Power Sector Reform and Investment -...
Transcript of Power Sector Reform and Investment -...
www.gsb.uct.ac.za/mir
Prof Anton Eberhard Management Program in Infrastructure Reform and Regulation
University of Cape Town
Power Sector Reform and Investment Comparing Uganda with Kenya and Tanzania
www.gsb.uct.ac.za/mir
www.gsb.uct.ac.za/mir
Drivers for utility reform in developing countries
• Inefficiencies in investment and operations – soft budgets, poor governance, regulatory failure, no competition, few
incentives for cost reduction
– deterioration or collapse of services
• Financing for capacity expansion – public resources insufficient -> private
• Part of overall economic restructuring – macro-economic constraints or crises
– state re-defines relationship to SOE’s
• Technological innovation – Changing economies of scale and scope
– New possibilities for competition
• Sector reform as a fad? – international role models
www.gsb.uct.ac.za/mir
Emergence of the “standard model” of reform
Vertically-integrated, publicly-owned monopoly
Commercialisation and corporatisation
Independent regulation
Unbundling to separate potentially competitive elements from non-competitive elements
Private sector participation
Introduction of competition IPPs for the market
or wholesale competition in the market
eventually customer choice and retail competition
www.gsb.uct.ac.za/mir
MODEL 1:NATURAL MONOPOLY
MODEL 4:RETAIL COMPETITION
MODEL 3:WHOLESALE COMPETITION
MODEL 2:SINGLE BUYER
Utilities are vertically integrated
Generation, transmission and distribution are not subject to competition
No-one has choice of supplier
Single buyer chooses from various generators (IPPs)
Access to transmission xxx not permitted for sales to final customers
Single buyer has monopoly over transmission networks and over sales to final customer
Distribution companies buy direct from generator (IPPs)
Distribution companies have monopoly over final customers
Open access to transmission wires
Generators compete to supply power
Power pool established to
facilitate x
All customers have choice of supplier
Open access to T & D wires
Distribution is separate from retail activity
Retail industry is competitive
Generation (G)
Transmission (T)
Distribution (D)
Customer (C)
IPP IPP
Single buyer G & T
D D
C
G GG
TPower poolexchange
Franchisecustomers
(FC)
Largecustomers
(LC)
D
C
D
LC
D
C
G GG
TPower poolexchange
www.gsb.uct.ac.za/mir
Progress in power reform in Africa
• About 30 African counties have established independent
electricity regulators
• Some countries have unbundled their state-owned utilities – e.g. Kenya (KenGEn & KPLC) e.g. Nigeria (Gencos, TCN, Discos)
– e.g. Ghana (VRA, GRIDco, ECG)
– e.g. Uganda (UEGCL, UETCL, UEDCL)
• Most countries have enacted laws permitting private sector
participation, but progress is mixed – Private concessions and management contracts
• e.g. Uganda, Cameroon, Cote d’Ivoire, Mali, Gabon concessions
• E.g. Namibia, Lesotho, Rwanda, Tanzania, Kenya, Nigeria management contracts
– Frameworks for small RE IPPs
• e.g. Tanzania, REFITs, etc
– About 50 IPPs across Africa
• e.g. Kenya (5 + 3 more), Uganda (first large IPP hydro + a number of smaller IPPs), Tanzania,
Ghana, Cote d’Ivoire, Senegal, Nigeria, Togo, South Africa (renewables), etc
www.gsb.uct.ac.za/mir
Progress in Africa’s two largest economies
• South Africa
– After slow start, a successful renewable energy IPP programme
– Rounds 1 & 2 = 47 projects totaling 2450 MW
– Wind prices drop 20% and solar PV 40%
– Round 3 in progress plus more
– Procurement of gas, coal & hydro IPPs planned
• Nigeria
– Sale of 5 out of 6 Gencos; sale of NIPPs planned
– Concessioning of 10 out of 11 Discos
– 25 % payment made; 75% expected by September 2013
– TCN management contract
– Bulk trader
– Transitional electricity market being designed
•
www.gsb.uct.ac.za/mir
Power market structures in E. Africa
D
T
G IPPs
Uganda
G G IPPs IPPs
