, site
for disposal of waste/overburden etc., The Plan showing the position of workings, proposed
extensions, bench parameters, pit configuration at the end of Plan Period is indicated in
Production & Development plan. Due care will be taken in designing the benches by
straightening & advancing the benches for effective and economical operation of the quarry.
Since the ground water table is not at much depth and the rainfall is very high during
monsoon, drainage of water shall be properly coursed with series of check dams & retaining
walls so as not to disturb the natural drainage pattern of the area.
3.5 RESOURCE OPTIMIZATION / RECYCLING AND REUSE
The waste material generated due to the mining process are used for dumping
purposes, making roads etc. and the waste water is filtered and processed for better use so
that it will not pollute the natural water resource. Intercalated waste of the Building Stone
handled during Quarrying operations is less as the entire area is almost a rocky terrain. An
estimated quantity of waste (voids& mining losses) will be handled during the proposedyear
plan period. To temporarily accommodate this waste material, non‐mineralized area and same
will be utilized for haulage road maintenance, filling of pot holes & formation of safety bunds
all along the 7.5m safety zone.
The Quarrying pits after extraction of the Granite Building Stone will be reclaimed by
suitable afforestation techniques and portion of the pit may be left as water reservoir &
storage of rain water shall help in recharging the ground water table and improve the water
regime of the area. Proper fencing of the lease area shall be taken up to avoid entry of
animals & trespassing into the lease area and also such that the same is also useful to the local
community.
Rainwater harvesting is also adopted in the premise.
8
4. SITE ANALYSIS
4.1 CONNECTIVITY
The project site is well connected with all infrastructures like National Highway,
Railway, Airport, telephone, internet, fax, post, etc
Following infrastructure facilities are available in application area:
Name of the place Distance Direction
Nearest railway
Station
Kottayam 35 Km SW
Nearest Airport Cochin 90 Km N
Nearest Highway NH 220 Ponkunnam -Thodupuzha 5 Km NE
Electric Line LT 110M NE
Telephone At Office (Mobile) - -
Water Near to the site (Pond & wells) - -
Dispensary Govt - Hospital 2 Km SW
Post office Bharananganam 4Km W
School/College Pala 9Km SW
9
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP
Present Land Use Pattern:
S. No Particulars Present area (in Ha)
1. Pits Nil
2. Road Nil
3. Drainage / Pond Nil
4. Build-up Area Nil
5. Existing mine 0.0877 Ha
6. Un-worked Area 0.6109 Ha
7. 7.5 m Buffer Zone (Out side) 0.2926 Ha
Total 00.9912 Ha.
4.3 TOPOGRAPHY
The Physiography of the area has partial vegetation, as the area is existing mine.
About the topography of the applied area, the highest elevation is 100 m. MSL and lowest is
60 m MSL. As the proposed area is rock, the drainage of the application area is towards south
west.
4.4EXISTING LAND USE PATTERN, SHORTEST DISTANCE FROM THE
PERIPHERY OF THE PROJECT TO PERIPHERY OF THE FOREST,
NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE AREA,
WATER BODIES (DISTANCE FROM THE HFL OF THE RIVER)
Sl.
No
Name Distance from the proposed area
1 Vagamon (Forest) 40 Km
2 Eravikulam (National
Park)
140 Km
3 Periyar Tiger Reserve (
Wild life sanctuary)
90 Km
10
4.5 SOIL CLASSIFICATION
Soil in the study area primarily Sandy Loam and Silt Loam. Porosity is an important
soil parameter for any project where flow of water through soil or rock is a matter of concern.
Electrical Conductivity (EC) of soil depends on the porosity, water content, salinity
level, etc
4.7 CLIMATIC DATA FROM SECONDARY SOURCES
The district experiences humid type of climate. South west followed by the Northeast
monsoon gives the maximum rainfall during the year. The other months receive considerably
less rainfall. The temperature is pleasant from December to February. The annual rainfall
varies from 1883 to 3347 mm based on long term normal. The district receives on an average
2615 mm of rainfall annually. Major rainfall is received during June to September in the
southwest monsoon (71%).
11
5. PLANING BRIEF
5.1 PLANNING CONCEPT
The entire strike length of the deposit is exposed & the quarry is envisaged to be
worked forming benches of 5 mtrs height and width more than the height of the bench with a
general pit slope of 45° degrees. The ultimate pit limit is marked as shown on the Geological
plan. However, when the Building Stone is proved to its full depth, the conceptual plan will
be duly modified. The possibility of building stone below is to be examined further by
exploration.
