PPT - Mining Metallurgy and Exploration - SME

26
Heat Study and Modelling of Future Climatic Conditions at Coleman/McCreedy East Mine – Vale Inco • Charles Kocsis & Stephen Hardcastle CANMET-MMSL, Sudbury, Canada • Brian Keen Vale Inco, Coleman/McCreedy East Mine, Levack, Canada

Transcript of PPT - Mining Metallurgy and Exploration - SME

Page 1: PPT - Mining Metallurgy and Exploration - SME

Heat Study and Modelling of Future Climatic Conditions at Coleman/McCreedy East Mine – Vale Inco

• Charles Kocsis & Stephen HardcastleCANMET-MMSL, Sudbury, Canada

• Brian KeenVale Inco, Coleman/McCreedy East Mine, Levack, Canada

Page 2: PPT - Mining Metallurgy and Exploration - SME

Objectives

• Perform climatic survey quantify changes in TDB, TWB, RH and Barometric Pressure of the intake air from surface to the 4810L, through a Cut &Fill stoping area and to the exhaust system of the 153 Orebody

• Evaluate the heat load added to the intake air by auto-compression, strata, fans and mining equipment

• Predict the climatic conditions for the deepest operating level (5700L) within the future 170 Orebody

• Predict the climatic conditions along this future orebody’s main haulage ramp – an exhaust airway ascending from 5700L to 5100L

Page 3: PPT - Mining Metallurgy and Exploration - SME

Methodology

• Perform a climatic survey collect data determine the heat load added to the mine environment

• Perform mine activity monitoring to differentiate between constant (i.e. strata) and transient (i.e. mining equipment) heat sources

• Develop a climatic model of the mine’s intake system and the C&F stopes on the 4810L (153 Orebody) validate simulation data against field data

• Transpose climatic model to the 5700L (future 170 Orebody) with intake airflow, BP and VRT entered for this deeper level predict climatic conditions on 5700L

• Extend climatic model to include the ramp system between 5700L and 5100L predict climatic conditions

Page 4: PPT - Mining Metallurgy and Exploration - SME

Coleman/McCreedy East Mine• Two Alphair 11200-AMF-

6600 (880 RPM) in parallel

• Power: 1,118 kW (1500hp) each

• Two Joy 72-26-880RPM (Series 2000 )-100hp each

Page 5: PPT - Mining Metallurgy and Exploration - SME

No.1 Intake Shaft

Two 1120 kW (1500 hp) Alphair 1120-AMF-6600 (880RPM) in Parallel Arrangement

Two Exhaust Fans in Parallel Arrangement

Page 6: PPT - Mining Metallurgy and Exploration - SME

Environmental Data Collection

• Eleven ACR data loggers were installed along the intake system (surface-4810L) & across the C&F production area

• These pocket units continuously recorded TDB, RH and BP, 24 hrs/day at 1-minute intervals TWB were calculated using standard equations

• An infrared (Raytek MX) was used to measure wall surface temperatures along the access drifts and stope area

• Kerstel 4000 Pocket Weather Tracker was used for spot measurements within the C&F production stopes

• Environmental data was downloaded to a mobile computer at the end of every production shift

Page 7: PPT - Mining Metallurgy and Exploration - SME

Installation of ACR Units On 4810L (#4 Mining Block)

Page 8: PPT - Mining Metallurgy and Exploration - SME

Mine Activity Tracking on 4810L(#4 Mining Block)

• During 14-day survey on day-shifts, drilling, bolting/screening, explosive loading, blasting and mucking were monitored and recorded

• Data included type and location of activity, start & finish times, mining equipment used, duration of scheduled (i.e. lunch) & unscheduled (i.e. equipment breakdowns) production delays

• The operational status (On/Off) of the auxiliary fan was also recorded

• The air volumes at the flexible duct discharge to each individual C&F stope was measured for every production arrangement

Activity/Equipment Equipment Information

Drilling:Mini-Jumbo

34 kW (45 hp) diesel,37 kW electrical motor,2.2 kW compressor motor

Bolting/Screening:Jacklegs

Compressed air system

Mucking-Small LHD:moving blasted ore from the face of the 3W, 2W, 2WB stopes to the remuck bay

2.5 yd3 – 86 kW diesel

Mucking-Large LHD:moving ore from the remuck bay to the 4810 level ore pass

8 yd3 – 250 kW diesel6 yd3 – 200 kW diesel

Miscellaneous Vehicles Utility – 37 kW dieselSmall truck – 32 kW dieselFork lifts: 33 & 37 kW dieselPersonnel – 100 kW diesel

