Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4...

80
 COMMISSION SECRETARIAT Level 13, 301 George Street SYDNEY, NSW 2000 GPO BOX 3415, SYDNEY, NSW 2001 TELEPHONE (02) 9383 2100 FAX (02) 9299 9835 [email protected]        Port Waratah Coal  Services Terminal  4 Project Review Report                   Mr Paul Forward (Chair) Mr Joe Woodward PSM Mr Brian Gilligan      1 December 2014   

Transcript of Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4...

Page 1: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

COMMISSION SECRETARIAT Level 13, 301 George Street SYDNEY, NSW 2000 GPO BOX 3415, SYDNEY, NSW 2001 TELEPHONE (02) 9383 2100 FAX (02) 9299 9835 [email protected]

       

Port Waratah Coal Services Terminal 4 Project Review Report                   

Mr Paul Forward (Chair) Mr Joe Woodward PSM Mr Brian Gilligan      1 December 2014 

   

Page 2: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

                      

Port Waratah Coal Services Terminal 4 Project PAC Review Report©  State of New South Wales through the NSW Planning Assessment Commission, November 2014.   NSW Planning Assessment Commission Level 13, 301 George St Sydney NSW Australia Telephone: (02) 9383 2100 Email: [email protected] ISBN 978-0-9871563-8-9   Disclaimer  While every  reasonable effort has been made  to ensure  that  this document  is  correct at  the time  of  publication,  the  State  of New  South Wales,  its  agencies  and  employees,  disclaim  all liability to any person  in respect of anything or the consequences of anything done or omitted to be done in reliance upon the whole or any part of this document.  The NSW Planning Assessment Commission advises that the maps included in the report are to give visual support to the discussion presented within the report.  Hence information presented on the maps should be seen as  indicative, rather than definite or accurate.   The State of New South Wales will not accept responsibility for anything, or the consequences of anything, done or omitted to be done in reliance upon the mapped information.  

Page 3: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

i

Executive Summary   

The  Planning  Assessment  Commission  (the  Commission)  has  been  directed  to  review  the  Port Waratah  Coal  Services  (PWCS)  Terminal  4  Project  and  its  supporting  studies.  In  particular,  the Commission has been asked  to assess  the merits of  the project, paying particular attention  to  the potential noise and air quality, traffic, biodiversity and contamination impacts; and recommend any appropriate measures to avoid, minimise and/or offset these impacts. 

The Commission  to undertake  the  review was constituted by Paul Forward, Brian Gilligan and  Joe Woodward (PSM).  The Terminal 4 Project  is a proposal  for a  fourth coal export  terminal  to be  located on Kooragang Island in the Port of Newcastle. The terminal would have a capacity to export up to 70 million tonnes of coal per annum (mtpa) and  includes rail and coal receival  infrastructure; coal stockpile pads and associated machinery; wharf and berth infrastructure; coal conveyors; feeders and transfer stations; and  other  associated  infrastructure.  Three  biodiversity  offset  sites  located  at  Ellalong  Lagoon, Brundee Swamp Nature Reserve and Tomago also form part of the proposed development.  The proposal has an estimated capital  investment value of $4.8 billion and  is expected to generate 1,500  construction positions and up  to 80 operational positions. The  facility would operate as an ‘open  access  terminal', meaning  access  to  terminal  facilities would  be  available  to  any  operator wanting to export coal.  Newcastle  is  the world's  largest  coal  export  port1,  exporting  over  134 million  tonnes  of  coal  per annum in 2012, and handling over $20 billion in general trade annually. Notwithstanding the current softening  of  coal  demand  in  the  world  market,  the  Reserve  Bank  of  Australia,  the  Australian Government Bureau of Resources and Energy Economics (BREE) and the Newcastle Port Corporation all expect demand  to  continue  to  grow. The  current  combined  capacity of  the Port of Newcastle (comprising NCIG, KCT and CCT terminals)  is 211 million tonnes per annum and  if T4 was approved and built, capacity would be 281 mtpa.  The Secretary’s Preliminary Environmental Assessment Report (PEAR) states that  in 2013 a peak of 150.5 million tonnes of coal was exported through the Port of Newcastle, representing an  increase of  17  percent  on  the  previous  year's  exports.  Notwithstanding  this  increase,  the  Commission acknowledges the demand for coal has since softened and there is no immediate need for the fourth coal  terminal. However, while  fluctuations  in  the market may delay  the  requirement  for a  fourth terminal,  it  is  recognised  that  the  ability  to meet  an  increased  demand  in  the  future  requires continued investment and expansion in supporting infrastructure.   The proposed development is a Major Project subject to the transitional provisions of Part 3A of the Environmental  Planning  and  Assessment  Act  1979.  The  project  is  also  a  controlled  action  and requires approval under  the Environment Protection and Biodiversity Conservation Act 1999. The Commonwealth Minister  for  the  Environment  will  make  a  determination  on  the  proposal  with reference to the Department's assessment of matters of national significance.  

                                                            1 NSW Department of Planning and Environment. 2014. Secretary’s Preliminary Environmental Assessment Report.p.2. June 2014 

Page 4: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

ii

The Commission held public hearings on  the project on 26  and 27 August 2014, where over 130 verbal  and  written  submissions  were  made  for  and  against  the  proposal.  Speakers  in  support explained  that  the  coal  terminal  would  provide  regional  employment  and  economic  growth  to Newcastle and the wider region. A number of speakers encouraged the use of existing industrial land for the terminal, as it is located away from residential properties. Significant concerns and objections to the project came from the  local community and special  interest groups, with the primary  issues being air quality health impacts, biodiversity impacts and contamination. Another recurring concern heard by the Commission was that the economic benefits of the proposal have been overstated and that there is no economic rationale for a fourth coal terminal.  The Commission has carefully considered all the information identified by the Minister as relevant to the  review.  The  merits  and  potential  impacts  associated  with  the  project  have  been  critically examined,  as  well  as  measures  proposed  to  avoid,  mitigate  or  manage  them  through  the Department’s draft conditions of approval. Prior to the Public Hearing, the Commission visited the site  and  surrounds  and met  with  representatives  of  Newcastle  City  Council  and  Port  Stephens Council.  During  the  course  of  the  assessment,  various  meetings  were  held  with  government agencies,  including the Environment Protection Authority, The Office of Environment and Heritage and the Commonwealth Department of Environment.  Acknowledging the community’s significant concerns about the economic rationale for an additional coal  terminal  at  the  Port  of  Newcastle,  the  Commission  engaged  the  Centre  for  International Economics  (CIE)  to  review  the  robustness of  the Proponent’s economic analysis  in  support of  the additional  coal  terminal;  and  consider  the  criticisms made  in  the Australia  Institute’s  submission regarding  the  Proponent’s  economic  assessment.  The  CIE  concluded  that  the  general  approach taken by the Proponent is generally reasonable and based on current contracted volumes, estimates that the project would not be needed until after 2023.  In considering  the project as a whole, the Commission  largely agrees with  the position adopted  in the Department’s Preliminary Assessment Report. This position is that the Proponent’s rationale for the  fourth coal terminal  is generally credible, although  the  timing and staging of the development could  be  better  defined.  The  reasons  for  this  are  set  out  in  detail  in  this  Review  report.  The Commission considers that if the recommendations outlined below are adopted, then there is merit in allowing the project to proceed.   

1. Approval lapse period The  Commission  recommends  a  five  year  rather  than  ten  year  approval  period  for  the project.   A ten year commencement period could result  in extended delays  in dealing with contamination  and  biodiversity  issues;  as well  as  sanctioning  a  project  out  of  step with potential changes to air quality standards and greenhouse gas policies. A five year approval provides  a  reasonable  period  to  commence  construction  based  on  current  planning  and environmental requirements.     

2. Biodiversity (a) The  Commission  is  of  the  view  that  the  Proponent  needs  to  demonstrate  that  the 

proposed  Tomago  offset  area  is  functioning  successfully  prior  to  construction commencing  at  the  project  site. While  the  Commonwealth  recommends  one  year  of demonstrated  success,  the Commission  considers Tomago  should be  functioning  for a minimum of three years to be confident of documenting at  least one successful season of usage by migratory shorebirds. 

(b) Further  consideration of  the design of  the project  is  required, especially  the northern location of stockyards, to minimise impact on the frog populations in the Frog Pond and 

Page 5: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

iii

Railway  Pond.  This  could  also  provide  improved  Australasian  Bittern  habitat  and minimise  the  impact  on  migratory  shorebirds  utilising  habitat  along  the  northern shoreline of Deep Pond. 

(c) The  Commission’s  recommended  five  year  approval  period  would  provide  an appropriate timeframe for the Proponent to commence the priority conservation works outlined in this report, which would have significant biodiversity benefits and constitute substantial commencement of  the development. A  ten year approval could potentially delay a start to the important conservation works. 

 3. Contamination 

(a) The  Commission  considers  that  the  contamination  on  Kooragang  Island  should  be remediated as  soon as practicable. A  five year approval  (rather  than  the proposed 10 year approval) would ensure that the remediation process  is not unnecessarily delayed and  provide  increased  certainty  that  these  important  public  interest  benefits  are delivered  in a cost effective manner. As a first step  in resolving the remediation of the site,  the Commission  is of  the view  that  the Proponent,  the EPA and  the HDC need  to negotiate and agree on a comprehensive remediation strategy and timetable with roles and responsibilities, before a determination is made on the project.  

(b) The Commission  recommends adoption of  the amendments and additional  conditions recommended by  the EPA  in  the correspondence dated 10 October 2014.  In addition, Condition B32  should be amended  to  reference a one  in 100 year average  recurrence interval discharge event, (as in correspondence from the EPA dated 25 August 2014). 

 4. Air quality 

The Commission received many submissions expressing concern about the health impacts of particulate  emissions  associated with  the  project.  Having  sought  expert  advice  from  the NSW Health and the Environment Protection Authority, and considered the  issue  in detail, the Commission  is  satisfied  that by  concentrating  coal handling on Kooragang  Island, at a greater distance from residential areas than other existing sources, T4 could provide greater flexibility  to  improve  air quality  in Newcastle  residential  areas  if  community  expectations and regulatory requirements tighten as expected.  

5. Covering Coal Wagons The best  information available  to  the Commission at  this  time  is  that  the most  significant sources of particulate emissions  from  coal  trains are  from  the diesel  locomotives and  the undercarriage  of  recently  unloaded wagons,  rather  than  the  uncovered  tops  of wagons. There  is  little or no evidence  that uncovered wagons contribute significantly  to particulate air  quality  in  the  Newcastle  area  and  therefore  no  justification  for  recommending  that wagons be  covered. To  the extent  that emissions  from  loaded wagons are  identified as a problem,  requirements  to profile  loads, maintain moisture  levels and/or apply veneers  to suppress dust appear to represent more viable alternative controls. 

 

   

Page 6: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

iv

Table of Contents 

Executive Summary ........................................................................................................................ i 

Table of Contents ........................................................................................................................... iv 

Glossary ......................................................................................................................................... vi 

  INTRODUCTION ...................................................................................................................... 1 1

1.1  Site Description ..................................................................................................................... 1 1.2  The Proponent ...................................................................................................................... 1 1.3  Strategic context ................................................................................................................... 1 1.4  Proposal ................................................................................................................................ 2 1.5  Comparison between the current application original proposal .......................................... 6 1.6  The Secretary’s Preliminary Environmental Assessment Report (PAR) ................................ 7 

  THE COMMISSION’S REVIEW TASK .......................................................................................... 8 2

2.1  Terms of Reference for the Review ...................................................................................... 8 2.2  Public Hearings and Submissions .......................................................................................... 9 2.3  Documents, meetings and site inspections ........................................................................ 10 

  JUSTIFICATION ....................................................................................................................... 11 3

3.1  Proponent’s justification ..................................................................................................... 11 3.2  Department’s position ........................................................................................................ 12 3.3  Alternative economic analysis ............................................................................................ 12 3.4  Review of proponent’s economic analysis .......................................................................... 13 3.5  Commission’s view .............................................................................................................. 14 

  COMMENTS, FINDINGS AND RECOMMENDATIONS RELATING TO THE TERMS OF REFERENCE 14 4

4.1  Biodiversity ......................................................................................................................... 14 4.1.1  Migratory Shorebirds ............................................................................................. 16 4.1.2  Australiasian Bittern ............................................................................................... 19 4.1.3  Green and Golden Bellfrog (GGBF) ........................................................................ 21 4.1.4  Hunter Estuary Wetlands Ramsar site ................................................................... 23 4.1.5  Conclusions and Recommendations ...................................................................... 24 

4.2  Contamination .................................................................................................................... 25 4.2.1  Background ............................................................................................................ 25 4.2.2  Proposed remediation and rehabilitation .............................................................. 26 4.2.3  Dredging materials and groundwater .................................................................... 27 4.2.4  EPA advice .............................................................................................................. 31 4.2.5  Conclusions and Recommendations ...................................................................... 31 

4.3  Air Quality and associated health impacts .......................................................................... 32 4.3.1  Current particulate levels and standards ............................................................... 32 4.3.2  Impacts of the Project ............................................................................................ 34 4.3.3  Conclusion and Recommendations ........................................................................ 45 

4.4  Noise ................................................................................................................................... 46 4.5  Traffic .................................................................................................................................. 51 4.6  Other Considerations .......................................................................................................... 52 

4.6.1  Greenhouse Gas Emissions .................................................................................... 52 

Page 7: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

v

4.6.2  Strategic direction for the Port and City of Newcastle and wider Hunter Region . 57 4.6.3  Stormwater/ground water ..................................................................................... 62 4.6.4  Voluntary Planning Agreement AND DEVELOPMENT CONTRIBUTIONS ................ 63 

5.  CONCLUSION ......................................................................................................................... 65 

6.  Recommendations .............................................................................................................. 66 

References .................................................................................................................................... 68 

List of Appendices ......................................................................................................................... 71 

 Figures Figure 1 – Site and surrounding land uses ‐ western view Figure 2 – Site and surrounding land uses ‐ eastern view Figure 3 ‐ Indicative outline of the site and surrounding areas Figure 4 ‐ Landfill areas Figure 5 ‐ Proposed contamination management and remediation measures  Tables  Figure 1:  Site and surrounding land uses ‐ western view (source:  PPR, 2014, p.25) ............................ 4 Table 1 – Summary of Issues ................................................................................................................... 9 Table 2 – List of Commission meetings ................................................................................................. 11 Figure 3: Indicative outline of the site and surrounding areas (Source: T4 Project Response to Submissions and PPR (EMM 2013)) ...................................................................................................... 16 Table 3 ‐  Summary of Issues raised by the Commonwealth Department of Environment regarding Migratory Shore Birds ........................................................................................................................... 18 Table 4 ‐ Summary of Issues raised by the Commonwealth Department of Environment regarding the Australasian Bittern .............................................................................................................................. 20 Table 5 ‐ Summary of Issues raised by the Commonwealth Department of Environment regarding the Green and Golden Bell Frog .................................................................................................................. 22 Table 6 ‐ Summary of Issues raised by the Commonwealth Department of Environment regarding Ramsar Wetlands .................................................................................................................................. 24 Table 7 ‐ Ownership status of Landfill Areas on the Project Site .......................................................... 26 Figure 4:  Landfill areas (Source:  T4 Project Response to Submissions and PPR (EMM 2013)) ........... 29 Figure 5:  Proposed contamination management and remediation measures (Source:  T4 Project Response to Submissions and PPR (EMM 2013)) ................................................................................. 30 Table 8 ‐ Current NEPM Standards and Goal for particulates (as varied in 2003) ................................ 32 Table 9– NSW EPA Impact Assessment Criteria for Particulates .......................................................... 33 Table 10 ‐ Annual Average PM10 and PM2.5 levels (sourced from OEH air quality data) ...................... 33 Table 11– Highest predicted particulate emissions contribution from the project at Sandgate, under different stages of development .......................................................................................................... 36 Table 12 ‐ Maximum allowable noise contribution (dBA) under the planning approval for the Kooragang Coal Terminal  ..................................................................................................................... 47 Table 13 – Proponent’s predictions (dBA) of the combined intrusive impact from T4 and the existing Kooragang Coal Terminal ...................................................................................................................... 47 Table 14 Department's recommended Maximum allowable noise contribution (dB(A)) from the combined operations of T4 and the Kooragang Coal Terminal ............................................................ 48 Table 15 ‐ EPA Recommended Noise Limits (dBA) and Localities ......................................................... 48 

    

Page 8: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

vi

Glossary 

ARTC  Australian Rail Track Corporation 

BMP  Biodiversity Management Plan  

BOP  Biodiversity Offset Package  

BOS  Biodiversity Offset Strategy  

CBA  Cost Benefit Analysis 

CCT  Carrington Coal Terminal  

CFA  Capacity Framework Agreement 

the CIE  The Centre for International Economics 

CO2‐e  Carbon dioxide equivalent 

Commission  Planning Assessment Commission constituted for this review and public hearing, Mr Paul Forward (Chair), Mr Joe Woodward PSM and Mr Brian Gilligan  

dB(A)  Decibels (A weighted) 

EEC  Endangered Ecological Community 

EA  Environmental Assessment prepared by EMM Consultants, February 2012 

EP&A (or the Act)  Environmental Planning and Assessment Act 1979 

EPA  Environment Protection Authority 

EPBC Act  Commonwealth  Environmental  Protection  and  Biodiversity  Conservation  Act 1999 

EPL  Environment Protection Licence 

GGBF  Green and Golden Bell Frog 

GHG  Greenhouse Gases 

HDC  Hunter Development Corporation 

HVCC  Hunter Valley Coal Chain 

INP  NSW Industrial Noise Policy 

KCT  Kooragang Coal Terminal 

LCP  Landfill Closure Plan 

LGA  Local Government Area 

Mtpa  Million tonnes per annum 

NCIG  Newcastle Coal Infrastructure Group 

NEPM  National Environment Protection Measure 

OEH  Office of Environment and Heritage 

PAC  Planning Assessment Commission 

PEAR  Secretary’s  (of  the  Department  of  Planning  and  Environment)  Preliminary Environmental Assessment Report 

PM10  Particulate matter with an aerodynamic diameter smaller than 10 micrometres 

Page 9: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

vii

PM2.5  Particulate matter with an aerodynamic diameter smaller than 2.5 micrometres 

PPR  Proponent’s  Response  to  Submissions  and  Preferred  Project  Report  (EMM, September 2013) 

RAP  Remediation Action Plan 

ROM  run‐of‐mine coal 

RTS  Proponent’s Response to Submissions 

SCA  State Conservation Area 

the Department  Department  of  Planning  and  Environment  (previously  Planning  and Infrastructure) 

the Proponent  In this report being PWCS .  ‘Proponent’ includes the Proponent’s EIS consultants. 

the proposal  The subject of the application under the transitional arrangements  in place as a result of the repeal of Part 3A of the EP&A Act 1979, in this report being the Port Waratah Coal Services Terminal 4 Project.  Mainly referred to as ‘the project’. 

PWCS  Port Waratah Coal Services 

TAI  The Australia Institute 

TSP  Total suspended particulate 

TSC Act  Threatened Species Conservation Act 1995 

 

Page 10: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

1

INTRODUCTION1 

1.1   SITE DESCRIPTION The  project  area  comprises  approximately  300  ha  of  land  at  Kooragang  Island with  ship  loading facilities on the Hunter River South Arm,  in the Port of Newcastle (see Figures 1 and 2). It  is zoned SP1  Special  Activities  under  the  State  Environmental  Planning  Policy  (Major Development)  2005, which permits port development with consent. The ownership of the site  includes PWCS, OneSteel Manufacturing Pty  Limited, Pacific National Pty  Limited and BHP Billiton  Limited and Crown  land.  The majority of  the Crown  land  is managed by Newcastle Port Corporation  (NPC) and  the Hunter Development Corporation (HDC).  Kooragang Island was originally a series of low lying deltaic islands in the Hunter River estuary, which have been subject  to  land  reclamation  for  industrial development since  the  late 1800s. The  island currently  comprises a  reclaimed  landmass of approximately 2,600 hectares,  situated between  the north  and  south  arms  of  the  Hunter  River.  Kooragang  Island  supports  significant  industrial development  in  its  southern  section  (the  location of  the proposed coal  terminal),  including heavy and  light  industries,  transport  and  distribution  infrastructure,  and waste  emplacement  and  port facilities.  These  facilities  include  the  PWCS  Kooragang  Coal  Terminal  and  Newcastle  Coal Infrastructure Group  (NCIG)  coal  terminals,  Boral  cement manufacturing  and  distribution  facility, OneSteel  and  Orica's  ammonium  nitrate  facility  as  well  as  various  other  manufacturing  and distribution facilities.  Historically, the project site has been used for waste and contaminated material disposal associated with past  activities of nearby  industry  and  the port.  The proposed  coal  terminal would be partly constructed on three licensed landfill areas: 

Areas A and B ‐ part of the Kooragang Island Waste Emplacement Facility (KIWEF) owned by 

HDC; 

Area C ‐ Delta Electrolytic Manganese Dioxide owned by PWCS; and 

Area D ‐ Fines Disposal Facility owned by PWCS.  To the north and west of the industrial and port areas are estuarine wetlands, mangroves, saltmarsh as  well  as  pastured  and  forested  lands,  including  the  Hunter  Wetlands  National  Park,  the international  significance of which has  resulted  in  listing  as  the Hunter Estuary Wetlands Ramsar site.  

1.2 THE PROPONENT  PWCS  comprises  a  joint  venture  between  a  number  of  coal  producers  and  other  coal  industry participants, including exporters and importers. PWCS owns and operates two coal terminals in the Port of Newcastle – the Carrington Coal terminal adjacent to Tighes Hill and Mayfield East residential areas and the Kooragang terminal on Kooragang Island.   

1.3 STRATEGIC CONTEXT The project  site  is  located  in  the  Lower Hunter  region, which  is an  important economic  centre  in NSW and Australia. The need to expand and maintain competitive port infrastructure to support the coal industry in NSW has been recognised in strategic policies and frameworks including: 

Hunter Strategic Infrastructure Plan 2013; 

Hunter Economic Infrastructure Plan; 

Page 11: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

2

Draft Strategic Development Plan for the Port of Newcastle; 

NSW Freight and Ports Strategy; 

Three Ports State Significant Site Proposal for New South Wales: Major Ports of Newcastle, 

Botany and Port Kembla;  

2013‐2022 Hunter Valley Corridor Capacity Strategy; and 

NSW Government NSW Coal and Gas Strategy Scoping Paper (February 2011).  A number of projects resulting from these frameworks and strategies have been completed or are under  construction.  These  include  the  expansion  of  Kooragang  and  Carrington  Coal  Terminals (operated by PWCS) to increase combined throughput capacity to 145 mtpa; the expansion of NCIG to 66 mtpa throughput capacity; and rail upgrades including the Maitland to Minimbah and Nundah Third Track projects.  The rail network and port facilities at Newcastle are key infrastructure in the coal chain. The majority of coal production in New South Wales is in the Hunter Valley with a growing number of mines in the Gunnedah Basin,  approximately  300  kilometres  north‐west  of Newcastle.  The Hunter Valley  Coal Chain (HVCC) ‐ the process of extracting coal from the mine to loading on vessels at the port ‐ is the largest coal export operation in the world.2  It consists of approximately 35 coal mines owned by 11 coal producers with 31  load points and coal haulage distances of up to 380km. Coal  is transported from the mines to the Port via rail and is then received at one of three coal export terminals (PWCS’s Kooragang  Island terminal, PWCS’s Carrington Coal Terminal or NCIG's Kooragang  Island  terminal). Management  of  coal  transportation  by  rail  is  the  responsibility  of  the  Australian  Rail  Track Corporation (ARTC) which  is regulated by an Environment Protection Licence (EPL) administered by the Environment Protection Authority (EPA).   The Port of Newcastle  is  a  state  and nationally  significant  trade  gateway, with  total  imports  and exports  in  2011‐12  contributing  $20  billion  to  the  NSW  economy.  Seventy  nine  percent  of  this investment  is underpinned by coal exports which totalled $15 billion  in 2011‐12. The Port and the associated  coal  terminals  therefore  play  a  critical  role  in  the  NSW  coal  industry,  contributing significantly to both the NSW and Australian economies.  

1.4 PROPOSAL PWCS proposes to construct and operate a new coal export terminal on Kooragang Island, referred to as Terminal 4. This will essentially be an extension of the existing Kooragang coal terminal, though operated  independently.  The  new  terminal  will  have  a  capacity  of  up  to  70  mtpa,  which  is  a reduction  from  the  120  mtpa  proposed  by  the  Proponent  within  the  original  Environmental Assessment  (EA).  The  Secretary’s  PEAR  states  that  the  capital  investment  value  of  the  project  is estimated at $4.8 billion.  The  major  components  of  the  proposal  are  detailed  in  Table  1  of  the  Secretary’s  Preliminary Environmental Assessment Report (PEAR), and can be summarised as follows:   

Site establishment and remediation works. 

Development of terminal infrastructure, including: o rail  infrastructure,  stockpile  pads,  conveyers  and  ship  loaders,  berthing  facilities, 

access, services, water management and supporting infrastructure. o Up to four arrival tracks converging into up to three dump stations. 

