Power & Energy _Presentation_M Tamim
-
Upload
mahbubul-haque -
Category
Documents
-
view
224 -
download
0
Transcript of Power & Energy _Presentation_M Tamim
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 1/45
Power and Energy:Bangladesh Scan
M Tamim
PMRE Dept, [email protected]
Jan 2009
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 2/45
Presentation Outline
Background
Last Ten Years
Present Status
Was Petrobangla sleeping?
Petrobangla Limitation
What to do? POWER
Way Forward
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 3/45
Background
Gas Discovered 1959 (chattak1) First Commercial Use 1962 (CCF)
Dhaka Household Supply 1968 Major fuel switching between 1980-85
After Independence 3 rnd of PSCs First PSC production from 1998
Present production BD 50%: IOC 50%
B k d
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 4/45
0
2
4
6
8
2
P G
I I P t
c f
1950 1960 1963 1977 1988 1990 1996
Year
Res
Rev
Bangladesh Gas Discoveries
C h a t t a k
S yl h e t
R
a s h i d p ur
K a i l a s
h t i l a
T i t a s
H a b i g a n j
B
a k h r a b a d
J a l a l a b a d
S a n g u
Bi b yi a n a M’ b
a z a r
PB discovery between 1977-2004is 2.5 tcf at 3:1 success ratio
Background
Shell (P) Discovery
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 5/45
Last Ten Years
1998 – Bibiyana 4 tcf gas discovered andstranded till 2004 dev request from PB
All IOCs stopped exploration from 1999
2000 – Unocal proposed gas export 2001 – Bangladesh Forex reserve $ 1.3 bil
yearly IPP and gas payment $400 mil
Business unable to open LC Petrobangla behind IOC payment by 6-7 months
2002 – 9-member Gas Util Committee formed
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 6/45
Last Ten Years
2002 Gas Util Comm Report
At least 5 year lead time required between activityand discovery
‘Limited export’ from new discovery is suggested as amarket signal to initiate immediate exploration work
(PB forex burden would reduce) As first right of refusal in the contract, Bangladesh
can always buy the gas (avoiding any export option) Irrespective to the reserve potential (floating on gas!)
if ‘new gas’ is not found, unmet demand will kick-inas early as 2010 If proper measures are not taken the ‘export’ and
‘import’ will not be far apart Encourage increase of gas use
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 7/45
Last Ten Years
No market signal of any kind was given to encourage
vigorous exploration IOCs relinquish all areas of risky investment and just
maintains minimum work program to hold onto thegood prospects
Only Bangura (.44 tcf) is discovered by Tullow withinold seismic data area (Leanest decade in BDexploration history)
In absence of IOC activities, BAPEX was also keptidle from exploration work
To use up Bibiyana reserve, gas use was encouragedin all sectors (the only recommendation implemented
by the governments)
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 8/45
Present Status
Total Production 1800 MMcfd Petrobangla 900 MMcfd
IOCs 900 MMcfd
Demand 2000 MMcfd Unmet demand 200 MMcfd
Due to transmission limitation 100 MMcfd Due to production limitation 100 MMcfd
ik
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 9/45
Tullow
4%
Niko
0.29%
Cairn
3%
SGFL
10%BAPEX
2%
Chevron
41%
BGFCL
40%
P r o d u c t i o n
PGCL
0%
BGSL
6%
JGTDSL
4%
GTCL70%
TGTDCL
20%
PGCL4%
JGTDSL
6%
BGSL
16%
TGTDCL
74%
Power
42%
Loss
3%Dom
10%CNG
5%Tea
0.2%Com
1%
Ind
13%Cap
11%
Fert
15%
Supply Chain1778 MMCFD
Di s t r i b u t i on
T r a n s m
i s s i o n
Consumption
H did i h ?