T T
D D
Kenya Tanzania
Private State-owned
UEDCL
UETCL
UEGCL
KenGen
KPLC
Tanesco
Umeme
Eskom
www.gsb.uct.ac.za/mir
IPP performance differs
• Kenya has best record in attracting IPPs
– Dynamic planning system
– Timely initiation of international competitive
tenders
– Capacity to effectively procure and contract built in
KPLC
• Tanzania has worst record
– Poor planning
– Unsolicited bids rater than ICBs
– Series of corruptions scandals in new power deals
–
Kenya’s IPPs much cheaper and reliable than Tanzania
www.gsb.uct.ac.za/mir
Uganda IPPs MW
• Bujagali 250
• Jacobsen, Namanve 50
• Electro-Maxx, Tororo 20
• Mpanga Hydro 18
• TronderPower, Bugoye 13
• Kasese Cobalt, Mubuku III 9.5
• Kilembe Mines 5
• EcoPower, Ishasha 6.5
• Kakira Sugar 12
• Kinyara Sugar (captive) 5
• Kabalega 9
www.gsb.uct.ac.za/mir
Uganda GETFit
• Aims to fast-track portfolio of <20MW grid connected renewable energy projects by offering a premium to feed-in tariff
Feed-in Tariff GETFiT Premium
Small hydro >10MW 7.9 1.4
Bagasse 8.1 1
• Payments front-loaded in 1st 5 years
• Standardised PPA and IAs
• Possible WB PRGs
• Facilitated Tx interconnection
• Number of RfP windows
• 8 projects approved to date totaling Euros 48m & 73MW
www.gsb.uct.ac.za/mir
Improving generation expansion
planning, procurement & contracting
• Allocate responsibility and build capacity for generation
expansion planning
• Develop clear criteria for allocating new build opportunities between the incumbent SOE and IPPs?
• Allocate responsibility & initiate timely competitive bids for IPPs
• Develop procedures for evaluating unsolicited bids
• Develop capacity for contract negotiations with new IPPs
• Avoid potential conflicts of interest when SOEs are the Single-Buyer
www.gsb.uct.ac.za/mir
Power
Off-taker
Power Purchase
Agreement
IPP Project
Company
Fuel suppliers
FSA
Lenders
O&M Contractor
O&M Contract
EPC Contractor Shareholders
EPC Contract Loan Agreement
Environmental
Authorities
Permit
Shareholders
agreement
Regulator
License Government Concession
Modified from Clive Ferreira, Fieldstone
Source: Clive Ferreira - Fieldstone
Government
Understand IPP risks
www.gsb.uct.ac.za/mir
• Implementation Agreement (“IA”)
(Typically granting land or rights);
• Power purchase agreement (“PPA”);
• Fuel supply agreement (“FSA”);
• Operation and maintenance agreement (“O&M”);
• Engineering Procurement Contract (“EPC”);
• License;
• Permits;
• Financing agreements;
• Inter-creditor agreements; and
• Insurance agreements
• Guarantees?
Source: Clive Ferreira, Fieldstone
A lawyers dream:
a developers nightmare!
Source: Clive Ferreira - Fieldstone
Key IPP contracts
www.gsb.uct.ac.za/mir
• Non-competitive, non-
transparent tender and
award process
• Corruption
Risk Mitigation
• Open bidding to foster competition
• Transparent notification of
procurement intention and tender
process, including timetable
• Comprehensive information and
documentation packages for bidding
and negotiation, pre-bid conferences
• Information on avoided costs
• Pre-qualification, bid-securities set at
appropriate level
• Objective evaluation criteria with
independent scrutiny
Tender and
bid process
Source: Clive Ferreira, Fieldstone
Traditional risk management (1 of 5)
www.gsb.uct.ac.za/mir
• Late completion
• Reduced output
• Inefficient (high heat rate)
• Environmental compliance
Risk Mitigation
• Turnkey, lump sum, date
certain contract
• Liquidated damages for
performance failure
Fuel Supply
Construction
Operational
• Low availability
• High operating cost
• Fixed fee contract with
performance bonuses
• Operational guidelines and
penalties/termination for
performance failure
• Reliable fuel supply to
specification
• Adequate resources for
life of project (PPA)
• Proven reserves
• Alternative supply obligation
• Liquidated damages for
delivery failure
• Cost pass through
Source: Clive Ferreira, Fieldstone
Source: based on Clive Ferreira – Fieldstone.