                                                            2 NSW Department of Planning and Environment. 2014. Secretary’s Preliminary Environmental Assessment Report. June 2014. p 2 

Page 12: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

3

o Up  to  four departure  tracks  combining  into  a  single  track  around Kooragang Coal Terminal. 

o Rail tracks realigned at Mosquito Creek to minimise disturbance to the creek. o Rail tracks realigned at arrival onto Kooragang Island to accommodate NCIG's tracks. o Up to four coal stockpile pads with total throughput capacity of 70 Mtpa. o Up to four stackers and four reclaimers. o Inbound  and  outbound  conveyors would  service  up  to  two  dump  stations  and  4 

stockpiles. 

Three ship berths on the north side of the Hunter River South Arm and a barge landing area 

on north bank of swing basin to unload large equipment. 

Three main settling ponds and one main transfer pond, south of stockyard. 

Three  land  based  biodiversity  offset  sites  secured  at  Ellalong  Lagoon  Offset  Site  (409 hectares), Tomago Offset Site (238 hectares) and Brundee Swamp Offset Site (204 hectares). 

The revised proposal would be progressively constructed in response to demand nominated by coal producers  and  commercial  requirements,  with  the  actual  timing  and  scale  of  the  development dependent on these factors.3  PWCS proposes to only construct the coal terminal and implement the associated  environmental  management  and  mitigation  measures,  including  contamination management, remediation and the biodiversity offset strategy, if demand requires it be constructed.   

                                                            3 PWCS (2014), Response to Submissions on Preferred Project, p.84, January. 

Page 13: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 

 4

Figure 1:  Site and surrounding land uses ‐ western view (source:  PPR, 2014, p.25) 

  

Page 14: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

 

 5

Figure 2:  Site and surrounding land uses ‐ eastern view (source: PPR, 2014, p.26) 

Page 15: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

6 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

1.5 COMPARISON BETWEEN THE CURRENT APPLICATION ORIGINAL PROPOSAL  The Commission met with representatives from the Department for a briefing on 22 July 2014.  One of  the  issues  discussed  was  the  differences  between  the  current  application  and  the  proposal presented  in the Environmental Assessment (EA). A comparison between the original proposal and the proposal contained in the Preferred Project Repot (RRP) is provided in the table below (which is also included as Appendix A in the Secretary’s PEAR): 

 

Page 16: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

7 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

  

1.6 THE SECRETARY’S PRELIMINARY ENVIRONMENTAL ASSESSMENT REPORT (PAR) 

The Secretary’s PEAR of  the proposal has been submitted  to  the Commission  for consideration as part of  the  review process. The PEAR considered  the proposal,  its strategic and statutory context, public and agency submissions, and  the Proponent’s PPR and  responses  to submissions  report.    It identified the key issues relating to this application to be: 

Upstream and downstream impacts; 

Air quality; 

Flora and fauna; 

Contamination; 

Stormwater and drainage; 

Flooding; 

Noise; 

Traffic and transport; and 

Visual.  The report concluded: 

The Government has taken strategic planning steps to ensure the Port is preserved and can accommodate  growth.  The  proposed  development  is  consistent  with  the  planning framework and strategies and the Capacity Framework Agreement (CFA) process. 

Page 17: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

8 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

The proposal  is  justified on the grounds that  it will enable  the coal chain  to meet  forecast export demand of coal through the Port of Newcastle. Fluctuations  in the coal market may delay  the  requirement  for  the  fourth  terminal,  but  are  unlikely  to  remove  its  need altogether. 

The  proposal  is  relatively well‐located  given  its  proximity  to  shipping  channels,  rail  lines, separation from sensitive receivers and appropriate zoning. 

Whilst there are some environmental constraints, the proposal is likely to provide significant environmental  advantages when  compared  to  locating  a new  terminal on  a  greenfield or alternative site.  

Although significant opposition to the proposal was raised in submissions on the basis that it would increase coal extraction and associated impacts, these concerns largely relate to coal extraction itself rather than the terminal infrastructure specifically. 

 Overall,  the  Department  is  confident  that  the  proposal  could  proceed  with  minimal  adverse environmental  impacts whilst realising significant benefits to the  local, regional, state and national economies.  It concludes  that the project’s benefits outweigh  its potential  impacts and therefore  it should  be  approved  subject  to  conditions.  The  Secretary’s  PEAR  includes  draft  recommended conditions of approval relating to the management of air quality/dust management, noise, surface water, ground water, contamination, biodiversity conservation and visual impact.  

THECOMMISSION’SREVIEWTASK2 

2.1   TERMS OF REFERENCE FOR THE REVIEW Section 23D of the Environmental Planning and Assessment Act 1979 (EP&A Act) provides for the Minister to request the Commission to conduct a review of a development application for a project and  to  hold  a  public  hearing  into  the matter  the  subject  of  the  review.  The Minister’s  terms  of reference for this review are dated 13 September 2012 and are to: 

  1.  Carry  out  a  review  of  the  Port  Waratah  Coal  Services  Terminal  4  Project (MP10_0125), and: a) consider the Environmental Assessment of the project, issues raised in public 

and agency submissions on the project, and any other  information provided during the course of the review; 

b) assess  the merits  of  the  project  as  a whole,  paying  particular  attention  to potential: 

noise and air quality impacts of the project; 

traffic impacts of the project; 

biodiversity and contamination impacts of the project; and 

any other potentially significant impacts of the project and c) recommend  appropriate measures  to  avoid, minimise,  and/or  offset  these 

impacts. 2.    Conduct public hearings during the carrying out of the review. 3.    Submit its final report on the review to me within three months of the receipt of 

the proponent’s response to submissions or preferred project report, unless the Director  ‐General  of  the  Department  of  Planning  and  Infrastructure  agrees otherwise. 

 

Page 18: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

9 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

The PPR was exhibited in late 2013 and consequently the original timeframe for the review past. At the time the PPR was exhibited, the Chair of the Commission sought clarification from the Minister regarding the terms of reference and the Minister’s previous advice to the Commission. The advice was  that  a  representative  relevant  to  the  consideration  of  Commonwealth  matters  would  be nominated to form part of the review panel.   On 6 March 2014 the Commission received a response advising that the Commonwealth would no longer  be  nominating  a  representative  to  participate  in  the  review.  The  Secretary’s  PEAR  was subsequently  received  by  the  Commission  on  27  June  2014  and  public  hearings  were  held  in Newcastle over two days from Tuesday 26 August 2014.  Following  the Hearing,  the Commission met with  various government agencies  to  seek additional advice  on  issues  raised  in  submissions  and  at  the  hearing. Written  advice  from  the  EPA  and  the Commonwealth Department of the Environment was received on 10 October 2014.  An independent economic  review  of  the  proposal  was  undertaken  and  was  received  by  the  Commission  on  17 November 2014.  Given the timeframe taken to receive advice from government agencies and other experts,  the  Commission  requested  an  extension  to  the  timing  of  the  review  until  30 November 2014.  

2.2   PUBLIC HEARINGS AND SUBMISSIONS In accordance with the Minister’s request, the Commission held public hearings on 26 and 27 August 2014  at Newcastle  Panthers. Over  130  verbal  submissions were made  to  the  Commission  at  the hearing  including  the Proponent,  special  interest  groups, Newcastle City Council,  local  councillors and  individual  residents. All  those seeking  to be heard were heard. The Commission also  received written and photographic submissions. Copies of the submissions are available on the Commission’s website: http://www.pac.nsw.gov.au. A brief summary of the issues is provided in the table below.  Table 1 – Summary of Issues 

Issue  Submissions from Public Hearing 

Summary of submissions supporting the project 

Social and Economic  The coal terminal will provide regional employment growth within Newcastle 

and the wider region. 

It will stimulate economic growth for the region. 

Making use of existing industrial land away from residential properties. 

Long‐term legacy of direct community benefits. 

Environmental  Provision of significant environmental offsets. 

Proposal will address existing contamination on the site. 

Summary of submission objecting to the project 

Contamination and 

Water 

Surface and groundwater impacts. 

Proposal will make contamination worse. 

Dredging impacts on aquatic and estuarine habitats. 

Cumulative impacts on the Hunter River. 

Biodiversity  Concerns about the impacts on and loss of flora and fauna, including 

threatened species and native vegetation.   

Concern that biodiversity offsets proposed are not adequate. 

Habitat destruction.  

Page 19: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

10 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

Issue  Submissions from Public Hearing 

Impact on Ramsar wetlands and birdlife. 

Impact on GGBF resulting from loss of habitat. 

Air Quality  Potential impact on air quality (especially particulate levels) in the Newcastle 

region. 

Health and amenity implications for the Newcastle population and for those 

who live in the vicinity of railway lines used by coal trains. 

Uncovered coal wagons and stockpiles. 

Impact on existing poor air quality in the area. 

Comprehensive study of existing particle pollution levels is required. 

Social and Economic  The economic benefits have been overstated. 

There is no economic rationale for a fourth coal terminal. 

Questions about the data modelling and other studies. 

Concerns about the social impacts on the community. 

Health fears from coal dust. 

Impact on tourism. 

Public safety issues from chemical use. 

Rail  Rail dust, noise and vibration. 

Cumulative impacts of increased rail movements. 

Congestion of train lines.  

Climate Change  Concerns about the project contributing to climate change (from burning coal 

exported through the coal terminal). 

Traffic  Impact on traffic flow around Kooragang and Stockton 

Noise  Increased noise from new terminal and associated train movements. 

Visual  Visual impact of the new coal terminal. 

Other  Lack of transparency. 

Concern regarding review process. 

Lack of faith in the Commission and the Department/state government. 

 

2.3   DOCUMENTS, MEETINGS AND SITE INSPECTIONS The Commission reviewed a wide range of documents including: 

The Proponent’s EA (prepared by EMM, February 2012); 

Submissions from government agencies, special interest groups and the public made to the Department on the EA and submissions made directly to the Commission; 

The Proponent’s Response to Submissions and PPR (EMM, September 2013); 

The Proponent’s Response to Submissions on the PPR (EMM, January 2014) 

The Secretary’s PEAR (June 2014); and 

Review of Economic Analysis Port Waratah Expansion T4 (The CIE, November 2014).  The  Commission  visited  the  site  and  surrounding  suburbs,  met  with  government  agencies  and representatives of two local councils (Newcastle and Port Stephens) and met with the Proponent. A summary  of  the  Commissions meetings  in  relation  to  the  proposal  is  provided  in Appendix  3.  In short, the Commission met with:   

Page 20: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

11 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

Table 2 – List of Commission meetings 

Date  Meeting 

22 July 2014  Department of Planning and Environment 

14 August 2014  EPA 

OEH (inspection of Tomago offset area) 

Port Stephens Council 

15 August 2014  PWCS (including site inspection) 

Newcastle Council 

12 September 2014  The CIE 

15 September 2014  EPA 

Department of Planning and Environment 

24 September 2014  EPA 

1 October 2014  NSW Department of Health 

Commonwealth Department of Environment 

(teleconference) 

30 October 2014  The CIE 

6 November 2013  Department of Planning and Environment 

 The Commission visited the site on 15 August 2014 with the Proponent. The Commission also met on multiple occasions to discuss issues arising from its review of the proposed development. 

JUSTIFICATION3 One of  the primary  issues  raised by speakers at  the public hearing was  that  the construction of a fourth coal terminal is not justifiable on economic grounds. This section of the report considers the Proponent’s  justification  for  the  fourth  coal  terminal,  the Department’s position as  set out  in  the Secretary’s PEAR as well as  the expert advice sought by  the Commission  to clarify  issues  raised  in submissions.    

3.1 PROPONENT’S JUSTIFICATION  The  lease for the Kooragang  Island terminal requires PWCS to operate the terminal as a "common user facility", meaning access to the terminal on a non‐discriminatory basis must be provided to any producer wishing to ship coal. Allocation of port capacity to producers  is currently managed under long‐term operational  framework governed by Capacity  Framework Agreements  (CFAs). The CFAs were developed by the NSW government and the coal industry, and form a critical part of the long‐term export plan for coal produced in the region. The CFAs include contractual obligations for PWCS to  ensure  its  terminal  facilities  have  enough  capacity  to meet  the  contracted  coal  throughputs. Where a shortfall is predicted that cannot be accommodated by further expansion of its existing coal export terminals, PWCS is required, under the agreement, to build a new terminal within four years of the capacity shortfall being formally acknowledged.  

Page 21: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

12 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

The  PPR  explains  that  the  CFAs  are  intended  to  provide  a  solution  to  the  historic  inefficiencies, uncertainty and capacity constraints experienced  in  the HVCC. They  include an annual process  for coal producers to nominate export capacity required for the coming 10 years on a "ship or pay" basis (i.e.  penalties  or  the  costs  of  coal  handling  are  paid  by  the  producer  regardless  of whether  the allocation  is  used).  This  is  to  ensure  the  existing  terminals  have  enough  capacity  to  service  the contracted coal throughputs.  The  long‐term contracts have  resulted  in producers nominating allocations during  the peak of  the mining boom, which ultimately  triggered  the  requirement  for PWCS  to  seek approval  for a  fourth terminal. In 2012 PWCS projected capacity shortfalls at its Carrington Coal Terminal and Kooragang Coal Terminal in Newcastle by 2015. This was based on the assumption that world demand for coal would  continue  to  grow  strongly,  based  on  trends  at  the  time.  The more  recent  slowing  of  coal demand  from  the Port of Newcastle has exposed over‐allocations.  In May 2013 PWCS voluntarily accepted  a  reduction  in  contracted  tonnages  from  the majority  of Hunter  Valley  producers,  and announced that the requirement for the Terminal 4 project had been un‐triggered.4 Consequently, the  capacity  of  the  proposed  coal  terminal was  downsized  by  the  Proponent  from  120mtpa  (as proposed in the EA) to a 70 mtpa terminal in the PPR and no immediate need for the terminal was signalled. The Commission notes that the layout of the revised proposal allows for further expansion if warranted by future demand.  Any future expansion within the project area to achieve a nominal capacity  of  120  mtpa  would  be  subject  to  future  demand,  with  separate  assessment  and determination under the relevant legislation.  

3.2 DEPARTMENT’S POSITION The  Secretary’s  PEAR  states  that  coal  currently  provides  approximately  40  per  cent  of  world electricity demand and  the export of  thermal coal  is Australia's  third  largest export commodity by value. Notwithstanding the recent downturn in the global market, the export of coal is expected to continue to play an important role in the global energy mix in the future ‐ particularly for non‐OECD countries.  The  Department  acknowledges  that  all  economic  models,  including  that  prepared  by  Gillespie Economics on behalf of the Proponent, have limitations and can only ever provide estimations based on  the  assumptions  used.  It  is  generally  accepted  that  economic models,  such  as  cost  benefit analysis  (CBA)  are  useful  tools  in  decision  making.  The  Department  accepts  the  Proponent's modelling  and  considers  that  while  the magnitude  of  the  economic  costs  and  benefits may  be argued,  the  proposal  would  ultimately  be  in  the  public  interest.  It  would  result  in  increased throughput of coal  to global markets and  therefore  increased  revenue  for NSW. Additional public benefits would include increased employment opportunities, the upgrade of road infrastructure, the remediation  of  contaminated  land  and  the  payment  of  local  developer  contributions.  The Department  also  highlighted  consequences  arising  from  HVCC  inefficiencies  and  a  subsequent reduction in the global competitiveness of the Port of Newcastle should demand not be met.  

3.3  ALTERNATIVE ECONOMIC ANALYSIS In  a  detailed  submission  to  the  Commission  in  August  2014,  the  Australian  Institute  (TAI)  has provided a critique of the economic assessment undertaken by Gillespie Economics on behalf of the proposal.  TAI  has  questioned  key  assumptions  underpinning  the  Cost/Benefit  Analysis  (CBA)  and economic  impact  analysis,  and  has  provided  alternative  conclusions  for  a  CBA  based  on what  it considers more realistic assumptions. TAI’s main criticisms of the Gillespie CBA for the PPR are that: 

                                                            4   ARTC (2014), 2014‐2023 Hunter Valley Corridor Capacity Strategy, July, p.7. 

Page 22: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

13 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

Future throughput modelled for the terminal assumes growth rates  in coal export demand and supporting mining activity that do not reflect recent experience or likely future demands for terminal capacity; 

These future demands are likely to be much weaker than modelled given evidence on future global coal demand – and demand  for Australian exports – and  the ability of mines  in  the catchment  area of  the  terminal  to  profitably  supply  the  coal  volumes  implied,  as well  as evidence on coal production costs and coal prices. 

Time horizons for the scenarios modelled are too long and therefore distort the net present value gains from the earlier export of increased coal volumes that would be enabled by the construction of T4.  

TAI  argues  that  the  present  value  of  net  production  benefits  and  of  the  royalties  and  taxes components are significantly overstated by Gillespie Economics.  It raises significant doubt about the financial viability of  the  terminal  investment  in  light  if  the downsizing of  the proposed  throughput capacity from 120 mtpa to 70 mtpa.   

3.4 REVIEW OF PROPONENT’S ECONOMIC ANALYSIS In response to the submissions received criticising the modelling and assumptions used by Gillespie Economics  to  justify  the  requirement  for  a  fourth  coal  terminal  at  the  Port  of  Newcastle,  the Commission  engaged  the  Centre  for  International  Economics  (CIE)  to  undertake  an  independent review of the economic analyses. The scope of the CIE’s review was as follows: 

Review the framework for analysis developed by the Proponent; 

Review the key assumptions made within the methodology used; 

Consider the conclusions compared to alternative assumptions about future coal exports via the terminal and the timing of the construction of the project.  

Gillespie Economics assessed the economic efficiency of the project using a CBA. An additional study analysing the expected economic impacts of the project was also conducted for the Proponent. The impact analysis examined the wider economic gains to the regional, state and Australian economies of the project.  The CIE’s  report on  its  review of  the Gillespie Economics  analysis  is  attached  at Appendix 7.  The conclusions reached are summarised below: 

The general approach taken to construct the CBA  is reasonable, although  it only provides a partial  analysis  due  to  the  exclusion  of  a  range  of  potential  future  social/environmental impacts arising from the mining and transportation of coal to the Port.  

The results of the CBA are highly dependent on the assumptions regarding the throughput 

volumes  and  timing  of  the  construction/operation  of  the  project.  These  assumptions  are 

uncertain and depend,  in turn, on factors such as future coal prices and global demand for 

coal. Some assumptions adopted in the original economic modelling appear to be optimistic 

based on currently available market data. Nevertheless, even under  the Proponent’s most 

pessimistic  assumptions,  the  project  would  still  accelerate  coal  extraction,  generating 

around $1 billion (in present value terms) in additional royalties and company tax. Although 

not quantified,  the potential environmental/social  impacts under  these more conservative 

assumptions would  also  be  reduced,  given  that  (under  the  pessimistic  assumptions)  the 

project is bringing forward a smaller volume of coal. 

Page 23: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

14 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

While  there  is  significant  uncertainty  regarding  a  range  of  factors,  current  information suggests that the project  is unlikely to be required until around 2023. Therefore,  from the Proponent’s  perspective,  the  rationale  for  the  project  is  precautionary.  Project  approval provides  the Proponent with  an option  value  that  can be  exercised  at  some point  in  the future depending on market conditions.  

If the Project is approved but construction is deferred (and possibly abandoned) because of future  revised  price  and  volume  expectations,  there  are  public  benefit  consequences  to consider.  These  include  the  postponement  of  measures  to  address  ongoing  adverse environmental outcomes (e.g. site remediation).  

A potential rationale for delaying the approval of the project is if new information is likely to arise in the near future that would allow a more complete CBA to be conducted to account for potential environmental/social impacts at the site (for example, new information on the health  impacts of coal dust emissions at the site). The CIE  is currently unaware of any new information  that would result  in a significant public benefit  from delaying  the project. Any new  information  on  future  coal  excavation  and  transportation  activities  should  be  taken  into account as part of any future mining assessment process. 

There may be options for staging future construction or modifying the existing design so as to  reduce  environmental/social  impacts  arising  from  the  project  site.  These  should  be considered  as  part  of  the  assessment  of  the merits  of  the  project  from  a  public welfare perspective.   

3.5 COMMISSION’S VIEW The Commission understands that the immediate need for approving the project is dependent upon the future coal export demand through the Port of Newcastle, which triggers the provisions of the CFAs.  This is ultimately subject to the future world demand for coal and future coal prices, which are not known with any certainty.   The Commission recognises that the ability to meet increased demand for coal exports in the future will require commensurate expansion or  investment of the supporting  infrastructure,  including rail and port capacity. While  the  immediate need  for a new  terminal no  longer applies,  the  long  lead times  required  to  construct  and  commence operations of  such  significant  infrastructure warrants sufficient early consideration of any proposed expansion and also provides an opportunity for early action to address potential adverse impacts.  Public  interest considerations relating  to contaminated site remediation and demonstration of  the effectiveness of mitigation  and offset measures  to protect national  and  internationally  significant biodiversity  values  and biodiversity protection  require  very  careful  consideration of project  scale, design, timing and staging options.  

COMMENTS,  FINDINGS  AND  RECOMMENDATIONS  RELATING  TO  THE 4TERMS OF REFERENCE 

 

4.1 BIODIVERSITY Under  the Minister’s Terms of Reference  the Commission  is  required  to  consider  the biodiversity impacts of the project and recommend appropriate measures to avoid, mitigate and/or offset these impacts. Potential ecological impacts associated with the project have been a major focus of many of the  submissions made  on  the  project,  including  those  by  government  agencies,  special  interest 

Page 24: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

15 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

groups and individuals regarding the Environmental Assessment (EA), Preferred Project Report (PPR) and presentations at the public hearing.  In summary, the main concerns raised are as follows: 

Impacts on the green and golden bell frog (GGBF) and migratory shorebirds; 

Impacts on other birdlife that use Swan Pond and Deep Pond; 

Potential for regional extinction of many species; 

Clearing of endangered ecological communities; 

Cumulative/incremental  and  unacceptable  impacts  on  wetland  habitats,  including  the 

Ramsar‐listed wetlands; 

Not fulfilling obligations under International Treaties that apply to the Ramsar wetlands; 

Not fulfilling obligations under Commonwealth and NSW legislation; and 

The suitability, adequacy and potential effectiveness of the proposed offset areas.  The project site is located adjacent to the Hunter Wetlands National Park, which includes the Ramsar Hunter  Estuary  Wetlands,  the  former  Kooragang  and  Hexam  Swamp  Nature  Reserve,  Stockton Sandpit  and  part  of  Ash  Island  (see  Figure  3).  A  detailed  overview  of  the  existing  ecological characteristics  and  features  of  the  site  is  provided  in  Section  10.1  and  Appendix  K  of  the  EA. Extensive  flora  and  fauna  surveys  of  the  site  and  surrounding  area  were  untaken  by  Umwelt Ecologists (on behalf of the Proponent) and recorded the following: 

Five vegetation communities; 

One endangered flora species (a pondweed, Zannichellia pallustris); 

Two endangered ecological communities (coastal saltmarsh and freshwater wetlands); 

61 migratory  species  (within  or  flying  over  the  site  to  access  adjacent  habitat  areas  of international significance, which use the T4 project area as foraging habitat), of which 27 are listed in international treaties for migratory birds; 

20 threatened fauna species, including three threatened species (Australasian bittern, GGBF, and the grey‐headed flying fox); and 

An additional 60 threatened fauna species within 10 kilometres of the site. 

The Secretary’s Preliminary Environmental Assessment Report (“assessment report”) recognises that construction of the proposed coal terminal would affect existing ecological values on and around the project  site.  273.3  hectares  of  vegetation  is  proposed  to  be  cleared,  including  174.6  hectares  of disturbed or modified  land,  75 hectares of natural  vegetation/habitat  and  21.3 hectares of open water.  The Proponent has  sought  to avoid and minimise  the  impacts of  the proposal on  threatened and protected species and communities through a range of measures prepared in consultation with the Department,  Office  of  Environment  and  Heritage  (OEH)  and  the  Commonwealth  Department  of Sustainability,  Environment, Water,  Population  and  Communities  (“the  Commonwealth”).  These measures are outlined in Table 5 on Page 32 of the Secretary’s assessment report and include: 

Creation of an on‐site GGBF habitat corridor; 

851 hectares of direct land‐based offsets across three sites secured by the Proponent within 

the same bioregion: 

o Ellalong Lagoon in Cessnock LGA (409 hectares); o Brundee Swamp in Shoalhaven LGA (204 hectares); and o Tomago offset site in Port Stephens LGA (238 hectares). 

Habitat restoration and creation works on the Tomago Offset site; and 

Page 25: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

16 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

Monetary  contributions  to  research,  weed  control  and  other  ongoing  management measures. 

This chapter of the report reviews the biodiversity  issues associated with the project by  identifying the  potential  impacts  on  flora  and  fauna;  assessing measures  proposed  to  avoid  or mitigate  the impacts and consider the proposed offset strategy, which seeks to offset residual impacts.   