All the basic facilities like tap water, sanitation & drinking water, lunch space & First
aid box is provided within premises.
The project site is well connected with the road. Finished products and raw materials
will be transported through road. There is no requirement for the development of other road .
5.2 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL)
The project site is well connected with all the infrastructure facilities. Production will
be carried out within the existing production facility and infrastructure available.
The existing road network will be sufficient to meet the proposed production
capacity. However, required infrastructure for transport within the leasehold area will be
further strengthened and improved. No new routes or alternations are required in this
regards.
Local people will be hired for various jobs and they will be trained within unit. Thus,
no social infrastructure will require.
5.3 AMENITIES / FACILITIES
The door of employment opportunities has a positive impact on the socio‐economic
conditions of the surrounding as most of the work force employed will be from the nearby
areas. Local persons will be hired for meeting the requirement of trucks loading, plantation,
construction of check dams, retaining walls etc. The benefits due to Quarry to the local
population will be in the form of Direct and indirect employment opportunities.
All the basic facilities like tap water, sanitation & drinking water, lunch space is
provided within premises.
First aid box, free medicines & doctor service (on call basis) is provided.
12
6. PROPOSED INFRASTRUCTURE
1. Industrial Area Nil
2. Residential Area Yes
3. Connectivity Well connected
4. Drinking Water Management Yes
5. Solid Waste Management Yes
13
7. REHABILITATION AND RESETTLEMENT PLAN
After the mining activity, quarried area Converted to water storage and plantation,
tress will be planted for the protection and conservation of environment and nature. And also,
the area will have reclaimed with planting native vegetation, crops / trees with monitoring for
success. The Quarrying pits after extraction of the Granite Building Stone will be reclaimed
by suitable afforestation techniques and portion of the pit may be left as water reservoir &
storage of rain water shall help in recharging the ground water table and improve the water
regime of the area. Proper fencing of the lease area shall be taken up to avoid entry of
animals & trespassing into the lease area and also such that the same is also useful to the local
community.
During the afforestation work, the combination of different species shall be done. This
selection shall be made on the basis of the local plant growth in the surrounding areas. It is
always better to plant mixed species together. Guidance from the local forest department shall
be taken in the selection of species and their maintenance. The plantation work requires
considerable quantities of seeds, seedlings and saplings of different species; Nursery stock for
this plantation will be available from the local forest and horticulture department.
As far as Quarry area is concerned, so far none of the proposed Quarry area is
matured or completely exhausted as this is a new lease in the process of grant. Hence, the
measures like Retention walls, drainage system and afforestation works etc., shall be taken
up.
14
8. PROJECT SCHEDULE & COST ESTIMATES
8.1 LIKELY DATE OF START OF ESCAVATION AND LIKELY DATE OF
COMPLETION
Mr. Rajesh Roy. Owned the mining area. Calculation for 5years and mining plan
prepared for 5 year only. Especially the mine life is 5 years.
8.2 PROJECT COST ESTIMATION
Sr. No Machine Type Required No of m/c Estimated cost in
Lakhs
1 Excavator 2 3600000.00
2 Rock Breaker 1 600000.00
3 Air Compressor 1 600000.00
4 Tippers/ trucks 4 2800000.00
5 Jack-Hammer 4 120000.00
The return on the investment is by way of sale of mineral (Granite Building Stone).
All the minerals shall be marketed. The machinery is of the Company and additional required
if any shall be on hire basis as per the requirement for production.
15
9. ANALYSIS OF PROPOSAL
9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE
BENEFIT TO THE LOCAL PEOPLES.
No tribal population exists within 10 km radius of project area.
Due to proposed project it is expected that employment will increase for people who reside
nearby project area. Approx. 14 men will get employment directly.
Due to increase in raw material and product transportation activity, indirect
employment will generate.
As local people will get job, their living status will increase.
Due to rain water harvesting system, water table level in project area will increase
which is beneficial to surrounding farmers.
16
FINAL RECOMMENDATION
The quarrying area of land is own land. The financial estimates reveal high rate of
returns and the project is economically viable. The estimates have also taken into
consideration the occupational health, environmental conservation with protective measures,
social welfare etc.
Rajesh Roy
Place: Alanad
Date: 06 .06. 17