Pre-Construction Information Meeting
CTH PD, McKee Road(Meriter Way – Maple Grove Drive)
April 26, 2017
![Page 2: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/2.jpg)
Project Overview
CTH PD Project Corridor:2017 Construction Year$10.3 million Awarded Contract
CTH M Project Corridor:2017-2019 Construction Year
![Page 3: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/3.jpg)
CTH M Project Corridor Schedule• 2010 – 2011
– Pleasant View Rd / Valley View Rd
• 2012 – 2014– CTH M & S
• 2017 – 2019– CTH PD
• 2017 – 2019– Mid Town Rd
![Page 4: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/4.jpg)
Project Purpose & Need• Poor Pavement Condition• Congestion (Corridor & Intersections)
• Substandard Bike/Pedestrian Accommodations• Substandard Sight Distance and Steep Grades• Deficient Operations at Intersections
![Page 5: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/5.jpg)
Proposed ImprovementsReconstruct Pavement
Meriter Way – High Point Road
High Point Road – Maple Grove Drive
![Page 6: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/6.jpg)
Proposed ImprovementsIncrease Sight Distance and Reduce Vertical Grades
11’
![Page 7: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/7.jpg)
Proposed ImprovementsIce Age National Scenic Trail & Ice Age Junction Path
![Page 8: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/8.jpg)
Proposed ImprovementsHigh Point Road Intersection
– High Point Additional Lane• Future Southbound Dual Left Turn
– Median for Refuge & Safety
– CTH PD Left Turn Lanes• Extend Eastbound• Add Westbound
– Replace Traffic Signals• Countdown Timers
– Bus Pads
– Realigned Parking Lot Driveway
![Page 9: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/9.jpg)
Proposed ImprovementsMuir Field / Country Grove Intersection
– Muir Field / Country Grove Left Turn Lanes• Add Northbound & Southbound
– Box Culvert Extension• Badger Mill Creek
– CTH PD Left Turn Lanes• Add Westbound & Eastbound
– New Traffic Signals• Countdown Timers
– Bus Pads and Pull-Outs
– Median for Refuge & Safety
– Crosswalks• All Legs of Intersection
![Page 10: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/10.jpg)
Proposed ImprovementsJ-Turn Access between Muir Field and Silverton Trail
![Page 11: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/11.jpg)
Proposed ImprovementsMaple Grove Drive Intersection
– Maple Grove Additional Lane• Southbound Through Lane
– Modify Traffic Signals• Countdown Timers• Future Accommodation of NB Lt Turn Arrow• Future Accommodation of EB Lt Turn Arrow
– Bus Pads
![Page 12: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/12.jpg)
Proposed ImprovementsIce Age Trail & Ice Age Junction Path Bridge Structure over CTH PD
Cannonball Path over Madison Beltline
CTH PD (Looking West)
![Page 13: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/13.jpg)
Proposed ImprovementsDrainage / Storm Water
– Badger Mill Creek Storm Detention– Storm Sewer System
Utility– Sanitary Sewer– Water Main– Street Lighting– American Transmission Company– Madison Gas & Electric
Real Estate Acquisition– Right-of-Way– Temporary Easements – Permanent Easements
![Page 14: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/14.jpg)
Project CoordinationConstruction
– Access to Business and Residential Properties– Monthly meetings with business/property owners s– Notify business/property owners in advance of
closure or restriction of access– Rock Blasting– Overnight Detour for Structure Construction – Special Events (PGA Champions Golf Tournament,
WI Ironman, Epic UGM)
![Page 15: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/15.jpg)
Construction StagingHoffman Construction
![Page 16: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/16.jpg)
Project Website & NotificationsProject Website Information & Subscribe to Email Updates:
http://www.cityofmadison.com/engineering/projects/county-highway-pd
EmailUpdates
![Page 17: Pre-Construction Information Meeting · • 2012 – 2014 – CTH M & S • 2017 – 2019 – CTH PD • 2017 – 2019 – Mid Town Rd. Project Purpose & Need • Poor Pavement Condition](https://reader034.fdocuments.us/reader034/viewer/2022050505/5f96f87b4aa6ae43d56495f3/html5/thumbnails/17.jpg)
Questions or Comments?Construction Contacts:
Chris Petykowski, P.E. Chad RascheinCity of Madison Engineering CGC, inc.608-267-8678 [email protected] [email protected]