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 10/45
Annual Gas Demand at Different Growth Rates
0.2
0.4
0.6
0.8
1.0
1.2
1.4
2 0 0 1
2 0 0 2
2 0 0 3
2 0 0 4
2 0 0 5
2 0 0 6
2 0 0 7
2 0 0 8
2 0 0 9
2 0 1 0
2 0 1 1
2 0 1 2
2 0 1 3
2 0 1 4
2 0 1 5
2 0 1 6
2 0 1 7
2 0 1 8
2 0 1 9
2 0 2 0
T c f
3%
7%
1.28
1.06
0.88
0.72
0.60
Year 2000 consumption = 0.33 Tcf
How did we arrive here?
For the first time demand hasoutgrown all forecast!
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 11/45
Growth of CNG Filling Stations
7 2 3 6 41 41 23 42 647 9 12
18
59
100
123
165
229
0
50
100
150
200
250
1983-2000 2000-2001 2001-2002 2002-2003 2003-2004 2004-2005 2005-2006 2006-2007 2007-08
(April '08)
CNG Stations Cummulative Nos.
YEAR
N O S .
1Pabna
86Bogra
1B’baria1Lakhmipur
813Sylhet
116229Total
25Feni
612Comilla
1729Chittagong
12Manikganj
2Tangail
3Narsingdi
3Kishorganj
69N’ganj
627Gazipur
416Savar
5899Dhaka
ConversionWorkshop
CNGStation
Location
Captive Power Grow th wasequally phenomenal
Oil price rising
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 12/45
Was Petrobangla Sleeping?
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 13/45
GAS PRODUCTION-PETROBANGLA & IOC’s : FY 2002-03 to 2007-08(Jan,08)
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
G a s
i n M M S C M
PB 9449 9715 10086 10117 10149 5410
Cairn 1466 1480 1341 1573 1128 417
Chevron 1011 1626 2158 2930 3954 3353
Tullow 0 0 0 76 565 402
NIKO 0 0 198 225 124 33
TOTAL 11926 12821 13783 14921 15920 9615
2003 2004 2005 2006 2007 2008
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 14/45
Production Increase Between 2007 and 2008
17701644Jun17541646May
17571644Apr
16861574Mar
15721496Feb
16711407Jan
20082007Month
AVERAGE DAILY GAS PRODUCTION
(MMCFD)
Avge increase of 120 MMcfd was mostly used by non-bulk
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 15/45
GAS SALES STATEMENT :FY 2002-2008(UPTO JAN,08)
0
2000
4000
6000
8000
10000
12000
14000
16000
G a s i n M M C M
2002-035274 2716 741 1182 128 15 21 0 1269 11347 9.90%
2003-04 5647 2628 904 1313 136 5 23 55 1395 12106 6.69%
2004-05 5975 2661 1070 1456 138 0 23 103 1491 12917 6.70%
2005-06 6354 2523 1384 1791 147 0 21 194 1607 14020 8.61%
2006-07 6262 2647 1770 2194 160 0 21 335 1791 15185 8.30%
2007-08 3711 1313 1248 1445 106 0 17 328 1117 9286 4.83%
Power Fertilizer Captive Industry Comm Brick Tea CNG Dom Total%of
increase
System Loss
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 16/45
System Loss
1 7 7
6 5 5
7 7 6
6 9 2
6 7 8
5 3 7
0
10 0
2 0 0
3 0 0
4 0 0
50 0
6 0 0
70 0
8 0 0
9 0 0
2 0 0 2
/ 0 3
2 0 0 3
/ 0 4
2 0 0 4
/ 0 5
2 0 0 5
/ 0 6
2 0 0 6
/ 0 7
2 0 0 7
/ 0 8 ( U p
t o N o v )
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
G a s i n
M M S C M
Outstanding bill of Tk 270 crore recovered since Jan 2007
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 17/45
Petrobangla Limitation
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 18/45
Petrobangla Limitation Total IOC E&P Investment $1.5 Bill (since 1992)
Resulting 900 MMcfd production
Total PB E&P Investment $0.05 Bill (since 1990) Resulting 15 (30) MMcfd production
Lack of funding and latitude under the present modeof operation do not allow PB to react and rectifymarket imbalance like a true energy company on anemergency basis
If the commercial framework of gas business is notcorrected, Petrobangla will never be able to supplygas reliably
( b )
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 19/45
PSC Gas (December 2007)
10666:340.44(0.3)
Sep ‘10161Bangura2008
13671:293.1
(2.4)
Mar ‘10405Bibiyana
2007
9149:500.45
(0.36)
Recovered100M’bazar
2005
5730:701.19
(0.84)
Mar ’03217Jal’bad
1999
16280:201.03
(0.84)
Ongoing660Sangu
1998
Gas Price
Tk/Mcf
Cum gasshare
IOC:BD
Reserve
(Rec) tcf
CostRecvy yr
Cap Invst
Mill US$
Petrobangla Reality
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 20/45
Petrobangla Reality
OLD GAS vs. NEW GAS
90% of present PB gas was bought from
Shell at US$ 10 million(!) in 1975
Old Gas – less than $ 0.10/Mcf (!)