 Figure 3: Indicative outline of the site and surrounding areas (Source: T4 Project Response to Submissions and PPR (EMM 2013)) 

 

4.1.1 MIGRATORY SHOREBIRDS 

Impact Construction of the coal terminal as proposed would require the removal of 7.5 hectares of mudflat at the northern area of Deep Pond and 18.8 hectares of saltmarsh habitat (including 2.3 hectares of Swan Pond). As a consequence,  five migratory shorebird species  that  regularly use  the habitats of Swan Pond and Deep Pond will be directly affected. These species are: 

Common greenshank; 

Curlew sandpiper; 

Marsh sandpiper; 

Red‐necked stint; and 

Sharp‐tailed sandpiper.  Moderate  impacts  are  also  anticipated  on  four  other  species  and  low  impacts  on  a  further  10 species.  Mitigation / Offset strategy Deep Pond The  Commission  acknowledges  that  in  an  effort  to  reduce  the  ecological  impacts  of  the development, amendments were made to the project as part of the PPR. This included the retention 

Hunter Wetlands National Park & Ramsar siteHunter Wetlands National Park 

Ash Island

T4 site

Hexham Swamp 

Stockton 

Page 26: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

17 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

of approximately three hectares of open water habitat at the southern end of Deep Pond to provide habitat  for  the migratory  shorebirds. While  the Commission believes  this  is a positive outcome,  it considers  there  is  further  scope  to  retain  more  of  Deep  Pond.  The  reduction  in  the  nominal maximum throughput by the Proponent from 120 mtpa to 70 mtpa has not resulted in any reduction in  the  proposed  incursion  of  the  stockyard  into  the  north  eastern  section  of  Deep  Pond.  The Commission  notes  that  the  proposed  layout  of  the  terminal’s  coal  pads  provides  space  for  two additional  pads  that  could  be  developed  as  part  of  a  future  expansion  beyond  the  proposed  70 mtpa.  If these two additional undeveloped pads were located at the north rather than the south of the stockyard  layout,  it would provide a greater ability to protect the deep pond for the  life of this proposal. Development of these pads could be reconsidered for any future expansion of the terminal after  which  time  considerably  more  information  would  be  available  regarding  biodiversity implications and the success of the proposed offset strategy.  The Commission acknowledges  that  the Proponent considered an option  to build  the stockpiles  in the southern portion of the site to avoid specific frog habitat ponds, such as railway pond. The study conducted suggested  this option would be more expensive, would take  longer to design/construct and would  be  inconsistent with  remediation  plans  on  the  site5.  The  Commission’s  review  of  the related documentation has identified several matters warranting some further clarification:  

1. The  comparative  costings  seem  to  lack  detail.  For  example,  if  the  major  direct  cost (estimated at $49M) is the provision of a combined Sheet Pile and Cement‐Bentonite Slurry Wall  to  isolate  the  Frog  ponds  and  Deep  Pond  from  the  areas  being  filled  for  the  coal stockyard.  The  costs  seem  to  be  presented  as  totally  additional  to  the  costs  of  similar barriers proposed to be established along the railway embankment rather than considering the possibility  that at  least a significant amount of  the barrier would be  instead of,  rather than additional to that set out  in the PPR. Additional works  identified also seem to carry a generous contingency allowance.  

2. The costings seem to assume a site preparation/construction time imperative which may not now apply. $71M of the estimated additional cost is described as ‘indirect’. It is unclear how much of this might relate to ‘delays’ which might now be costed somewhat differently.  

3. Much  seems  to be made of  the  fact  that  any  change  in  the design/layout would  require revision of the relevant Landfill Closure Plans. However, the Draft Recommended Conditions of  Approval  at  B43  require  that  ‘prior  to  commencement  of  construction  ……..,  the Proponent  is  to  finalise  and  submit  the  landfill Closure Plan, Remediation Action Plan  for each  stage and  the  containment  cell design  for  the approval of  the  Secretary.’ Given  this coupled  with  the  commitment  to  integrate  remediation  works  across  the  whole  site,  it seems  there might  be  considerable  detailed  design work  that  still  has  to  be  done which could provide an opportunity for some refinement of the designed footprint.   

4. The  Commission  recommends  that  the  design  of  the  stockyard  be  refined  to  reduce  the impact on Deep Pond and the adjacent pond areas along the rail corridor. Although the costs may be marginally greater,  it should still be possible to construct two stockpile pads to the south  rather  than  the  north without  limiting  the  proposed  capacity  of  the  terminal.    In addition, a staging strategy to achieve the 70 mtpa capacity would provide additional time to achieve and demonstrate a successful offset strategy. 

 Tomago offset site To offset  the project’s  residual  impacts on  saltmarsh  and migratory  shorebird habitat, PWCS has secured  238  hectares  of  land  in  Tomago  (“Tomago  offset  site”).  This  land  has  high  conservation 

                                                            5 PPR, Appendix T (EMM 2013)  

Page 27: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

18 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

significance  in  the Hunter estuary due  to  its proximity  to  the Hunter Wetlands National Park and Hunter Estuary Wetlands Ramsar site. It  is also close to the wetlands on the T4 project area.   With input from shorebird and saltmarsh experts, a restoration concept of up to 140 hectares of shorebird habitat has been prepared. The concept comprises a series of shallow tidal lagoons that incorporate mudflats, saltmarsh habitat and island roosts.    During  the  review  process,  the  Commission  received  two  submissions  from  Hardie  Holdings  Ltd regarding  the use of  the Tomago site as part of  the proposal’s biodiversity offset strategy. Hardie Holdings Ltd raised  issues concerning the history of the offset  land and suggested that utilising the site as part of an offset package  for  the proposal would amount  to  'double‐dipping’  land  for  the purpose of a biodiversity offset. The Commission carefully considered this submission and the site’s complex history. Ultimately the Commission believes the site is legally unencumbered.  OEH advice The Commission met with  representatives  from  the OEH  in August 2014 and undertook a guided inspection the Tomago offset site. The OEH officers were supportive of the proposed offset strategy for Tomago, as it has the potential to result in habitat areas that are commensurate with (if not an improvement on) the habitat areas found on the proposed development site.   Commonwealth advice During  its  review  of  the  EA  submissions  and  public  hearing  presentations,  the  Commission  gave particular  attention  to  the  concerns  previously  raised  by  the  Commonwealth  regarding  the assessment of the level of biodiversity impacts, the adequacy of efforts to minimise impacts and the value of  the proposed biodiversity offset package. The Commonwealth  submission  (dated 10 May 2012) stated  that  the T4 project would have a significant  impact on migratory shorebirds and  the proposed mitigation measures would have a limited effect. These issues were consistent with those raised by  the Hunter Bird Observers Club, which believes Tomago  is not a suitable habitat  for  the migratory shorebirds.  The Commission noted that resolution of these specific concerns was not explained  in detail  in the Department’s assessment  report and as a consequence,  the Commission  sought  clarification  from the  Commonwealth.  A  summary  of  the  issues  raised  in  2012  and  the  Commonwealth’s  updated advice is provided in the table below:  Table 3 ‐  Summary of Issues raised by the Commonwealth Department of Environment regarding Migratory Shore Birds 

Issues raised in Environmental Assessment submission (May 2012) 

Updated advice from Commonwealth (October 2014)

Impact on migratory shorebirds and habitat 

The project will result in highly significant impacts on migratory shorebirds by removing habitat and having indirect impacts on two significant wetlands ‐ Deep Pond and Swan Pond. 

 

During the earlier stages of the assessment process, there was a lack of complete information about the different migratory bird habitats on the site and the extent of impact. This meant that a more precautionary approach was warranted, particularly with regard to the dredge return channel.  The Proponent has since provided more complete and better quality information about the presence and behaviours of shorebirds on the site.  As a result, the impacts are considered to be of lesser significance ‐ although residual impacts will still require mitigation and an offset. 

Offsets  If successful, the Tomago site will achieve an appropriate offset.  The offset must be proven prior to the impact 

Page 28: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

19 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

The proposed wetland habitat creation at Tomago appears to have the potential to adequately compensate for the loss of shorebird habitat from the impact site. However, the habitat will need to be created and demonstrated to adequately offset the impacts of the proposal prior to the impact occurring to be acceptable as an offset 

occurring. Any conditions of approval will need to include a set of practical, operational requirements which relate to monitoring and evaluating its success. 

A single season that shows successful use of the site by shorebirds (including the full range of species abundance and effective foraging and breeding habitats) will be acceptable in terms of proving the success of the offset. However, several seasons of monitoring may be necessary prior to reaching this point.  

 The Commission acknowledges  that  there will be some  impacts upon migratory shorebirds on  the project  site. However, based on  the  advice  received  from  government  agencies,  the Commission accepts that the Tomago offset site has the potential to provide an acceptable offset and potentially a net conservation gain for the hunter estuary.  To ensure its viability, the Commission is of the view that the Proponent would need to demonstrate that the Tomago offset area is functioning successfully prior to commencing construction of the coal loader  facilities  at  the  project  site. While  the  Commonwealth  recommends  one  successful  year (migratory  season),  the Commission  recommends  the earthworks, vegetation plantings and water control measures would need to be in place for a minimum of three years in order for the success of the  offset  strategy  to  be  fully  demonstrated  before  there  is  any  impact  on  the wetlands  on  the proposed T4 site.  

4.1.2 AUSTRALIASIAN BITTERN 

Impact The Australasian Bittern  is endangered under both  the NSW Threatened Species Conservation Act 1995 and the Commonwealth EPBC Act. The species is in decline, predominantly due to modification and incremental degradation/loss of habitat.  The project site contains 27 hectares of wetlands suitable for the Australasian Bittern. Surveys have been  undertaken  on  behalf  of  the  Proponent  as well  as  the  Hunter  Bird  Observers  Club, which suggest that the species occurs at the site at relatively high density. Although the existing wetlands are  situated  in  a  highly  disturbed  environment,  in  2012  the  habitats were  reported  by  Umwelt Ecologists to be in good condition based on the number of birds recorded.  The proposed development requires the complete removal of the Australiasian Bittern habitat at the site  (with  the  exception  of  the  GGFC  corridor), meaning  the  impacts  on  the  species  would  be significant.   Offset strategy In order to offset the impacts on the Australian Bittern, an offset strategy is proposed across three locations in the Sydney Basin Biosphere.  These are discussed below:  Tomago The Tomago offset site includes the conservation of 11 hectares of Freshwater Wetland Endangered Ecological Community  (EEC),  the  restoration of  saltmarsh habitat and  the  construction of  shallow tidal  lagoons.  It would  be  designed  to  support  comparable  habitat  features  to  those within  the adjoining Hunter Wetlands National Park and Hunter Estuary Ramsar site. Given its location, Tomago has  the  potential  to  provide  habitat  for  the  same  geographically  distinct  regional  population  of 

Page 29: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

20 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

Australiasian Bitterns found on the project site (though it is noted that it currently does not support a viable population).  The  Proponent  predicts  that  if  the  offset  site  does  not  proceed,  the  potential  for  Australiasian Bittern habitat at Tomago will be reduced over the next 10 years. This is due to the deterioration of floodgates  controlling  tidal  flows  into  the  site  and  the  encroachment  of  Swamp Oak  forest.  The Commonwealth advised the Commission that although it cannot draw any conclusions regarding the likely effects of these processes, it accepts the Proponent’s assumptions.   Brundee offset site  To  further  offset  the  impacts  of  the  project  on  the  Australiasian  Bittern,  the  Proponent  has  an agreement to purchase land adjoining the Brundee Swamp Nature Reserve. The land is located 250 kilometres south of the project site, within the Shoalhaven local government area. It is proposed to secure  and  conserve 135 hectares of  known Australasian bittern habitat by providing permanent wetland habitat for the species.   The Proponent has  indicated  that current  land use practices on  the Brundee offset  site  (including grazing and slashing) are causing ongoing degradation of the site and there  is potential to  improve its condition. Advice received from the Commonwealth  in October 2014 suggests that the ongoing management of Brundee to explicitly provide habitat  for the species  (and the GGBF)  increases the likelihood of the habitat quality improving within 10 years. The Commission accepts this advice and considers the regeneration of Australiasian Bittern habitat at Brundee would be a positive legacy of the proposed T4 development.  Ellalong Lagoon offset site The Proponent has secured an offset site at Ellalong Lagoon within the Cessnock  local government area. The offset site  is  located 40 kilometres west of the project site and  is 409 hectares  in size.  It provides a further 35 hectares of Freshwater Wetland EEC and is a potential drought refuge for the Australasian bittern and other waterbirds. No objection or concern has been raised by the OEH or the Commonwealth in relation to this offset area.  Commonwealth advice The  Commonwealth  initially  raised  concerns  in  relation  to  the  impact  of  the  proposal  on  the Australian  Bittern  and  the  proposed  offset  strategy.  Advice  sought  from  the  Commonwealth  in October 2014 included an update on these issues, the response to which is summarised in Table 4.   Table 4 ‐ Summary of Issues raised by the Commonwealth Department of Environment regarding the Australasian Bittern 

Issues raised in Environmental Assessment submission (May 2012) 

Updated advice from Commonwealth (October 2014) 

Impact on species and habitat 

The EA states that the proposal would have a significant impact on a "geographically distinct regional population" of the Australasian Bittern, which is listed as an endangered species under the EPBC Act. 

 

The impacts to the Australiasian Bittern will need to be mitigated and/or offset (see below). 

Offsets 

The proposed offsets do not adequately 

The Tomago offset site accounts for a small proportion of the offsets required for the bittern.  

Page 30: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

21 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

compensate for the loss of habitat for the Bittern when assessed using the Department's Offsets Assessment Guide. 

A reduction in impacts or additional offsets will be required to adequately offset the stated impacts of the proposal on this species. 

Given that the population being impacted is geographically distinct, it would be most appropriate if any additional offsets were located within the area occupied by the population. 

Most of the offset will be provided at the Brundee site.  This is considered acceptable if proven to be successful. 

Based on the type of management proposed and the habitats present, the ecological benefit could potentially be achieved at Brundee within 10 years.     

 If, as proposed above, the designed configuration of the stockyard is refined to reduce the extent of the  incursion  into  the Deep  Pond  and  adjacent  ponds  along  the  rail  corridor, while  still  allowing remediation plan objectives  to be met,  the overall  impact on Australasian Bittern habitat  can be further reduced. Based on the updated advice received from the Commonwealth and the conditions recommended  by  the  Secretary,  the  Commission  is  satisfied  that  any  residual  impacts  of  the proposal upon the Australasian Bittern can be adequately offset.   

4.1.3 GREEN AND GOLDEN BELLFROG (GGBF) Impact  The  GGBF  is  listed  as  endangered  under  the  Threatened  Species  Conservation  Act  1995  and vulnerable under  the  Environment Protection  and Biodiversity Conservation Act 1999  (EPBC Act). The species has become threatened as a result of habitat  loss, predation and disease, however the population  on  Kooragang  Island  remains  the  largest  in  the  Hunter  region.  The  GGBF  has  been repeatedly and extensively recorded within the 5.8 hectares of breeding habitat on the project site, which would be cleared as part of the proposed development.  Mitigation and offsets A range of measures are proposed by PWCS to avoid, mitigate and offset the expected impact of the proposal  on  the  existing  GGBF  population  on  the  site.  These  are  outlined  in  the  Secretary’s assessment report (Section 5.3, Table 5) and the primary elements are discussed below:  Proposed habitat corridor As part of the offset strategy, the Proponent has designed a GGBF corridor across Kooragang Island to provide connectivity across the site and between the National Park and Ash Island. The corridor will be a minimum of 12 hectares and will include 4.7 hectares of wetland, as well as terrestrial and breeding habitat.   The Commission recognises the importance of conserving the GGBF in the Hunter and supports the establishment of the corridor. In August 2014, the Commission inspected trial ponds on the subject site,  which  were  installed  in  2012  having  been  designed  as  part  of  research  into  best  practice methods. Based on data collected  in  January 2014,  there  is evidence  that successful breeding has been recorded in the trial ponds. The Commission’s earlier recommendation to redesign the proposed 

stockyard to reduce the impact on Deep Pond will also assist in minimising the impact on the GGBF if the  adjacent  ponds  known  as  ‘frog  pond’  and  ‘railway  pond’  along  the  rail  corridor  can  also  be protected.  While  the Commonwealth and OEH  support  the habitat corridor,  they have  indicated  that  further refinements  need  to  be made  and  a  refuge  is  needed  for  frogs  that  become  displaced  during construction. This may  include  the  successful  installation of  temporary habitat  (similar  to  the  trial 

Page 31: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

22 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

ponds) prior  to  removing  inhabited  areas  across  the project  site. The Commission notes  that  the Department has  responded  to  these concerns  in  its  recommended conditions  (B17  to B22).  It has also  recommended  that  an  Integrated  Kooragang  Island GGBF Management  Plan  be  prepared  in consultation with adjoining stakeholders, the OEH and Commonwealth.   Brundee offset site In addition to providing habitat for the Australiasian Bittern, the Brundee offset site will also be used to further conserve the existing GGBF population. This site is referred to in the NSW Draft Recovery Plan as a stronghold for the species and is likely to be important for its long‐term survival. Although opportunities  to offset  the green and golden bell  frog  in  the Hunter Region were  investigated by PWCS  (as  outlined  in  Appendix  J  of  the  Response  to  Submissions  and  PPR),  no  areas  containing known populations or habitat were identified as suitable. The  Commonwealth  initially  raised  some  concern  that  Brundee would  not  adequately  offset  the impacts of  the proposal when assessed using  the EPBC Act Environmental Offsets Policy  (October 2012). This is because the existing GGBF habitat at Brundee is already high quality and there is a low risk of habitat  loss due  to current/future zoning of  the  land. However,  the OEH’s view  is  that  the offset measures would  likely  provide  appropriate  numbers  of  ecosystem  and  species  ‘credits'.  In addition,  the  Commonwealth  has  advised  that  securing  the  land  as  an  offset  site will  allow  the regeneration of native vegetation and likely result in an improvement in the GGBF population. Given this,  the Commission accepts  that Brundee  is an appropriate GGBF offset  site and notes  that  the Department’s recommended conditions ensure that the Commonwealth, OEH and relevant Council will continue to be consulted regarding its ongoing management and conservation.  Commonwealth advice The Commonwealth  initially raised concerns regarding the  impact on the GGBF population and the proposed offset package.  These  concerns were  specifically  referenced  in October 2014 when  the Commission received updated advice, which is summarised in Table 5:  

Table 5 ‐ Summary of Issues raised by the Commonwealth Department of Environment regarding the Green and Golden Bell Frog 

Issue raised with EA submission (May 2012)  Updated advice from Commonwealth 

(October 2014) 

Impact on species and habitat 

Permanent removal of the most important known area of breeding habitat for this population and other connected breeding/foraging habitat 

Substantial reduction in the size and ongoing viability of the GGBF population on Kooragang Island 

 

During the earlier stages of the assessment process, there was a lack of complete information regarding the different frog habitats on the site, the extent of impact and proposed avoidance and mitigation measures.  This meant that a highly precautionary approach was warranted. The Proponent has since provided more complete and better quality information.  As a result, the area of impact has been revised down and the effectiveness of mitigation strategies (including wetland habitat creation, creation of a movement corridor and potential new breeding areas) has been realised. 

Proposed habitat corridor 

The proposed habitat corridor appears to have the potential to partly mitigate the loss of GGBF habitat from other parts of the T4 site and provide connectivity between known GGBF habitat, which would otherwise be fragmented by the project. 

The design of the corridor should be further refined using the best available information 

The design of the proposed corridor has been refined and is one of a suite of avoidance, mitigation and offset measures. The Proponent has demonstrated the development of artificial habitats that have produced breeding frogs, which will be further monitored and refined in the context of the overall project. This point is now not considered a critical issue. 

Page 32: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

23 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

in GGBF habitat creation to ensure that it provides the maximum possible benefit to a residual population.  

Offsets 

Brundee does not adequately offset the impacts of losing high quality GGBT habitat on the subject site when assessed against the Commonwealth’s Offsets Assessment Guide. 

A reduction in impacts and/or additional offsets would be required to reach consistency with the Commonwealth’s Environmental Offsets Policy. 

Due to the initial lack of information, a more conservative view of the value of the proposed offsets was warranted. The Proponent has since provided more complete and better quality information about the Brundee offset area, and engaged the assistance of a local expert (Gary Daly ‐ GAIA Research). This process has added completeness and value to the information set, and improved the inputs into the offsets calculator.  The Commonwealth is now satisfied that the proposed offsets meet the requirements of the EPBC Act.  Based on the type of management proposed and the habitats present, the ecological benefit of Brundee could be achieved within 10 years. 

 Based on this advice, the Commission is satisfied that the impact on the GGBF can be further reduced and that any residual impacts can be adequately offset.  

4.1.4 HUNTER ESTUARY WETLANDS RAMSAR SITE  

Impact The Hunter estuary wetlands are  listed  internationally under  the Ramsar Convention due  to  their unique mix of wetland types and importance for maintaining biological diversity and conservation of migratory shorebirds, including supporting the East Asian–Australasian Flyway population of Eastern Curlew. The Ramsar site  is  located within 500 metres of the project area’s northern boundary and adjoins it for approximately 1.2km.  The Secretary’s assessment report states that these areas are unlikely to be directly impacted by the proposal,  as  no works  are  proposed  in  that  area  (with  the  exception  of  reinstating  an  estuarine channel to assist in maintaining the existing tidal regime to the wetlands). The Commission’s concern was the proposal’s potential to exceed or contribute to a breach of the Limits of Acceptable Change in habitat for the GGBF and migratory shorebirds. This could compromise the values for which it was initially nominated as an internationally significant wetland site.   Mitigation and offsets The  proposed  impact  avoidance,  mitigation  and  offset  strategies  for  the  GGBF  and  migratory shorebird populations in the vicinity of the project site have been outlined earlier in this chapter.   Commonwealth Advice As mentioned above, the Commission was concerned that the proposal could result  in a breach of the Limits of Acceptable Change  for  the GGBF and migratory shorebirds on  the Ramsar site.  In  its submission  on  the  EA,  the  Commonwealth's  raised  this  issue,  however  its  resolution  was  not detailed in the Secretary’s assessment report.  The Commission sought a detailed explanation from the Commonwealth,  including the calculations used to assess the specific proposals against the Limits of acceptable change.  In October 2014 the Commonwealth  informed  the  Commission  that  additional  advice  had  been  received  from  the Proponent, and the Commonwealth was now satisfied that the potential impacts to the Ramsar site are within the Limits of Acceptable Change. This advice is summarised in Table 6.  

Page 33: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

24 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

Table 6 ‐ Summary of Issues raised by the Commonwealth Department of Environment regarding Ramsar Wetlands 

Issues raised in Environmental Assessment submission (May 2012) 

Updated advice from Commonwealth (October 2014) 

Impact on Ramsar wetland – migratory shorebirds 

The proposal has the potential to contribute both to the decline in numbers of migratory shorebirds and the number of shorebird species that occur in the Ramsar wetland. Migratory shorebirds are a critical ecosystem component of the Hunter Estuary Wetlands Ramsar site. 

The creation of an appropriate offset site will balance out this potential impact. 

Impact on Ramsar site – Australiasian Bittern 

The Australasian Bittern is a critical ecosystem component of the Hunter Estuary Wetlands Ramsar site and is integral to the values of the wetland, since its nationally endangered status assisted the estuary in meeting the criteria for Ramsar listing. 

The provision of a successful offset at Tomago would result in this concern being less relevant.   

Impact on Ramsar site ‐ GGBF 

The likely reduction in the size, extent, connectivity and breeding/dispersal capability of the GGBF population could threaten its continued occurrence in the Ramsar site, which could result in a breach of the Limits of Acceptable Change for the wetland. 

No evidence has been provided to support the Proponent’s claim that the GGBF does not occur in the Ramsar site.

Further survey information and discussions with NSW assessment officers have resolved that there are no significant population elements in the area of the Ramsar site that is located directly adjacent to the T4 site.  While it is possible that frogs may or could move into the Ramsar site, it is not considered a critical aspect (though connectivity to the Ramsar site will be maintained). It is not currently considered that impacts to the GGBF will breach the Limits of Acceptable Change for the wetland.

 Based on the updated advice from the Commonwealth, the Commission is satisfied that the proposal would not directly impact upon the migratory birds or the GGBF frog to the extent that the Limits of Acceptable Change would be compromised for the Hunter Estuary Wetlands Ramsar site.  

4.1.5 CONCLUSIONS AND RECOMMENDATIONS  

Having  carefully  considered  the  extensive  submissions  and  advice  received  from  government agencies,  the  public  and  special  interest  groups,  the  Commission  is  satisfied  that  with  further redesign work on the footprint of the stockyard, the impacts of the proposal can be further reduced and that any residual impact will be adequately offset by the proposed offset strategy as long as it is implemented in a timely manner. The Commission agrees with the Department that the three land‐based offset sites in combination with the proposed habitat management actions have the potential to provide for substantial threatened species habitat protection and management.   The following recommendations are provided by the Commission in relation to biodiversity: 

The Commission considers it is critical that the detailed design of the offset sites be prepared in consultation with government agencies  including the Commonwealth, OEH and relevant Council. It is noted that the Department’s recommended biodiversity conditions (B16 to B21) adequately address this recommendation. 

