Status as on 30.04.2012 S.No. Stretch State Name NH No Total Length (In Km) Completed Length (In Km) NHDP Phase Category LOA Date Concessionaire Funded By Present Status 1 Chitradurga -Tumkur Bypass(Approved Length 145 Km) Karnataka 4 114 42.335 NHDP Phase V May-2010 M/s IRB Infrastructure Developer Ltd BOT (Toll) Under Implementation 2 4 Laning of Barhi - Hazaribagh(Approved Length 40 Km) Jharkhand 33 41.314 5 NHDP Phase III May-2010 M/s Abhijeet Infrastructure Ltd-Corporate Ispat Alloy Ltd(JV) BOT (Toll) Under Implementation 3 Etawah -Chakeri (Kanpur) Uttar Pradesh 2 160.2 0 NHDP Phase V Nov-2011 Oriental Structural Engineers Ltd. BOT (Toll) Under Implementation 4 Agra-Etawah Bypass Uttar Pradesh 2 124.52 0 NHDP Phase V Nov-2011 Ramky Infrastructure Ltd. BOT (Toll) Under Implementation 5 Surat - Dahisar (Six lane) Gujarat[118.2]/Maharas htra[120.77] 8 239 229.1 NHDP Phase V Feb-2008 IRB Infrastructure Developers Ltd.- Deutsche Bank AG BOT (Toll) Under Implementation htra[120.77] Phase V Ltd.- Deutsche Bank AG (Toll) Implementation 6 Six Laning of Krishnagiri- walajhapet section Tamil Nadu 46 148.3 19 NHDP Phase V Mar-2010 Larsen & Toubro Ltd. BOT (Toll) Under Implementation 7 Six Laninig of Kishangarh – Udaipur-Ahmedabad Rajasthan[434.5]/Gujrat [121] 79A, 79 ,76 & 8 555.5 0 NHDP Phase V Sep-2011 GMR Infrastructure Ltd. BOT (Toll) Under Implementation 8 Gurgaon - Kotputli - Jaipur (Six lane) Haryana[64.3]/Rajastha n[161.3] 8 225.6 138.35 NHDP Phase V Feb-2008 Emirates Trading Agency LLC - KMC Construction Ltd. BOT (Toll) Under Implementation 9 Pune – Satara(Approved Length 145) Maharashtra 4 140.35 10 NHDP Phase V Jan-2010 Reliance Infrastructure Ltd - JTEG Consortium BOT (Toll) Under Implementation 10 Indore-Dewas(Approved Length 55 Km) Madhya Pradesh 3 45.05 10.9 NHDP Phase V Mar-2010 DLF-Gayatri BOT (Toll) Under Implementation 11 Delhi - Agra(Approved Length 180.3 Km) Haryana[74]/Uttar Pradesh[105.5] 2 179.5 0 NHDP Phase V May-2010 M/s Reliance Infrastructure Ltd BOT (Toll) Under Implementation 12 Chennai - Tada (Six lane) Tamil Nadu 5 43.4 7 NHDP Phase V Feb-2008 Larsen & Toubro Ltd. BOT (Toll) Under Implementation 13 Six Laning of Chandikhol-Jagatpur- Bhubaneswar(Approved Length 61 Km) Orissa 5 67 9.98 NHDP Phase V Apr-2010 SREI-Simplex-Galfar Consortium(Shree Jagannath Expressway pvt.ltd.) BOT (Toll) Under Implementation Six-laning of Barwa Adda- Jharkhand[43]/West NHDP BOT Under 14 Six-laning of Barwa Adda- Panagarh Jharkhand[43]/West Bengal[79.88] 2 122.88 0 NHDP Phase V May-2011 DSC Ltd. BOT (Toll) Under Implementation

Transcript of Ppp

Page 1: Ppp

Status as on 30.04.2012

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

1Chitradurga -Tumkur

Bypass(Approved Length 145 Km)Karnataka 4 114 42.335

NHDP

Phase VMay-2010

M/s IRB Infrastructure

Developer Ltd

BOT

(Toll)

Under

Implementation

2

4 Laning of Barhi -

Hazaribagh(Approved Length 40

Km)

Jharkhand 33 41.314 5NHDP

Phase IIIMay-2010

M/s Abhijeet Infrastructure

Ltd-Corporate Ispat Alloy

Ltd(JV)

BOT

(Toll)

Under

Implementation

3 Etawah -Chakeri (Kanpur) Uttar Pradesh 2 160.2 0NHDP

Phase VNov-2011

Oriental Structural Engineers

Ltd.

BOT

(Toll)

Under

Implementation

4 Agra-Etawah Bypass Uttar Pradesh 2 124.52 0NHDP

Phase VNov-2011 Ramky Infrastructure Ltd.

BOT

(Toll)

Under

Implementation

5 Surat - Dahisar (Six lane)Gujarat[118.2]/Maharas

htra[120.77]8 239 229.1

NHDP

Phase VFeb-2008

IRB Infrastructure Developers

Ltd.- Deutsche Bank AG

BOT

(Toll)

Under

Implementationhtra[120.77] Phase V Ltd.- Deutsche Bank AG (Toll) Implementation

6Six Laning of Krishnagiri-

walajhapet sectionTamil Nadu 46 148.3 19

NHDP

Phase VMar-2010 Larsen & Toubro Ltd.

BOT

(Toll)

Under

Implementation

7Six Laninig of Kishangarh –

Udaipur-Ahmedabad

Rajasthan[434.5]/Gujrat

[121]

79A, 79

,76 & 8555.5 0

NHDP

Phase VSep-2011 GMR Infrastructure Ltd.

BOT

(Toll)

Under

Implementation

8Gurgaon - Kotputli - Jaipur (Six

lane)

Haryana[64.3]/Rajastha

n[161.3]8 225.6 138.35

NHDP

Phase VFeb-2008

Emirates Trading Agency LLC -

KMC Construction Ltd.

BOT

(Toll)

Under

Implementation

9Pune – Satara(Approved Length

145)Maharashtra 4 140.35 10

NHDP

Phase VJan-2010

Reliance Infrastructure Ltd -

JTEG Consortium

BOT

(Toll)

Under

Implementation

10Indore-Dewas(Approved Length

55 Km)Madhya Pradesh 3 45.05 10.9

NHDP

Phase VMar-2010 DLF-Gayatri

BOT

(Toll)

Under

Implementation

11Delhi - Agra(Approved Length

180.3 Km)

Haryana[74]/Uttar

Pradesh[105.5]2 179.5 0

NHDP

Phase VMay-2010

M/s Reliance Infrastructure

Ltd

BOT

(Toll)

Under

Implementation

12 Chennai - Tada (Six lane) Tamil Nadu 5 43.4 7NHDP

Phase VFeb-2008 Larsen & Toubro Ltd.

BOT

(Toll)

Under

Implementation

13

Six Laning of Chandikhol-Jagatpur-

Bhubaneswar(Approved Length

61 Km)

Orissa 5 67 9.98NHDP

Phase VApr-2010

SREI-Simplex-Galfar

Consortium(Shree Jagannath

Expressway pvt.ltd.)

BOT

(Toll)

Under

Implementation

Six-laning of Barwa Adda- Jharkhand[43]/West NHDP BOT Under 14

Six-laning of Barwa Adda-

Panagarh

Jharkhand[43]/West

Bengal[79.88]2 122.88 0

NHDP

Phase VMay-2011 DSC Ltd.

BOT

(Toll)

Under

Implementation

Page 2: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

15

Bharuch to Surat Package BOT- II

(Six lane) 48.32(Six lane

completed ) 16.68 (Four lane

completed)

Gujarat 8 65 65NHDP

Phase VJul-2006 IDAA Infrastructure Pvt. Ltd.