Cost of finding new gas from Green Fields BAPEX Tk. 65/Mcf (wellhead)
IOCs Tk. 70 – 110/ Mcf (wellhead)
Adding Proc, Trmn, Distbn (Cost+ price is Tk 140/Mcf) PB Weighted Ave price Tk. 93/Mcf
Minimum cost of import Tk. 500/ Mcf !
Chronology of World and
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 21/45
Chronology of World and
Bangladesh Gas Price
6508.065.0069.00- 10.81.0763.473.912007
1753.326.7858.15+1.71.2060702003
1703.226.2052.140.01.1854.662.92000
501.814.7440.25+11.31.1841.347.51994
1352.520.4535.80+112.01.0632.837.91990
5803.427.5331.00+6.30.5015.615.61985
8304.435.6916.25+2.10.477.757.71980
1701.310.4108.080.463.723.71974
Saving%
Eqvgasprice,
$/Mcf
Oil price$/bbl
Exchangerate
Taka/$
GasPrice(power)
change%
GasPrice(Power)
$/Mcf
GasPrice(Fertilizr)
Tk/Mcf
GasPrice(Power)
Tk/Mcfear
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 22/45
What to Do?
Gas Reserve Vs Production
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 23/45
Gas Reserve Vs Production(As of December 2007)
21.265
7.6918
5.4711
7.98 7.42
15.4035
0
5
10
15
20
25
Possible
Recoverable
Probable
Recoverable
Proven
Remaining
Product ion Prov en
Recoverable
Proven
G a si n
T
C F
> 9 0 %
4 0 - 8
0 %
<4 0 %
Current Reserve Categories –Supply Demand Balance
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 24/45
Current Reserve Categories –Supply Demand Balance
0
1000
2000
3000
4000
5000
6000
2 0 0 5
2 0 0 7
2 0 0 9
2 0 1 1
2 0 1 3
2 0 1 5
2 0 1 7
2 0 1 9
2 0 2 1
2 0 2 3
2 0 2 5
G a
s m m c f d
Proved Probable Possible Case B Demand
Shortfall would commence in 2011 against Proved ReservesShortfall would commence in 2011 against Proved Reserves
Ref: GSMP
2006
50 Bangladesh Floating on Gas!
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 25/45
0
5
10
15
20
25
30
35
40
45
PAST PRESENT FUTURE
G
a s i n T c f
Resources
Reserves
0.6 Tcf/year
Used up to 2007
7.4 Tcf
Bangladesh Floating on Gas!