Page 34: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

25 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

The Commission recommends that a five year approval, rather than the 10 year timeframe be considered. A five year approval period would provide an appropriate timeframe for the Proponent  to establish  the conservation works outlined  in  this chapter, which would have significant biodiversity benefits. Although  the Commission  recognises  that additional work and  fine  turning may be  required beyond  the  five years, subject  to  the  learnings  from  the initial strategy. A  ten year approval could delay  these works, which could  result  in  further degradation of habitat and loss of population. 

The Commission is of the view that the Tomago offset area would need to demonstrate that is it functioning successfully prior to construction commencing at the project site. While the Commonwealth recommends one year of demonstrated success, the Commission considers Tomago should be functioning for a minimum of three years to be confident of documenting at least one successful season of use by migratory shorebirds. That is, there is considerable lead‐time to be able to demonstrate “one year of success”. 

Consideration  should  be  given  to  refining  the  stockyard  layout  so  that  it  has  a  reduced impact  on  Deep  Pond  and  the  nearby  Frog  Pond  and  Railway  Pond.  This would  provide improved  GGBF  and  Australasian  Bittern  habitat  as  well  as  minimising  the  impact  on migratory  shorebirds  and  any  potential  to  impact  on  the  values  of  the  Hunter  Estuary Wetlands Ramsar site. 

 

4.2 CONTAMINATION  Under the Minister’s Terms of Reference the Commission is required to consider the contamination impacts of the project and recommend appropriate measures to avoid, mitigate and/or offset these impacts.   The Commission notes  that  the PPR  includes  a number of  changes  to  the proposal  in  relation  to groundwater and contamination. These changes are proposed in response to the issues raised with the EA, including by the EPA, and include: 

changes to the indicative construction schedule; 

changes to stockyard size and layout; 

removal of facilities from the southern bank of the Hunter River South Arm; 

modifications to the dredging and reclamation plan; 

changes to the water management system; and 

refinement of the remediation and management measures. 

4.2.1 BACKGROUND 

The site has historically been used as an  industrial waste disposal area  for contaminated material, substances  and  general  refuse  associated  with  past  activities  of  nearby  industry  and  the  port. Douglas Partners has undertaken extensive contamination investigations of the T4 site (see Part 7 of the EA) and  found that  fill substances  include materials dredged  from the Hunter River and waste from  the  former  BHP  steelworks  and  subsidiaries.  The  remainder  of  the  site  contains  areas  of localised contamination and the potential for acid sulfate soils.  The site consists of three licensed landfill areas (shown in Figure 4): 

Kooragang Island Waste Emplacement Facility (KIWEF); 

Delta Electrolytic Manganese Dioxide (EMD) landfills; and  

Fines Disposal Facility. 

Page 35: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

26 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

Landfill  Closure  Plans  (LCPs)  have  been  developed  for  the  KIWEF  and  EMD  sites  as  part  of  the process of surrendering the applicable Environment Protection Licence  (EPL). The LCPs provide  for the stabilisation of  the  landfill, management of any  remnant human health or environmental risks with a view to enable  future use of the site. A summary of the ownership and status of  the  three landfill areas on the project site are outlined in the table below: 

 Table 7 ‐ Ownership status of Landfill Areas on the Project Site 

Site  Ownership   Landfill Status 

Site A & B 

Kooragang Island Waste  Emplacement Facility   (KIWEF) 

Hunter Development Corporation (HDC) 

This site was in operation from 1972‐ 1999. 

Surrender Notice  for the  EPL  has been issued requiring capping and closure works to Area 1 (around K2 and K10 North) to be completed by 31 December 2014; and Areas 2 and 3 (around K3 and K10 south) to be completed by 30 June 2017. 

The Surrender Notice also allows works to be completed in synergy with the construction of Terminal 4 if approved.  

Site C 

Delta EMD waste disposal facility  

PWCS  This site was in operation from 1989 ‐ 2009. 

EPL was varied in 2011 to require the final cap to be constructed and installed in accordance with the Technical Specification ‐ Kooragang Island EMO Facility Capping Walks and the Construction Quality Assurance Plan ‐ Kooragang Island EMO Facility Capping Walks. 

The existing licence must be surrendered should T4 be approved and constructed. 

Site D 

Fines Disposal Facility 

PWCS  This site has been in operation from 1993 and licensed from 2001 to receive and treat fines dredged from the Hunter River for coal terminal expansion works at Kooragang Coal Terminal. 

This site has been periodically filled with material dredged from the Hunter River. EPL applies to the site and a LCP has not been completed.  If T4 is approved and constructed, a LCP will be prepared and the existing licence will be surrendered. 

4.2.2 PROPOSED REMEDIATION AND REHABILITATION 

A summary of the remediation and rehabilitation measures proposed by PWCS to address the risks associated  with  existing  contamination  on  the  site  is  provided  in  Table  9  of  the  Secretary’s assessment  report. This  includes capping, barrier walls and extracting and  treating contamination. Excavation and disturbance of contaminated material would be minimised during construction, as most works would occur within the upper fill layers, avoiding the need to impact on the underlying contaminated layer.  Key  areas  of  contamination within  the  project  area will  be managed  or  remediated  through  the implementation of a RAP prepared as part of  the PPR. The RAP has been  reviewed by an auditor accredited  by  the  NSW  Environment  Protection  Authority  (EPA)  under  the  Contaminated  Land Management  Act  1997.  The  auditor  has  issued  an  ‘interim  opinion’  which  states  that  the  RAP 

Page 36: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

27 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

adequately addresses  the  key  contamination  issues  identified, and provides  adequate options  for remediation measures. The final RAP will also be reviewed by the auditor and a site audit statement report prepared.  As part of  the PPR, PWCS has prepared an  integrated LCP  that combines  the existing LCPs  for  the site’s  landfill areas and  includes  the Fines Disposal Facility  (Site D). The  integrated LCP details  the proposed  capping  of  areas  that  would  be  impacted  by  construction  and  operation  of  the  coal terminal.  The  Commission  understands  that  the  LCP would  result  in  an  optimal  outcome  for  the project  site,  as  the  capping  associated with  construction  of  the  terminal would  be  equivalent  or superior to that already approved for the KIWEF and the Delta EMO land.  Construction of a low permeability stockyard and sealed surfaces will form a cap over land owned by PWCS. The capping and closure works on the HDC land do not form part of the proposed works for the  T4  project.  The  existing  EPL  Notice  to  Surrender  requires  the  works  to  be  completed  by December 2014 (Area 1) and June 2017 (Area 2), but also allows capping and closure to occur as part of the construction of Terminal 4  (if approved). The Commission acknowledges that the timing  for commencement of construction  is unknown due  to  the uncertainty  surrounding  the global export demand for coal. It is concerned that the remediation works required to be completed by June 2017 may not be funded by the Proponent as it may not have activated an approval by that time. Further, a 10 year approval could delay remediation and rehabilitation of the remainder of the project site in accordance with  the  integrated  LCP.  The  Commission  considers  a  five  year  approval  to  be more appropriate  than a 10 year approval.  Ideally  the various  timeframes  for  the different  remediation works on the site should be resolved prior to any determination of the proposal. This would provide greater  certainty and  cost effectiveness  regarding  the  rehabilitation of  the project  site which  is a significant public interest consideration.  As  a  first  step  in  resolving  the  remediation  of  the  site,  the  Commission  is  of  the  view  that  the Proponent,  the  EPA  and  the HDC need  to negotiate  and develop  a  comprehensive  cost  effective remediation strategy, before a determination is made.   The  Commission  considers  that  if  the  Proponent  was  to  commit  to  a  comprehensive  and  cost effective  remediation  strategy  of  the  site,  this  would  resolve  the  significant  public  benefit uncertainties  associated with  the project while  also  triggering  the  commencement of  the project providing the Proponent ongoing certainty about the development potential of the site.  If approval is not granted for the proposed coal terminal, PWCS would prepare and implement a LCP for the Fines Disposal Facility  land and  implement the existing LCP for the Delta EMO. Closure and capping of all other areas would remain  the responsibility of HDC, requiring  temporary capping at public expense.   

4.2.3 DREDGING MATERIALS AND GROUNDWATER 

The  Secretary’s assessment  report explains  that during  the  initial works phase, excavated natural material or  solid waste material with a  low  likelihood of  contamination will be dredged  from  the Hunter River South Arm. Investigations by Douglas Partners have found that the underlying sand  is suitable  to be used as  fill on  the Delta EMD  site and  stockyard area, as well as parts of  the  land owned by Newcastle Port Corporation and HDC. An ultimate cap on top of the fill would make any previously constructed or historical underlying caps redundant. The potential duplication of capping works  which  might  be  undertaken  by  the  HDC  brings  into  question  the  most  appropriate expenditure of public money.  

Page 37: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

28 Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

 

 The dredge return water would  flow along a  temporary  fill channel with  low permeability barriers prior  to  discharge  to  the Hunter River  at  a  point west  of  Sandgate Bridge.  The  low  permeability barriers  in Deep Pond would  limit migration of  saline water  to groundwater and wetlands  to  the north‐west and south. Any waste material not able to be re‐used as general fill would be placed in a purpose built containment cell within the project site or treated (if required) and disposed of at an appropriately  licenced  facility  offsite.  The  Commission  supports  the Department’s  recommended condition which requires  the preparation and  implementation of a Materials Management Plan  to manage any potentially contaminated material not covered by the LCP or the RAP.  A  fill aquifer and an estuarine aquifer are  located under the project site. The  fill aquifer  is  located above the estuarine aquifer and  is separated by an  impermeable  layer  (aquitard). A barrier wall  is proposed to be  installed on the KIWEF area to contain and treat contaminants  in groundwater and avoid disturbance across the fill aquifer. The Commission accepts the advice of Douglas Partners that the  vertical movement  of  saline water  into  the  estuarine  aquifer  is  unlikely  to  occur  due  to  the thickness  and  low permeability of  the  clay  aquitard  in  this  location.  The proposed barrier wall  is more permeable and therefore water is more likely to flow through it.   The proposed contaminant management measures are shown  in the Secretary’s assessment report (see Figure 5) and are predicted to lead to an overall decrease in long‐term flow rates and mobility of contaminants compared to the current situation.   There will be some short term and temporary increases in groundwater flow rates and levels of surface water bodies as groundwater is "squeezed" out during  the pre‐loading phase.   However, once  settlement  is  complete and  the  site  is  capped, ground  flow  in  the  fill  and  estuarine  aquifers would  be  reduced  to  below  existing  levels  for  the majority of the site, resulting in a long term reduction in contamination mobility.   Concern was raised at the Public Hearing that the works required to contain contamination prior to the development commencing pose a higher risk of dispersion than if the current operations on the site were to continue. A groundwater and contamination assessment has been prepared by Douglas Partners  which  examines  the  effectiveness  of  the  proposed  contamination  remediation  and management measures in limiting off‐site migration of contaminants. It was found that by adopting the proposed contamination management measures, off‐site contaminant levels would not increase to  an  extent  that  would  threaten  environmental  values  or  human  health.  These measures  will improve  the  long‐term  environmental  condition  of  the  project  site  and  surrounding  land  by addressing the risks associated with existing contamination.  

Page 38: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

29  

 

 

 

                               

Figure 4:  Landfill areas (Source:  T4 Project Response to Submissions and PPR (EMM 2013))

Fines Disposal Facility 

former Delta EMD site 

KIWEF 

Page 39: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

30  

 Figure 5:  Proposed contamination management and remediation measures (Source:  T4 Project Response to Submissions and PPR (EMM 2013))

Page 40: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

31  

4.2.4 EPA ADVICE 

In 2012  the EPA provided a submission  to  the EA, which  raised  the  following points  in  relation  to contamination issues associated with the project site: 

The  contamination  assessment  presented  in  the  EA  is  generally  adequate  and  identifies likely impacts on existing contamination at Kooragang Island;  

The EA does not provide adequate information regarding the quality of the sediments likely to be encountered during dredging operations; 

 

Additional details of the proposed contaminated groundwater control works and measures are required; 

 

The Proponent needs to assess the potential impact on existing groundwater contamination if saline groundwater is reinjected or allowed to seep into the groundwater table. 

The Commission met with the EPA  in Newcastle on 14 August 2014 to discuss the revised proposal and additional information received by the Department as part of the PPR. At this meeting the EPA explained  that  while  the  RAP  is  supported,  there  was  still  concern  about  the  management  of dredging and the potential impact on Deep Pond. The EPA also explained that if the development of T4 does not proceed,  the  site will need  to be  capped  and  remain  that way  ‐ pending  any  future development.   Correspondence received by the Commission on 25 August 2014  from the EPA confirmed that the draft  conditions  recommended  by  the  Department  address  the majority  of  the  EPA’s  concerns. However,  the  EPA  believes  that  the  conditions  relating  to  stormwater  and  surface  water management need additional detail.  It was also recommended  that Condition B32 be amended  to reference a one in 100 year average recurrence interval discharge event, which is consistent with the PPR and EA.   Further correspondence  from  the EPA  reviewed by  the Commission on 10 October 2014 provided recommended  revised wording  and  additional  conditions  relating  to  the  RAP  and  surface water management.   The EPA has provided a  table detailing  these amendments, which  the Commission agrees should be  included  in any  future approval.   A copy of  the  table summarising  the proposed amendments  is contained at Appendix 6 of this report.   The recommended conditions would have the effect of  requiring  that  final capping works must be  implemented and completed prior  to any dredge material emplacement, preloading or construction at the project site. This will ensure that if a  staged  approach  is  undertaken  by  PWCS,  and  dredging  preloading  or  construction  is  delayed, existing groundwater contamination is managed by limiting surface water infiltration.  

4.2.5 CONCLUSIONS AND RECOMMENDATIONS 

The  Commission  is  of  the  view  that  the  integrated  LCP  and  RAP  will  adequately  manage  the remediation of the project site for its intended use, and reduce the risk of offsite contamination. It is recognised  that  applying  a  consistent  level  of  capping  that  is  equivalent  to  or  better  than  that currently proposed across  individual  land parcels would be beneficial. Therefore,  the Commission agrees with  the Department  that  the  proposed management  of  contamination would  result  in  a positive contribution to the environment and human health when compared to the current  landfill arrangements.  If however the project is approved but construction is not commenced for up to ten years, as proposed,  then  the  current  requirements  for  remediation  could be put on hold  for  that period.  

Page 41: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

32  

The following recommendations are provided by the Commission  in relation to contamination and remediation: 

The  Commission  believes  that  the  contamination  on  Kooragang  Island  needs  to  be remediated  as  soon  as  practicable.  Before  a  determination  is  made,  the  Commission recommends  that  the  Proponent,  the  EPA  and  the  HDC  negotiate  and  agree  on  a comprehensive  remediation  strategy, with  clear  roles  and  responsibilities,  and  an  agreed time‐table. 

A  five year approval  (rather than the proposed 10 year approval) would provide  increased certainty and would ensure that the remediation process is not unnecessarily delayed.  

The  Commission  recommends  adoption  of  the  amendments  and  additional  conditions recommended  by  the  EPA  in  the  correspondence  dated  10  October  2014.  In  addition, Condition  B32  should  be  amended  to  reference  a  one  in  100  year  average  recurrence interval discharge event, (as in correspondence from the EPA dated 25 August 2014). 

 

4.3 AIR QUALITY AND ASSOCIATED HEALTH IMPACTS The Commission’s  terms of  reference  for  the Review  require  it  to pay particular attention  to  the noise and air quality  impacts of  the project. Many of  the submissions  received, and presentations made during the public hearing, also raised concerns about air quality. Of particular concern was the potential for the proposed T4 Coal Terminal  to impact on air quality (especially particulate levels) in the Newcastle region, with associated health and amenity implications for the Newcastle population, as well as those who live in the vicinity of railway lines used by coal trains delivering coal to the T4 Terminal.  

4.3.1 CURRENT PARTICULATE LEVELS AND STANDARDS 

Australia has adopted ambient air quality standards as a National Environment Protection Measure (NEPM), as set out in Table 8. The Air Quality NEPM have been the subject of review in recent years and at the time of writing draft amendments had recently been exhibited. NSW has adopted impact assessment  criteria  for  particulates  consistent  with  the  NEPM  standards,  as  well  as  additional standards including; an annual average value for PM10 , Total suspended particulates, and Deposited dust, as set out in Table 9.   Table 8 ‐ Current NEPM Standards and Goal for particulates (as varied in 2003)6 

Pollutant  Averaging period  Maximum (ambient) concentration 

Notes

Particles as PM10  1 day  50 µg/m3 Maximum allowable exceedances, 5 days a year*  

Particles as PM2.5  1 day  25 µg/m3 Reporting standard.  Goal is to gather sufficient data nationally to facilitate a review of the standard as part of the review of this Measure scheduled to commence in 2005. 

1 year  8 µg/m3

* Allowable exceedances relate to bushfires, dust storms and fuel reduction burning for fire management purposes.       

                                                            6 National Environment Protection (Ambient Air Quality) Measure, Schedule 2, http://www.comlaw.gov.au/Details/C2004H03935 accessed 6 November 2014. 

Page 42: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

33  

Table 9– NSW EPA Impact Assessment Criteria for Particulates7 

Pollutant  Averaging period Concentration  Source 

PM10  24 hours  50 µg/m3 NEPC (1998) 

Annual  30 µg/m3 EPA (1998)  

Total suspended  particulates (TSP) 

Annual  90 µg/m3 NHMRC (1996) 

Deposited dust Annual  2 g/m2/month (Maximum 

increase in deposited dust level.) 

NERDDC (1988) 

Annual  4 g/m2/month (Maximum total deposited dust level.) 

NERDDC (1988) 

 Several  submissions  from  agencies  and  the  pubic  referred  to  the  current  review  of  the  NEPM standards  and  some  suggested  that  the proposed new  standards  in  the  current discussion paper should be adopted for this project given its proposed long development and operating periods.  The Commission’s approach to the draft standards is discussed later in this section.   Air  Quality  monitoring  data  for  the  Newcastle  area  is  publicly  available  from  the  Office  of Environment and Heritage’s website  for Beresfield, Wallsend, Mayfield, Carrington and Newcastle (near Hamilton South). The Mayfield and Carrington monitors have only recently been  installed, so very little data is available from these monitors.   As shown in Table 10 air quality has fluctuated over the years. The Commission has not undertaken statistical analysis of  the available data, but  from a general overview, particulate  levels across  the region,  to which  the broad Lower Hunter population are exposed do not appear  to have changed dramatically over the last decade and a half.  Table 10 ‐ Annual Average PM10 and PM2.5 levels (sourced from OEH air quality data) 

Year  PM10  Wallsend  µg/m3 

PM10 Beresfield µg/m3 

PM10 Newcastle µg/m3 

PM2.5 Wallsend µg/m3 

PM2.5 

Beresfield µg/m3 

1997  18.5  19.5    6.5  

1998  17.1  18    5.4 5.1 

1999  16  16.9    4.9 5.6 

2000    17.8    5.3 5.6 

2001  17.8  21.5    7  

2002  21.3  27.1    8.1 10.3 

2003  18.1  19.1    6.6 6.2 

2004  18.7  20.9    6.7 7.8 

2005  18.2  20.3  21.6  6.5 6.8 

2006  18.5  21.3  21.1  6.4 6.8 

2007  17.3  20.4    5.8 6.3 

2008  15.4  18.5  20.6  5.9 6 

2009  26.7  28.7  31.3  8 8.6 

2010  14.9  16.6  18.7  4.7 6 

                                                            7 NSW Department of Environment and Conservation. 2005. Approved Methods for the Modelling and Assessment of Air Pollutants in New South Wales. P 28 http://www.epa.nsw.gov.au/resources/air/ammodelling05361.pdf accessed 6 November 2014.   

Page 43: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

34  

Year  PM10  Wallsend  µg/m3 

PM10 Beresfield µg/m3 

PM10 Newcastle µg/m3 

PM2.5 Wallsend µg/m3 

PM2.5 

Beresfield µg/m3 

2011  14.2  17.2  19.1  4.8 5.5 

2012  14.9  21.4  20.6  5.1 8 

2013    21.5  22.6  7.6 8.3 

2014*  15.8  18.5  19.7  6.4  7.3 

Average  17.7  20.3  21.7  6.2  6.9 

Maximum  26.7  28.7  31.3  8.1  10.3 

Minimum  14.2  16.6  18.7  4.7  5.1 * year to date (1 January 2014 – 7 October 2014) 

 The Proponent’s Environmental Assessment summarises PM10 monitoring data from other monitors at Fern Bay, Steel River and Stockton for the decade to 20108. That data shows that the current NSW annual  average  criteria,  of  30  µg/m3, was  exceeded  in  some  years  in  the  early  part  of  the  new millennium.   Some  speakers  at  the  public  hearing  suggested Newcastle’s  air  quality  is  relatively  poor.  The  air quality monitoring data does not support this view. The Commission notes that air quality across the region  is  generally within  the NSW  criteria but  acknowledges  that  there may be  individuals with specific exposure  sensitivities  close  to emission  sources who  report  localised health effects which are not problematic across the wider regional population.  

4.3.2 IMPACTS OF THE PROJECT 

Air emissions would be produced from a range of sources and activities associated with the project, and can be broadly categorised as: 

Loading  and unloading of  coal on  the  site,  including  the  transfer of  coal  to and  from  the 

stockpiles; 

Storage of coal on the site, emissions from the stockpiles;  

Transport of coal  to and  from  the site,  including  the emissions  from  loaded and unloaded 

coal trains and the emissions from ships; and 

Other up and downstream  impacts,  including upstream emissions  from extracting  the coal 

resource and transporting  it to the site and downstream emissions from transport and use 

of the coal at its destination. 

4.3.2.1 EMISSIONS FROM THE PROJECT SITE 

The  Proponent  has  estimated  the  emissions  from  the  project  site  taking  into  account mitigation measures  such as water  sprays and also enclosure of  some  (and partial enclosure of  some other) equipment.  The EA has included the emissions from the use of rail locomotives and ship boilers and auxiliary engines while on  site or at  the port. The  coal  stockpiles on  site are proposed  to be  left uncovered,  but  would  be  sprayed  with  water,  which  is  said  to  have  a  control  efficiency  of approximately 67% (modelling has assumed 50% efficiency)9. Transfer equipment  including the rail receival dump station, conveyors and ship loaders would be at least partially enclosed with efficiency control of between 70 to 85% at each source.  

                                                            8PWCS/EMM. 2012 T4 Project, Environmental Assessment. February 2012. Appendix M Figure 15, p 35 9 PWCS/EMM. 2013. T4 Project, Response to Submissions and Preferred Project Report. September 2013. Appendix C p 22 

Page 44: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

35  

 The Proponent has modelled air quality impacts of the activities that would occur on the project site, taking  into  account  the  control  measures  proposed;  and  considering  existing  air  quality  levels, additional emissions  from some currently proposed or approved developments  (which have yet to be constructed) and the potential emissions from this site.  

BackgroundlevelsadoptedbytheProponent’smodellingThe background air quality levels used have been criticised in submissions as the data is not the most recent available and particulate levels were lower that year (2010), than some other years.   Particulate  levels  fluctuate over  time  (see Table 10) and will  continue  to do  so. Nonetheless,  the Commission considers that the background levels adopted by the Proponent are at the lower end of the range measured over the past decade. For PM2.5 the Proponent has adopted an annual average background  level of 4.6 µg/m3 and up to an additional 0.9 µg/m3 for future development. For PM10 the  Proponent  has  adopted  an  annual  average  background  level  of  between  17  µg/m3  and  17.7 µg/m3  depending  on  the  location with  up  to  an  additional  2.6  µg/m3for  future  development.  In responding  to criticism of  the background  levels adopted,  the Proponent  indicated  it undertook a sensitivity  analysis which  considered  the maximum  concentrations measured  during  the  2007  to 2011  period,  but  excluded  ‘atypical’  results  from  the  2009  regional  dust  storm.  The  Proponent advises  that  this  substitution of maximums  into  the  cumulative  assessment did  not  result  in  any exceedance  of  the  annual  average  EPA  PM10  criteria,  or  NEPM  PM2.5  goals

10.  The  Commission acknowledges this, but notes that: 

since  2011  annual  average  PM10  and  PM2.5  levels  have  generally  been  higher  than  levels measured during the 2007‐2011 period; and 

in  relation  to  the exclusion of  ‘atypical’  results  associated with  regional dust  storms,  the Commission  is  not  aware  of  any  allowable  exception  for  these  events when  considering annual average particulate levels. For 24 hour average PM10 levels the NEPM does allow “5 exceedances  for  the PM10  standard  [explaining  these] were  introduced  to account  for  the impact of bushfires, dust storms and fuel reduction burning for fire management purposes. These exceedances are often misused and have been applied to urban air pollution and,  in some cases, individual sources”11.   

Nonetheless, given the uncertainties about the timeframe for developing the project and the criteria that would  apply  at  that  time,  the  predicted  contribution  from  the  project  is  perhaps  the more useful measure.  