BOT

(Toll)Completed

16 Samaikhiali-Gandhidham Gujarat 8A 56.16 0NHDP

Phase VJan-2010 Larsen & Toubro Ltd.

BOT

(Toll)

Under

Implementation

17 Ahmedabad to Vadodara Section Gujarat 8 102.3 0NHDP

Phase VApr-2011 IRB Infrastructure Ltd.

BOT

(Toll)

Under

Implementation

18 Varanasi-AurangabadBihar[135]/Uttar

Pradesh[57.4]2 192.4 10

NHDP

Phase VApr-2010 Isolux-Soma Consortium

BOT

(Toll)

Under

Implementation

19Six-Laning of Aurangabad-Barwa

Adda

Bihar[70]/Jharkhand[15

1.346]2 221.346 0

NHDP

Phase VMar-2012 KMC Constructions Ltd.

BOT

(Toll)

Under

Implementation

20Six Laning of Nellore-

ChilkaluripetAndhra Pradesh 5 183.52 31.675

NHDP

Phase VMay-2010 KMC-BSCPL Consortium

BOT

(Toll)

Under

Implementation

21Vadodara to Bharuch Package

BOT-1 (Six lane)Gujarat 8 83.3 83.3

NHDP

Phase VJul-2006

Larsen & Toubro Badodara

Bharuch Tollway Limited

BOT

(Toll)Completed

Four lanning of Ludhiyana- NHDP Essel Infra Projects Ltd.- Pan BOT Under 22

Four lanning of Ludhiyana-

Talwandi sectionPunjab 95 78 0

NHDP

Phase IIIDec-2010

Essel Infra Projects Ltd.- Pan

Indian Networks Ltd.

BOT

(Toll)

Under

Implementation

234-Laning of Solapur -

Maharashtra/ Karnatka SectionMaharashtra 9 100.06 0

NHDP

Phase IIIDec-2011 Coastal-SREI Consortium

BOT

(Toll)

Under

Implementation

24Belgaum-Dharwad(Approved

Length 111 Km)Karnataka 4 80 37.51

NHDP

Phase VMay-2010 Ashoka Buildcon

BOT

(Toll)

Under

Implementation

254/6 Laning of Maharastra/Goa

Border - Panaji Goa/KNT BorderGoa 17 139 0

NHDP

Phase IIIMay-2010

IVRCL Infrastructure &

Projects Ltd

BOT

(Toll)

Under

Implementation

26Rohtak - Bawal(Approved Length

97 Km)Haryana 71 82.553 45

NHDP

Phase IIIFeb-2010 JMC-SREI(JV)

BOT

(Toll)

Under

Implementation

27Panipat - Rohtak(Approved

Length 73 Km)Haryana 71A 80.858 53

NHDP

Phase IIIJan-2010 Sadbhav Engineering Ltd

BOT

(Toll)

Under

Implementation

28 Ambala - Zirakpur Haryana[6]/Punjab[30] 21, 22 36 36NHDP

Phase IIIJun-2005

GMR Energy Ltd. & GMR

Infrastruture Ltd. Consortium

BOT

(Toll)Completed

29 Panji-Goa/Karnatka Border Goa 4A 69 0NHDP

Phase IIIJan-2010 IRB-MRM Consortium

BOT

(Toll)

Under

Implementation

30 Kondhali - Telegaon Maharashtra 6 50 50NHDP

Aug-2005

Oriental Structural Engineers

Pvt. Ltd.- Delhi Brass BOT

Completed30 Kondhali - Telegaon Maharashtra 6 50 50NHDP

Phase IIIAug-2005 Pvt. Ltd.- Delhi Brass

Consortium

BOT

(Toll)Completed

Page 3: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

31 Trichy - Karur Tamil Nadu 67 79.7 69.5NHDP

Phase IIIMar-2007 Reliance Energy Limited

BOT

(Toll)

Under

Implementation

324-lanning of Kannur Vengalem

Kuttipuram (Package -II)Kerala 17 81.5 0

NHDP

Phase IIIJul-2009 KMC Construction Ltd.

BOT

(Toll)

Under

Implementation

33KNT/Kerala Border to Kanuur

Section(Approved Length 286.3)Kerala 17 126.6 0

NHDP

Phase IIIMay-2010

M/s Transstry-OJSC

Consortium

BOT

(Toll)

Under

Implementation

344-lanning of Kannur Vengalem

Kuttipuram (Package -I)Kerala 17 83.2 0

NHDP

Phase IIIJul-2009 KMC Construction Ltd.

BOT

(Toll)

Under

Implementation

35Chilkaluripet - Vijayawada (Six

lane)Andhra Pradesh 5 82.5 23.66

NHDP

Phase VFeb-2008

IJM Corporation Berhad -

IDFC Ltd.

BOT

(Toll)

Under

Implementation

36End of Durg Bypass - Chattisgarh

/ Maharashtra BorderChattisgarh 6 82.685 82

NHDP

Phase IIIDec-2006 Ashoka - IDFC Consortium

BOT

(Toll)

Under

Implementation

NHDP Hindustan Construction BOT Under 37 4 Laning of Raiganj-Dalkola West Bengal 34 50 0

NHDP

Phase IIIFeb-2010

Hindustan Construction

Company Ltd.

BOT

(Toll)

Under

Implementation

38 Vadodara-Surat Section Gujarat 8 6 0NHDP

Phase VApr-2012 HCC Concessions Ltd.

BOT

(Toll)

Under

Implementation

39

Tirupati -Tiruthani -

Chennai(Approved Length 125.5

Km)

Tamil

Nadu[61.47]/Andhra

Pradesh[63.23]

205 124.7 16NHDP

Phase IIIApr-2010

Transstroy -OJSC

Consortium(JV)

BOT

(Toll)

Under

Implementation

404 Laning of Gomti Chauraha -

UdaipurRajasthan 8 79.31 0

NHDP

Phase IVMar-2012 Sadbhav Engineering Limited

BOT

(Toll)

Under

Implementation

41Hyderabad-Yadgiri (Approved

Length 30)Andhra Pradesh 202 35.65 32.09

NHDP

Phase IIIDec-2009

Sadbhav Engineering Ltd.

(Hyderabad-Yadgiri Tollways

Pvt. Ltd.)

BOT

(Toll)

Under

Implementation

42Ghaziabad-Aligarh (Approved

Length 106 )Uttar Pradesh 91 126 25.5

NHDP

Phase IIIDec-2009

SREI - PNC - GALFAR

Consortium

BOT

(Toll)

Under

Implementation

43 Meerut-Muzaffarnagar Uttar Pradesh 58 79 79NHDP

Phase IIIMar-2005

Nagarjuna Construction Co.

Ltd. - MAYTAS Consortium

BOT

(Toll)Completed

44Muzaffarnagar - Haridwar

(Approved Length 77 )

Uttar

Pradesh[21]/Uttarancha

l[59]

58, 72 80 0NHDP

Phase IIIDec-2009 ERA-SIBMOST

BOT

(Toll)

Under

Implementation

6-Laning of Dhankuni-Khargpur NHDP BOT Under 45

6-Laning of Dhankuni-Khargpur

SectionWest Bengal 6 111.4 0

NHDP

Phase VFeb-2011 Ashoka Buildcon Ltd.

