Transcript of Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.
![Page 1: Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.](https://reader036.fdocuments.us/reader036/viewer/2022082713/5697bfbd1a28abf838ca241c/html5/thumbnails/1.jpg)
Portola Middle School and Gompers/Leadership Public Schools
OPSC Funding Status Update
![Page 2: Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.](https://reader036.fdocuments.us/reader036/viewer/2022082713/5697bfbd1a28abf838ca241c/html5/thumbnails/2.jpg)
Portola Middle School
• Estimated State Funding -- $14.3M– Seismic and modernization requests– No bonding authority reserved; seismic
conceptual approval on 3/23/11
• Funding requests submitted upon CDE/DSA approval– Approvals anticipated 1-2 weeks (maybe sooner)– Preparing submittal in anticipation of agency
approvals
![Page 3: Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.](https://reader036.fdocuments.us/reader036/viewer/2022082713/5697bfbd1a28abf838ca241c/html5/thumbnails/3.jpg)
Gompers/LPS
• LPS– Current estimated State funding $13.4M
• includes January 2012 construction cost index adjustment of 3.76%
• Includes $3M loan component• Preliminary apportionment on 5/28/08; bond authority reserved
up to maximum of $15.3M
– Funding requests submitted upon CDE/DSA approval• Approvals anticipated end of February• Applicant switch has been submitted• Preparing submittal in anticipation of agency approvals• Strategize timing of submittal to maximize funding; balance with
availability of funds for Gompers
![Page 4: Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.](https://reader036.fdocuments.us/reader036/viewer/2022082713/5697bfbd1a28abf838ca241c/html5/thumbnails/4.jpg)
Gompers/LPS
• LPS– Advanced fund release option -- $2.4M• Requires update to Charter financial soundness
(received on 1/25/12)• Requires executed Charter School Agreements which
the District and LPS are working to finalize• Submittal deadline is 5/2/12
![Page 5: Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.](https://reader036.fdocuments.us/reader036/viewer/2022082713/5697bfbd1a28abf838ca241c/html5/thumbnails/5.jpg)
Gompers/LPS
• Gompers– Estimated State Funding -- $1.8M• Modernization request
– Funding requests submitted upon CDE/DSA approval• Approvals anticipated by end of February (same plan
set as LPS)• Preparing submittal in anticipation of agency approvals
in coordination with LPS funding request
![Page 6: Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.](https://reader036.fdocuments.us/reader036/viewer/2022082713/5697bfbd1a28abf838ca241c/html5/thumbnails/6.jpg)
Other Funding Updates
• De Anza HS– Fund Released to District -- $13.3M
• Warrant issued on 2/2/12
• Richmond HS and Nystrom ES– Unfunded approvals
• Richmond -- $11.5M• Nystrom – $747K
– Submitted to participate in current priority in funding round
– State GO Bond sales scheduled for March and April 2012• Amounts and school facility share of sale to be determined
• Kennedy HS – Submitted to OPSC -- $6.1M
![Page 7: Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.](https://reader036.fdocuments.us/reader036/viewer/2022082713/5697bfbd1a28abf838ca241c/html5/thumbnails/7.jpg)
Thank you!