EmissionssourcesFor  PM2.5  the  Proponent  has  predicted  that  the  ships  at  the  dock  would  generate  the  highest contribution,  followed by  the wind erosion of  the  stockpiles,  train  idling,  train unloading,  stacker reclaimers  and  conveyor  transfers12.  The  preferred  project  report  noted  that  the  locomotive combustion emissions had been underestimated  in the original assessment as  it had assumed that locomotives would be compliant with Tier 2 emissions performance. The Commission understands there is no emission control requirement in place for rail locomotives at present and consequently it is  appropriate  that  the  Proponent  has  taken  a  more  conservative  approach  to  estimating  the combustion emissions from the rail locomotives. The standards for ship fuel and rail and ship engine 

                                                            10 PWCS/EMM. 2013. T4 Project, Response to Submissions and Preferred Project Report. September 2013. Appendix C 11 National Environmental Protection Council Service Corporation. 2011. National Environmental Protection (Ambient Air Quality) Measure Review – Review Report. p 30 12 PWCS/EMM. 2012 T4 Project, Environmental Assessment. February 2012. Appendix M 

Page 45: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

36  

emissions  performance  are  expected  to  improve  in  the  future,  and  acceptable  and  achievable mitigation measures are also likely to evolve (this is further discussed in the following sections).   For  PM10 wind  erosion  from  stockpiles  is  the  highest  contributing  source,  followed  by  vessels  at berth, stacker reclaimers, conveyor transfers and then combustion emissions from locomotives.  

EmissionscontributionThe Proponent has undertaken modelling  to predict  the dispersion patterns of  the emissions  that the  project  would  produce.  Ten  locations  around  Newcastle  were  modelled  with  the  highest predicted impacts in Sandgate. The Proponent has modelled three different scenarios: 

construction; 

operation at a throughput capacity of 25 million tonnes a year while construction continues 

on other portions of the site; and  

operation at maximum capacity, 70 million tonnes a year.  

As shown  in Table 11, the  impacts of the project are predicted to be highest during the combined construction and operations at 25 million tonnes a year scenario.   Table 11– Highest predicted particulate emissions contribution from the project at Sandgate, under different stages of development 

  Contribution during construction only (µg/m3) 

Highest predicted contribution, operations at 25 Mtpa and construction (µg/m3) 

Contribution duringoperations at maximum capacity (70 Mtpa)( µg/m3) 

24 hour average PM10  15  17.9 6.8 

24 hour average PM2.5  3.3  4.7 4.0 

Annual average PM10  2.2  2.5 1.0 

Annual Average PM2.5  0.5  0.7 0.6 

 Other  suburbs  are  predicted  to  have  higher  background  levels,  particularly  Stockton  North,  so although  the  contribution  from  the  project would  be  smaller  at  these  locations,  the  cumulative levels would sometimes exceed those at Sandgate.  The Proponent’s modelling of the cumulative  impacts of this project’s emissions combined with  its adopted background  levels, and  contributions  from  future development  suggests  that  the project would not cause any additional exceedances of the existing criteria for PM10 and PM2.5 during any of the  scenarios modelled.  As  noted  earlier  in  this  section,  the  Commission  has  some  reservations about the background levels adopted. 

AcceptabilityofthepredictedimpactThere are at  least three aspects which need to be considered to determine the acceptability of the predicted impact; 

1. does  the proposal  include all  reasonable and  feasible measures  to minimise and manage 

emissions from the site? 

2. do the predicted  impacts meet the health and environmental standards for the protection 

of regional air quality? 

3. Are the current air quality standards appropriate for this proposal? 

CurrentpolicyandregulatoryrequirementsThe  Department’s  preliminary  assessment  is  supportive  of  the  control  measures  proposed, particularly the real time predictive and reactive air quality control system as well as the Proponent’s ongoing  commitment  to  minimise  dust.  The  Department  has  also  accepted  the  Proponent’s 

Page 46: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

37  

argument that the proposal would not cause any exceedance of the annual average PM10 criteria for NSW set out in the Approved Methods for the modelling and Assessment of Air Pollutants in NSW, of 30 µg/m3, nor any further exceedances of the 24 hour average PM10 criteria.   During  its  meetings  with  the  Commission  (summarised  in  Appendix  3)  the  NSW  EPA  has  also indicated  it  is  generally  satisfied  that  the  proposed mitigation measures  represent  best  practice. Nonetheless the Commission noted that some submissions and speakers at the Public Hearing had raised  concerns  that  the  proposal  did  not  represent  current  best  practice  control  of  fugitive emissions.  The  EPA  agreed  to  consider  the points  raised  and provided  a written  response  to  the Commission, dated 10 October 2014.  In  that  response  the EPA notes  that  some  conveyors would only be partially enclosed, but  that  this  is due  to operational  restrictions and where machinery  is required  to  travel along  the  conveyor. The EPA also noted  concerns had been  raised about  stage loader/crusher activities, but clarified that it understood this crushing or resizing activity would not be occurring on the site.  Ultimately the EPA concluded that “implementation of proactive, real‐time best  practice management measures  are  critical  to minimise  the  risk  of  dust  impacts  from  the proposed project” 13.   Health concerns were raised by numerous speakers at the public hearing, and in submissions.  NSW Health’s submission dated 17 November 2013 stated “The health effects of exposure  to PM2.5 and PM10 are well established. As the proponent’s response to submissions acknowledges, no threshold has been  identified below which exposure to PM  is not associated with health effects.   Compliance with air quality  standards  is not,  therefore, completely protective of health.   The  lack of  identified threshold is recognised in the National Plan for Clean Air, a goal of which is to develop an “exposure reduction framework” that will encourage reductions in population exposure to PM, even where the standards are met. … While the modelled air quality impacts comply with the current EPA assessment criteria,  should  the  project  be  approved  it  is  recommended  that  the  proponent  is  required  to implement  all  reasonable  and  feasible measures  to  control  emissions  of  PM2.5  and  PM10  from  all sources.  This will ensure that any health impact is minimised.”14    The Commission met with senior representatives from NSW Health on 1 October 2014.  NSW Health referred to the World Health Organisations most recent findings on particulates15, which emphasises the  health  risks  associated with  fine  particles  (PM2.5)  but  also  that,  although  “Data  from  clinical studies are  scarce;  toxicological  studies  report  that  coarse particles  can be as  toxic as PM2.5 on a mass basis.16” At  the Commission’s  request NSW Health  considered  the  risks  associated with  the project related PM2.5 emissions and subsequently provided the Commission with a written response to  this  issue. NSW Health’s  letter  is  included  in Appendix 6 of  this  report and generally concludes that the health risks associated with the predicted PM2.5 emissions would be classed as tolerable and an order of magnitude lower than that which is considered unacceptable. NSW Health’s letter goes on to highlight that although assessment criteria are not expected to be breached “it is not unlikely that future standards will be different to today’s” and conditions should include the requirement to mitigate the impacts of particulate matter.   

                                                            13 NSW EPA 2014. Correspondence to the PAC. Dated 10 October 2014 p 2 14 NSW Health, Hunter New England Local Health District. 2013. Letter to the NSW Department of Planning and Infrastructure titled Port Waratah Coal Services Limited Response to Community Submissions – Terminal 4 project, dated 17 November 2013.  15 WHO 2013. Review of evidence on health aspects of air pollution – REVIHAAP Project: Technical Report. http://www.euro.who.int/__data/assets/pdf_file/0004/193108/REVIHAAP‐Final‐technical‐report‐final‐version.pdf accessed 3 November 2014 16 WHO 2013. Review of evidence on health aspects of air pollution – REVIHAAP Project: Technical Report p 11 

Page 47: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

38  

AppropriateAirQualityStandardsAs  noted  earlier  in  this  section  (and  in  submissions,  including NSW Health’s  letter),  the  recently exhibited Draft NEPM amendments propose tightening and additions to the existing particulate air quality standards in Australia. These included possible lowering the 24‐hour average PM10 level from 50 to 40‐50 µg/m3

, introducing an annual average PM10 of 20 µg/m3 (this is consistent with the World 

Health Organisation  goal but  lower  than  the  level of 30 µg/m3  currently  adopted by  the  EPA  for NSW),  and  introduction  of  standards  for  PM2.5  (there  are  currently  no  standards  for  PM2.5,  only reporting goals).  The associated Impact Statement, released for consultation was open for comment up until 10 October 2014, so a decision on the final levels adopted may still be some time away. The Department has proposed  to provide  the Proponent with an approval  that would only need  to be acted on within 10 years of any determination to approve the project.  In this scenario, it is possible, if  not  likely,  that  knowledge  of  health  impacts  will  continue  to  evolve  and  the  review  of  the standards  will  be  finalised  before  the  Proponent  even  commences  construction,  let  alone  any operations.  The Commission has a number of concerns about the proposed 10 year  lapsing period noting that most,  but  not  all  developments  are  limited  to  5  years  to  commence works  before  the  approval would lapse.  The Department provided examples of developments that have been approved with 10 year commence periods, however the Commission considers that there are several uncertainties for this  proposal  (these  are  also  discussed  in  other  sections  of  this  report)  that  are  likely  to  change during  a  ten  year period.  It  is unclear  if,  and how  any new  tighter  standards might  apply  to  this project.  Normally the contemporary standards at the time of approval would apply and it would be up to the regulatory authority, eg the EPA, to consider application of any future standards through its ongoing licensing system.  This generally precludes however, major redesign or limiting maximum throughput below those approved in the planning approval. Consequently the Commission considers any approval should be for a 5 year period. By considering a 5 year approval period, the Commission can assess the application against the existing NSW Impact Assessment Criteria17.  ConsiderationagainstEnvironmentalStandardsThe Commission has some concerns about the suitability of the background air quality levels used in the air quality modelling (which excluded impacts from the 2009 dust storm in the consideration of cumulative  impacts). The resulting modelling, which shows  the project will meet  the existing NSW Air Quality Standards, are potentially somewhat optimistic.   Given that there are already occasional exceedances of air quality standards in the Newcastle area, it could  be  argued  that  any  additional  emission,  no matter  how  small,  should  be  disallowed.  This approach would however go against a common sense approach of targeting the most cost effective means of achieving net air quality improvements.   The proposed site  is within  the  industrial precinct on Kooragang  Island with  the Hunter River and additional  industrial  land  sitting  between  the  site  and  residential  areas.  Given  its  location,  the Commission  is  satisfied  that even allowing  for  some uncertainties around modelling assumptions, the net contribution to particulate emissions in the Newcastle area from a fully operational T4 would be modest.   Nonetheless,  the Commission considers  that adaptive management will be critical  to ensuring  the project meets contemporary  requirements and does not  impede on  the development potential of 

                                                            17 NSW Department of Environment and Conservation. 2005. Approved Methods for the Modelling and Assessment of Air Pollutants in New South Wales. P 28 http://www.epa.nsw.gov.au/resources/air/ammodelling05361.pdf accessed 6 November 2014.   

Page 48: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

39  

the remaining industrial and port side lands. NSW Health has highlighted that the Proponent should be  required “to  implement all  reasonable and  feasible measures  to control emissions of PM2.5 and PM10 from all sources”18 to ensure health impacts are minimised. Further the NSW EPA has indicated “implementation of proactive, real‐time best practice management measures are critical to minimise the risk of dust impacts from the proposed project” 19.  ReasonableandFeasiblemitigationandmanagementThe Proponent  argues  that  the proposal  is  already  committed  to  include best practice mitigation measures on  the T4  site.  Some  submissions have noted however  that another  recently proposed coal  terminal  in Western Australia  included enclosure of  stockpiles  to  further mitigate particulate emissions.  The  Commission  accepts  the  Proponents  advice  that  full  enclosure  of  the  T4  terminal would be technically challenging and prohibitively expensive. The Commission also notes that for the smaller particle fractions (PM2.5) the emissions from the stockpiles are predicted to be less significant than  those  from  vessels  at berth; while  locomotives  are  also predicted  to  account  for  significant PM2.5 emissions from the site.    ShipsThe Commission acknowledges  that  some of  the most  significant  sources of particulate emissions are associated with ships and locomotives, and to some extent beyond the control of the Proponent. Options  to manage  emissions  from  ships  both  at  dock  and  in  the  vicinity  of  a  port  are  available however and have been considered in work commissioned by the EPA, such as “Potential Measures for Air Emissions  from NSW Ports: Preliminary Study”20. This  study assessed  ship emission  control methods including: 

Low sulfur fuel at berth; 

Low sulfur fuel in NSW Greater Metropolitan Region; 

Shore Power, including the possibility of cogeneration; 

Vessel Speed Reduction; and 

Prohibiting ship on‐board incineration. 

Of  these  options,  the  use  of  low  sulfur  fuel was  found  to  have  the  greatest  potential  benefit  in reducing PM10 and Sulfur Dioxide emissions. While a 20% vessel speed reduction at sea would have the greatest mitigation effect on Nitrogen Oxides. Supply of shore power while ships are at berth would also have benefits, although there is a high capital cost associated with installing shore power, both at the port and on the vessels. Nonetheless, once installed the cost of electricity was said to be less  than  that of diesel  fuel and would also  reduce auxiliary engine maintenance costs. The  study found that “Some recently developed berths have been required under planning approvals to make spatial provision for shore power, should  it be used  in future”21. The Commission considers this  is a reasonable  requirement and  recommends  that  this  is  included  in any  conditions of approval. The Commission also notes  that some of  the other measures  identified  in  the study should be  further explored by the Proponent in ensuring it meets best practice standards.    

                                                            18 NSW Health, Hunter New England Local Health District. 2013. Letter to the NSW Department of Planning and Infrastructure titled Port Waratah Coal Services Limited Response to Community Submissions – Terminal 4 project, dated 17 November 2013.  19 NSW EPA 2014. Correspondence to the PAC. Dated 10 October 2014 p 2 20 PAEHolmes. 2011. Potential Measures for Air Emissions from NSW Ports: Preliminary Study. Prepared for the NSW Office of Environment and Heritage, 23 June 2011.  21 PAEHolmes. 2011. Potential Measures for Air Emissions from NSW Ports: Preliminary Study. Prepared for the NSW Office of Environment and Heritage, 23 June 2011. P 17 

Page 49: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

40  

LocomotivesEmissions  from diesel  locomotive engines also represent a key contribution  to  the emissions  from the  project  site.  The  Commission  met  with  the  NSW  EPA  to  discuss  rail  emissions  sources.  In discussing this  issue the EPA referred the Commission to  its current work addressing air emissions from  rail.  Amongst  these  is  the  2013  Locomotive  Emissions  Project:  Scoping  Study  of  Potential Measures  to Reduce Emissions  from New and  In‐service Locomotives  in NSW and Australia, which states: 

“Diesel‐fuelled  locomotives are an  important  contributor  to anthropogenic  fine particulate and oxides of nitrogen emissions  (NOx). The World Health Organisation  (WHO) has  classified diesel engine exhaust as being  carcinogenic  to humans.  It  found  that exposure  to diesel exhaust  is a cause  of  lung  cancer  and  increases  the  risk  of  bladder  cancer.  In  Australia,  there  are  no  air emission limits for new or re‐manufactured locomotives. Nor are there any substantive programs within Australia addressing air emissions from in‐service locomotives.”22 

 Further,  in 2012  locomotives were estimated to contribute 4.7% to national emissions of PM2.5 and 4.2% to national emissions of NOx.23 The NSW EPA’s Position paper: Review of regulation of railway systems  activities  under  the  ‘Protection  of  the  Environment Operations  Act  1997  of  August  2014 states that: 

Current  EPLs  [Environment  Protection  Licences]  specify  that  all  plant  and  equipment  used  on licensed premises must be properly and efficiently operated. Additionally, EPLs  include a general requirement for  licensees to minimise dust from their premises. However, EPL conditions do not specifically address issues associated with air emissions from locomotives.24 

 The paper notes  that under  the current  system only  rail  system operators have EPLs while  rolling stock operators are not directly accountable to the EPA for their environmental performance.  A number of submissions and speakers at the public hearing raised concerns about the  impacts of coal trains, both at the site and travelling to and from the site. Particular concern was raised about the use of uncovered coal wagons. The Commission has considered the impacts of coal trains on the rail network in a later part of this section, see 4.3.2.2, Up and downstream transport of coal.    In relation to emissions from diesel combustion in locomotives, the Commission supports the EPA’s current  work  to  address  this  issue,  which  is  said  to  include  investigations  into  imposing  diesel emission  standards  on  new  and  existing  locomotives  operating  in  NSW.  Adoption  of  such requirements would be consistent with measures already in place in the US and other OECD Nations. Ultimately,  it  appears  that  “Locomotives  used  for  coal  transfer  to  ports  within  NSW  generally comprised  newer  locomotives  and were  identified  for  potential  upgrade  but  not  for  accelerated replacement.”25  This  apparent  use  of  newer  locomotives  potentially  provides  greater  options  to ensure that emissions performance is controlled, idling is minimised and other shut down activities are  able  to  be  implemented  during  adverse  conditions.  The  Proponent’s  management  of 

                                                            22 ENVIRON. 2013. Locomotive Emissions Project: Scoping Study of Potential Measures to Reduce Emissions from New and In‐service Locomotives in NSW and Australia. P vii http://www.epa.nsw.gov.au/resources/air/locoemissrep.pdf accessed 6 November 2014 23 ENVIRON. 2013. Locomotive Emissions Project: Scoping Study of Potential Measures to Reduce Emissions from New and In‐service Locomotives in NSW and Australia. P ix 24 NSW EPA. 2014. Review of regulation of railway systems activities under the ‘Protection of the Environment Operations Act 1997, Position paper. August 2014 p 7 http://www.epa.nsw.gov.au/resources/epa/14657railpospap.pdf accessed 5 November 2014 25 ENVIRON. 2013. Locomotive Emissions Project: Scoping Study of Potential Measures to Reduce Emissions from New and In‐service Locomotives in NSW and Australia. Pxiii http://www.epa.nsw.gov.au/resources/air/locoemissrep.pdf accessed 12 November 2014 

Page 50: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

41  

locomotives  on  the  site  cannot  be  considered  in  isolation  however. Management  of  locomotives would need to  include consideration of both the onsite  logistics of the coal handling operation, as well as the site’s integration with the broader rail freight network, the rail system operators and the rolling stock operators.  Proactive,Real‐timeBestPracticeManagementMeasuresThe  Department’s  draft  recommended  conditions  include  requirements  for  an  air  quality management plan, to include pro‐active and reactive mitigation. The conditions do not specify which pro‐active and reactive mitigation measures would be implemented to manage dust (this is left to be determined  in  the  plan).  Correspondence  from  the  EPA  indicates  that  it  “expects  the  emission control measures  identified  in the Statement of Commitments of the Preferred Project Report to be implemented  should  approval  for  the  project  be  granted.”26  The  Proponent’s  Statement  of Commitments  proposes  that  the  predictive  and  reactive  real  time  management  system  would identify  triggers  for  contingency dust management,  such  as  additional use of water  sprays27. The Commission  notes  that  additional water  spraying  is  not  considered  sufficient  for modern mining operations,  which  are  required  to  scale  back  and  if  necessary,  temporarily  shut  down  some operations during certain periods when air quality  is already poor, and/or during adverse weather conditions. The Commission acknowledges that there are a number of differences between mining operations  and  this  proposed  coal  terminal.  Nonetheless,  further  consideration  of measures  to reduce emissions during adverse weather conditions should be provided  to ensure health  impacts are minimised.  Given  significant  particulate  emissions  are  produced  from  ships  and  locomotives  on  the  site  the Commission considers that some mechanism to manage these emissions would need to be  found, for example with shut down of engines, or adjusting the scheduling of ship loading at the port when adverse  conditions  are  predicted  or  occurring.  The  Commission  acknowledges  this would  impose some  constraints  on  the  operation  of  the  T4  coal  project,  but  considers  these  and  options  for addressing them should be further explored.   The Commission notes that emissions from ship engines and locomotives may be able to be reduced by the Proponent through options such as provision of shore power to ships, or having ships use low sulfur fuel; and by minimising idling of locomotives, for example by ensuring the machines to restart the  older  locomotives  that  do  not  have  the  capacity  to  be  easily  switched  off  and  restarted  are readily available on the site (or by phasing out acceptance of older locomotive engines). Further, the Commission  considers  there  could  be  some  opportunities  for  trade‐offs  to  be  considered.  For example there may be merit  in arguing that some ships might be allowed to berth and  load during some  (but not necessarily all) adverse conditions, as  long as additional controls  ‐ of a greater net benefit were provided on one of  the other sites  in  the Port  (for example by covering or removing one  of  the  other  stockpiles  or  terminal  sites).  This  type  of  offsetting  of  impacts  should  only  be considered for emissions from T4 that are largely beyond the control of the Proponent, i.e. ship and locomotive  emissions.  Further,  any  compensatory  works  provided  as  offsets  would  need  to  be additional  voluntary measures  beyond  any  existing  requirements  of  an  EPA  Pollution  Reduction Program, or other pre‐existing requirements to provide reasonable and feasible mitigation. It would be up to the Proponent to determine whether there are any measures that might be available to it and  then  it would be necessary  for  the EPA  to  carefully  review  any proposal,  to ensure  that  the offset measures proposed would provide a greater net benefit and could not have reasonably been required through existing licencing and management requirements. 

                                                            26 NSW EPA 2014. Correspondence to the PAC. Dated 10 October 2014 p 2. 27 PWCS/EMM. 2013. T4 Project, Response to Submissions and Preferred Project Report. September 2013. Volume 1 Page 318 

Page 51: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

42  

 The Commission heard  from  a number of  speakers  at  the public hearing who were  impacted by activities  at,  or  directly  associated with,  the  Carrington  Coal  Terminal,  particularly  in  relation  to noise,  but  also  dust.  The  activities  at  Carrington  are  not  relevant  to  this  assessment,  except  in relation to the cumulative  impacts. At present the Proponent’s modelling  indicates that cumulative impacts  will  generally  comply  with  the  existing  NSW  air  quality  criteria.  Nonetheless,  the Commission must still consider whether the Project incorporates best available technological control and best practice management of emissions. The fact that the Carrington coal terminal is owned and operated  by  the  Proponent  provides  a  wider  range  of  options  to  demonstrate  best  practice  in minimising cumulative air quality and noise impacts across its various facilities.  Some have called  for an estuary wide model  for managing  impacts  from  industrial activities  in the Port of Newcastle. This is consistent with the 2013 Draft Strategic Development Plan for the Port of Newcastle which  proposed  a whole  of  Port  approach  to managing  issues  such  as  air  quality  and noise28. As discussed  in the next section on noise, the Department has also commenced work on a port wide approach to managing noise. The Commission supports the Government’s consideration of  such  an  approach. A whole  of  Port management  approach  should  be  able  to  provide  a more effective  regulatory  system  with  improved  environmental  performance  outcomes  for  the community. Such a scheme would also provide a greater range of management options for Industry allowing it to identify and implement the most cost effective management and mitigation measures. This would ensure the most efficient management of impacts such as air emissions and noise while also optimising the development capacity of the Port.   As  the  owner  and  operator  of  two  of  the  port's  existing  coal  handling  facilities,  PWCS  (the Proponent) should be required to play a crucial role in devising and implementing such an air quality risk management strategy. By concentrating coal handling on Kooragang Island, at a greater distance from  residential areas  than other existing sources, T4 could provide greater  flexibility  in efforts  to improve air quality in residential areas over time. The Commission is satisfied that T4 could be part of the solution, rather than simply adding to the problem.  The Commission  considers  that with  the proactive  real  time management and options  to explore port wide  improvements  in  place,  it  should  be  possible  for  the  T4  terminal  to  operate without causing, significant additional exceedances of NSW’s Impact Assessment Criteria. Nonetheless, it will be  important  that  the arrangements  for pro‐active and reactive management are clarified prior  to the project being  referred  to  the decision maker  for determination as  the current deferral of  this issue to a future management plan, does not provide sufficient certainty as to how the impacts can be managed acceptably.  

4.3.2.2 UP AND DOWN STREAM IMPACTS 

The  Commission  heard  significant  concerns  from  the  community  about  the  upstream  impacts  of mining the coal, noting that in addition to all the existing mining, and the extensions or replacement mines for each of these as the mine exhausts  its resource, a number of  large new mines would be needed  to  supply  the  70 million  tonnes  of  coal  that  would  be  transferred  through  terminal  4 annually.   

                                                            28 Newcastle Port Corporation. 2013. Draft Strategic Development Plan for the Port of Newcastle P 42. http://pandora.nla.gov.au/pan/139583/20130403‐1108/newcastleportplan.com.au/document/show/9.pdf accessed 28 October 2014 

Page 52: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

43  

The Department has argued that the upstream and downstream  impacts are outside the control of the Proponent and “the assessment, management and regulation of these impacts are appropriately covered by other mechanisms”29.  

CumulativeimpactsofadditionalminingIn  relation  to  the  upstream  impacts  of  mining  the  coal,  the  Commission  agrees  with  the Department’s position and is satisfied that the impacts of each mine would need to be assessed on its merits prior to gaining any approval to extract coal. As the coal could be extracted using either underground or open cut methods and could be sourced  from a wide variety of possible  locations potentially as  far afield as the Warrumbungle LGA  the Commission  is not  in a position  to consider the  potential  cumulative  impacts  of  the  additional mining  operations  that may  be  developed  to supply this proposed coal terminal. As  is currently the case, each new coal mine would need to be assessed against the existing environment around the site and the cumulative impacts that might be produced by other activities in the area.  