Traditional risk management (2 of 5)
www.gsb.uct.ac.za/mir
• Creditworthiness of Power
Purchaser
• Poor billing and collection
• Demand for electricity
• Non-dispatch
• Currency convertibility and
transferability
• Devaluation of local
currency
• Inflation
• Change in fuel prices
• Accounting and financial
information available on power
purchaser
• Long term power purchase
agreements
• Sovereign guarantees
• Front-loading of tariffs
• Escrow accounts
• Dollar denominated contracts
• Indexation of key costs
• Local currency financing
(established financial markets)
Revenue
Source: Clive Ferreira, Fieldstone
Source: based partly on Clive Ferreira – Fieldstone and Woodhouse, E 2005.
Traditional risk management (3 of 5)
Mitigation Risk
“The odour of over-pricing can set back IPPs for years!”
www.gsb.uct.ac.za/mir
Traditional risk management (4 of 5)
Regulatory
• Arbitrary changes to rules,
and/or addition of new
rules
• Misapplication of rules
• Too much regulatory
discretion in price reviews
• Additional cost risks
(associated with
performance and
environmental standards,
accounting rules, taxation)
• Change of law exemption
• Clarity of regulatory
framework and approval
processes
• Regulatory discretion
limited
• Regulatory capacity built
• Political risk insurance
• Partial risk guarantee
• Appeal process and
dispute settlement facilities
Risk Mitigation
Political interference risk: government intervenes in regulatory process
www.gsb.uct.ac.za/mir
Traditional risk management (5 of 5)
Legal and
political
• Lack of clarity in investment,
taxation and contract law
• Lack of clarity in energy policy
and restructuring
• Movement to merchant market
• No recourse to courts
• Change of law
• Cancellation of contracts
• Enforceable legislative framework for
foreign investment / taxation / property
rights / contract law
• Published energy policy backed by
legislation and reform steps with clear
IPP framework and level-playing field
with incumbent
• Change of law exemption
• Multi-lateral partners / finance
• Equity turn-over / local partners
• Renegotiation or exit options, linked
across issues
• Political risk insurance
• Partial risk guarantee
• Off-shore arbitration
Risk Mitigation
• Force Majeure for unforeseen circumstances, usually insurable
• Strikes and labour disputes usually contentious issue
• Parties to receive payments from power purchaser under Force Majeure
www.gsb.uct.ac.za/mir
Contributing elements to IPP success
• Favourable investment climate
• Clear policy and legal framework
• Coherent power sector planning
• Transparent and credible regulatory oversight
• Competitive bidding practices
Country level
www.gsb.uct.ac.za/mir
Contributing elements to success
• Committed equity partners
• Favourable debt arrangements
• Secure and adequate revenue stream – Credit worthiness of off-taker
– PPA
– Appropriate security & credit enhancement measures
• Secure, competitive fuel contracts
• Positive technical performance
• Ongoing strategic and risk management
Project level
www.gsb.uct.ac.za/mir
Non-OECD investments are unlocking projects
• Some Chinese examples
• Uganda: Karuma & Isimba Hydros
• Zambia: Kariba North Bank Hydro
• Zambia: Kafue Gorge Lower Hydro
• Ghana: Bui Hydro
• Ghana: Sun Asogli gas-fired power plant
• Ethiopia: Genale Dawa & other hydro
• etc
• Need for a better understanding of how these deals are
structured, risk assessed, procurement undertaken and
finance arranged – and how they might be replicated?
www.gsb.uct.ac.za/mir
DfiD’s role in facilitating more investment in power
• Strengthen enabling environment for investment – Clear policy and legal framework
– Coherent power sector planning PPIAF
– Transparent and credible regulatory oversight TAF
– Competitive bidding practices
• Support to governments in structuring transactions (DevCo)
• Early stage project development (InfraCo Africa)
• Mobilisation of domestic capital markets (DevCo)
• Long-term debt & mezzanine finance (EAIF)
• Specific support for renewables (GETFiT, GAP)
• …………
• …………
www.gsb.uct.ac.za/mir
Prof Anton Eberhard Research, training courses, consultancy
University of Cape Town
The Management Programme in Infrastructure
Reform & Regulation (MIR) is an emerging centre
of excellence and expertise in Africa. It is
committed to enhancing knowledge and capacity to
manage the reform and regulation of the electricity,
gas, telecommunications, water and transport
industries in support of sustainable development.
www.gsb.uct.ac.za/mir