May 3, 2019 Chicago O’Hare International Airport 2019 Construction Update O’Hare Noise Compatibility Commission

Transcript of PowerPoint Presentation · 2019. 5. 8. · Title: PowerPoint Presentation Author: Michelle Piette...

Page 1: PowerPoint Presentation · 2019. 5. 8. · Title: PowerPoint Presentation Author: Michelle Piette Created Date: 5/2/2019 3:08:31 PM

May 3, 2019

Chicago O’Hare International Airport

2019 Construction Update

O’Hare Noise Compatibility Commission

Page 2: PowerPoint Presentation · 2019. 5. 8. · Title: PowerPoint Presentation Author: Michelle Piette Created Date: 5/2/2019 3:08:31 PM

RUNWAY 9C/27C CONSTRUCTION OVERVIEW

2

East Package

Complete Fall 2018

Package 1

Complete Fall 2019

Package 2

Complete June 2020

Package 3

Complete June 2020

Taxiway Z/J

Complete

Spring 2019

4L

22R

9R 27L

Central Deicing Pad

9C 27C

4L-22R Recon.

Complete

October 31, 2019

Page 3: PowerPoint Presentation · 2019. 5. 8. · Title: PowerPoint Presentation Author: Michelle Piette Created Date: 5/2/2019 3:08:31 PM

RUNWAY 9R-27L RUNWAY STATUS LIGHTS

Installation of approximately 10,000 linear feet of electrical ductbank, handholes, and airfield lighting cable to complete the installation of the FAA Runway Status Lights (RWSL) system for Runway 9R-27L. A FAA-RWSL shelter to be located adjacent to the existing Runway 27L ALSF shelter will also be installed. A new Com Ed service feed as well as fiber optic cable connectivity to the air traffic control tower will be required to make the RWSL shelter fully functional.

Complete August 2019

CONSTRUCTION

3

Page 4: PowerPoint Presentation · 2019. 5. 8. · Title: PowerPoint Presentation Author: Michelle Piette Created Date: 5/2/2019 3:08:31 PM

TERMINAL 5 INVESTMENTS –$1.2 BILLION OVER THE NEXT FIVE YEARS

4

10 additional gates

(2 will be A380 compatible)

Reconfigured international arrivals

facility and security checkpoint

New airline lounges (consolidated

SkyTeam lounge) and expanded

commercial offerings

KEY OPENING DATES:

KEY HIGHLIGHTS:

Early 2021

New Concourse

Mid-2021

Terminal Expansion

& Parking Garage

Late 2021

Delta Air Lines

relocates to Terminal 5

After 2023

Curbside roadway

expansion and new hotel

New SkyTeam

lounge

Expanded gate holdrooms and

amenities

New baggage handling system

Page 5: PowerPoint Presentation · 2019. 5. 8. · Title: PowerPoint Presentation Author: Michelle Piette Created Date: 5/2/2019 3:08:31 PM

TERMNAL 5 CONCOURSE M EXTENSION

5

Site preparation and paving for the two story 260,000 SF concourse extension from Gates M19 through M27. Work also includes relocation of existing Guard Post 11, a new trituratorbuilding, and new storm sewer piping to the south basin.

C O N S T R U C T I O N

Page 6: PowerPoint Presentation · 2019. 5. 8. · Title: PowerPoint Presentation Author: Michelle Piette Created Date: 5/2/2019 3:08:31 PM

LET’S US KEEP IN TOUCH!

6

@fly2ohare

facebook.com/fly2ohare

SIGN UP FOR WEB ALERTS OR THE CDA

QUARTERLY NEWSLETTER AT

flychicago.com

instagram.com/flyohare

@fly2midway

facebook.com/fly2midway

instagram.com/flymidway

Page 7: PowerPoint Presentation · 2019. 5. 8. · Title: PowerPoint Presentation Author: Michelle Piette Created Date: 5/2/2019 3:08:31 PM