ImpactsofcoalatthereceivingportanditsenduseLikewise  the downstream  impacts of  transporting  the coal  to, and using  the coal at,  the  receiving power station, steelworks or other use  is not able to be accurately considered by the Commission. This  is because, the coal could be sent to a wide range of possible  locations with varying emissions control  measures  and  infrastructure  in  place.  Ultimately  noise,  dust  and  other  local  emissions impacts produced from the use of the coal would need to be considered by the receiving port and user. Given the large variety of coal sources available to any individual end user, the Commission is satisfied that the impact at the receiving location cannot be attributed to this port, as the coal would likely be sourced from another port, if it was not available through the Port of Newcastle. 

GreenhouseGasEmissionsThe Commission heard considerable concern about the carbon dioxide (CO2) emissions and climate change impacts associated with the downstream use of the coal. The Commission acknowledges that it  is  reasonable  to expect  that  the  coal exported would be  consumed and would produce  carbon emissions with global climate change ramifications. The Commission has considered this issue of the downstream production of Greenhouse Gas emissions separately, in section 4.6.1. 

UpanddownstreamtransportofcoalThe Department has also argued  that  the  transport of coal  to and  from  the coal  terminal  site are 

upstream and downstream impacts which cannot be controlled by the Proponent. The Department 

notes that impacts from rail transport is the responsibility of the ARTC and the rail freight operators, 

regulated  by  an  Environmental  Protection  Licence  administered  by  the  Environment  Protection 

Authority  (EPA).  The  Department  also  suggests  that  the  Proponent  “does  not  have  control  or 

responsibility over the ships at port nor the combustion of the coal at its final destination”30.  

The Commission accepts that other mechanisms may be available to control the  impacts of use of the  rail  corridor;  however  it  is  clear  from  presentations  and  submissions  made,  and  from  the Commission’s  discussions  with  representatives  from  the  NSW  EPA  that  there  is  room  for improvement  in managing  air  quality  impacts  associated with  rail  transport  of  coal.  Likewise,  as discussed  above,  shipping  is  also  a major  source  of  pollution  and work  undertaken  for  the  EPA 

                                                            29 NSW Department of Planning and Environment. 2014. Secretary’s Preliminary Environmental Assessment Report. June 2014. p 21 30 NSW Department of Planning and Environment. 2014. Secretary’s Preliminary Environmental Assessment Report. June 2014. p 21 

Page 53: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

44  

suggests31  there  is  scope  for  reducing emissions  from  ships berthed at port and  travelling  to and from port.  AirEmissionsfromTrainsThe Commission heard significant concern about the air emission impacts associated with coal trains transporting coal from the mines to the port, including concerns about the cumulative impacts from the additional 70 million tonnes of coal that would be transported to terminal 4, on top of the coal already delivered to the existing coal terminals at the port. The community raised particular concern about  the  particulate  emissions  that may  be  produced  from  uncovered  coal  wagons  and  cited monitoring  data  that  has  shown  increased  particulate  levels  as  trains  pass.  The  Commission  has considered the air emissions from coal trains and discussed this with both the NSW EPA and NSW Health. NSW  Health  particularly  emphasised  that  the  health  effects  of  the  smaller  PM2.5  fraction  of  the particulates are  the most  clearly evident and of most  concern, because  the PM2.5  fraction  readily disperses, so impacts from these emissions would not just impact on those close to the rail corridor, but  also  the wider  region.  The  Commission  notes  that  given  the  ready  dispersion  of  PM2.5,  this impact would be included in the monitoring data from existing air quality monitors.   The best information available to the Commission at this time is that the most significant sources of particulate  emissions  from  coal  trains  are  from  the  diesel  locomotives  and  the  undercarriage  of recently unloaded wagons, rather than the uncovered tops of wagons. There is little or no evidence that uncovered wagons contribute significantly to particulate air quality  in the Newcastle area and there is no justification for recommending that wagons be covered. To the extent to which emissions from  loaded wagons are  identified as a problem, requirements  to profile  loads, maintain moisture levels  and/or  apply  veneers  to  suppress  dust  appear  to  represent  more  viable,  cost  effective alternative controls.  The Commission considers that coal should only be accepted at the project site where  it has been appropriately profiled within the wagon and where the coal at the top of the wagon (i.e. that which could be exposed to the wind) meets suitable moisture content levels, or has been treated with an effective chemical veneer  (the Commission understands  that a number of different products have been used).  

The EPA has proposed that any approval should include a condition: “The Proponent must design and construct the rail unloading facility to enable the installation and operation of equipment to remove  any  and  all  residual  coal  from  empty  wagons  prior  to  the  locomotives  leaving  the premises.”  The Commission agrees that cleaning of wagons after unloading, to ensure significant quantities of coal are not left on the wagons to become a further source of dust, is also important. In this regard the Commission understands a wagon surveillance and shaking device is installed at the Port Kembla Coal  Loader.  It will be up  to  the Proponent  to determine  the  type of  system  to be used, but  the Commission  recommends  that  the conditions  require wagons  to be empty, closed and sufficiently clean to ensure there  is no visible evidence of coal deposition on the ballast around the rail tracks from trains leaving the site.  

                                                            31 PAEHolmes. 2011. Potential Measures for Air Emissions from NSW Ports: Preliminary Study. Prepared for the NSW Office of Environment and Heritage, 23 June 2011. 

Page 54: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

45  

 These  recommendations  relating  to  conditions  for  the  receival  of  coal wagons  on  site  and  the cleaning of coal wagons prior to leaving the site should assist in reducing particulate emissions and deposition associated with the coal wagons on the wider rail network.   The  Commission  notes  the  EPA’s  advice  that  the  current  system  for  regulating  rail  operators  is limited and  impacts  from associated  locomotives, which produce particulate emissions associated with the combustion of diesel, are significant. The EPA Position Paper states: “the current approach to  licencing  does  not  make  rolling  stock  operators  directly  responsible  for  the  environmental performance of rolling stock. This fact has  inhibited the EPA from adequately addressing noise and air emissions in the NSW operational rail sector.  This regulatory challenge needs to be addressed as a matter of priority.32 The paper goes on to note that “as part of  its Non‐road Diesel Strategy, the EPA  is  currently  investigating  imposing diesel  emission  standards on new and  existing  locomotive operating  in NSW.”33 The presentations  the Commission heard at  the Public Hearing attest  to  the need for this  issue to be addressed. Ultimately this is not a matter for the Commission as it cannot be  reasonably  controlled  in  this  application, however  the Commission notes  that  concerns  about regulation  of  impacts  in  rail  corridors  were  raised  at  the  public  hearing  and  it  supports  the Government’s efforts to introduce regulation of locomotives and rolling stock operators.  

4.3.3 CONCLUSION AND RECOMMENDATIONS  

 Given that there are already occasional exceedances of air quality standards in the Newcastle area, it could be argued that any potential additional emission, no matter how small, should be disallowed. This  approach would  however  go  against  a  common  sense  approach  of  targeting  the most  cost effective means of achieving net air quality improvements.   The  Commission  is  satisfied  that  even  allowing  for  some  uncertainties  around  modelling assumptions,  the  net  contribution  to  particulate  emissions  in  the  Newcastle  area  from  a  fully operational T4 would be modest. EPA efforts to  improve particulate air quality  in residential areas such as inner Newcastle are focussed on reducing emissions from diesel locomotives and ships in the port. It is clear to the Commission that an integrated 'whole of port' approach needs to be taken to provide  the  framework  for  implementation  of  adaptive  operational  strategies  across  all  emission sources when adverse weather conditions  indicate an elevated risk of a deterioration  in air quality. As  the owner  and operator of  two of  the port's  existing  coal handling  facilities, PWCS  should be required  to play a  crucial  role  in devising and  implementing  such an air quality  risk management strategy.   By  concentrating  coal  handling  on  Kooragang  Island,  at  a  greater  distance  from  residential  areas than other existing  sources, T4 could provide greater  flexibility  in efforts  to  improve air quality  in residential areas over time. The Commission is satisfied that T4 could be part of the solution, rather than simply adding to the problem.  Pro‐activeandReactiveManagementThe  Commission  supports  the  Department’s  proposed  requirements  for  pro‐active  and  reactive management  of  air  quality  and  recommends  that  consideration  be  given  to  strengthening  the Department’s conditions requiring pro‐active and reactive mitigation and management. In particular 

                                                            32 NSW EPA. 2014. Review of regulation of railway systems activities under the ‘Protection of the Environment Operations Act 1997, Position paper. August 2014 Executive Summary (unnumbered page)  33 NSW EPA. 2014. Review of regulation of railway systems activities under the ‘Protection of the Environment Operations Act 1997, Position paper. August 2014 p 14. 

Page 55: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

46  

it would be necessary  to  confirm what mitigation measures would be  applied, which operational components  could  be modified  or  scaled  down  and  provide  clear  justification  for  any  continued emissions  during  adverse  conditions.  This  would  also  need  to  extend  to  the  management  of emissions from ships and locomotives that are associated with the project to the extent to which it is within the control of the Proponent.  ShorePowerThe Commission  recommends  that  the Proponent be  required  to make spatial provision  for shore power  for vessels,  so  that  it  could be  installed on  the  site  in  future,  in  the event  this becomes a viable option.  MinimisingemissionsfromcoalwagonsThe Commission recommends any approval should  include conditions that ensure coal should only be accepted at the project site where it has been appropriately profiled within the wagon and where the coal at the top of the wagon (i.e. that exposed to the wind) meets appropriate moisture content levels, or has been treated with an effective chemical veneer. CleaningofcoalwagonsThe Commission  recommends any approval should  include conditions  that  require wagons  leaving the site to be completely empty, with dump doors fully closed and sufficiently clean to ensure there is no visible evidence of coal deposition on the ballast around the rail tracks from trains leaving the site.  

4.4 NOISE The Commission’s terms of reference for this Review require it to assess and pay particular attention to the potential noise impacts of the project.  The proposed T4 coal terminal will produce noise from a  range of  sources across  the  site, however  the  closest  residential  receivers are over a  kilometre away and other industrial land or premises sit between residential areas and most parts of the site. Nonetheless  the  Proponent’s  assessment  considers  receptor  locations  at  Fern  Bay,  Stockton, Carrington,  Mayfield,  Warabrook  and  Sandgate.  Because  the  site  is  relatively  distant  to  these residential  areas  the  noise  contribution  from  the  project  is  predicted  to  be  relatively  small  and largely imperceptible during most conditions. The exceptions are Warabrook, Mayfield and Mayfield West where noise levels from the T4 project are expected to reach 36, 39 and 40 dBA respectively. These predicted levels are still likely to often be imperceptible against background noise levels from the general Kooragang Island industrial area. The Commission notes that the Proponent’s monitoring reports suggest that road and rail traffic noise generally characterise the existing background noise levels  in these, but that there are sometimes very quiet periods at night34, with background  levels recorded below 32 dBA LAeq  (15 minute) during one period of attended monitoring  in Mayfield West  in 201335. Consequently noise from T4 would be noticeable at certain times.  Noise  is commonly assessed against the existing background noise  levels, and  impacts that are  less than  5  decibels  above  the  background  levels  are  considered  acceptable.  This  situation  becomes more complicated when there are multiple sites and operations contributing noise, which combine to produce a cumulative noise impact. In cases where there are a number of sources contributing to noise, amenity criteria are also applied to protect the overall amenity of the location and noise from all sources should remain below the amenity criteria for a location.   

                                                            34 PWCS/EMM. 2012 T4 Project, Environmental Assessment. February 2012. Appendix L 35 PWCS. 2014. KCT Annual Noise Investigation Report (2014).  

Page 56: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

47  

There are already two coal terminals on Kooragang  Island  (as well as other  industrial sources) and the residential areas that could be impacted by the T4 project are likely already receiving some noise from these other industrial sources. This makes it particularly difficult to establish appropriate noise criteria and, as acknowledged in the Department’s preliminary assessment, it also makes monitoring of compliance against those criteria highly challenging, if not impossible.  This is because it would be very difficult to identify, distinguish and separate the noise coming from the T4 terminal operations, from other noise coming from industry on Kooragang Island.  The Proponent also operates the Kooragang Coal Terminal, and because of this, it has assessed the combined  impact  of  operations  from  both  the  existing  KCT  and  proposed  T4  terminals.  This assessment found the two operations would be able to meet the existing criteria that apply to the Kooragang Coal Terminal (see Table 12)– that  is, no  increase  in noise would need to be allowed. In fact,  the predicted noise  levels  from  the  two operations  (see Table 13) would be slightly  less  than the maximum allowable noise contribution  limit  that applies  to  the Kooragang Coal Terminal. The exception  is  the Warabrook  and  Sandgate  area, which  is  not  currently  listed  as  a  noise  affected location  in  the  KCT  and NCIG  Terminal  approvals. Warabrook  and  Sandgate might  receive  some small, but perceptible, noise impact as a result of the combined operations.   Table 12 ‐ Maximum allowable noise contribution (dBA) under the planning approval for the Kooragang Coal Terminal 36 

Location  Day, Evening, NightAt all times 

Night10:00pm to 7:00am Monday to Sunday 10:00pm to 8:00 am Sundays and Public Holidays 

LAeq(15 minutes)  LAeq(night) LA1(1 minute) 

Fern Bay North  46  43 55 

Fern Bay West  50  47 55 

Fern Bay East  49  46 55 

Stockton West  50  47 57 

Stockton East  49  46 56 

Mayfield West  41  37 56 

Mayfield  44  38 58 

Carrington  42  38 52 

 Table 13 – Proponent’s predictions (dBA) of the combined intrusive impact from T4 and the existing Kooragang Coal Terminal37 

Receiver Area 

Day time   Evening Night

LAeq(15 minute) LAeq(15 minute) LAeq(15 minute) LA1(1 minute) 

Predicted  Criteria  Predicted Criteria Predicted Criteria  Predicted  Criteria

Fern Bay North 

36  45  40 45 46 45 52  55

Fern Bay West 

40  45  46 45 49 45 55  55

Fern Bay East 

39  45  45 45 49 45 55  56

Stockton West 

38  45  49 45 49 45 55  57

Stockton  38  45  48 45 49 45 55  57

                                                            36NSW Department of Planning and Infrastructure. 2012. Project Approval, Kooragang Coal Terminal Mod 3. https://majorprojects.affinitylive.com/public/d5ca8de27579d43ce753fabb7f9bd2d3/Consolidated%20Approval%20(MODS%201,%202%20&%203)_Nov%202012.pdf  37 PWCS/EMM. 2013. T4 Project, Response to Submissions and Preferred Project Report. September 2013., App N app F1 and F2  

Page 57: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

48  

Receiver Area 

Day time   Evening Night

LAeq(15 minute) LAeq(15 minute) LAeq(15 minute) LA1(1 minute) 

Predicted  Criteria  Predicted Criteria Predicted Criteria  Predicted  Criteria

East 

Mayfield West 

34  50  43 50 41 46 47  56

Mayfield  34  51  43 51 41 48 48  58

Carrington  31  47  41 46 39 42 45  52

Maryville  32  53  27 52 37 50 43  60

Warabrook  29  50  37 48 35 44 41  54

Sandgate  29  53  37 50 36 45 42  55

 The Department has recommended that noise levels consistent with those that apply to the Kooragang Coal Terminal should be included in conditions for the T4 project, but with the added requirement that the noise generated by T4, in concert with noise generated by the KCT do not exceed the criteria listed (see Table 14). The Commission has carefully considered this approach, including the following questions: 

1. Do the locations listed in the KCT approval cover all the locations potentially impacted by the 

T4 project? 

2. Are the levels appropriate? 

3. Is the condition valid and enforceable? 

4. Are the conditions suitable and is there a better alternative? 

Table 14 Department's recommended Maximum allowable noise contribution (dB(A)) from the combined operations of T4 and the Kooragang Coal Terminal 

Location  At all times Night Only 

LAeq(15 minute) LA1(1 minute)

Fern Bay  50  55

Stockton  50  57

Mayfield  44  58

 As noted above, the KCT and NCIG Terminal approvals do not include noise criteria for Warabrook and Sandgate. This is understandable as Warabrook is approximately 3 km from the existing terminal sites and residential areas in Mayfield West sit between the terminals and Warabrook (Sandgate is even further away). The T4 proposal would be built west of the existing terminals however, closer to Warabrook and Sandgate. The Proponent has assessed the noise impact in these suburbs and predicts a relatively small noise contribution, but one that may nonetheless be perceptible at certain times. The EPA’s recommended noise criteria (Table 15) include a noise limit for both suburbs and the Commission considers a noise limit for Warabrook and Sandgate should be included in any conditions of approval.  Table 15 ‐ EPA Recommended Noise Limits (dBA) and Localities38  

Locality  Day  Evening Night

LAeq(15 minute)  LAeq(15 minute) LAeq(15 minute) LAeq(9 hours) LA1(1 minute)

Fern Bay and Stockton 

49  49  49 46 55 

Mayfield West  43  43  41 38 47 

Mayfield and Mayfield East 

43  43  42 38 48 

Carrington  41  41  39 35 45 

                                                            38 NSW EPA. 2014. Letter to PAC dated 25 August 2014 

Page 58: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

49  

Locality  Day  Evening Night

LAeq(15 minute)  LAeq(15 minute) LAeq(15 minute) LAeq(9 hours) LA1(1 minute)

Sandgate  37  37  36 35 45 

Warabrook  37  37  35 35 45 

 With  regard  to  the  noise  limit  levels  adopted,  the  Commission  notes  that  the  Department’s recommended  condition  adopts  the  same  noise  levels  that  are  included  in  the  Kooragang  Coal Terminal approval condition 2.8. However it is apparent that these are not the preferred noise levels as  the  approval  for  the  Kooragang  Coal  Terminal,  also  includes  a  condition  (2.10)  requiring  the Proponent to  investigate and,  if reasonable and feasible, reduce noise  impacts from the project to achieve noise contributions of no greater than 43 dB(A) LAeq(night) and 45 dB(A) LAeq(15 minute) at Fern Bay and Stockton. The draft conditions  for T4 do not  include  this  requirement  to  try and achieve  this tighter limit, but do include a more general requirement to minimise noise emissions from plant and equipment operated on the site.  The  EPA  has  recommended  tighter  noise  limits,  consistent with  the  Proponent’s  predicted  noise impacts  from  the  combined operations of  the Kooragang Coal Terminal and  the T4 Terminal. The PEAR has not provided justification for proposing more relaxed noise limits.  The Commission agrees that  the  tighter,  predicted  noise  levels would  be  a more  appropriate  noise  limit,  than  the  ones currently  included  in the draft conditions. However, the Commission notes that  if the  limits are to apply  to  the  combined operations of  the  two  terminals  it would not be possible  for  limits  in  this approval to be tighter than the ones in the existing Kooragang Coal Terminal Approval.  While the Commission agrees with the principle of adopting noise criteria that would apply to the combined operations, the Commission has a number of reservations about how this could be applied in  practice.  Firstly,  the  Commission  notes  that  in  2013  the  Land  and  Environment  Court  raised concerns about the validity of conditions that apply to two planning approvals stating: 

371 The difficulty with accepting the combined criteria is that compliance with two different consents for two different mines  is assumed; and while  it may be accepted that  in practice the two mines are operated as a single entity, the legal separation remains. There is no evidence before the Court as to any contractual or other arrangements between  the  two mines. No condition has been put  forward that would specify what is the noise limit for the Warkworth mine operations alone. 

…  If noise  is emitted from Warkworth transferring overburden onto Mount Thorley  land which takes up most  of  the  42  dB(A)  allowed  for  the  combined  operation,  then  that would  impact  on Mount Thorley's ability to continue operations. That would be beyond the reach of any approval granted to Warkworth for its operations. 

373  … any conditions  imposed on a project approval must  relate  to  that project, and be capable of implementation  by whomever  is  carrying out  the activities  authorised  by  the approval: Hub Action Group Inc v Minister for Planning & Orange City Council [2008] NSWLEC 116; (2008) 161 LGERA 136 at [118]. A condition imposed on an approval granted in these proceedings could not purport to impose obligations on the operator of a separate mine that is subject to its own consent.39 

 The Commission  acknowledges  that  the  specifics of  that  case  are  very different  to  this proposal. Nonetheless,  the  condition would  effectively  require  the  operations  at  T4  to  be  scaled  back  to reduce noise, in the event that the KCT operations were contributing noise up to the allowable limit, the Commission has  some  concerns  this may not provide  the Proponent with  sufficient  certainty regarding its ability to operate. While this is unlikely to be a problem while the Proponent continues 

                                                            39 Bulga Milbrodale Progress Association Inc v Minister for Planning and Infrastructure and Warkworth Mining Limited [2013] NSWLEC 48.  

Page 59: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

50  

to operate both sites, the conditions do not provide for any contingency – for example, in the event that one of the operations came under different management control.   The Commission  considers  that  some  further explanation of  this proposed  condition  (B13) would need to be provided to the decision maker before such a condition could be  imposed.  Ideally, the noise levels should also be reduced, to those that are predicted to be achieved (as recommended by the EPA).There  is also merit  in considering  inclusion of an additional set of noise  limits that would apply to T4  in the event that the two operations were managed separately, or the KCT facility was closed at any time in the future.  Ultimately the Commission is satisfied the proposal is relatively distant from sensitive noise receivers and  that  the  noise  emissions  from  the  project would  be  acceptable.  Nonetheless,  some  further consideration or clarification on the wording of conditions to  limit noise from the site  is needed to ensure noise can be adequately regulated.  The Commission recommends: 

1. that  noise  limits  should  be  included  for  locations  at  Warabrook  and  Sandgate  (as 

recommended by the EPA); 

2. that options to tighten the noise limits that would apply to T4 in concert with the Kooragang 

Coal Terminal should be further explored; and 

3. that additional noise limits specific to the T4 operations should be considered. 

The  Commission  notes  that  the  Department’s  preliminary  assessment  also  considers  the construction noise, rail noise and broader cumulative port noise  issues.  In relation to construction, the  Commission  is  satisfied  the  draft  conditions  require  construction  noise  to  be  managed  in accordance with the Interim Construction Noise Guideline, but recommends: 

4. that where  the  conditions  specify  that  issues  shall  be managed  in  accordance with  the 

relevant guidelines, the condition specifies that the latest version of the policy or guideline 

would apply.   

With regard to rail noise, the Commission agrees with the Department’s position, that “it would be unreasonable  to hold  the project  responsible  for all  rail noise  impacts on  the  rail network”40. The Commission also notes that the concerns about rail noise raised at the public hearing largely related to activities at or associated with the Carrington Coal Terminal, which are outside the scope of this review. Nonetheless the development of the T4 proposal may provide some scope for the Proponent to  rationalise operations  in  the  future  across  its  three  sites, which  could potentially  improve  the situation at Carrington. The EPA’s  recent Review of  regulation of  ‘railway systems activities’ under the Protection of the Environment Operations Act 1997 proposes a number of improvements to the regulation of impacts in rail corridors. The concerns raised at the public hearing and in submissions, and the Commission’s own consideration of this application all corroborate the need for  improved regulation of activities in the rail corridor and the Commission supports the EPA’s work on this issue.  In relation to cumulative impacts, the Department notes the difficulties in regulating noise under the current system of case by case assessments. The Department’s assessment considers the possibility of  adopting  a whole of port  approach  to managing noise  across  the  greater Newcastle Port. The Commission agrees that regulation under the current system is difficult; this was also highlighted by a number of speakers at the public hearing. The Commission considers the proposed “whole of port” 

                                                            40 NSW Department of Planning and Environment. 2014. Secretary’s Preliminary Environmental Assessment Report, June 2014. P 22 

Page 60: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

51  

approach  suggested  by  the  Department  has  considerable merit  and  supports  the  Department’s efforts to progress this option.  

4.5 TRAFFIC  

The Terms of Reference  specifically  require  the Commission  to consider  the  traffic  impacts of  the proposed development. While this was not one of the key concerns raised at the Public Hearing and in the submissions, traffic congestion around Kooragang Island was mentioned several times.  A  traffic assessment was prepared by EMM as part of  the EA and was updated  for  the PPR.  It  is noted that the intersections assessed as part of the PPR are generally the same for those assessed as part of the EA, however the Industrial Drive / Woodstock Street intersection and the Tourle Street / OneSteel access  intersection are not  required  for  the  revised project access. Therefore,  they have not been considered in the revised traffic assessment.  The Secretary’s PEAR recognises that traffic congestion currently occurs in the vicinity of the site in the morning and afternoon peak hour periods.  It  is expected  that  the proposal would have  some impact on traffic  in the vicinity of the site during construction and operation of the proposed coal terminal, but that these impacts will be reasonable. This is discussed below:   4.5.1  Construction traffic Daily and peak‐hourly traffic generation predictions were calculated and assessed by EMM  for the predicted peak of construction. It is predicted that the maximum number of construction workforce travelling  by  car  to  and  from  construction worksites  on  Kooragang  Island  each weekday will  not exceed 1,200 people. The rationale for this is that at the time of the traffic counts (2011) there was a combined  construction  workforce  of  1,200  for  KCT  and  NCIG.  While  natural  traffic  growth  is expected over time (whether or not the proposal proceeds), construction at KCT and NCIG is likely to be  complete  before  peak  construction  of  the  fourth  coal  terminal  is  reached.  The  Commission therefore accepts that this maximum figure is reasonable.  The proposed construction workforce car parking areas will provide approximately 980 car parking spaces41, which  EMM  considers  adequate  for  the  proposed  peak  project  construction workforce. This  assumes  a  reasonable  level of  car  sharing  (an  average  vehicle occupancy of 1.2 persons per vehicle) for workers travelling to and from the site by car or other private vehicles.   

