Portfolio Performance January-mid October 2006

2
SO DPO Sponsor Update/Rev iew November End 2006 11/30/2006 SO 5A 30021 Replace DSM6 High Speed Freq Rec (1.1b) 50002 Enhancements to MOMS ISR (1.0a) SO 5B (2005 Carry) 50050 Satellite Communication for Black Start Suppliers (1.3) 50008 PRR502 Aggregation of Combined Cycle Units (1.0b) 40090-01 Operator Training Center (1.0a) SO 5C (2005 Carry) 30105 Congestion Management Reports (1.0b) 50135 Topology Estimation System Phase 1 (1.1a) 50136 EMMS Software Upgrade – OSI PI, OAG (1.1b) 50151 Additional SMP Front End 50021 Improve Reliability of Freq Input (1.0b) 50005 EDW EMMS Extracts (1.0a) Portfolio Performance January-mid October 2006 System and Market Operations Market Oversight Division Qualified Transmission Service Providers Energy and Market Management Texas Market Link Settlements and Billing Market Oversight EDW/Business Intelligence Monitoring Stakeholders Systems Q2 ‘06 Q3 ‘06 Q1 ’06 Q4 ’05 Q4 ‘06 Q1 ‘07 Release SO 6B2 Release SO 5C Release SO 6B1 Release 6B1 60002_01 Increase Number of Seats for Study MCE (1.1a) 50083_01 Breaker to Breaker one lines map (1.1b) 60080_01 SCR747 Removal of Price Admin for Zonal Cong (1.1) and 60079_01 Upgrade of ERCOT MCE Software to AIMMS 3.6 (1.1) 50003 Enhancements to MOMS Study MCE (1.0a) Release SO 4A and 4B Release 4A (2004 Carry) 30161 PRR413 - Optimization for the Whole Operating Day in RPRS Procurement Process (1.1) 40072 PUCT Add Corrected MCPEs to the MOS dbase and pass to MMS (1.1) Release 4b (2004 Carry) 40098 Perf Monitoring for SCADA/SE (1.0b) 40113 RAP-C Modeling Enhancements (1.0b) 40084 Outage Scheduler Phase II (1.0a) Cancelled Cancelled 40086 Incident Report (1.0a) 30084 CSC Thermal and Voltage Limit Calcs (1.0a) 40100 RTCA Archiving (1.0b) Active (at least in Initiation) New or Not Started SO 5A SO 5B Release 6B2 50029 Improvement of VSA/DSA – Phase 2 (1.0b) 60001_01 EIS BI Foundations III (1.1) 40090-02 Operator Training Simulator (1.0a) 60082_01 SCR746 Dynamic Rating Data through ICCP (1.1) 60081_01 15 Minute Ramping for BES and Base Power Schedule (1.1) 60084_02 Mid Term Load Forecast Enh Ph 2 (1.1) Completed

description

Portfolio Performance January-mid October 2006. Energy and Market Management Texas Market Link Settlements and Billing Market Oversight EDW/Business Intelligence Monitoring. System and Market Operations - PowerPoint PPT Presentation

Transcript of Portfolio Performance January-mid October 2006

Page 1: Portfolio Performance January-mid October 2006

SO DPO Sponsor Update/Review November End 2006

11/30/2006

SO 5A • 30021 Replace DSM6 High Speed Freq Rec (1.1b)• 50002 Enhancements to MOMS ISR (1.0a)

SO 5B (2005 Carry)• 50050 Satellite Communication for Black Start

Suppliers (1.3)• 50008 PRR502 Aggregation of Combined Cycle

Units (1.0b)• 40090-01 Operator Training Center (1.0a)

SO 5C (2005 Carry)• 30105 Congestion Management Reports (1.0b)• 50135 Topology Estimation System Phase 1 (1.1a)• 50136 EMMS Software Upgrade – OSI PI, OAG