13.4 tcf Remaing
32 tcf Potential(50%)
Expected Augmentation (short term)
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 26/45
Expected Augmentation (short term)
Based on Proven reserve and new drilling
175 MMscfd115 MMsfd165 MMscfd
(85 Wkover +80 Cap addn)
2010-112009-102008-09
Production AugmentationProduction Augmentation
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 27/45
Production AugmentationProduction Augmentation
Activ ities (Long term) Activ ities (Long term)
Cairn
Total EP& JV
Cairn-Chevron
Company
200Nov ’08 – June
‘12
Exploration in Block # 5 ,7,10
100Nov ’08
– June ‘12
Exploration Dril ling of Magnama &
Hatiya Structure
300 - 5002009-2016
Bangladesh Offshore Bidding Round 2008
50 - 100Nov ’08 – June
‘12
Exploration in Block # 17 & 18(3-D Seismic followed by explorationdril l ing)
Production
MMSCFD
PeriodPrograms
Transmission Projects under Implementation
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 28/45
30”x235k m
ADBDec 2011 Ashuganj-BKB-CTG Trans. Pipeline
(under active consideration of ADB)
30”x60kmWBJune 2010Bakhrabad – Siddirganj
24”x14km ADB/GOBJune 2010Pipeline from Titas field to A-Bpipeline
20”x165k m
ADBJune 2011 Bheramara-Khulna Pipeline
SizeFunded ByCompletionTime
Projects
12”x51km ADBJune 2009 Bonpara-Rajshahi Pipeline
30”x87km ADBJune 2010 Hatikamrul-Ishwardi-BheramaraPipeline
10000 hp ADBJune 2011 Elenga Compressor
Expansion to West Zone
BB Corridor Expansion
30”x51km ADBJune 2009Monohordi-JMB East Loopline
18000 hp ADBDec 2011 Ashuganj Compressor Station
12000 hp ADBDec 2011 Muchai Compressor Station
North-South System Expansion
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 29/45
CT Gov Measures 3D Seismic of 5 major PB gas fields to be completed
by 2011 may add 5 tcf of probable reserve to thesystem
With gas price increase, at least 1 tcf of thin bedreserve within PB fields will be commercially viable
BAPEX was granted $0.5 billion to be self supportingin seven years (highest in Bangladesh history)
Launched 3rd round offshore bidding
Actively pursued to vacate the onshore explorationmoratorium imposed by the high court Tried to resolve all disputes with the IOCs Tried to formulate coal policy
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 30/45
Power
The key to power is available anddiverse primary energy
Generally, funding and managementcan resolve power problem
POWER INDICATORS
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 31/45
POWER INDICATORS
137 kWhPER CAPITA CONSUMPTION
1 : 5 : 3.5 :2.5BD:IND:PAK:SL
4500 MWSUMMER PEAK DEMAND
700-900 MWPOWER SHORTAGE
3600-3800MW
PEAK GENERATION
40% ACCESS TO ELECTRICITY
STATUSINDICATORS
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 32/45
PRESENT POWER SITUATION
GENERATION CAPACITY
361247625232TOTAL
135214541454IPP
226033083778PUBLIC
MWMWMW
AVAILABLECAPACITY
(AS ON 08 APR 08)
DE-RATEDCAPACITY
INSTALLEDCAPACITY
TYPE
Maximum generation in history - 4130 MW
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 33/45
Fuel Mix of Power generation
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 34/45
Facts 2000 power sector master plan forecasted 5000 MW peak
demand for 2007 Only 80 MW power was added during 2001-2006 period
Presently 400-500 MW stranded capacity due to gas supplylimitation
300-400 MW F/S and maintenance 150-180 MW short in Kaptai due to water shortage Why gas shortage now?
