PowerPoint Presentation - Home - ETIP · PPT file · Web viewO valor da corrente de defeito fase...

14
Direção de Tecnologia e Inovação EDP Distribuição - Energy Storage Project Accessing the potential of grid connected storage 28th September of 2017 Para preencher o rodapé: 1. Pressione a tecl... 2. Prima o seguinte...

Transcript of PowerPoint Presentation - Home - ETIP · PPT file · Web viewO valor da corrente de defeito fase...

Direção de Tecnologia e Inovação

EDP Distribuição - Energy Storage ProjectAccessing the potential of grid connected storage

28th September of 2017

Para preencher o rodapé:1. Pressione a tecla F5

2. Prima o seguinte botão

DTI/TIID 2

1. Brief introduction to EDP Distribution.2. MV Storage - Project Overview.3. Main Project Challenges.4. Ongoing and Future Tasks.5. Interaction with other projects – SENSIBLE.6. Key Takeaways.

Agenda

DTI/TIID 3

Project Overview / Technical Characteristics

• Located in Évora University Campus• Commissioning Date - December of 2015• Lithium Ion Batteries• Power / Energy ratings - 480 kW/ 360 kWh

Évora’s storage pilot project

Quality of service improvement:o Continuity of service: backup to

universityo Quality of energy: voltage control.

Network CAPEX deferral:o Resource providing flexibility

(impact on network planning)o Peak Shaving of distributed energy.

Integration of distributed sources:o Integration of a higher share of

renewables

DTI/TIID 4

MV Storage Project Implementation Highlights

1º Sem. 2015

2º Sem. 2015

1º Sem. 2016

2º Sem. 2016

SS adaptation / Civil works related to Siestorage

Functionalities development

Interaction with other projects- SENSIBLE

Project detail, construction, licensing, SCADA, SS adaptation plan, studies.

SATs

November

Kick-off U.Evora Cooperation

Protocol

Start of Real Operation

DTI/TIID 5

Main Project ChallengesLe

gal a

nd

Regu

lato

ry • Safety issues regarding the use of high power batteries

• Storage Licensing with specific Island Mode operation

• LV protection systems compliance with regulation requirements

Tech

nica

l • Secondary substation adaptation for storage test and commissioning

• System adaptation for all required functions (PQ, Vf, Hybrid mode)

• Corporate systems adaptation for the project (SCADA, GIS…)

Oth

er

Cons

trai

nts

• Knowledge retention and transfer.

• Training on system operation and maintenance.

DTI/TIID 6

Main Project Challenges: LV protection systems compliance

Storage system behavior in controlled real operation context• Real Short Circuit Test• PQ operation mode and Vf transition• Islanding operation• Oscillographic analysis• Clients’ LV and storage MV protection schemes

validation for safety concerns

Main Results• Differences found between manufacturersimulations and actual results obtained.• Minimum frequency while switching to islanding operation mode determined as well as drop andrecovery times.• No significant restraints to the storage operationwere identified.• Real tests were crucial for assuring safe operation!!

DTI/TIID 7

Main Project Challenges: Phase Neutral fault in island mode

iL1 iL2 iL3 t/s-0.4 -0.3 -0.2 -0.1 0.0 0.1 0.2 0.3 0.4 0.5 0.6I/ A-40-20020 uL1 uL2 uL3 t/s-0.4 -0.3 -0.2 -0.1 0.0 0.1 0.2 0.3 0.4 0.5 0.6U/ V-10000010000

Main Conclusions:• Overvoltage values below

expected in simulations.• Fault current differs from

the supplied simulation • Real tests were crucial for

assuring safe operation!!

DTI/TIID 8

Main Project Challenges: Switching to island mode

Main Conclusions:• Minimum frequency reached

and drop time determined • Currents assume load

unbalance• Recovery time for frequency

determined• Islanding tests had

implication on protection parameters.

• Real tests were crucial for avoiding unwanted trips!!

iL1 iL2 iL3 t/s-0.10 -0.00 0.10 0.20 0.30 0.40I/ A-100 uL1 uL2 uL3 t/s-0.10 -0.00 0.10 0.20 0.30 0.40U/ V-10000010000

DTI/TIID

Storage – New R&D Activities / Projects on Energy Storage

Energy Storag

e

Grid Integration

Business ImpactAssessment

Standardization / optimization

Technological analysis

DTI/TIID

Ongoing and future tasks

UC1 Island operation validation

UC2 Performance Monitoring

UC3 Service Quality / Energy Quality

UC4 Advanced Peak Shaving

UC5 Extended Islanding Operation

UC6 Storage System Optimization

UC7 Business Models Evaluation

Initial Use Cases

DTI/TIID 11

Performance Monitoring – Key activity for BM evaluation

Storage Container

Outside

Interior Thermomete

r

Meteorological Station

Batteries

Air Conditioned

S7 Controller

Power Electronics

Medium Voltage Cells

Local Command Point

System Monitoring Interface

Solar Panels – Auxiliary services and AC power consumption

DTI/TIID

Performance Monitoring

12

Must Have• I,V P e Q MV Cells

• Temperature

• BMU Data

• Inverter Data

• AS Consumption

• AC Consumption

• Active Function Mode

• State of health (Batteries)

Should Have• Energy Quality

• System Reliability1. SCADA2. Comms3. Hardware

• Individual Battery Rack Data

Overall Efficiency

Correlation Between Main Variables

KPI Evaluation

Battery Degradation Model

DTI/TIID

Next innovation steps on energy storage

Main Projects Objectives• Demonstrate concrete applications of distributed energy storage and energy management tools for the DSO. • Enabling innovative Business Models.• Understand how EDP’s Smart Grid concept should evolve in order to facilitate the referred applications.• Understand what regulatory framework and policy developments should be promoted.

DTI/TIID

1. Need for more standardization in network connected storage solutions2. Lifecycle optimization of the use of storage, minimizing power losses and

battery degradation. 3. Assessment of renewables integration benefits.4. Further Interaction and coordination with other projects or new storage

projects for new innovative business models5. Continued cooperation with universities and R&D organizations.6. Further exploring legal and regulatory issues.7. Understanding storage impact for network planning.8. Development of algorithms for automatic centralized control.

14

KEY TAKEAWAYS