BOT

(Toll)

Under

Implementation

Page 4: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

46 Badarpur Elevated Highways Delhi[2.7]/Haryana[1.7] 2 4.4 4.4NHDP

Phase VJun-2008 BFTL

BOT

(Toll)Completed

47 Panipat - Jalandhar (Six lane)Haryana[116]/Punjab[17

5.1]1 291 215.93

NHDP

Phase VFeb-2008

Isolux Corsan Concesionnes

Sa - Corsan Corviam

Constructions SA - Soma

Enterprise Ltd

BOT

(Toll)

Under

Implementation

48 Pondicherry - Tindivanam Tamil Nadu 66 38.61 38.61NHDP

Phase IIIMar-2007 Maytas - NCC Consortium

BOT

(Toll)Completed

49 Nellore - Tada (AP-7) Andhra Pradesh 5 110.517 110.517NHDP

Phase IAug-2001 CIDBI Malaysia

BOT

(Toll)Completed

50Krishnagiri to Thopurghat (NS-

2/TN1)Tamil Nadu 7 62.5 62.5

NHDP

Phase IISep-2005

Larsen & Toubro Ltd. (M/S L &

T Krishnagiri Thopurghat Toll

Road Pvt. Ltd.)

BOT

(Toll)Completed

51

Four laning from

MP/Maharashtra border to

Nagpur I/C Kamptee Kanoon and Maharashtra 7 95 58.5

NHDP

Phase IIAug-2009

Oriental Structural Engineers

Ltd.

BOT

(Toll)

Under

Implementation51

Nagpur I/C Kamptee Kanoon and

Nagpur bypass

Maharashtra 7 95 58.5Phase II

Aug-2009Ltd. (Toll) Implementation

52 Thrissur to Angamali (KL-I) Kerala 47 40 40NHDP

Phase IISep-2005

KMC Construction Ltd. - SREI

(JV) [Guruvayoor

Infrastructure Pvt. Ltd.]

BOT

(Toll)Completed

53Panipat Elevated Highway (Six

lane)Haryana 1 10 10

NHDP

Phase IIJun-2005 Larsen & Toubro Ltd.

BOT

(Toll)Completed

54

Armur to Kadloor Yellareddy (NS-

2/AP-1) (Approved

Length 60.25)

Andhra Pradesh 7 59 58.89NHDP

Phase IIMay-2009 Navyouga KPCL Consortium

BOT

(Toll)

Under

Implementation

55Farukhanagar to Kotakatta (NS-

2/AP-4)Andhra Pradesh 7 55.74 55.74

NHDP

Phase IISep-2005

Larsen & Toubro Ltd. (L & T

Western Andhra Tollways Pvt.

Ltd.)

BOT

(Toll)Completed

56Farukhanagar to Kottakata (NS-

2/AP-3)Andhra Pradesh 7 46.162 46.162

NHDP

Phase IISep-2005

GMR Energy Ltd. & GMR

Infrastruture Ltd. Consortium

(GMR Jadcherla Expressways

Pvt. Ltd.)

BOT

(Toll)Completed

57 ROB at Kishangarh Rajasthan 8 1 1NHDP

Phase IMar-1998 MSK Projects (I) Ltd.

BOT

(Toll)Completed

Mahapura (near Jaipur) - NHDP Consortium of GVK BOT58

Mahapura (near Jaipur) -

Kishangarh (6 Lane)Rajasthan 8 90.38 90.38

NHDP

Phase IApr-2003

Consortium of GVK

International-BSCPL

BOT

(Toll)Completed

Page 5: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

59

4 Laning of UP/Haryana Border-

Yamunanagar-Saha-Barwala-

Panchkula

Haryana 73 107 0NHDP

Phase IIIMar-2012

Gammon Infrastructure

Projects Ltd.

BOT

(Toll)

Under

Implementation

60 Satara - Kagal Maharashtra 4 133 133NHDP

Phase IFeb-2002 MSRDC Ltd. Mumbai

BOT

(Toll)Completed

61 Karur to Madurai (TN-4) Tamil Nadu 7 68.125 68.13NHDP

Phase IISep-2005

Madhucon Projects Ltd. - SREI

[TN(DK) Expressways Ltd.]

BOT

(Toll)Completed

62

Elevated Highway from Silk

board junction to electronic city

junction

Karnataka 7 9.98 9.98NHDP

Phase IIIDec-2005

SOMA - NCC - MAYTAS

Consortium

BOT

(Toll)Completed

63Vivekananda Bridge and

ApproachWest Bengal 2 6 6

NHDP

Phase ISep-2002

SVBTG Consortium of Pacific

Alliance Inc -PBIDC - STRADEC

Inc- CES & L & T

BOT

(Toll)Completed

64 Padalur - Trichy (Pkg - VI-C) Tamil Nadu 45 38.427 38.427NHDP

Phase IIFeb-2006

Navayuga - Indu - Abhisek

Consortium (Indu Navayuga

Infras. Pvt. Ltd.)

BOT

(Toll)Completed

Phase IIInfras. Pvt. Ltd.)

(Toll)

65 Ulundurpet - Padalur (Pkg- VI-B) Tamil Nadu 45 93.89 93.89NHDP

Phase IIFeb-2006

IJM - Sapoorji Pallonji (JV)

(Trichy tollway Pvt. Ltd.)

BOT

(Toll)Completed

66Tindivanam - Ulundurpet (Pkg -VI-

A)Tamil Nadu 45 72.9 72.9

NHDP

Phase IIFeb-2006

GMR Infras. Ltd. - GMR

Energy Ltd.(GMR Ulundrupet

Expr. Pvt. Ltd.)

BOT

(Toll)Completed

67Delhi - Gurgaon Section (Access

Controlled 8/6 Lane)Delhi[9.7]/Haryana[18] 8 27.7 27.7

NHDP

Phase IApr-2002

Jaiprakash Industries Ltd. - DS

Constt. Ltd.

BOT

(Toll)Completed

68 Nandigama - Vijayawada Andhra Pradesh 9 35 35NHDP

Phase IAug-2001 CIDBI Malaysia

BOT

(Toll)Completed

69 Durg Bypass Chattisgarh 6 18 18NHDP

Phase IMar-1999 Shakti Kumar M. Sancheti Ltd.

BOT

(Toll)Completed

70 4 Laning of Solapur - BijapurMaharashtra[35]/Karnat

aka[75.542]13 110.542 0

NHDP

Phase IIIMar-2012 Sadbhav Engineering Limited

BOT

(Toll)

Under

Implementation

71

Rehabitation and Upgradation to

Birmitrapur to Barkote (4 Lane-

75.66 Km)-(2 Lane-49.955 Km)

Orissa 23 125.615 0NHDP

Phase IVMar-2012

Gammon Infrastructure

Projects Limited

BOT

(Toll)

Under

Implementation

72 Tumkur - Neelmangala Karnataka 4 32.5 32.5NHDP

Phase IJun-2002

Jas Toll Road Co. Ltd.

(Consortium of Jayaswals - BOT

(Toll)Completed72 Tumkur - Neelmangala Karnataka 4 32.5 32.5

Phase IJun-2002 (Consortium of Jayaswals -

Ashoka Buildcon-SERI Intl.)(Toll)

Completed

Page 6: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

73 Jabalpur to Lakhanadone Madhya Pradesh 7 80.82 0NHDP

Phase IVJul-2011 Gannon Dunkerley & Co. Ltd.

BOT

(Toll)

Under

Implementation

74Panikholi-Rimoli (Approved

Length 106 Km)Orissa 215 163 0

NHDP

Phase IIIAug-2011 Gayatri Projects Ltd.

BOT

(Toll)

Under

Implementation

75 4 Laning of Faraka-Raiganj West Bengal 34 103 23.83NHDP

Phase IIIFeb-2010

Hindustan Construction

Company Ltd.