4.5.2  Operational traffic Once construction is complete, 80 additional PWCS employees are proposed to operate the project (however PWCS has advised that  if the  latest automation technology  is  implemented, there will be no additional operational positions created  for  the new coal  terminal). The Department considers that the additional traffic associated with 80 operation employees  is not significant, as they would generally work 12 hour shifts with approximately 20 people per shift. The Commission accepts that this is within the capacity of the road network, subject to the mitigation measures outlined below.  

4.5.3  Mitigation measures To limit the traffic impacts of the proposal, PWCS has committed to the following: 

Upgrade of the existing Cormorant Road and Pacific National Road T‐intersection; 

                                                            41 PWCS/EMM. 2013. T4 Project, Response to Submissions and Preferred Project Report. September 2013. p.212 

Page 61: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

52  

Upgrade of the Cormorant Road and NCIG Wharf Access Road T‐intersection; 

Accessing the site via a left turn into the Delta EMO Access Road from the Tourle Street bridge direction, but generally exit the work site via the new traffic signals at the Pacific National Access Road. Where possible, this access will be limited to light vehicles only. 

Provide a shuttle bus when the construction workforce exceeds 1,200 persons, to transport the additional employees between the project site and off‐site parking location(s)/pick up point(s) away from Kooragang Island. 

Stagger traffic departures during the peak period of 4pm to 5pm. 

Adopting construction practices which minimise truck movements, such as the transport of dredged material onto the site via pipes. 

The commitments outlined above are supported by the Commission and should assist  in mitigating traffic  congestion  in  the  vicinity of  the  site.    The  Commission  also  agrees with  the Department’s recommendation  that  a  condition be  applied  to  any  future  approval,  requiring development of  a shuttle bus route as part of the Construction Traffic Management Sub Plan in consultation with RMS and  Council.  The  Construction  Traffic  Management  Plan  should  also  detail  the  proposed management of vehicles leaving the site.  The Commission  agrees with  the Department  that  signalising  the Cormorant  and Pacific National Access  Road  and  the NCIG Wharf Access  Road  intersections would  improve  their  operation,  and should  be  functioning  prior  to  the  time when  the  peak  construction workforce  is  required.  The Secretary’s  PEAR  notes  the  RMS’s  plan  for  the  upgrade  of  Tourle  Street  and  duplication  of Cormorant  Road.  On  10  October  2014  the  NSW  Minister  for  Roads  and  Freight,  Duncan  Gay, announced that the detailed design of the upgrade was expected to be complete by mid‐2015. If the proposal  is approved,  the Commission encourages PWCS  to consult with RMS  in order  to manage cumulative construction impacts.  

4.5.4  Conclusion The Commission  agrees with  the Department  that while  construction  traffic may  add  to baseline traffic congestion in the vicinity of the project site, short‐term impacts similar to those experienced during the expansion of the KCT and NCIG projects should be expected and are reasonable. These impacts  need  to  be  appropriately managed  by  the  implementation  of  the  proposed mitigation measures and statements of commitment, in consultation with RMS and Newcastle City Council.  

4.6 OTHER CONSIDERATIONS  

4.6.1 GREENHOUSE GAS EMISSIONS 

Although only briefly mentioned  in the Assessment Report and not specifically  listed as an  issue  in the Terms of Reference  for  the Review,  the Commission heard numerous speakers and received a number of submissions raising concerns about the Greenhouse Gas Emissions particularly from the downstream use of the coal to be exported from the project site. Submissions cited a range of local and  international sources highlighting the need to reduce greenhouse gas emissions and  indicating “The World Bank, the OECD and the International Monetary Fund advise that coal must be left in the ground”42. Some speakers cited predictions that coal demand had already peaked; others suggested there would be strong growth noting “The Australian Government Bureau of Resources and Energy Economics notes  that  Japan has  reaffirmed coal as a source of energy, and are building new, high 

                                                            42 Rose, J. 2014. Submission to PAC. P2 

Page 62: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

53  

efficiency, generators. The Bureau also notes continued demand  from China who  is simultaneously increasing the use of renewable energy and building new coal generators.”43   Both  the  Proponent  and  the Department  have  considered  the  Scope  1,  2  and  3  greenhouse  gas emissions associated with the project.  In relation to the Scope 1 and 2 emissions from the site the Department notes that: 

“Annual  Scope  1  and  2  emissions would  contribute  approximately  0.0002  per  cent  to  current global, 0.01 per cent  to national and 0.05 per cent  to NSW C02‐e emissions or 0.0001 per cent, 0.01 per cent or 0.04 per cent respectively to 2030 mid‐range projected emissions. The Proponent has committed  to a  range of strategies  to minimise or optimise energy use during construction and operation such as selecting energy efficient equipment and lighting and optimising feed rates, investigating low GHG emission fuel for the project's fleet and establishing a reduction target and monitoring plan.  

To  strengthen  this  commitment, a  condition  is  recommended which  requires preparation of an Energy Efficiency Plan  confirming  the measures  to be  implemented  to minimise  the energy use and  greenhouse  emissions  attributable  to  the  project  and  to  explore  the  opportunities  to  use renewable energy sources.”44 

 The Commission notes that the current policy on Greenhouse Gas Emissions  in Australia  is a Direct Action  Plan  and  an  Emissions  Reductions  Fund  to  “provide  incentives  for  emissions  reductions activities across the Australian economy”45. The Commission is satisfied the Department’s proposed requirement  for  an  Energy  Efficiency  Plan  accords with  this  policy, which  ultimately  sets  out  “to reduce Australia’s greenhouse gas emissions and deliver improvements to our environment”46.  In  relation  to  the Scope 3 emissions  from  the project  (from  the downstream use of  the  coal)  the Department’s PEAR states: 

“The  Department  acknowledges  and  does  not  question  the  potential  greenhouse  gas  impacts caused by the burning of coal. Notwithstanding, it must also be acknowledged that the project in itself does not drive demand for the mining or burning of coal. Instead, the Proposal facilitates the link between  the producer  (the mine) and  the consumer. Not proceeding with  the development would not result in a decrease in demand for coal products (or C02 emissions), which is driven by current and projected future global demand for energy. 

The Proponent argues that Scope 3 emissions have been provided for completeness, however as it cannot control these emissions, these should not be counted towards the impacts of the project. The Department accepts that Scope 3 emissions are beyond the control of the Proponent and are accounted  for  by  others/other  developments  (as  either  Scope  1  or  2  emissions).  Further,  the worldwide demand for coal, whilst subdued in recent years, is not likely to diminish to any great extent  in  the near  future. Therefore,  the Scope 3 emissions  from  the export of 70 Mtpa of coal would  still  be  realised  even  if  the  proposal  did  not  proceed  as  coal  to  satisfy  global  energy demand would be sought from alternative sources and consumed.”47 

 

                                                            43 Port of Newcastle. 2014. Submission to PAC, part 2. p2 44 NSW Department of Planning and Environment. 2014. Secretary’s Preliminary Environmental Assessment Report. June 2014. P 69 45 Department of Environment Website. 2014. http://www.environment.gov.au/climate‐change/emissions‐reduction‐fund accessed 6 November 2014 46 Department of Environment. 2014 http://www.climatechange.gov.au/reducing‐carbon/reducing‐australias‐emissions accessed 6 November 2014. 47 NSW Department of Planning and Environment. 2014. Secretary’s Preliminary Environmental Assessment Report. June 2014. P 23 

Page 63: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

54  

Many  submissions and  speakers at  the public hearing disagreed with  the position adopted by  the Department,  indicating  the  project  should  be  refused  due  to  concerns  about  the  downstream burning  of  the  coal  proposed  to  be  exported  through  this  proposed  T4  Coal  Terminal  and  the resulting contribution to climate change.   The Commission has considered the Proponent’s assessment of the Greenhouse Gas Emissions that would be produced, along with  the Department’s position  that  the Scope 3 emissions are beyond the control of the Proponent. The Proponent estimates that Scope 3 emissions would be equivalent to 174,210,870 tonnes of CO2 a year, comprising 275,870 tonnes of CO2‐e for transport of the coal to the port; 1, 911,000 for shipment of the coal from the port to the end user; 130,527,000 tonnes for the  end  user  combustion  of  thermal/steaming  coal;  and  41,497,000  tonnes  for  the  end  user combustion of coking coal. The Proponent estimates this would represent 0.36% of current annual global  emissions48.  The  Commission  acknowledges  the  significant  contribution  this  represents, noting that it is greater than that currently produced by NSW (which is believed to be approximately 154.7 million tonnes CO2‐e a year

49).  The Commission heard a number of strong and compelling arguments for reducing greenhouse gas emissions and  these arguments were  then extended  to  suggest  that  they  constituted grounds  for 

this project to be refused. During the public hearing the Commission was advised that “In February this year US Secretary of State John Kerry called climate change "the world's most fearsome weapon of mass destruction"50. Since  then,  at  the United Nations’  recent  2014 Climate  Summit  Secretary General Ban Ki‐moon declared climate change the “defining issue of our time”51. The need to reduce global greenhouse gas emissions is acknowledged by the Commission.  Presentations pointed out that “at the  international climate change negotiations  in 2009, countries party to the UNFCCC (including Australia) affirmed that holding any temperature increases to below 2  degrees Celsius  above  preindustrial  levels  is  needed  to  prevent  dangerous  climate  change”  and suggested  that  “if  the world were  to meet  a  2  degree  target‐  T4 would  contribute  17.4%  of  the 

allowable  increase  in  emissions”52.  The  Commission  notes  that  a  range  of  different  emissions 

reductions scenarios have been modelled,  including some that allow  for  increases  in emissions  for the short term. Nonetheless, the United Nations states that “Scenarios show that in order to have a likely  chance  of  limiting  the  increase  in  global mean  temperature  to  two  degrees  Celsius,  global greenhouse gas emissions would have  to be  lowered by 40  to 70 per cent compared with 2010 by mid‐century, and  to near  ‐zero by  the end of  this  century. Ambitious mitigation may even  require removing carbon dioxide from the atmosphere.” 53   Policy on achieving the necessary reductions in greenhouse gas emissions continues to evolve both locally and  internationally. In the time since this project was originally proposed many factors have changed,  and  are  likely  to  change  again  before  any  coal  could  be  exported  from  the  site.  The application process for this project commenced at the height of the coal mining boom and at a time 

                                                            48 PWCS/EMM. 2013. T4 Project, Response to Submissions and Preferred Project Report. September 2013.Appendix P p 9 49 NSW Office of Environment and Heritage. 2014. Emissions Overview 2011/12. http://www.environment.nsw.gov.au/climatechange/emissionsoverview.htm accessed 21 October 2014 50 Rose, J. 2014. Submission to PAC. P2 51 United Nations Website http://www.un.org/climatechange/summit/2014/09/ban‐seeks‐vision‐concrete‐action‐world‐leaders‐un‐climate‐summit/ accessed 20 October 2014 52 Dean, A. 2014. Submission to PAC. p3.  53 United Nations Website http://www.un.org/climatechange/science-and-solutions/ accessed 20 October 2014 

Page 64: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

55  

when  the  coal price had  reached unprecedented highs.  In  the  intervening period  climate  change policy  has  varied  widely.  In  Australia  an  Emissions  Trading  Scheme  was  proposed  and  then subsequently  shelved;  and  a Carbon Tax was  introduced  and  subsequently  repealed.   Meanwhile internationally policies on climate change have also gradually been evolving. During the recent 2014 United Nations Climate Summit “Seventy‐three national Governments, 11 regional governments and more than 1,000 businesses and investors signalled their support for pricing carbon.  Together these leaders  represent 52 per  cent of global GDP, 54 per  cent of global greenhouse gas emissions and almost  half  of  the  world’s  population”54.  Notably,  China  has  recently  made  a  number  of announcements  about  its  intentions  to  limit  coal  consumption  and  imports  at  a  regional  and national  level  respectively. One  submission  reported  that  Professor Ross Garnaut  indicated  “that projected Chinese use of  coal  for power production would  fall  on average by 0.1 per  cent a  year between 2014 and 2020. ‘After the growth of 11 per cent per annum in coal use in power generation in the first 11 years of the century, this is a turnaround of historic dimension and global importance,’ he said.”55 The Commission acknowledges that in a joint statement with the United States, China has now announced “targets to peak CO2 emissions around 2030, with the intention to try to peak early, and to increase the non‐fossil fuel share of all energy to around 20 percent by 2030”56.  Nonetheless, other  submissions  indicated  “Thermal  coal  exported  through Newcastle  is  of  a  high quality,  and  continues  to  be  the  preference  for  the  premium  power  generation  markets  where importance is placed on quality, efficiency and reduced emissions”57. Further, alternatives to coal are not necessarily  readily  available,  economical or  accepted.  For  example  it has been  reported  that Germany  has  increased  its  consumption  of  coal  in  recent  years,  and  this  has  variously  been attributed to  its phasing out of nuclear power generators  (after the Fukushima reactor accident  in 2011)58  or  to  the  reduction  in  electricity  production  from  gas  burning,  along  with  increased electricity exports 59. Also, at a  local  level, strategic planning for the region supports the growth of the coal mining and export sector for NSW and the Port of Newcastle (see the next section 4.6.2).   While there has been a recent downturn in coal prices and associated scaling back of production at many mines in NSW, a number of submissions cited various reports from the International Energy Agency. It’s World Energy Outlook for 2013 suggests that: 

“Coal  remains a cheaper option  than gas  for generating electricity  in many  regions, but policy interventions to improve efficiency, curtail local air pollution and mitigate climate change will be critical in determining its longer‐term prospects. Policy choices in China, which has outlined plans to cap the share of coal in total energy use, will be particularly important as China now uses as much  coal  as  the  rest  of  the  world  combined.  In  our  central  scenario,  global  coal  demand increases by 17% to 2035, with two‐thirds of the increase occurring by 2020. Coal use declines in OECD  countries.  By  contrast,  coal  demand  expands  by  one‐third  in  non‐OECD  countries  – predominantly  in  India,  China  and  Southeast Asia  –  despite  China  reaching  a  plateau  around 

                                                            54 United Nations Website http://www.un.org/climatechange/summit/2014/09/2014‐climate‐change‐summary‐chairs‐summary/ accessed 20 October 2014 55 Doyle, T. 2014. Submission to PAC. p1 56 The White House. 2014. FACT SHEET: U.S.‐China Joint Announcement on Climate Change and Clean Energy Cooperation. http://www.whitehouse.gov/the‐press‐office/2014/11/11/fact‐sheet‐us‐china‐joint‐announcement‐climate‐change‐and‐clean‐energy‐c accessed 13 November 2014 57 Port of Newcastle. 2014. Submission to PAC, part 2. P2. 58 U.S. Energy Information Administration website http://www.eia.gov/countries/country‐data.cfm?fips=gm accessed 20 October 2014 59 The Guardian, 22 July 2014, Germany, UK and Poland top ‘dirty 30’ list of EU coal‐fired power stations, http://www.theguardian.com/environment/2014/jul/22/germany‐uk‐poland‐top‐dirty‐30‐list‐eu‐coal‐fired‐power‐stations accessed 20 October 2014  

Page 65: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

56  

2025.  India,  Indonesia  and  China  account  for  90%  of  the  growth  in  coal  production.  Export demand makes Australia the only OECD country to register substantial growth in output”60. 

The recently released World Energy Outlook 2014 updates these figures but still predicts growth  in demand, indicating:  

“While coal is abundant and its supply secure, its future use is constrained by measures to tackle pollution and reduce CO2 emissions. Global coal demand grows by 15% to 2040, but almost two‐thirds of the increase occurs over the next ten years… Current low coal prices have put pressure on producers worldwide to cut costs, but the shedding of high‐cost capacity and demand growth are expected to support an  increase  in price sufficient to attract new  investment. China,  India, Indonesia and Australia alone account for over 70% of global coal output by 2040.”61 

 The 2014 Outlook  continues  to  caution  that  this action will not be  sufficient, and  calls  for urgent action, indicating that: 

“[its central  scenario predictions put]  the world on a path  consistent with a  long‐term global average  temperature  increase  of  3.6  °C.  The  Intergovernmental  Panel  on  Climate  Change estimates  that  in order  to  limit  this  temperature  increase  to 2  °C –  the  internationally agreed goal to avert the most severe and widespread implications of climate change – the world cannot emit more than around 1 000 gigatonnes of CO2 from 2014 onwards. This entire budget will be used up by 2040 in our central scenario. Since emissions are not going to drop suddenly to zero once this point  is reached,  it  is clear that the 2 °C objective requires urgent action to steer the energy system on to a safer path.”62 

 While the 141 nations, signatory to the 2009 Copenhagen Accord agreed that emissions needed to be  reduced  so  that  global  temperature  increases  are  limited  to  below  2  degrees  Celsius,  some nations, particularly non‐OECD nations, may continue to increase imports of coal, from Australian or elsewhere. Particularly as policy and  regulations  to achieve  the emissions  reductions needed have yet  to be agreed and  implemented  in many nations,  including Australia.   This  is an evolving policy area.  In 2006, in considering whether Scope 3 greenhouse gas emissions (from the downstream use of the coal  to  be mined)  should  be  considered,  the  Land  and  Environment  Court  found  that  “It  is  not appropriate to limit the Scope of the environmental assessment on the basis that GHG emissions may or may not be subject to regulation in the future whether in NSW or overseas.”63. As noted earlier in this section, the Proponent has considered the greenhouse gas emissions of the project, but notes that  it cannot control  the end use of  the product. The Department’s assessment accepts  that  the emissions would be accounted  for by others and,  also  that;  if  the  coal  from  this project was not available,  alternative  sources  would  be  found.  The  Commission  accepts  that  planning  controls cannot be used to regulate Scope 3 emissions from the downstream use of the coal exported.  Notwithstanding  this,  the  Commission  notes  that  the  global  response  to  climate  change  and  the future coal demand and pricing is uncertain. In discussing the future of coal the International Energy 

                                                            60 International Energy Agency, 2013, World Energy Outlook 2013 p1, 2, 5 & 6 http://www.iea.org/publications/freepublications/publication/WEO2013_Executive_Summary_English.pdf accessed 21 October 2014 61 International Energy Agency, 2014, World Energy Outlook 2014 p3. http://www.iea.org/Textbase/npsum/WEO2014SUM.pdf accessed 13 November 2014. 62 International Energy Agency, 2014, World Energy Outlook 2014 p2.  63 Gray v The Minister for Planning and Ors [2006] NSWLEC 720 138, http://www.lawlink.nsw.gov.au/lecjudgments/2006nswlec.nsf/c45212a2bef99be4ca256736001f37bd/dc4df619de3b3f02ca257228001de798?OpenDocument accessed 28 October 2014 

Page 66: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

57  

Agency notes  the need  to  reduce  “the  risk  that  capacity  is  idled before  recovering  its  investment costs.”64  It will be important to ensure that the development and investment in this project does not become  the  justification or driver of coal production.  In  this  regard  the Commission considers  the project should be developed in stages, so that the facility’s coal handling capacity is no larger than is necessary. From a private investment perspective, staging the project also has merit to ensure that excess  capacity  and  over  investment  is  avoided.    In  addition,  a  five  year  rather  than  ten  year approval  timeframe would enable a reconsideration of  the project  in  light of evolving policies and legislation should commencement of construction of the coal loader be delayed beyond five years.   

4.6.2 STRATEGIC DIRECTION FOR THE PORT AND CITY OF NEWCASTLE AND WIDER HUNTER 

REGION 

An  issue directly  linked  to  the question of climate change and global demand  for coal,  is whether expansion of coal mining and coal exports  is consistent with  the strategic direction  for  the Hunter Region.  The  Port of Newcastle  is  currently  said  to be  the  largest  coal port  in  the world  and  this additional coal terminal would further expand the coal handling capacity of the port. In submissions and at  the Public Hearing,  the Commission heard a number of arguments against  intensifying  the region’s  coal  sector.    The  key  arguments  put  to  the  Commission  against  continued  growth  and intensification of the coal industry, were that: 

the additional coal mining operations needed to supply the increased throughput capacity at 

the port would have unacceptable impacts on the region;  

the cumulative  impacts of  transporting  the coal  to  the port and managing  the coal at  the 

port posed unacceptable health risks for the community, particularly from dust;  

there is a need for global reductions in consumption of fossil fuels such as coal and increased 

extraction and export of coal  is  inconsistent with  this need  to address climate change and 

would  be  better  focusing  on  investments  in  alternative  industries,  such  as  renewables, 

rather than continuing to rely on coal production; 

the  coal  industry does not have  a  sustainable  long  term  future  and Newcastle  should be 

diversifying its economy rather than intensifying its ties to the coal industry.   

The Commission has considered each of these points. In relation to the impacts of mining the coal, the  Commission  is  satisfied  that  the  extraction  of  coal  to  supply  the  port would  be  subject  to  a separate  assessment of  each  coal mine  application  and  is not  a matter  for  consideration on  this proposal.  The  cumulative  impacts  on  air  quality  around  the  port  and  along  the  train  lines  are considered in section 4.3.   As noted  in  the previous  section, despite  the need  to  reduce  carbon emissions  to  achieve  global climate change goals and meet the target of no more than 2°C of warming, global demand for coal is still predicted to increase in the coming decades. Whether these predictions prove correct will only be known in time. Nevertheless, many countries have invested heavily in coal‐fired power stations to produce  electricity.  So  long  as  electricity  can  continue  to  be  produced  economically  from  these plants, coal will continue to be in demand as a source of power.   Some  speakers  argued  for  the  development  of  a  renewable  energy manufacturing  sector  in  the region, rather than further coal mining. The Commission does not see any impediment to such a plan stemming directly from this proposal. The success of such a venture would be dependent on a range 

                                                            64 International Energy Agency, 2014, World Energy Outlook 2014 p3. http://www.iea.org/Textbase/npsum/WEO2014SUM.pdf accessed 13 November 2014 

Page 67: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

58  

of factors largely unrelated to this application, although the Commission does acknowledge that the recent high Australian dollar and competition for  labour have  impacted on other sectors,  including manufacturing in previous mining boom periods.  Coal  mining  and  its  associated  support  industries  represent  a  significant  Industry  sector  and employer in the Hunter, and the region may need to consider options to diversify its economy away from thermal coal mining at some point in the future. Whether it is sensible to continue to build this industry, potentially at the expense of alternative sectors is a matter that is beyond the scope of this review, but which is recommended for further government consideration and direction.  Setting aside the merits of the coal  industry, or even  its  long term future, there  is an argument for diversifying the region’s economy and associated port facilities rather than continuing to expand its coal handling capacity. The coal  industry has always been exposed  to global coal prices and, as  is evident at the moment, mining jobs are sensitive to this exposure.  The allocation of prime port side  land for a further coal terminal,  in what  is already said to be the biggest coal port in the world, is an important strategic consideration for the region.  The Proponent has argued  that  this proposal will not  impede other  industries65. The Commission accepts that at present the site is underutilised; requires remediation of contamination on the site; and  may  continue  in  its  undeveloped  state  for  some  years.  Further,  there  is  no  shortage  of alternative portside land available for development, as significant parts of the Mayfield Precinct are also  currently  vacant.  Nonetheless,  over  the  life  of  the  project  this  situation  may  change  as Newcastle  and NSW  continue  to  grow.  Ideally,  this would  be  considered  in  the  various  strategic planning documents covering NSW Ports, the Lower Hunter and the City of Newcastle.  In March 2014, the NSW Ports’ Five Year Port Development Plan was released, however, the Port of Newcastle  is  not  considered  in  this  document,  presumably  due  to  its  recent  lease  by  the  NSW Government.  

4.6.2.1 NSW FREIGHT AND PORTS STRATEGY 

The older, 2013, NSW Freight and Ports Strategy indicates “that Port growth plans developed by the port operators will clarify the way  in which NSW ports will expand to meet future growth  in freight volumes”. On the Port of Newcastle, the strategy states that “it will continue to be NSW’s primary coal  export  port.  The  Port  of  Newcastle  will  also  continue  to  service  bulk  grain  and  other commodities”66. In this Strategy document the T4 project is listed as a key capacity development for the Port of Newcastle.  In addition to coal, the Strategy also highlights potential gas and continuing grain  exports  for  the  Port  of  Newcastle.  In  relation  to  gas,  it  notes  that  there  is  increasing commercial  interest – but  that any proposed  facility would need  to undergo  rigorous assessment particularly around safety and environmental  issues.  In relation to grain,  it  is  listed as a key export product for the Port of Newcastle and indicates that the existing nominal grain export capacity of 4.2 million tonnes per annum “is sufficient for forecast growth demands. Achieving this nominal capacity is, however, dependent upon receiving sufficient rail access to move these volumes to port as well as 

                                                            65 PWCS/EMM. 2013. T4 Project, Response to Submissions and Preferred Project Report. September 2013 66 NSW Government. 2013. NSW Freight and Ports Strategy. http://freight.transport.nsw.gov.au/documents/tfnsw‐freight‐and‐ports‐strategy‐low‐res.pdf accessed 28 October 2014 p 116 

Page 68: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

59  

supply, demand and logistic support impacts.”67 The Strategy sets a number of tasks, including “2D‐2 – to develop a Port of Newcastle growth plan”.  