(1.1b)• 50151 Additional SMP Front End• 50021 Improve Reliability of Freq Input (1.0b)• 50005 EDW EMMS Extracts (1.0a)

Portfolio Performance January-mid October 2006

System and Market OperationsMarket Oversight Division Qualified SchedulingTransmission Service Providers Entities

Energy and Market Management Texas Market LinkSettlements and Billing Market OversightEDW/Business Intelligence Monitoring

StakeholdersSystems

Q2 ‘06 Q3 ‘06Q1 ’06Q4 ’05 Q4 ‘06 Q1 ‘07

Release SO 6B2

Release SO 5C

Release SO 6B1

Release 6B1•60002_01 Increase Number of Seats for Study MCE (1.1a)•50083_01 Breaker to Breaker one lines map (1.1b)•60080_01 SCR747 Removal of Price Admin for Zonal Cong (1.1) and 60079_01 Upgrade of ERCOT MCE Software to AIMMS 3.6 (1.1)•50003 Enhancements to MOMS Study MCE (1.0a)

Release SO 4A and 4B

Release 4A (2004 Carry)• 30161 PRR413 - Optimization for the Whole

Operating Day in RPRS Procurement Process (1.1)

• 40072 PUCT Add Corrected MCPEs to the MOS dbase and pass to MMS (1.1)

Release 4b (2004 Carry)• 40098 Perf Monitoring for SCADA/SE (1.0b)• 40113 RAP-C Modeling Enhancements (1.0b)• 40084 Outage Scheduler Phase II (1.0a) CancelledCancelled• 40086 Incident Report (1.0a)• 30084 CSC Thermal and Voltage Limit Calcs

(1.0a)• 40100 RTCA Archiving (1.0b)

Active (at least in Initiation)New or Not

Started

SO 5A SO 5B

Release 6B2 • 50029 Improvement of VSA/DSA – Phase 2 (1.0b)• 60001_01 EIS BI Foundations III (1.1)• 40090-02 Operator Training Simulator (1.0a)• 60082_01 SCR746 Dynamic Rating Data through

ICCP (1.1)• 60081_01 15 Minute Ramping for BES and Base

Power Schedule (1.1)• 60084_02 Mid Term Load Forecast Enh Ph 2 (1.1)

Completed

Page 2: Portfolio Performance January-mid October 2006

SO DPO Sponsor Update/Review November End 2006

11/30/2006

Release 5C (2005 Carry)• 50021 Improve Reliability of Freq Input• 50130 SCE Performance and Monitoring (1.1a)• 50134 DC Tie Automation• 60084_01 Mid Term Load Forecast Enh Ph 1 (1.1)

Portfolio Performance January-October 2007

System and Market OperationsMarket Oversight Division Qualified SchedulingTransmission Service Providers Entities

Energy and Market Management Texas Market LinkSettlements and Billing Market OversightEDW/Business Intelligence Monitoring

StakeholdersSystems

Q2 ‘07 Q3 ‘07Q1 ’07Q4 ’06 Q4 ‘07 Q1 ‘08

Release 6B2

Release 5C

Release 7A

Release 4B

Release 4b (2004 Carry)• 30084 CSC Thermal and Voltage Limit Calcs

Active (at least in Initiation)New or Not

Started

Release 6B2 • 60081_01 15 Minute Ramping for BES and Base Power

Schedule• 60082_01 SCR746 Dynamic Rating Data through ICCP• 50029 Improvement of VSA/DSA – Phase 2 • 40090-02 Operator Training Simulator• 60084_02 Mid Term Load Forecast Enh Ph 2

Completed

Release 7A• 50052_01 Operations Support Study Environment• 40085_01 Performance Monitoring for ERCOT, TDSP, & QSE• 50038_01 Generator Database Automation• 50071_01 Governor Analysis Enhancements• 50093_01 Outage Coordination Statistical Reports• 50055_01 Voltage/Reactive Compliance Management Database• 50070_01 Unit Testing-Electronic Submittal via Web