BOT

(Toll)

Under

Implementation

76 4 Laning of Brahampore-Faraka West Bengal 34 103 30.57NHDP

Phase IIIFeb-2010

Hindustan Construction

Company Ltd.

BOT

(Toll)

Under

Implementation

77 Rampur - Kathgodam Uttaranchal 87 93.226 0NHDP

Phase IIINov-2011

ERA Infra Engineering Ltd.-

OJSC-SIBMOST (JV)

BOT

(Toll)

Under

Implementation

78Rajkot Bypass & Gondal Jetpur

(Package-VII)Gujarat 8B 36 36

NHDP

Phase IIMar-2005 West Gujrat Expressway Ltd.

BOT

(Toll)Completed

79 4-Laning of Angul - Sambalpur Orissa 42 153 0NHDP

Phase IVNov-2011 Abhijit Roads Ltd.

BOT

(Toll)

Under

Implementation

80 4-Laning of Cuttak - Angul Orissa 42 112 0NHDP

Phase IIINov-2011 Ashoka Buildcon

BOT

(Toll)

Under

Implementation

81Four laning of Orissa/Chattisgarh

Boarder - Aurang sectionChattisgarh 6 150.4 0

NHDP

Phase IVAug-2011 BSCPL Infrastructure Limited

BOT

(Toll)

Under

Implementation

82 4-Laning of Raipur - Bilaspur Chattisgarh 200 126.525 0NHDP

Phase IVNov-2011 IVRCL Assets Holding Ltd.

BOT

(Toll)

Under

Implementation

83 Four laning of Shivpuri-Dewas Madhya Pradesh 3 330.21 0NHDP

Phase IVSep-2011

GVK Transportations Network

Ltd.

BOT

(Toll)

Under

Implementation

84 Salem to Karur (NS-2/TN-2) Tamil Nadu 7 41.55 41.55NHDP

Phase IISep-2005

MVR - MRK - JTEC (JV) [MVR

infrastructure & Tollway Pvt

Ltd.]

BOT

(Toll)Completed

85Four laning of Jabalpur-Katni-

Rewa SectionMadhya Pradesh 7 225.686 0

NHDP

Phase IVAug-2011 SOMA Tollways Pvt. Ltd.

BOT

(Toll)

Under

Implementation

86 Salem to Karur (NS-2/TN-3) Tamil Nadu 7 33.48 33.48NHDP

Phase IISep-2005

Reliance Energy Ltd. [NK Toll

Road Ltd.]

BOT

(Toll)Completed

87 Hospet - Chitradurga Karnataka 13 120.03 0NHDP

Phase IIINov-2011 Ramkey Infrasructure Ltd

BOT

(Toll)

Under

Implementation

88 MH/ KNT Border Sangareddy Karnataka 9 145 0NHDP

Phase IIINov-2011

L&T Infrasructure

Developement Projects Ltd

BOT

(Toll)

Under

Implementation

894-Laning of Hospet-Bellary-

Karnataka/AP BorderKarnataka 63 95.44 0

NHDP

Phase IVOct-2011

PNC Infratech Ltd.- BF Utility

Ltd. ConsortiumL

BOT

(Toll)

Under

Implementation89

Karnataka/AP BorderKarnataka 63 95.44 0

Phase IVOct-2011

Ltd. ConsortiumL (Toll) Implementation

Page 7: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

90New 4-Lane Elevated Road from

Chennai Port - MaduravoyalTamil Nadu 4 19 0

NHDP

Phase VIIJan-2009 Chennai Elevated Tollway std

BOT

(Toll)

Under

Implementation

91

Upgradation of Hyderabad-

Bangalore Section(Upgradation

on exixting Six Lane)

Karnataka 7 22.12 13.98NHDP

Phase VIIFeb-2010 Navayuga Engg Co.Ltd

BOT

(Toll)

Under

Implementation

92

Chengapalli to Coimbatore

Bypass and End of Coimbatore

Bypass to TN/Kerala Border

Tamil Nadu 47 54.83 33NHDP

Phase IIJan-2010

IVRCL Infrastructure &

Projects Ltd

BOT

(Toll)

Under

Implementation

93Salem to Kerala Border Section

(TN-7)Tamil Nadu 47 48.51 48.51

NHDP

Phase IISep-2005

IVRCL Infrastructure Projects

Ltd. (Kumar Palayam Tollway

Ltd.)

BOT

(Toll)Completed

94Salem to Kerala Border Section

(TN-6)Tamil Nadu 47 53.525 53.525

NHDP

Phase IISep-2005

IVRCL Infrastructure Projects

Ltd. ( Salem Tollways Ltd.)

BOT

(Toll)Completed

(TN-6) Phase II Ltd. ( Salem Tollways Ltd.) (Toll)

95 Karur to Madurai (TN-5) Tamil Nadu 7 53.025 53.03NHDP

Phase IISep-2005

Reliance Energy Ltd. [DS Toll

Road Ltd.]

BOT

(Toll)Completed

964-Laning of Rohtak-Jind

(Approved Length 45 Km)Haryana 71 48.6 0

NHDP

Phase IIIDec-2011 Vijai Infrastructure Ltd.

BOT

(Toll)

Under

Implementation

97 Four laning of Gwalior-Shivpuri Madhya Pradesh 3 125.03 0NHDP

Phase IVSep-2011 Essel Infraprojects Ltd.

BOT

(Toll)

Under

Implementation

98 Panvel-Indapur Maharashtra 17 84 0NHDP

Phase IIIOct-2010

Supreme Infrastructure India

Ltd.-Mahavir Road &

Infrastructure Pvt. Ltd.-China

State Construction Engg.

Hongkong Ltd.

BOT

(Toll)

Under

Implementation

99Neelamangala Junction on NH 4

with NH 48 to DevihalliKarnataka 48 81 81

NHDP

Phase IIIApr-2007

Lanco Devihalli Highways Pvt.

Ltd.

BOT

(Toll)

Under

Implementation

100Devihalli-Hassan(Approved

Length 73 Km)Karnataka 48 77.23 11

NHDP

Phase IIIApr-2010 Larsen & Toubro Ltd.

BOT

(Toll)

Under

Implementation

101 Charthalai-ochira Kerala 47 83.6 0NHDP

Phase IIIJan-2010 ISOLUX-SOMA

BOT

(Toll)

Under

Implementation

102

Rimoli - Roxy -

Rajamunda(Approved Length

163Km)

Orissa 215 96 0NHDP

Phase IIIApr-2010 MBL-SREI

BOT

(Toll)

Under

Implementation163Km)

Phase III (Toll) Implementation

Page 8: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

103 Aurang - Raipur Chattisgarh 6 43.485 43.07NHDP

Phase IIIMar-2005

Apollo(UK) - JLI(UK) -

DSC(Indian) - LOR(UK)

Consortium

BOT

(Toll)

Under

Implementation

104Bhubneshwar-Puri(Approved

Length 59 Km)Orissa 203 67 0

NHDP

Phase IIIMay-2010

KSS-Valecha (Bhubneshwar

Expressway Pvt. Ltd.)

BOT

(Toll)

Under

Implementation

105 Trichy - Dindigul Tamil Nadu 45 88.273 88.273NHDP

Phase IIIMar-2007 Reliance Energy Limited

BOT

(Toll)Completed

106 Sitapur - Lucknow Uttar Pradesh 24 75 75NHDP

Phase IIIAug-2005

Apollo(UK) - JLI(UK) -

DSC(Indian) - LOR(UK)

Consortium

BOT

(Toll)Completed

107Muradabad-Bareily (Approved

Length 112)Uttar Pradesh 24 121 45

NHDP

Phase IIIDec-2009 IL & FS Transportation Ltd.