Page 9: PPT - Mining Metallurgy and Exploration - SME

Mine Activity Tracking - Example

Task Codes: D – Drilling; GS – Ground Support; M – Mucking; L – Explosive Loading

Sub-Task Codes: DH – Drill Holes; IRB – Install Rock Bolts; MFB – Mucking from Face to Bay; MOB – Mucking from Bay to Ore pass; LH – Load Holes; WU – Wire Holes; CG – Clear and Guard; OW – Other Work; PREP – Prepare for Ground Support Activities; EI – Equipment inspection

Page 10: PPT - Mining Metallurgy and Exploration - SME

Environmental and ActivityData Analysis

• The TDB (0C), RH (%) and BP (kPa) data were compiled into daily electronic spreadsheets

• The psychrometric TWB (0C) was calculated for each individual set of measurements

• Within the spreadsheets the collected activity information, the status of the auxiliary fans and air volumes were also compiled

• Once combined it was possible to identify in temperature and humidity graphs where and when mining activity had an impact on the U/G environment

Page 11: PPT - Mining Metallurgy and Exploration - SME

Wet-Bulb, Dry-Bulb and RH in the C&F Production Stopes• During activities not requiring diesel/el. Equipment, stope background temp. were 28.50C & 23.50C

• During two scheduled production delays with aux. fan Off, TDB decreased from 28.5 to 26.90C & from 30 to 28.40C

• During bolting/screening (9:00-10:00) TDB, RH & WB remained fairly constant at 28.00C, 58% & 22.00C

• Elevated temp. occurred during concurrent mining activities (15:40–16:20). Most airflow directed to adjacent stope T

TD

B

DB

= 2

.9=

2.9

00 CC

TTDBDB = 3.5 = 3.500CC TTDBDB = 4.5 = 4.500CC

Page 12: PPT - Mining Metallurgy and Exploration - SME

Average DB and WB Temperatures at the Monitoring Locations (Surface – 4810L)

• Greatest temp. increase occurred between surface – intake to 4810L (TDB=+10.60C, TWB=+6.90C ) mainly due to auto-compression

• Booster fan delivering air to the 4810L produced TDB=+1.30C in the intake air

• The 150hp aux. fan delivering air to the mining block produced TDB=+2.50C

• TDB decreased along the aux. duct

(TDB=-0.50C) some of the fan heat was transferred to the 48” steel duct

• Within the stope area, on average TDB decreased by -2.50C. However TWB

increased by 0.40C evaporative cooling in the production area

LOCATION TDB

(C)ΔTDB

(C)TWB

(C)ΔTWB

(C)

Surface Intake 18.4 - 15.7 -

4810 Level Intake - Loc.10 29.0 +10.6 22.6 +6.9

48” Aux. Duct Intake - Loc.1 30.3 +1.3 22.9 +0.3

48” Aux. Duct after Fan - Loc.3 32.8 +2.5 23.1 +0.2

36” Auxiliary Duct - Loc.5 32.3 -0.5 22.9 -0.2

Aux. Pipe Discharge - Loc.7 31.9 -0.4 23.4 +0.5

Stope Face (3W/2W/2WB) - Loc.8

29.4 -2.5 23.8 +0.4

Stope Return - Loc.6 29.4 0 23.9 +0.1

Access Drift Return - Loc.4 29.4 0 23.9 0

Ventilation Drift Return - Loc.2 29.4 0 23.5 -0.4

Footwall Drift to RAR - Loc.9 29.1 -0.3 24.0 +0.5VRT4810L = 26.5 0C

Page 13: PPT - Mining Metallurgy and Exploration - SME

The Monitored EnvironmentalConditions in the Production Area

• Environmental monitoring data showed that TDB, TWB, RH changed quickly according to the mining activities

• Any elevated TDB and TWB returned to stope background conditions with the completion of the activity

• These changes were local as TDB and TWB remained fairly constant at the exhaust of the mining block (TDB=0.40C, TWB=0.90C)

• The highest TDB and TWB occurred during concurrent mining activities in adjacent C&F stopes (drilling & mucking)

• Working conditions in the production stopes were a function of the air volume delivered to each individual stope

Page 14: PPT - Mining Metallurgy and Exploration - SME

Climatic Modelling - #4 Mining Block (4810L)

• The climatic model of the #4 mining block (153 Orebody) developed using ClimsimTM

• Model based upon mine layouts and the following rock properties:

– VRT @ 1,466.5m (4810L) = 26.50C

– Geothermal Step: 63 m/0C

– Rock Conductivity 5.6 W/m0C

– Diffusivity: 2.5 x 10-6 m2/s

• Model developed by combining all airway segments from surface to 4810L and the C&F stopes

• Simulations showed some difficulties in replicating TDB/TWB in individual stopes with air volume being continually adjusted

• As a result & to allow simulation of concurrent activities in adjacent stopes, a “block” model combining all C&F stopes (2W, 2WB, 3W) was developed

VRT was provided by Vale Inco obtained from measurements in boreholes

Page 15: PPT - Mining Metallurgy and Exploration - SME

Example of Ventilation Parameters & Heat Sources used in the 4810L Model

• Air volume delivered by the auxiliary fan through the 1.2 m steel duct: Vd = 27.5 m3/s

• Combined air volume directed to the production stopes through flexible fabric ducts: Vs = 11.5 m3/s

• Depth = 1,466 m; Barometric Pressure: BP = 118 kPa

• Mini-Jumbo power characteristics: PElectrical = 37 kW; PDiesel = 34 kW; PCompressor= 2.2 kW

• Diesel LHD power characteristics: 2.5 yd3 (86 kW); 6.0 yd3 (200 kW); 8.0 yd3 (250 kW)

Page 16: PPT - Mining Metallurgy and Exploration - SME

Model Simulated TDB and TWB for the Active #4 Mining Block (4810L)

• Comparing simulation vs. average measured data only major difference is TDB/TWB at the face

• Simulations were set to represent concurrent activities in two adjacent stopes

LOCATIONTDB (C)

SimulatedMeasured

ΔTDB (C)SimulatedMeasured

TWB (C)SimulatedMeasured

ΔTWB (C)SimulatedMeasured

48” Aux. Duct Intake – Location 1

30.330.3

_ 22.922.9

_

48” Aux. Duct after Fan – Location 3

32.932.8

+2.6+2.5

23.923.1

+1.0+0.2

Auxiliary Pipe Discharge – Location 7

31.931.9

-1.0-0.4

23.523.4

-0.4+0.5

Stope Face (3W/2W/2WB) –Location 8

33.029.4

+1.1-2.5

24.223.8

+0.7+0.4

Stope Return – Location 6

30.029.4

-3.00

24.323.9

+0.1+01

Access Drift Return – Location 4

29.929.4

-0.10

24.323.9

00

Ventilation Drift Return – Location 2

29.529.4

-0.40

24.123.5

-0.2-0.4

Footwall Drift to RAR – Location 9

29.129.1

-0.4-0.3

24.024.0

-0.1+0.5

Page 17: PPT - Mining Metallurgy and Exploration - SME

Climatic Modelling – Future 170 Orebody (5700L)

• The 4810L (Depth = 1,467m) climatic model was transposed to the 5700L (Depth = 1,738m) of the 170 Orebody

• Air volumes through the auxiliary ducting system, equipment & auxiliary fan heat sources were similar as within 4810L

• VRT entered according to the deeper 5700L (VRT5700L=30.8 0C)• However, to determine the starting TDB and TWB and barometric

pressure of the intake air to the 5700L additional modelling work was required

Page 18: PPT - Mining Metallurgy and Exploration - SME

Determining TDB, TWB and BP Through Climatic Modelling

43.6 m(143’)

1248 m(4094’)

3830’Level

Surface

# 1 Intake Shaft

Q = 486 m 3/s (1,030 kcfm )

Q = 349 m 3/s (739.5 kcfm)

Q = 217 m 3/s(460 kcfm )

Q = 165 m 3/s(350 kcfm)

Q = 165 m 3/s (350 kcfm)

Q = 71 m 3/s (150 kcfm)

Q = 165 m 3/s (350 kcfm)

288 m (945’)

259 m (850’)

131 m (430’)96 m (315’)

96 m (315’)

5.8 m diam.k = 0.0076 kg/m 3 (41 lb * min2 / ft4)

13’ diam. boreholek = 0.0055 kg/m 3 (30 lb * min2 / ft 4)

18’ x 17’ transfer driftk = 0.0129 kg/m 3 (70 lb * min 2 / ft4)

16’ x 17’ transfer driftk = 0.0129 kg/m 3 (70 lb * min 2 / ft4)

Q = 217 m 3/s(460 kcfm)

13’ diam. boreholek = 0.0055 kg/m 3 (30 lb * min2 / ft 4)

15.2 m (50’)

22.8 m (75’)

