Powering Seattle through the 21st Century Denny Substation Program QUARTERLY REPORT 4TH QUARTER | 2017 POWERING SEATTLE INTO THE 21ST CENTURY 2017 was a year of accomplishment for the Denny Substation Program. Among our significant achievements were the installation of three 125,000-pound transformers at the substation and progress on the elevated walkway and the architectural siding. We also upgraded the substation’s transmission line, which means we’re one step closer to being powered up! As we move toward program completion in 2018, you’ll see the community’s “fingerprints” on the project as public input provided during the design comes to life. THE PROJECT TEAM THANKS ALL OF YOU for your ongoing involvement and interest in this significant investment in Seattle. Cheers to 2018 and the project’s final stage! THEN: Bird’s-eye view taken in January of 2017. NOW: A year later, with the walkway, siding, and interior nearing completion. Powering Seattle through the 21st Century Denny Substation Program ANOTHER MILESTONE ON THE HORIZON The Denny Network reached the 97% mark of completion for duct bank installation and roadway restoration south of Denny Way. Although all 30 vaults have been installed, more utility work, saw cutting, excavation, shoring, and roadway restoration will keep us busy in 2018 throughout the South Lake Union neighborhood. In 2017, over 6,400 feet of duct bank was installed, bringing duct bank installed to date to a total of more than 11,500 feet! WHAT’S NEXT? In early 2018, crews will complete installation of the substation’s siding and glass and will put the finishing touches on the elevated walkway. Other upcoming visible work in and around the substation includes restoration of the alley, build-out of the community spaces, and final paving on Minor Avenue N and inside the substation. In addition to advancing improvements in the Cascade neighborhood, the Denny Network will continue duct bank installation and roadway restoration in the South Lake Union area. VISIT OUR WEBSITE: www.seattle.gov/light/dennysub SEND US AN EMAIL: [email protected] CALL OUR HOTLINE: (206) 257-2142 8TH AVE 8TH AVE 9TH AVE BOREN AVE TERRY AVE 7TH AVE 7TH AVE 6TH AVE 5TH AVE 4TH AVE 9TH AVE BOREN AVE MINOR AVE 8TH AVE 7TH AVE 6TH AVE PINE ST PIKE ST STEWART ST STEWART ST VIRGINIA ST BLANCHARD ST BELL ST OLIVE WAY MERCER ST MERCER ST E MERCER ST E REPUBLICAN ST E HARRISON ST E THOMAS ST REPUBLICAN ST HARRISON ST DENNY WAY FAIRVIEW AVE N THOMAS ST WESTLAKE AVE N 9TH AVE N 8TH AVE N BROAD ST DEXTER AVE N TERRY AVE N BOREN AVE N YALE AVE N MINOR AVE YALE AVE DENNY PARK MINOR AVE N MELROSE AVE E BELLEVUE AVE E BELLEVUE AVE E SUMMIT AVE E BELMONT AVE E PONTIUS AVE N CASCADE PLAYGROUND CASCADE P-PATCH HOWELL ST RAMPS TO AND FROM I5 3RD AVE JOHN ST E JOHN ST E DENNY WAY E HOWELL ST E OLIVE ST E PINE ST E PIKE ST DENNY SUBSTATION WESTLAKE AVE LENORA ST E UNION ST BOYLSTON AVE E SUMMIT AVE E CRAWFORD PL BELMONT AVE E BOYLSTON AVE E E OLIV E W AY Project map showing the areas of work in the next phases of the Denny Substation and Denny Network Denny Substation and Denny Network Construction Map SCHEDULE 2015 2016 2017 2018 2019 2020 CONSTRUCTION Denny Substation Denny Network Electrical Work SUBSTATION ENERGIZED ONGOING NETWORK SERVICE CONNECTIONS

Transcript of Powering Seattle through the 21st Century Denny Substation ... · transmission line, which ......

Powering Seattle through the 21st Century

Denny Substation Program

QUARTERLY REPORT 4 T H Q UA R T E R | 2 0 1 7

POWERING SEATTLE INTO THE 21ST CENTURY2017 was a year of

accomplishment for the

Denny Substation

Program. Among our

significant achievements

were the installation of

three 125,000-pound

transformers at the

substation and progress

on the elevated walkway

and the architectural

siding. We also upgraded

the substation’s

transmission line, which

means we’re one step

closer to being powered

up! As we move toward

program completion in

2018, you’ll see the

community’s “fingerprints”

on the project as public

input provided during the

design comes to life.

THE PROJECT TEAM

THANKS ALL OF YOU

for your ongoing

involvement and interest

in this significant

investment in Seattle.

Cheers to 2018 and the

project’s final stage!

THEN: Bird’s-eye view taken in January of 2017.

NOW: A year later, with the walkway, siding, and interior nearing completion.

Powering Seattle through the 21st Century

Denny Substation Program

ANOTHER MILESTONE ON THE HORIZONThe Denny Network reached the 97% mark of completion for duct bank installation and roadway restoration south of Denny Way. Although all 30 vaults have been installed, more utility work, saw cutting, excavation, shoring, and roadway restoration will keep us busy in 2018 throughout the South Lake Union neighborhood. In 2017, over 6,400 feet of duct bank was installed, bringing duct bank installed to date to a total of more than 11,500 feet!