BOT

(Toll)

Under

Implementation

108 Vijayawada-Machhlipatnam Andhra Pradesh 9 64.611 0NHDP

Phase IIINov-2011 Madhucon Projects Ltd.

BOT

(Toll)

Under

Implementation

109Kundapur-Surathkal & Mangalore-

Karnataka 17 90 32NHDP

Nov-2009 Navayuga - KPCL ConsortiumBOT Under

109Kundapur-Surathkal & Mangalore-

KNT/Kerala BorderKarnataka 17 90 32

NHDP

Phase IIINov-2009 Navayuga - KPCL Consortium

BOT

(Toll)

Under

Implementation

110 Thanjarur - Trichy Tamil Nadu 67 56 54.2NHDP

Phase IIIFeb-2006 Madhucon Projects Ltd.

BOT

(Toll)

Under

Implementation

111Beawar-Pali-Pindwara (Approved

Length - 246 Km)Rajasthan 14 244.12 0

NHDP

Phase IIIMay-2011

L&T Infrastructure

Development Projects Ltd.

BOT

(Toll)

Under

Implementation

112Jaipur-Tonk - Deoli(Approved

Length 148.77 Km )Rajasthan 12 150 85

NHDP

Phase IIIOct-2009 IRB-MRM Consortium

BOT

(Toll)

Under

Implementation

113 Deoli - Kota Rajasthan 12 83 7NHDP

Phase IIIApr-2010

GVK Development Projects

Pvt Ltd

BOT

(Toll)

Under

Implementation

114 Kota - Jhalawar Rajasthan 12 88.09 0NHDP

Phase IIIApr-2011 Keti Constructions Ltd.

BOT

(Toll)

Under

Implementation

115Jaipur-Reengus(Approved Length

52.65 Km )Rajasthan 11 54 39

NHDP

Phase IIIOct-2009 RIL-AAA- JTEG Consortium

BOT

(Toll)

Under

Implementation

116 Mahua-Jaipur Rajasthan 11 108 108NHDP

Phase IIIMar-2005 JMTPL(I) Corporation Project

BOT

(Toll)Completed

117 Bharatpur-Mahua Rajasthan 11 57 57NHDP

Phase IIIMar-2005 Madhucon Projects Ltd. - SREI

BOT

(Toll)Completed

118 Agra - Bharatpur

Uttar

Pradesh[24.75]/Rajastha

n[20.25]

11 45 45NHDP

Phase IIIJul-2005

Oriental Structural Engineers

Pvt. Ltd.- Delhi Brass

Consortium

BOT

(Toll)Completed

n[20.25]Phase III

Consortium(Toll)

119 Delhi/Haryana Border to Rohtak Haryana 10 63.49 58NHDP

Phase IIIJul-2007 KCT - ERA consortium

BOT

(Toll)

Under

Implementation

Page 9: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

120 Kudapa-Mydukur-Kurnool Andhra Pradesh 18 188.752 78NHDP

Phase IIIFeb-2009

KMC Construction Ltd. - IVRCL

Consortium

BOT

(Toll)

Under

Implementation

1212-Laning with paved sholder of

Muzaffarpur - BarauniBihar 28 107.56 0

NHDP

Phase IVOct-2011 KNR

BOT

(Toll)

Under

Implementation

122 4-Laning of Hoskote-Dobbaspet Karnataka 207 80.02 0NHDP

Phase IVMar-2012 Transstroy-OJSC Consortium

BOT

(Toll)

Under

Implementation

1234-Laning of Punjab/Haryana

Border-JindHaryana 71 68 0

NHDP

Phase IIIMar-2012 Unity Infraprojects Ltd.

BOT

(Toll)

Under

Implementation

1244-Laning of Jalgaon-

Maharashtra/Gujrat BorderMaharashtra 6 208.844 0

NHDP

Phase IVMar-2012

L&T Infrastructure

Development Projects Ltd.

BOT

(Toll)

Under

Implementation

125 4-Laning of Amravati-Jalgaon Maharashtra 6 275.225 0NHDP

Phase IVMar-2012

L&T Infrastructure

Development Projects Ltd.

BOT

(Toll)

Under

Implementation

126Six-Laning og Anandapuram-

Visakapatnam-AnakapalliAndhra Pradesh 5 58.222 0

NHDP

Phase VMar-2012

Transstroy (India) Ltd.-OJSC

Corporation Transstroy-

Cosortium

BOT

(Toll)

Under

Implementation

127Six-Laning of Gundugolanu

RajamundryAndhra Pradesh 5 120.741 0

NHDP

Phase VMar-2012

IVRCL Assests & Holding

Limited

BOT

(Toll)

Under

Implementation127

RajamundryAndhra Pradesh 5 120.741 0

Phase VMar-2012

Limited (Toll) Implementation

128 Vijayawada-Gundugolanu Section Andhra Pradesh 5 103.59 0NHDP

Phase VFeb-2012

Gammon Infrastructure

Projects Ltd.

BOT

(Toll)

Under

Implementation

1294 Laning of Obedullaganj-Betul

SectionMadhya Pradesh 69 125 0

NHDP

Phase IIIFeb-2012 Transstroy (India) Ltd.

BOT

(Toll)

Under

Implementation

130Four Laning of Kiratpur-Ner

Chowk SectionHimanchal Pradesh 21 84.32 0

NHDP

Phase IIIFeb-2012

IL & FS Transportation

Networks Ltd.

BOT

(Toll)

Under

Implementation

131

4 Laning of Ahmedabad to

Godhara (Approved Length 210

Km)

Gujarat 59 117.6 58.45NHDP

Phase IIIJan-2010

ESSEL Infra & CR-18

Consortium

BOT

(Toll)

Under

Implementation

1324-Laning of Mahulia to Behragora

to Kharagpur

West

Bengal[30]/Jharkhand[9

7]

33 & 6 127 0NHDP

Phase IVDec-2011

Simplex Infrastructure

Projects Ltd.

BOT

(Toll)

Under

Implementation

133

4 Laning of Godhara to Gujarat

/MP Border(Approved Length

210 Km)

Gujarat 59 87.285 5.517NHDP

Phase IIIJan-2010 BSPCL Ltd

BOT

(Toll)

Under

Implementation

134 4-Laning of Lucknow - Sultanpur Uttar Pradesh 56 125.9 0NHDP

Phase IVOct-2011 ESSAR - Atlanta (JV)

BOT

(Toll)

Under

Implementation

135Four laning of Meerut

BulandshaharUttar Pradesh 235 66.482 0

NHDP

Phase IVSep-2011 C & C Constructions Limited

BOT

(Toll)

Under

Implementation135

BulandshaharUttar Pradesh 235 66.482 0

Phase IVSep-2011 C & C Constructions Limited

(Toll) Implementation

136 2-Laning with PS Aligarh - Kanpur Uttar Pradesh 91 268 0NHDP

Phase IVDec-2010 Lanco Infratech Ltd.