18’ x 17’ transfer driftk = 0.0129 kg/m 3 (70 lb * min2 / ft4)

Q = 165 m 3/s(350 kcfm )

13’ diam boreholek = 0.0055 kg/m 3 (30 lb * min2 / ft4)

2 Surface Fans in Parallel ArrangementP = 3,633 Pa (14.6”) Power = 2 x 1,118.5 = 2,237 kW

5475’ Level

5700’Level

5160 ’Level

4215’ Level

3970’ Level

Intake fresh Air System from Surface to the bottom of the 5700 Level FAR

18’ diam. Alimakk = 0.0129 kg/m 3

(70 lb * min2 / ft 4)L = 74.7 m (245”)

2 Booster Fans I Parallel ArrangementP = 1,244Pa (5.0 in. wg) Power = 2 x 298 kW (400hp)

16’ x 16’ transfer driftk = 0.0129 kg/m 3 (70 lb * min2 / ft4)

43.6 m(143’)

1248 m(4094’)

3830’Level

Surface

# 1 Intake Shaft

Q = 486 m 3/s (1,030 kcfm )

Q = 349 m 3/s (739.5 kcfm)

Q = 217 m 3/s(460 kcfm )

Q = 165 m 3/s(350 kcfm)

Q = 165 m 3/s (350 kcfm)

Q = 71 m 3/s (150 kcfm)

Q = 165 m 3/s (350 kcfm)

288 m (945’)

259 m (850’)

131 m (430’)96 m (315’)

96 m (315’)

5.8 m diam.k = 0.0076 kg/m 3 (41 lb * min2 / ft4)

13’ diam. boreholek = 0.0055 kg/m 3 (30 lb * min2 / ft 4)

18’ x 17’ transfer driftk = 0.0129 kg/m 3 (70 lb * min 2 / ft4)

16’ x 17’ transfer driftk = 0.0129 kg/m 3 (70 lb * min 2 / ft4)

Q = 217 m 3/s(460 kcfm)

13’ diam. boreholek = 0.0055 kg/m 3 (30 lb * min2 / ft 4)

15.2 m (50’)

22.8 m (75’)

18’ x 17’ transfer driftk = 0.0129 kg/m 3 (70 lb * min2 / ft4)

Q = 165 m 3/s(350 kcfm )

13’ diam boreholek = 0.0055 kg/m 3 (30 lb * min2 / ft4)

2 Surface Fans in Parallel ArrangementP = 3,633 Pa (14.6”) Power = 2 x 1,118.5 = 2,237 kW

5475’ Level

5700’Level

5160 ’Level

4215’ Level

3970’ Level

Intake fresh Air System from Surface to the bottom of the 5700 Level FAR

18’ diam. Alimakk = 0.0129 kg/m 3

(70 lb * min2 / ft 4)L = 74.7 m (245”)

2 Booster Fans I Parallel ArrangementP = 1,244Pa (5.0 in. wg) Power = 2 x 298 kW (400hp)

16’ x 16’ transfer driftk = 0.0129 kg/m 3 (70 lb * min2 / ft4)

18’ diam. Alimakk = 0.0129 kg/m 3

(70 lb * min2 / ft 4)L = 74.7 m (245”)

2 Booster Fans I Parallel ArrangementP = 1,244Pa (5.0 in. wg) Power = 2 x 298 kW (400hp)

16’ x 16’ transfer driftk = 0.0129 kg/m 3 (70 lb * min2 / ft4)

Simulations TDB = 35.3 0C; TWB = 24.4 0C; BP = 123 kPa

shardcas
Is the paper diagram this detailed
Page 19: PPT - Mining Metallurgy and Exploration - SME

Simulated TDB and TWB for the Future Mining Block on the 5700L

• Intake TDB/TWB at the 5700L increased by TDb = 5.00C & TWB = 1.50C due to additional booster fans (4215L) and auto-compression TDB now exceeds VRT = 30.80C

• The highest TDB & TWB in the production area would occur at the combined return from the stopes, namely 33.60C and 25.70C (for concurrent mucking & drilling in adjacent stopes)

LOCATIONTDB (C)5700L4810L

ΔTDB (C)5700L4810L

TWB (C)5700L4810L

ΔTWB (C)5700L4810L

48” Aux. Duct Intake – Location 1

35.330.3

_ 24.422.9

_

48” Aux. Duct after Fan – Location 3

37.832.9

+2.5+2.6

25.423.9

+1.0+1.0

Auxiliary Pipe Discharge – Location 7

36.231.9

-1.4-1.0

25.023.5

-0.4-0.4

Stope Face (3W/2W/2WB) –Location 8

TDB & TWB was much dependant to the air volume delivered to the individual C&F stopes