WHAT’S NEXT? In early 2018, crews will complete installation of the substation’s siding and glass and will put the finishing touches on the elevated walkway. Other upcoming visible work in and around the substation includes restoration of the alley, build-out of the community spaces, and final paving on Minor Avenue N and inside the substation.

In addition to advancing improvements in the Cascade neighborhood, the Denny Network will continue duct bank installation and roadway restoration in the South Lake Union area.

VISIT OUR WEBSITE:www.seattle.gov/light/dennysub

SEND US AN EMAIL:[email protected]

CALL OUR HOTLINE:(206) 257-2142

8TH AVE

8TH AVE

9TH AVE

BOREN AVE

TERRY AVE

7TH AVE

7TH AVE

6TH AVE

5TH AVE

4TH AVE

9TH AVE

BOREN AVE

MINOR AVE

8TH AVE

7TH AVE 6TH AVE

PINE ST

PIKE ST

STEWART ST

STEWART ST

VIRGINIA

ST

BLANCHARD ST

BELL ST

OLIVE WAY

MERCER ST

MERCER ST E MERCER ST

E REPUBLICAN ST

E HARRISON ST

E THOMAS ST

REPUBLICAN ST

HARRISON ST

DENNY WAY

FAIRVIEW

AVE N

THOMAS ST

ROY ST

WESTLA

KE AVE N

9TH AVE N

8TH AVE N

BROAD ST

DEX

TER AVE N

TERRY AVE N

BOREN

AVE N

YALE AVE N

MINOR AVE

YALE AVE

DENNY PARK

MIN

OR AVE N

MELRO

SE AVE E

BELLEVUE AVE E

BELLEVUE AVE E

SUM

MIT AVE E

BELMO

NT AVE E

PON

TIUS AVE N

CASCADEPLAYGROUND

CASCADEP-PATCH

HOWELL ST

RAMPS TO AND FROM I5

3RD AVE

JOHN ST E JOHN ST

E DENNY WAY

E HOWELL ST

E OLIVE ST

E PINE ST

E PIKE ST

DENNYSUBSTATION

WESTLA

KE AVE

LENORA ST

E UNION ST

BOYLSTO

N AVE E

SUM

MIT AVE E

CRAW

FORD

PL

BELMO

NT AVE E

BOYLSTO

N AVE E

E OLIVE WAY

Project map showing the areas of work in the next phases of the Denny Substation and Denny Network

Denny Substation and Denny Network Construction Map

SCHEDULE2015 2016 2017 2018 2019 2020

CONSTRUCTION

Denny Substation

Denny Network

Electrical Work

SUBSTATION ENERGIZED

ONGOING NETWORK SERVICE CONNECTIONS

PUBLIC BENEFITS COME TO LIFE

THEN: Exposed structural steel and concrete form the base for the elevated walkway in January 2017.

NOW: Concrete walkway, siding and handrail installation on the elevated walkway. The “portals” on the right side of the photo will allow the public to look into the substation and witness it at work.

SNEAK PEEK: It may not look like it now, but this will soon be a place for community gatherings and events.

Denny Substation ProgramPowering Seattle through the 21st Century

INSIDE THE SUBSTATION

PUTTING THE TRANSFORMERS TO WORK

THEN: Empty platforms ready to hold the weight of three gigantic transformers.

NOW: All three transformers resting on their foundations and being prepped for energization in December 2017.

OUTSIDE THE SUBSTATION

OUT WITH THE OLD, IN WITH THE NEWTYING IT ALL TOGETHER: Transmission line work on E Denny Way (between Summit Avenue and Boylston Avenue E) and on Denny Way (near Stewart Street and Denny Way intersection) was completed this quarter. This work was necessary for the Denny Substation to tie into the transmission line that runs underneath Denny Way.

This work involved excavating a large pit to expose the existing transmission line, freezing the oil-filled transmission line, removing a section of the old line, splicing new cable, filling the new line with oil, and restoring the street. The Denny Substation can now be connected to other City Light substations and can accept high voltage electricity that will then be transformed into voltages customers can use.

Crews removed approximately a half-mile of old cable as part of upgrading the transmission line for the substation.

AROUND THE SUBSTATION

NEIGHBORHOOD IMPROVEMENTS UNDERWAY The Denny Network has been busy working on project elements that will benefit the neighborhood. Crews have been working on the Cascade Neighborhood Street Improvements, which include a festival-style street (see rendering below) and pedestrian lighting, new sidewalks, and additional trees and landscaping. Feedback from Cascade residents, as well as guidance from other neighborhood plans, helped to shape these improvements.

The elevated walkway—one of the substation’s most prominent features and most popular public benefits— evolved dramatically this year. It will provide a public space for exercise and opportunities to see the inner workings of the substation.

In the fourth quarter, work began on two additional public benefits: the educational viewing portals and community rooms (pictured at right), which will serve as spaces for public use. Unlike most substations, which are designed to keep the public away, the Denny Substation incorporates unique community-requested features that are intended to draw people to the substation and encourage them to learn how it works.