BOT

(Toll)

Under

Implementation

Page 10: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

1372-Laning with PS Raibariely to

AllahabadUttar Pradesh 24B 119 0

NHDP

Phase IVDec-2010

Vijay Infrastructure Ltd-Vijay

Construction(JV)

BOT

(Toll)

Under

Implementation

138 2-Laning with PS Kanpur - Kabrai Uttar Pradesh 86 123 0NHDP

Phase IVNov-2010 PNC

BOT

(Toll)

Under

Implementation

139 2-Laning with PS Agra - Aligarh Uttar Pradesh 93 79 0NHDP

Phase IVNov-2010 JMC Project

BOT

(Toll)

Under

Implementation

140 Six Laning of Hosur-Krishnagiri Tamil Nadu 7 59.87 2.39NHDP

Phase VMay-2010 Reliance Infrastructure Ltd

BOT

(Toll)

Under

Implementation

141Kandla - Mundra Port(Approved

Length 73 Km)Gujarat 8A 71.4 0

NHDP

Phase IIIJan-2010 Reliance Infra Projects Ltd.

BOT

(Toll)

Under

Implementation

142 Salem-Ulundrupet (BOT-1/TN-06) Tamil Nadu 68 136.357 134NHDP

Phase IIIMar-2007 Reliance Energy Limited

BOT

(Toll)

Under

Implementation

143Bareily - Sitapur(Approved Length

134 Km)Uttar Pradesh 24 151.2 0

NHDP

Phase IIIApr-2010 ERA-SIBMOST

BOT

(Toll)

Under

Implementation

144Six lanning of Vadakkancherry -

ThrissuresectionKerala 47 30 0

NHDP

Phase IIFeb-2009

KMC Construction Ltd.-

CR18G Consortium

BOT

(Toll)

Under

ImplementationThrissuresection Phase II CR18G Consortium (Toll) Implementation

145 4 Laning of Khagaria-Bakhtiarpur Bihar 31 112.982 0NHDP

Phase IIIMar-2012

Navayuga Engineering

Company Ltd.

BOT

(Toll)

Under

Implementation

146 Gonde-Vadape (Thane) Maharashtra 3 100 100NHDP

Phase IIIJun-2005

Gammon India Ltd. - Sadbhav -

Billimoria Consortium

BOT

(Toll)Completed

147 Pimpalgaon - Nasik - Gonde Maharashtra 3 60 47NHDP

Phase IIIJan-2009

Larsen & Toubro Ltd. - ABL

Consortium

BOT

(Toll)

Under

Implementation

148 Dhule - Pimpalgaon Maharashtra 3 118 118NHDP

Phase IIIMar-2005 IRCON-SOMA Consortium

BOT

(Toll)Completed

149 Zirakpur - ParwanooHaryana[20]/Himanchal

Pradesh[6.69]/Punjab[2]22 28.69 28.69

NHDP

Phase IIIFeb-2007

Jaiprakash Associates-

(Himalyan Expressways Pvt.

Ltd.)

BOT

(Toll)Completed

150Khalghat - MP/Maharashtra

BorderMadhya Pradesh 3 82.8 82.8

NHDP

Phase IIIOct-2007 Navyuga Engineering Co. Ltd.

BOT

(Toll)Completed

151Amritsar - Pathankot (Approved

Length 101Km)Punjab 15 106 31

NHDP

Phase IIIJul-2009 IRB-MRM Pvt Ltd.

BOT

(Toll)

Under

Implementation

152 MP/Maharashtra Border-Dhule Maharashtra 3 98 87NHDP

Phase IIIJan-2009

Hindustan Construction

Company Ltd. -Laing-Sadbhav

Consortium

BOT

(Toll)

Under

ImplementationPhase IIIConsortium

(Toll) Implementation

153 Kurali - Kiratpur Punjab 21 42.9 42.9NHDP

Phase IIIDec-2006 BSCPL - C & C Consortium

BOT

(Toll)Completed

Page 11: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

154 Jalandhar - Amritsar Punjab 1 49 49NHDP

Phase IIIMay-2005

IVRCL Infrastructure Projects

Ltd.

BOT

(Toll)Completed

155Indore-Jhabua-Gujrat/MP

(Approved Length 168)Madhya Pradesh 59 155.15 121

NHDP

Phase IIIDec-2009

IVRCL Infrastructure Projects

Ltd.

BOT

(Toll)

Under

Implementation

156 Guna Bypass Madhya Pradesh 3 14 14NHDP

Phase IIIFeb-2005 Guna Infrastructure Ltd.

BOT

(Toll)Completed

157 Patna - Bakhtiarpur Bihar 30 50.6 14NHDP

Phase IIIDec-2010 BSC-C & C (JV)

BOT

(Toll)

Under

Implementation

158 Hyderabad-Vijayawada Andhra Pradesh 9 181.63 163.07NHDP

Phase IIIMay-2009

GMR-Punj LLOYD

Consortium(GMR-Hyderabad

Vijayawada Expressway Pvt.

Ltd.)

BOT

(Toll)

Under

Implementation

159 Madurai-Arupukottai-Tuticorin Tamil Nadu 45B 128.16 128.16NHDP

Phase IIIFeb-2006

Madhucon Projects Ltd. - SREI

- Madhucon granites Ltd (JV)

BOT

(Toll)Completed

1602-Laning with PS Motihari-Raxaul

Bihar 28A 68.79 10NHDP

Jan-2011 Tantia-Jiangsu (JV)BOT Under

1602-Laning with PS Motihari-Raxaul

(Approved Length 67 Km)Bihar 28A 68.79 10

NHDP

Phase IIIJan-2011 Tantia-Jiangsu (JV)

BOT

(Toll)

Under

Implementation

161

4 Laning of Belgaum-Khanpur

Section(Km 0.00 to Km 30.00)

and 2 Laning with paved

sholuders of khanpur-Knt/Goa

border.(Km 30.00 to Km 84.120)

Karnataka 4A 81.89 0NHDP

Phase IIIJul-2010

M/s GVR Infra Projects-RMN

Infrastructure Ltd

BOT

(Toll)

Under

Implementation

162 Patna - Buxar Bihar 30 & 84 124.85 0NHDP

Phase IIINov-2011

Gammon Infrastructure

Projects Ltd

BOT

(Toll)

Under

Implementation

163Talegaon-Amravat(Approved

Length 58Km)Maharashtra 6 67.8 23

NHDP

Phase IIIAug-2009 IRB-MRM Consortium

BOT

(Toll)

Under

Implementation

164Pune-Sholapur Pkg-II(Approved

Length I & II 170 Km)Maharashtra 9 105 16.5

NHDP

Phase IIIAug-2009

IL & FS Transportation

Network Ltd

BOT

(Toll)

Under

Implementation

165Pune-Sholapur Pkg-I(Approved

Length Pkg I & II 170 Km)Maharashtra 9 110.05 84

NHDP

Phase IIIFeb-2009

Navinya Buildcon-Atlantia

Spa(JV)

BOT

(Toll)

Under

Implementation

166 Indore-Khalghat Madhya Pradesh 3 80 80NHDP

Phase IIIJul-2005

Oriental Structural Engineers

Pvt. Ltd.- Delhi Brass

Consortium

BOT

(Toll)Completed

Phase IIIConsortium

(Toll)

167 Kishangarh-Ajmer-Beawar Rajasthan 8 82 76NHDP

Phase IIIApr-2009 Isolux-Soma Consortium

BOT

(Toll)

Under

Implementation

Page 12: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

168Gujarat/Maharashtra Border-

Surat - Hazira Port SectionGujarat 6 132.9 60.06

NHDP

Phase IIIFeb-2009 Isolux-Soma Consortium (JV)

BOT

(Toll)

Under

Implementation

169Chattisgarh / Maharashtra

Border - Wainganga BridgeMaharashtra 6 80 80

NHDP

Phase IIIDec-2006 Ashoka - IDFC Consortium

BOT

(Toll)Completed

170 Nagpur - kondhali Maharashtra 6 40 39.84NHDP

Phase IIISep-2005 Atlanta - SREI Consortium (JV)

BOT

(Toll)

Under

Implementation

171

4 laning of Jetpur-Somnath

section of NH-8D (approved

length 127.6)

Gujarat 8D 123.45 0NHDP

Phase IIISep-2010

IDFC-PLUS Expessway Berhad

Consortium

BOT

(Toll)

Under

Implementation

172Nagpur-Wainganga Bridge

(Approved Length - 60 Km)Maharashtra 6 45.43 0

NHDP

Phase IIIMay-2011 JMC Projects India Ltd.