It was always there. It has been exposed now due to power plantavailability by last year’s maintenance and management effort
Rapid decline of Sangu field Better performing fertilizer sector Unusual growth in CNG and captive power gas demand in a very
short span (2006-07)
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 35/45
Better but Not Good Enough(generation)
12033763256June
8134123331May
24036173376 April
66037733113March
81035032693FebruaryDiff (MW) 2008 (MW) 2007 (MW)
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 36/45
Measures by the CT Gov Through maintenance and Rehab, added 600 MW in
2007-08 Capacity addition in 2007-09
Plants commissioned 422 MW New Contracts signed 1100 MW Contracts in process 1400 MW
(Based on time bound (2008-2011) gas guarantee with someuncertainty)
NO MORE gas based power plants from existing
reserve Demand management
Efficiency – promoting CFL Conservation – Low usage Time shifting – Holiday staggering, Shopping hour Lifestyle motivation – Media campaign
S ( / i i )
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 37/45
System Loss (w/o transmission)
14.53
20.53
13.44
12.39
16.58
2006-07
%
13.0813.4WZPDCo
18.5819.03DESA
10.9210.62DESCO
14.314.07REB
14.5414.72PDB
Up to Apr’08 %
2007-08
%
Distn Cos.
Revenue increased by 1300 crore in 2007 over 2006(Average system loss reduction of 2%)
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 38/45
Other Measures by CTG Open merchant power generation for private
purchase (own fuel and market) Opening state gridlines for private use based on open
access rule Public-private partnership for all infrastructure
(mainly generation) Coal based power (coal policy to be approved) Renewable energy policy
Conservation act (in progress) Gas act (waiting final cabinet approval) Nuclear power
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 39/45
Way Forward
Power Sector Master Plan
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 40/45
Power Sector Master Plan
• Base plan for growth from 22,000 GWH to 100,000 GWH by 2025 calls for an additional 17,700megawatt (MW) of generating capacity to be installed by 2025. Will require significantinvestments, likely billions of dollars.
Current :~22000 GWH
Target 100,000GWH by 2025
Go Coal for Power Generation!R i B l d h
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 41/45
Reserves in Bangladesh
3906.68119-506Barapukuria,Dinajpur(1985) 1.
57230.00150-240Phulbari,Dinajpur(1997)
3.
143(GSB),685(Hosaf)
12.00257-483Khalaspir,Rangpur(1995)
2.
1,05016.00900-1000Jamalganj,Jaipur(1965) 4.
200
(partly
evaluated)
Yet to beKnown
327Dighirpar,Dinajpur(1995)
5.
No.
Total
Place/Field(Discovery)
2,897
Proven Reserve(Mill ion Ton)
Area(Sq. Km)
Depth(Meter)
A Probable Coal Consumption Scenario
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 42/45
A Probable Coal Consumption Scenario
1000 mill ion tons (1 bil l ion ton) 2014 1000 MW 3 m t
2015 1000 MW 2000 MW 6 m t 2016 1000 MW 3000 MW 9 m t
2017 1000 MW 4000 MW 12 m t
2018 1000 MW 5000 MW 15 m t
2019 1000 MW 6000 MW 18 m t 2020 1000 MW 7000 MW 21 m t
2021 1500 MW 8500 MW 25 m t
2022 1500 MW 10000 MW 30 m t
2023 1500 MW 11500 MW 35 m t 2024 1500 MW 13000 MW 39 m t
2025 1500 MW 14500 MW 43 m t
2026 1500 MW 16000 MW 48 m t
2027 2000 MW 18000 MW 54 m t 2028 2000 MW 20000 MW 60 m t 418 mill tons
COAL – Electricity Generation
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 43/45
COAL Electricity GenerationA COAL USE SCENARIO FOR BANGLADESH
0
10
20
30
40
50
60
70
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
YEAR
M I L L I O N
T O N S
8/3/2019 Power & Energy _Presentation_M Tamim
http://slidepdf.com/reader/full/power-energy-presentationm-tamim 44/45
Twenty Year Energy Security Find new gas, enhance existing production
Release maximum gas from power production usingcoal fired generation
Prioritize gas use for industry, CNG and fertilizer
Promote LPG for cooking Promote renewables, especially bio-gas and solar for
rural areas Immediate adjustment of all energy prices based on
ANY rational formula Reform of organizational and commercial framework
of energy business
Bottom Line!