Stope Return – Location 6

33.630.0

-3.9-3.0

25.724.3

0+0.1

Access Drift Return – Location 4

33.429.9

-0.2-0.1

25.724.3

00

Ventilation Drift Return – Location 2

33.129.5

-0.3-0.4

25.624.1

-0.1-0.2

Footwall Drift to RAR – Location 9

32.829.1

-0.3-0.4

25.624.0

0-01

Page 20: PPT - Mining Metallurgy and Exploration - SME

• The 5700L model was extended to include two sections of the main haulage ramp (5700L - 5475L) and (5475L - 5100L)

• These two sections were considered worst-case-operational conditions

• Example of data used for the 5700L – 5475L ramp section:– Volume of air through this section: 71 m3/s– Intake airflow conditions from previous segment:

TDB=32.80C; TWB=25.60C

– Equipment: Two 2.5 yd3 LHD (2 x 86.5 kW); One 6yd3 LHD (231 kW); Two diesel trucks (2 x 223.5 kW)

• Total diesel power: 851 kW

Climatic Modelling – Main Haulage Ramp

Page 21: PPT - Mining Metallurgy and Exploration - SME

Climatic Modelling – Main Haulage Ramp

• Climatic simulations along the (5700L - 5475L) section of the ramp predicted: TDB = 36.8 0C & TWB = 27.2 0C

• TWB would only exceed the mine’s design criteria (TWB = 25.5 0C) if all mining equipment would operate at the same time for prolonged period of time

• Predicted TDB & TWB in the upper section (5475L - 5100L) had lower temperatures due to a higher air volume throughout this section

Page 22: PPT - Mining Metallurgy and Exploration - SME

Climatic Simulation Summary – 170 Orebody and Haulage Ramp

• Temperature conditions predicted for the intake air to the 5700L would be: TDB=35.3 0C and TWB=24.4 0C

• Changes between surface conditions (18.4 0C/15.7 0C) and 5700L TDB=+16.9 0C & TWB=+8.7 0C are mainly due to heat generated by auto-compression and main/booster fans

• During concurrent activities (11.5 m3/s), the highest temperature conditions would occur at the common return location from the C&F stopes: TDB=33.6 0C & TWB=25.7 0C

• Along the return airways the predicted temperatures decrease to TDB=32.8 0C/TWB=25.6 0C

• Across the 5700L, heat generated by auto-compression, fans and machinery is rejected into the cooler surrounding rock (VRT=30.80C)

• For the 5700L - 5475L section of the main haulage ramp under worst-case-scenario conditions TDB/TWB was predicted to reach 36.8 0C and 27.2 0C – if all potential equipment operate

Page 23: PPT - Mining Metallurgy and Exploration - SME

CONCLUSIONS

• A climatic model of a C&F mining area for the active 153 Orebody (4810L) was successfully developed based on mine layouts and the auxiliary ventilation setup

• Output data generated through simulations were compared and validated vs. measured data (environmental & activity monitoring)

• Environmental and activity monitoring showed concurrent mucking and drilling activities generating some of the highest temperatures

• Elevated temperatures also occurred when auxiliary ventilation was not immediately adjusted to meet changes in production activity (TDB=+9.40C/TWB=+3.50C)

• The climatic condition within the future 170 Orebody were predicted using the 4810L model transposed to the 5700L airflow intake TDB/TWB, BP, VRT entered for that deeper level (5700L)

Page 24: PPT - Mining Metallurgy and Exploration - SME

CONCLUSIONS – Continued

• Climatic simulations of the future 170 Orebody showed that with the simplified working area TWB = 25.50C would not be exceeded

• However, TWB could be exceeded in the individual C&F stopes depending on the mining activities and air volume delivered to the individual stopes

• The only area where TWB would be exceeded is along the 5700L – 5475L section of the haulage ramp – if all potential equipment would operate simultaneously

• Study showed that providing appropriate auxiliary ventilation distribution able to meet various operating requirements has the greatest role in maintaining adequate environmental conditions

Page 25: PPT - Mining Metallurgy and Exploration - SME

Acknowledgement

The authors would like to thank Vale Inco for their permission to present this work and recognize the Ventilation and Engineering Staff of Coleman/McCreedy East Mine for their support and cooperation in collecting data and technical information

Page 26: PPT - Mining Metallurgy and Exploration - SME

Thank You

Questions ?