BOT

(Toll)

Under

Implementation

173Bijapur - Hungund Section

(Approved Length 194 Km)Karnataka 13 97.22 97.22

NHDP

Phase IIIFeb-2010 SEL-MCL Consortium

BOT

(Toll)Completed

174Banglore-Hoskote-Mudbagal

SectionKarnataka 4 79.724 79.724

NHDP

Phase IIIFeb-2007

Lanco Hoskote Highway Pvt.

Ltd.

BOT

(Toll)Completed

175Banglore - Neelamangala (Six

lane)Karnataka 4 19.5 19.5

NHDP

Phase IIIMar-2007 Navyuga Engineering Co. Ltd.

BOT

(Toll)Completed175

lane)Karnataka 4 19.5 19.5

Phase IIIMar-2007 Navyuga Engineering Co. Ltd.

(Toll)Completed

176

2 Laning of Jowai -

Meghalaya/Assam Border

(Approved length 109 Km)

Meghalaya 44 102 0NHDP

Phase IIIMar-2012 Simplex Infrastructure Ltd.

BOT

(Toll)

Under

Implementation

177Hungund-Hospet (Approved

Length 194 Km)Karnataka 13 97.89 79.897

NHDP

Phase IIIFeb-2010 GMR-OSE Consortium

BOT

(Toll)

Under

Implementation

178

4 Laning of Mulbagal - Karnataka

/ AP border-Approved Length (11

Km)

Karnataka 4 22.18 0NHDP

Phase IIIMar-2012 J.S.R. Construction Pvt Ltd

BOT

(Toll)

Under

Implementation

179Sambalpur-Baragarh-

Chattisgarh/Orrisa BorderOrissa 6 88 8

NHDP

Phase IIIMay-2010

M/s Ashoka Buildcon Ltd-

(Ashoka Sambalpur Baragarh

Expressway Pvt. Ltd.)

BOT

(Toll)

Under

Implementation

180 Lucknow - Raebareli Uttar Pradesh 24B 70 0NHDP

Phase IVNov-2011 Essel Infraprojects Ltd.

BOT

(Annuity)

Under

Implementation

181 Maharastra Border-Belgaum Karnataka 4 77 77NHDP

Phase IJun-2002

North Karnataka Expressway

Pvt. Ltd. (Consortium of IL &

FS - Punj Lloyd - CTNL)

BOT

(Annuity)Completed

182

4 Laning of Chappra-

Hajipur(Approved Length 153 Bihar 19 65 11NHDP

May-2010 M/s Madhucon Projects LtdBOT Under

182 Hajipur(Approved Length 153

Km)

Bihar 19 65 11NHDP

Phase IIIMay-2010 M/s Madhucon Projects Ltd

BOT

(Annuity)

Under

Implementation

Page 13: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

183

Kosi Bridge including approaches

and Guide Bond & Afflux Bond

(BR-5)

Bihar 57 10.63 10.63NHDP

Phase IIApr-2006

Gammon india Ltd. - GIPL

Consortium

BOT

(Annuity)Completed

184 Amritsar - Wagha border Punjab 1 35.93 35.93NHDP

Phase IIIAug-2007

Rohan Builders Pvt. Ltd. -

Rajdeep Buildcon Pvt. Ltd. -

IDFC Ltd. Consortium

BOT

(Annuity)Completed

1852-Laning with PS Gopalganj-

ChappraBihar 85 92 0

NHDP

Phase IIIFeb-2011 Abhijeet Infrastructure Ltd.

BOT

(Annuity)

Under

Implementation

186Jhansi to Lalitpur (NS-1/BOT/UP-

2)Uttar Pradesh 25, 26 49.7 44.46

NHDP

Phase IIApr-2006 Gayatri - IDFC Consortium

BOT

(Annuity)

Under

Implementation

187Lakhnadon to MP/MH Border (NS-

1/BOT/MP-2)Madhya Pradesh 7 49.35 40.11

NHDP

Phase IIApr-2006

Navabharat - Ferro Alloys

Ltd.(Malaxmi Higyways pvt.

Ltd.)

BOT

(Annuity)

Under

Implementation

1882 Laning of Forbesganj-

Jogwani(Approved Length 13 Km)Bihar 57A 9.258 1

NHDP

Phase IIIMay-2010 M/s GPT-RDS Consortium Ltd

BOT

(Annuity)

Under

Implementation

ITNL-Punj Lloyd Ltd.(JV)

189 Hazaribagh-Ranchi Jharkhand 33 75 50NHDP

Phase IIIAug-2009

ITNL-Punj Lloyd Ltd.(JV)

(Hazaribagh Ranchi Express

way ltd)

BOT

(Annuity)

Under

Implementation

190 Nellore Bypass Andhra Pradesh 5 17.166 17.166NHDP

Phase IOct-2002

Consortium of Soma

Enterprises & Navayuga Engg

Co. Ltd.

BOT

(Annuity)Completed

191Dharmavaram - Rajahmundry (AP-

15)Andhra Pradesh 5 53 53

NHDP

Phase IMay-2002

Rajahmundry Expressway Ltd.-

Gammon (JV)

BOT

(Annuity)Completed

192 Tuni - Dharmavaram (AP-16) Andhra Pradesh 5 47 47NHDP

Phase IMay-2002 Andhra Expressway Limited

BOT

(Annuity)Completed

1932-Laning with PS khagaria -

PurneaBihar 31 140 37

NHDP

Phase IIIFeb-2011 Punj Lloyd Infrastructure Ltd.

BOT

(Annuity)

Under

Implementation

194 Barasat - Krishnanagar West Bengal 34 84 0NHDP

Phase IIIFeb-2011 Madhucon Projects Ltd.

BOT

(Annuity)

Under

Implementation

195 Palsit - Dankuni West Bengal 2 65 65NHDP

Phase IOct-2002

Consortium of Gomuda

(Malaysia) & WCT Engineering

(Malaysia)

BOT

(Annuity)Completed

196 Panagarh - Palsit West Bengal 2 64.457 64.457NHDP

Phase IJun-2002

Gamuda Malaysia - WCT

Malaysia

BOT

(Annuity)Completed

197 Gwalior Bypass (NS-1/BOT/MP-1) Madhya Pradesh 75, 3 42 40.45NHDP

Phase IIMay-2006

Ramky - Era - Shriram

Consortium

BOT

(Annuity)

Under

Implementation197 Gwalior Bypass (NS-1/BOT/MP-1) Madhya Pradesh 75, 3 42 40.45

Phase IIMay-2006

Consortium (Annuity) Implementation

Page 14: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

198 Tambaram - Tindivanam Tamil Nadu 45 93 93NHDP

Phase IMay-2002

Tambaram-Tindivanam

Express way Pvt. Ltd.

(Consortium of GMR

Consortium & UE Malaysia)

BOT

(Annuity)Completed

199 Krishnanagar - Berhampore West Bengal 34 78 0NHDP

Phase IIIFeb-2011 SEW Infra.

BOT

(Annuity)

Under

Implementation

200 Ankapalli - Tuni Andhra Pradesh 5 58.947 58.947NHDP

Phase IMay-2002

GMR-Tuni-Ankapalli Express

Ltd.

