7/31/2019 Post Outage Feedback
1/12
Power outages - 2011
Post Outage Feedback
Rome, October, 6th 2011
-
7/31/2019 Post Outage Feedback
2/12
Aboo power plant general data
ABOO 1
Commissioned in 1974
Nominal output: 365,5 MW
ABOO 2
Commissioned in 1985Nominal output: 556,2 MW
Imported subbituminous coal +
+ BFG + COG + Steel mill gases
Open cycle cooling water
-
7/31/2019 Post Outage Feedback
3/12
Historical Frame
Ageing of units
As the plants age, nature of problems change (creeping, fatigue, electricalisolation)
Developement of plant scheduling
Greater user knowledge + warranties over + amortized equipment
Futureperspectives
Decommissiong Vs Repowering
-
7/31/2019 Post Outage Feedback
4/12
Present situation of (Spanish) market
Operation Pattern
2005 = Base load
2010 = Secondary Regulation
2012 = Stop?
Competitive situation
Plant efficiency and availability Vs flexibility and technical minimum load
-
7/31/2019 Post Outage Feedback
5/12
Learning organizations
Experience
Nobody does it better
Nobody does it the best
Learning organizations
-
7/31/2019 Post Outage Feedback
6/12
Benefits
Be more efficient, by internalization of better practices
Be more reliable, by developing better responses againstunexpected
Be safer, by continuosly reviewing our procedures
Be more flexible, by increasing versatility of own resources
Be more independent, by having the knowledge sharedby the team
-
7/31/2019 Post Outage Feedback
7/12
How we learn
We learn from our own mistakes
We learn from the mistakes of others
We learn from benckhmarking and networking
We search the market for better practices
We identify opportunities to improve
We use tools and levers
o Promoting day to day spaces for sharing of
knowledge, to develop common models
o Creating a Company Culture based on clear
politics to act as a guide to create a sharedvision.
o Involving staff in continuous improvement
projects
o Emphasizing from the leadership
o Spreading knowledge by making information
accesible and friendly.
-
7/31/2019 Post Outage Feedback
8/12
How we learn
DefineClear prioritization of goalsStandarized procedures
Detailed documentation about time
schedule and scope
ImplementInvolve
CommunicateProvide flexible and agile hierarchy
MeasureSet clear metrics which can be
validated
Focus on KPIs
Provide comprehensive
coverage(Technical, Economical, H&S,etc.)
AssessDetailed conclussions on achievement
of goals and deviations
-
7/31/2019 Post Outage Feedback
9/12
What we do; Planning
Matrixed organization
Same specilized workers involved indifferent projects teams leaded bydifferent project managers
Predefined Standard ScopeDetailed jobs, with estimation of times,
costs and spares. Used as a baseline forthe definition of the final scope.
Involvement of technicians asapThrough work teams complying withmatrixed organization where detailed
scope and planning is propposed.
Consolidation by managersProjects are merged into a consolidatedplanning by team managers with onlyone overhaul coordinator.
Jos AntonioGarca Martnez
Jos Antonio dela Guerra Alonso
EDP
Trabajos elctricose I&C en general
Alternador ytrafos
DCS / BMS /Turbotrol
Pedro Martnez Mielgo /Juan Francisco Fernndez
Pablo lvarez Vigil
Vanesa Hernndez / VctorFidalgo
QuemadoresBajo NOx
Automatizacinde Ignitores
Reconstruccincenicero
Enric ComaResponsable Proy. Ecos.
Interlocutor yCoordinador Revisin
DireccinRevisin
ProyectosLEAN
Agua decirculacin
Trabajosmecnicos engeneral
Molinos,Ventiladores yCAS
TurbinaIgnacio Alvarez / RafaelGutirrez
Carboneo ycenizasJorge Nieto Rodrguez
-
7/31/2019 Post Outage Feedback
10/12
What we do; Execution
Previous specific training for own personnel andcontractors
Additional supervising resources
Daily briefings with supervisors at the workshops
Project follow up meetings every 2-3 days, with projectmanagers, supervisors and contractor delegates
Weekly coordination meetings with concurrentcontractors, focusing on H&S issues
Preventive observations of H&S and environmentalbehaviours
-
7/31/2019 Post Outage Feedback
11/12
What we do; Measuring
Technical MeasurementsBaseline measurements before overhaulStandarized test program based on thermal performance of main equipmentindividually
Boiler Feedwater heaters Primary/Secondary air preheaters Boiler feedwater pumps
Circulating water pumps Turbine Condenser Overall thermal balance Other on demand
-
7/31/2019 Post Outage Feedback
12/12
What we do; Measuring
Economical MeasurementsControlling by projects. Each project corresponding to a main system:1. Boiler2. Generator & Turbine3. Secondary Air Preheaters4. ESP and Ducts
5. Cooling Water System6. Mills and Combustion7. Fly-ash and Bottom-ash Handling System8. Main Fans (IDF & FDF)9. Condensate and Feedwater System10. Main transformers and power distribution
11. HV Motors12. Control System13. FGD14. Others
This allows to compare developing of OPEX between overhauls.Spares and materials, tools and equipment, fungibles and labour are
considered separatelly.