BOT

(Annuity)Completed

201MH/AP border to Islam Nagar (NS-

2/BOT/AP-6)Andhra Pradesh 7 54.6 54.6

NHDP

Phase IIDec-2006 SOMA - Avinash Consortium

BOT

(Annuity)Completed

202 Reengus - Sikar Rajasthan 11 43.887 0NHDP

Phase IIIMar-2011 G.R.Infraprojects Ltd.

BOT

(Annuity)

Under

Implementation

203 Patna- Muzzaffarpur Bihar 19 & 77 63 42NHDP

Phase IIINov-2009 Gammon Infrastructure Ltd

BOT

(Annuity)

Under

Implementation

204 Ranchi - Rargaon - Jamshedpur Jharkhand 33 163.5 0NHDP

Phase IIIMar-2011 Madhucon Projects Ltd.

BOT

(Annuity)

Under

Implementation204 Ranchi - Rargaon - Jamshedpur Jharkhand 33 163.5 0

Phase IIIMar-2011 Madhucon Projects Ltd.

(Annuity) Implementation

2052 Laning of Dindigul-Perigulam-

Theni-KumiliTamil Nadu 220 134 14

NHDP

Phase IIIMay-2010

Transstroy-OJSC Consortium

Ltd

BOT

(Annuity)

Under

Implementation

206 4 Laning of Nagpur Betul

Madhya

Pradesh[120]/Maharash

tra[56.3]

69 176.3 0NHDP

Phase IVMay-2010

Oriental Structural Engineers

Pvt Ltd- Continental Engineers

Ltd

BOT

(Annuity)

Under

Implementation

207Jhansi to Lalitpur (NS-1/BOT/UP-

3)Uttar Pradesh 26 49.3 49.3

NHDP

Phase IIApr-2006 Gayatri - IDFC Consortium

BOT

(Annuity)Completed

208 Bara to Orai Uttar Pradesh 2, 25 62.8 62.8NHDP

Phase IIDec-2005 NCC - KMC Consortium

BOT

(Annuity)Completed

209Haridwar - Dehradun (Approved

Length 69)Uttaranchal 72 39 0

NHDP

Phase IIIDec-2009 ERA - SIBMOST(JV)

BOT

(Annuity)

Under

Implementation

210

2-Laning of Krishnagiri-

Tindivanam (Approved Length

170 Km.)

Tamil Nadu 66 176.51 0NHDP

Phase IIIMay-2011

Transstroy (I) Ltd. -

Corporation Transstroy OJSC

Consortium

BOT

(Annuity)

Under

Implementation

211

Two Laning of Trichy - Karaikudi

and Trichy Bypass(Approved

Length 100 Km)

Tamil Nadu 210 & 67 110.372 12.5NHDP

Phase IIIMay-2010

Transstroy Ltd-OJSC

Consortium

BOT

(Annuity)

Under

Implementation

212Bhopal-Sanchi(Approved Length

Madhya Pradesh 86Ex 53.78 0NHDP

May-2010Pratibha Industries-Abhyuday BOT Under

212Bhopal-Sanchi(Approved Length

40 Km)Madhya Pradesh 86Ex 53.78 0

NHDP

Phase IIIMay-2010

Pratibha Industries-Abhyuday

Housing Construction Ltd

BOT

(Annuity)

Under

Implementation

Page 15: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

213 2-Laning of Shilong-Bypass Meghalaya 40 & 44 50 35.5 SARDP-NE May-2010 M/s GR-Chetak(JV)BOT

(Annuity)

Under

Implementation

214 Jorbat-Barapani Meghalaya 40 61.8 0 SARDP-NE May-2010 M/s ILFS-RamkeyBOT

(Annuity)

Under

Implementation

215 Kadal to Armur (NS-2/BOT/AP-8) Andhra Pradesh 7 31 31NHDP

Phase IIDec-2006

Hindustan Construction

Company Ltd.

BOT

(Annuity)Completed

216 Jammu - Udhampur Jammu Kashmir 1A 65 0NHDP

Phase IIApr-2010 Shaboorji & Palonji Co. Ltd.

BOT

(Annuity)

Under

Implementation

217Lakhnadon to MP/MH Border (NS-

1/BOT/MP-3)Madhya Pradesh 7 56.475 27.73

NHDP

Phase IIJan-2007 Sadbhav - SREI (JV)

BOT

(Annuity)

Under

Implementation

218 Gwalior - Jhansi

Madhya

Pradesh[68.5]/Uttar

Pradesh[11.5]

75 80 52.77NHDP

Phase IIMay-2006 DSC - Apollo consortium

BOT

(Annuity)

Under

Implementation

219

AP/Karnatka border- Nandi Hill

crossing & Devenhalli to Meenu

Kunte Village

Karnataka 7 61.38 61.38NHDP

Phase IIApr-2006

Patel - KNR Infrasturture Pvt.

Ltd. (JV)

BOT

(Annuity)Completed

2202 Laning of Mokama-

Munger(Approved Length 70 Km)Bihar 80 69.27 43

NHDP

Phase IIIMay-2010 M/s BSCPL -C & C Consortium

BOT

(Annuity)

Under

Implementation

221Hyderabad Bangalore section (NS-

2/BOT/AP-5)Andhra Pradesh 7 74.65 74.65

NHDP

Phase IIFeb-2006

IL & FS CTNL Consortium

(Andhra Pradesh Expressway

Ltd.)

BOT

(Annuity)Completed

222Kadloor Yellareddy to Gundla

Pochampalli (NS-2/BOT/AP-2)Andhra Pradesh 7 85.74 85.74

NHDP

Phase IIDec-2005

GMR Infrastructure ltd - GMR

Energy Ltd. Consortium

BOT

(Annuity)Completed

223

2 Laning of Muzaffarpur -

Sonbarsa(Approved Length 89

Km)

Bihar 77 86 26NHDP

Phase IIIJul-2010 BSCPL-C&C(JV)

BOT

(Annuity)

Under

Implementation

224Islam Nagar to Kadtal (NS-

2/BOT/AP-7)Andhra Pradesh 7 53.01 53.01

NHDP

Phase IIMar-2007 Patel - KNR (JV)

BOT

(Annuity)Completed

225 Chenani-Nashri Jammu Kashmir 1A 12 0NHDP

Phase IIMay-2010

IL & FS Transportation

Networks Ltd

BOT

(Annuity)

Under

Implementation

226 Gorakhpur Bypass Uttar Pradesh 28 32.6 32.6NHDP

Phase IIApr-2006

Gammon india Ltd. - GIPL -

ATSL Consortium

BOT

(Annuity)Completed

227 Quazigund-Banihal Jammu Kashmir 1A 15.25 0NHDP

Phase IIApr-2010 Navyuga Engineering Co. Ltd.

BOT

(Annuity)

Under

Implementation

NHDP BOT Under 228 Srinagar to Banihal Jammu Kashmir 1A 67.76 0

NHDP

Phase IISep-2010 Ramkey Infra and JPTEG

BOT

(Annuity)

Under

Implementation

Page 16: Ppp

S.No. Stretch State Name NH No

Total

Length

(In Km)

Completed

Length

(In Km)

NHDP

Phase

Category

LOA

DateConcessionaire Funded By Present Status

229

Palanpur to Swaroopganj

(Rajasthan -42 km & Gujarat-34

km )

Rajasthan[42]/Gujarat[3

4]14 76 76

NHDP

Phase IIDec-2005

Larsen & Toubro Ltd., ECC

Division

BOT

(Annuity)Completed