4.6.2.2 DRAFT STRATEGIC DEVELOPMENT PLAN FOR THE PORT OF NEWCASTLE 

No  growth  plan  for  the  Port  of Newcastle was  available  at  the  time  of writing  (the  Commission understands one  is  in the process of being developed by the new  lessee’s The Port of Newcastle). The  2013 Draft  Strategic Development  Plan  for  the  Port  of Newcastle will  presumably  provide  a background starting point for this future work. In the existing plan the Port of Newcastle  is divided into  four spatial precincts, each with a specific  trade  focus,  the Kooragang Precinct’s  focus  is coal. The plan notes that “The coal industry has long‐term leases on the site of up to 45 years. Accordingly, this precinct will remain largely dedicated to coal exports over the life of the Strategic Development Plan.”68  At the time the Strategy was written, coal exports were forecast to grow, “driven by strong demand for thermal coal from east and south east Asia… The challenge for producers and the coal chain  in the period to 2025  is to build both production capacity and coal chain capacity to meet the export task.”69  It  goes  on  to  note  that with  the  addition  of  T4,  the  Port would  have  total  capacity  of between 280 and 330 million tonnes a year and this capacity is expected to be adequate for the coal export  task  to  2040.  Challenges  in  hauling  the  coal  long  distances,  from  outside  the Hunter,  are acknowledged.   The  Plan  notes  that  the  Port  also  handles  diversified  cargo  and  some  of  these  are  imports  that service the coal industry. Agriculture is another key export commodity with strong demand expected over the next 30 years, however determinants for growth in this sector are said to be dependent on the sector’s ability to  increase  its production as well as the capacity of the supply chains to deliver that cargo. In time, it is said that the port will handle containerised cargoes to service the expanding population, however any  future container  terminal development will only occur once Port Botany and Port Kembla are fully developed and utilised.  The  plan  nominates  key  priority  actions  for  the  port,  including  working  with  the  relevant government agencies and customers to achieve a whole of port approach to managing issues such as air quality and noise70.   The Commission acknowledges that expansion of coal handling facilities on Kooragang  Island  could  provide  greater  flexibility  to  deal  with  air  quality  and  noise  issues  attributable to the PWCS Carrington coal terminal.  

4.6.2.3 STRATEGIC PLANNING FROM NEWCASTLE CITY COUNCIL 

The City of Newcastle  is  in the process of developing a Local Planning Strategy and has released a number  of working  papers  as  part  of  this  process.  These will  build  on  the  2012  update  of  the Newcastle Urban Strategy, which acknowledges the significance of the port stating “the value of the land with frontage to the deep water of the Port of Newcastle will be recognised and protected. Land use controls will be developed to ensure this protection and to maintain a  land bank for future port 

                                                            67 NSW Government. 2013. NSW Freight and Ports Strategy. http://freight.transport.nsw.gov.au/documents/tfnsw‐freight‐and‐ports‐strategy‐low‐res.pdf accessed 28 October 2014 p 117 68 Newcastle Port Corporation. 2013. Draft Strategic Development Plan for the Port of Newcastle P 54. http://pandora.nla.gov.au/pan/139583/20130403‐1108/newcastleportplan.com.au/document/show/9.pdf accessed 28 October 2014 69 Newcastle Port Corporation. 2013. Draft Strategic Development Plan for the Port of Newcastle P 16.  70 Newcastle Port Corporation. 2013. Draft Strategic Development Plan for the Port of Newcastle P 42.  

Page 69: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

60  

related activities”  71 The strategy does not specifically mention coal. This  is  left  to  the City’s Local Planning Strategy Working Paper on Infrastructure, which notes that “There are currently 20 berths of varying capacity. Nine of these berths are allocated to the export of coal with the remaining eleven berths handle bulk liquids, solids, break bulk, containers and project cargo. The Port of Newcastle is a significant contributor  to  the Hunter Region’s economy.”72 The Terminal 4 proposal  is noted  in  the working paper, but no comment is provided. The Port will continue to be an important generator of industry and employment for the region. The availability of  industrial  land, the protection of routes into and out of the Port and interface issues will be key issues for the future.73 Regional Strategies and Plans The 2006 Lower Hunter Regional Strategy has limited discussion of the coal industry and associated freight capacity requirements, but notes that “the Region still retains significant coal resources and the potential for ongoing coal production and export”74.  

The 2012 Upper Hunter Strategic Regional Land Use Plan supports growth of the coal sector noting “Coal is NSW’s most significant commodity export ‐ worth over $14 billion in 2010/11. Approximately sixty per cent of this coal is mined in the Upper Hunter region. It is estimated that 63 per cent of the gross regional product comes from mining. Between 2006 and 2010, direct employment  in mining  in the  region  rose  from  5,500  to more  than  11,000. Mining  support  industries,  such  as  engineering, construction, transport, logistics and human resources have also become well established in Singleton and Muswellbrook.  

… Over the period to 2036, the region’s workforce  is expected to grow by between 7,400 and 8,200 jobs. Much of this increase will be driven by the growth of the coal and coal seam gas industries and focused  in  the  LGAs of  Singleton, Muswellbrook and Upper Hunter. Efficiency  improvements  in  the mining industry will also support growth, without the need for additional labour.”75 

The need for infrastructure and port capacity upgrades is also acknowledged in the Plan, stating: “The growth of the coal and gas extraction industries will be one of the most significant factors in shaping the communities and the infrastructure needs of the Upper Hunter region over the next few decades. The  growth of  these  sectors will  require  infrastructure provision  and upgrades,  for  example  to  rail infrastructure  linking  the mining  areas  to  the  Port  of Newcastle  and  upgrades  to  the  coal  loading capacity of the port.” 76  

 The Government’s 10 year Strategic Business Plan NSW 2021  is also referenced and the associated Hunter Regional Action Plan lists investment in economic diversity as a priority action, and proposes to  increase employment opportunities  in a range of sectors, one of which  is mining. The plan also 

                                                            71The City of Newcastle. 2012.  Newcastle Urban Strategy, A 25 year Revitalisation Plan for Newcastle ‐ Update July 2012, p 30 http://www.newcastle.nsw.gov.au/__data/assets/pdf_file/0015/116421/Newcastle_Urban_Strategy_Update_2012.pdf accessed 27 October 2014 72 The City of Newcastle. 2013. Draft Local Planning Strategy, Working Paper – Infrastructure. http://www.newcastle.nsw.gov.au/__data/assets/pdf_file/0004/213997/Working_Paper_‐_Infrastructure_FINAL.pdf accessed 27 October 2014. 73The City of Newcastle. 2013. Draft Local Planning Strategy, Working Paper – Infrastructure. P 44.  74 Department of Planning. 2006. Lower Hunter Regional Strategy 2006 – 2031. P 8 http://www.planning.nsw.gov.au/regional/pdf/lowerhunter_regionalstrategy.pdf accessed 28 October 2014. 75 Department of Planning and Infrastructure. 2012. Upper Hunter Strategic Regional Land Use Plan. p43 http://www.planning.nsw.gov.au/Portals/0/StrategicPlanning/FINAL%20low%20res%20Upper%20Hunter%20SRLUP.pdf accessed 28 October 2014 76 Department of Planning and Infrastructure. 2012. Upper Hunter Strategic Regional Land Use Plan. P36 http://www.planning.nsw.gov.au/Portals/0/StrategicPlanning/FINAL%20low%20res%20Upper%20Hunter%20SRLUP.pdf accessed 28 October 2014 

Page 70: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

61  

seeks to build “Newcastle as a renewable energy hub for research and deployment” and “Grow the visitor economy in the Hunter”77.  The Commission accepts that this fourth coal terminal proposal, and its associated expansion of the coal mining sector is consistent with the NSW Government’s planning and strategies for the Hunter Region and  the Port of Newcastle. Nonetheless  the Commission notes  these  strategies and plans assume that demand for NSW’s coal will grow. Given the present subdued coal price, and associated downturn  in  the  coal  sector;  the  Commission  cautions  against  continued  assumptions  of  growth based on past trends in coal exports in future planning for the region. While no one can predict the future, there seems to be a real possibility that coal prices and associated exports may not recover to the levels predicted in past forecasts.  Global coal prices and NSW coal exports are currently subdued, but some  forecasts are predicting strong demand for coal in the decades to come. While this proposal is not needed to meet current export  demand  requirements,  the  Commission  accepts  that  the  proposal  is  consistent  with  the region’s  future  planning  strategies  and  consequently  considers  it  is  reasonable  to  have  future expansion options available to cater for this, as long as it does not jeopardise or limit other economic development at the port and in the wider region.   Nonetheless,  at  present,  granting  an  approval  to  this  proposal  (when  it  is  not  needed  for  the immediate  future) provides  little public benefit  if no  investment occurs. However,  the Proponent stands to gain significant benefit from an approval, in terms of certainty and increased asset value to the  company.  If  an  approval  is  granted  but  no works  proceed  (a  likely  outcome,  as  there  is  no demand  for  the extra  throughput  capacity  in  the  immediate  future),  the  site will  remain a public liability  in  its current contaminated state (or the cost of remediation would be sourced from public funds).  The  Commission  considers  that  given  the  lack  of  demand  for  the  project  at  present,  the Proponent would need to commit to some public benefit works, to be provided  in the short term, such as a start to site remediation and biodiversity offset works, in order to ensure this project can be shown to be in the public interest.   Notwithstanding this it will be important that any final decision considers the latest up to date coal demand and pricing forecasts to justify the final throughput capacity of each stage of the terminal’s development. As noted  in other sections,  the Commission considers  that at  least  initially  reducing the  currently  proposed  70  million  tonne  annual  throughput  provides  greater  capacity  to  avoid environmentally sensitive portions of the site (see section 4.1) and would also reduce the total dust emission  impacts of  the project  (see  Section 4.3).  Staging of  the development of  this  throughput would need to be regulated to ensure each new stage is only developed when needed.  As  also  noted  in  the  previous  sections  on  Air  Quality  and  Noise,  the  Commission  agrees  with suggestions made  in  submissions  and  in  the  Department’s  assessment  that  options  to manage impacts  from  industries  in  the port  through a port wide  strategy have  some merit and  should be further  explored. A port wide management  approach has  the potential  to Provide  a more useful context  for  considering  cumulative  impacts,  along  with  up  stream  and  down  stream  impacts associated with  the port  (such  as  from  rail  and  shipping).  It  could  also provide  a better basis  for streamlined development of  responsive operational plans  for air quality and other environmental issues.  

                                                            77 NSW Government. 2012. Hunter Regional Action Plan. p 6 and 7 respectively. https://www.nsw.gov.au/sites/default/files/regions/regional_action_plan‐hunter.pdf accessed 28 October 2014 

Page 71: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

62  

In relation to the wider Hunter region, it will be important that future strategic planning work gives due consideration to the coal mining industry’s market exposure.   The  Commission  recommends  that  the  Proponent  and  the  Department  consider  the  latest  coal pricing  and  demand  forecasts  in  justifying  the  final  throughput  capacity  and  resulting  onsite development footprint, layout and staging plans, to ensure environmental impacts are minimised.  

4.6.3 STORMWATER/GROUND WATER 

A number of submissions received by the Commission raised concerns about possible contamination and pollution effects on Kooragang wetlands,  the Hunter River and Hunter Estuary. This  included impacts  from  construction,  cumulative  impacts  of  discharges,  surface  water  contamination  and future stormwater runoff.  Drainage  across  the  project  site  is  highly modified  by  culverts,  drains,  levees,  artificially  formed drainage  depressions  and  ponds.  The  ponds  were  predominantly  formed  as  a  result  of  rail embankments and past landfill activities and are recharged by rainfall, surface water, ground water and  limited exchange between ponds. Several of these artificial ponds are proposed to be filled to enable site capping and construction. These ponds do not have direct surface connections to water bodies outside of the project site, meaning the  impacts of filling on the surface‐water flow regime outside of the site are expected to be negligible.  The PPR explains  that proposed construction of  the coal  terminal would alter  the existing  surface flow regime within the project area. To avoid or minimise potential operational impacts to adjoining surface water bodies, PWCS has proposed  to operate  the site as a  'no discharge site'. This will be achieved through the use of retention ponds and by managing and reusing onsite surface water to limit  discharge  to  adjoining  waterways.  During  construction,  runoff  would  be  diverted  to  the northern portion of Deep Pond for settling before discharge to the Hunter River via the path of the existing culvert to the Hunter River South Arm.  It  is proposed to realign a portion of the culvert to avoid  the wetland at  the  river's edge. The northern portion of Deep Pond would be converted  to three settling ponds designed to improve water quality before discharge to the Hunter River.  In  its  statement of  commitments and PPR, PWCS has outlined a  range of other management and monitoring measures to ensure there are no significant adverse  impacts to receiving water quality during construction or operation of the proposed coal terminal. These include the following: 

An erosion and sediment control plan will be designed and implemented prior to and during construction. The principal objective of surface water management will be to prevent contamination of surface and ground waters. 

A surface water quality monitoring program will be developed and implemented to monitor water quality during construction. 

A realigned estuarine channel will be constructed to the north of the rail embankment, connecting Mosquito Creek and one of its tributaries, to maintain the existing tidal flow regime to wetlands potentially affected by disturbance to the southern end of Mosquito Creek Tributary. 

Works will be undertaken to avoid impacting the tidal regime of the wetland complex near the Eastern Watercourse. The mitigation design will be finalised prior to construction. Subject to approval from National Parks and Wildlife Services. 

Drainage will be provided within the rail embankment to maintain flows into the Eastern Freshwater Wetland from the rail area. 

Page 72: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

63  

The hydraulic connection of the southern portion of Deep Pond with Blue Billed Duck Pond will be unchanged.  Flows will continue to discharge to the Hunter River South Arm at the existing discharge point via a drainage channel that will be constructed linking the southern sections of Deep Pond to the existing culverts under the NCIG rail line. 

The surface water management system will maximise re‐use of captured stormwater runoff to meet process water demands on the site.  

 The  Commission  notes  that  PWCS’s  existing  coal  terminal  on  Kooragang  Island  (KCT)  has  similar operations,  catchment  characteristics  and  surface water management  to  that  anticipated  for  the proposed development.  The Department has advised that discharge from KCT is of similar quality to that  recorded  in  the  Hunter  River,  and  it  is  anticipated  that  discharge  from  the  proposed  coal terminal would be similar.  As advised  in Section 4.2.4 of this Review, the EPA has recommended amendments and additional conditions  in  relation  to  stormwater  and  surface  water  management78.  The  Commission recommends adoption of these conditions.  The Commission generally accepts the Department’s position that while  impacts to on‐site surface water  and  flooding  are  unavoidable,  the  Proponent  has  committed  to  appropriate management measures.  These  include  the  use  of  retention  ponds  and  developing  a  'no  discharge  site', where suitable water is re‐used wherever possible.  However, as discussed in Section 4.1 of this report, the Commission believes that there  is scope for further reduction  in  impacts on the biodiversity values of Deep Pond and the adjacent GGBF habitat ponds with refinement of the design and footprint of the proposed stockyards.   The Commission believes that with specialist advice and innovative design, the biodiversity values of Deep Pond could be enhanced at the same time as providing best practice stormwater management in a sensitive location.  

4.6.4 VOLUNTARY PLANNING AGREEMENT AND DEVELOPMENT CONTRIBUTIONS 

Council’s view Newcastle City Council’s Section 94A Development Contributions Plan 2009  (updated March 2011) sets  out  provisions  for  the  payment  of  developer  contributions  to  offset  the  costs  of  Council providing  social  infrastructure  required  as  a  result  of  development.  Under  the  plan,  levies  are generally applied at a  fixed  rate depending on  the cost of  the development.   The EP&A Act 1979 allow for developers and councils to enter  into a Voluntary Planning Agreement (VPA)  in  instances where the rates contained in a Section 94 plan are unsuitable.  On 15 August 2014  the Commission met with  the General Manager of Newcastle City Council  (Mr Ken Gouldthorp) and Director of Planning (Peter Chrystal) to discuss the proposed development.  At the meeting, Council explained  that while  it  is generally supportive of  the proposed coal  terminal, there is concern regarding the amount of Section 94A contributions that would be payable under the Department’s recommended conditions.    Condition A14 of the Department’s recommended conditions states: 

  Development Contribution A14  Prior  to  the  commencement  of  construction,  the  Proponent  shall  pay  The  City  of 

Newcastle Council an amount equivalent to one percent of Council’s works schedule                                                             78 NSW EPA. 2014. correspondence to Planning Assessment Commission dated 25 August 2014 

Page 73: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

64  

and new public facilities listed in Appendices A and B of the Section 94A Development Contributions Plan 2009 

 The Commission understands that under the terms of the condition above, PWCS would be required to pay a contribution of approximately $528, 140. By comparison, under Council’s Section 94A Plan a contribution of $48 million would be payable.  In a letter to the Commission dated 18 August 2014, Council explained that it does not support the Department’s approach.  At the meeting on 15 August 2014, Mr Gouldthorp acknowledged that while Council’s Section 94A plan does not contemplate development the size of Terminal 4, appropriate contributions need to be made to ensure sufficient community benefits. Council  is seeking to obtain these benefits via a VPA.  If an agreement cannot be  reached between parties, Council considers a contribution with a value of 1% of the project cost to be reasonable.    Proponent’s view The  PPR  and  Response  to  Submissions  (prepared  by  EMM  2013)  states  that  the  calculation  of development contributions based on  levies outlined  in Council’s Section 94A plan are unsuited  to large developments such as the subject proposal. This  is because the  levies are not commensurate with the demand they generate and do not account or credit community facilities provided by the Proponent. As such, PWCS  is open to considering negotiating a VPA that accurately represents the agreed  increase  in demand  for public amenities and  services  in  the area  caused by  the proposed development.   Department’s view The Secretary’s PEAR notes the difficulty associated with calculating a reasonable contribution based on  Council’s  Section  94A  plan when  the  capital  investment  value  is  very  large.    The Department accepts the Proponent’s position that the proposal will have limited social impacts on the region and therefore  considers  a  “modest  “contribution  to  be  appropriate.  This  is  reflected  in  the recommended condition A14 outlined above.  In  addition  to  Condition  A14,  the  Department  also  supports  the  Proponent's  commitment  to entering into a VPA with Newcastle City Council79. Newcastle City Council has responded to this in a letter to the Commission (dated 18 August 2014). Council explains that the Department's support for a VPA is “perplexing”, given Condition A14 would negate the need for a VPA.   Commission’s recommendation The Commission notes  that both  the Proponent and Council are willing  to enter a VPA and  seem committed  to  negotiating  terms.  The  Commission  encourages  this  collaborative  approach  and recommends the Department amend its Development Contribution condition to reflect the outcome of these negotiations.   

 

                                                            79 NSW Department of Planning and Environment. 2014. Secretary’s Preliminary Environmental Assessment Report. June 2014. p 70 

Page 74: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

65  

5. CONCLUSIONThe  Commission  has  carefully  reviewed  the  proposal,  along  with  the  submissions  made,  the Department’s preliminary assessment  report and draft  conditions and  the expert advice  from  the Centre for International Economics. The Commission agrees with the Department’s findings that the proposal  is  approvable.  Nonetheless  there  is  considerable  uncertainty  about  the  timing  for  the proposal and this raises some questions about the justification for granting an approval at this stage, when  there  is  considerable  uncertainty  about  when  or  even  whether  the  project  will  proceed. Alternatively  the  Commission  recognises  that  there  are  adverse  environmental  and  economic outcomes associated with allowing the site to remain in its current contaminated state and without any direct action to protect and enhance biodiversity values.  The  Commission  has  found  that  these  public  benefit  deficiencies  could  be  overcome with  some further clarification and commitments to undertake the remediation and biodiversity management works  in  a  timely  and  integrated manner.  It will be up  to  the Proponent  and  the Department  to ensure  the  current  potential  public  liabilities  and  uncertainties  regarding  the  timing  of  the remediation and biodiversity management works are resolved  in the final proposal referred to the decision maker.   With  some  innovative  refinements  to  the  layout of  the project,  the proposal has  the potential  to minimise  current  conflicts  between  biodiversity  values  and  the  need  to  remediate  the  highly disturbed and contaminated site.  The site’s location within the industrial lands in the Port of Newcastle means that impacts from the noise and dust emissions of the project should be able to be adequately contained with the adoption of a suite of proactive real‐time management measures. The Commission supports the Department’s initiative to examine a coordinated port wide management approach to issues such as noise and air quality.  Such  a  coordinated  approach  could  have  material  benefits  for  residential  communities around the port, as well as optimising the development, capacity and use of the port.  The  Commission  has  found  that  other  local  issues  such  as  stormwater management  and  traffic impacts can be adequately managed.   Numerous  submissions  and  presentations  to  the  Commission  called  for  rejection  of  the  project however,  due  to  concerns  about  the  up  and  downstream  impacts  of mining,  transporting  and burning  the  coal  that would  be  exported  through  the  terminal.  The  Commission  notes  that  the impacts of mining would need to be considered in the detailed merit assessment of each new mine proposal  sought.  In  relation  to  the  greenhouse  gas  emissions,  the Commission  acknowledges  the need to prevent dangerous climate change (defined  in current  international agreements as 2 °C of warming). Ultimately,  the Commission  accepts  that planning  controls  cannot be used  to  regulate scope 3  emissions  from  the downstream use of  the  coal  exported. Nonetheless,  the Commission notes that it would be prudent to ensure that future strategic planning work for the region gives due consideration to the coal mining industry’s market exposure and the potential economic implications of evolving international policy on climate change.  While the proposal before the Commission is for an approval to commence construction within ten years, the Commission considers that a five year approval is more appropriate given the uncertainties discussed in the report and also advice from the Department that the Proponent would not be required to carry out some of the environmental obligations until and if the project approval is triggered.    

Page 75: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

66  

The Commission is satisfied the project is approvable, subject to the following recommendations and associated refinements to the project and the draft conditions.  

6.  RECOMMENDATIONS  Lapsing Period 

1. The Commission recommends a  five year rather  than  ten year approval  lapsing period  for the project.   A  ten year commencement period could result  in extended delays  in dealing with contamination and biodiversity issues; as well as sanctioning a project out of step with potential changes to air quality standards and greenhouse gas policies. A five year approval provides  a  reasonable  period  to  commence  construction  based  on  current  planning  and environmental requirements. 

 Biodiversity 

2. The  Commission  considers  it  is  critical  that  the  detailed  design  of  the  offset  sites  be prepared in consultation with government agencies including the Commonwealth, OEH and relevant  Council.  It  is  noted  that  the  recommended  biodiversity  conditions  (B16  to  B21) adequately address this recommendation. 

 3. As noted above, the Commission recommends that a five year approval, rather than the 10 

year  timeframe  proposed  by  PWCS.  A  five  year  approval  period  would  provide  an appropriate timeframe for the Proponent to commence the conservation works outlined in this chapter, which would have  significant biodiversity benefits. A 10 year approval could delay  these  works,  which  would  result  in  further  degradation  of  habitat  and  loss  of population. 

 4. The Commission is of the view that the Tomago offset area would need to demonstrate that 

is it functioning successfully prior to construction commencing at the project site. While the Commonwealth recommends one year of demonstrated success, the Commission considers Tomago  should  be  functioning  for  a  minimum  of  three  years  to  be  confident  of documenting at least one successful migratory season. 

 5. The stockyard  layout should be refined so that  it has a reduced  impact on Deep Pond and 

the  nearby  Frog  Pond  and  Railway  Pond.  This  would  provide  improved  GGBF  and Australasian Bittern habitat as well as minimising  the  impact on migratory shorebirds and any potential to impact on the values of the Hunter Estuary Wetlands Ramsar site. 

 Contamination 

6. The  Commission  believes  that  the  contamination  on  Kooragang  Island  needs  to  be remediated  as  soon  as  practicable.  Before  a  determination  is  made,  the  Commission recommends  that  the  Proponent,  the  EPA  and  the  HDC  negotiate  and  agree  on  a comprehensive  remediation  strategy, with  clear  roles  and  responsibilities,  and  an  agreed time‐table. 

 7. The  Commission  recommends  adoption  of  the  amendments  and  additional  conditions 

recommended  by  the  EPA  in  the  correspondence  dated  10  October  2014.  In  addition, Condition  B32  should  be  amended  to  reference  a  one  in  100  year  average  recurrence interval discharge event, (as in correspondence from the EPA dated 25 August 2014). 

  

Page 76: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

67  

Air Quality 8. Pro‐active and Reactive Management 

The  Commission  supports  the  Department’s  proposed  requirements  for  pro‐active  and reactive  management  of  air  quality  and  recommends  that  consideration  be  given  to strengthening the Department’s conditions requiring pro‐active and reactive mitigation and management.  In  particular  it  would  be  necessary  to  confirm  what mitigation measures would be applied, which components could be shut down (as is required of modern mining operations)  and  provide  clear  justification  for  any  continued  emissions  during  adverse conditions. This would also need to extend to the management of emissions from ships and locomotives that are associated with the project. 

 9. Shore Power 

The  Commission  recommends  that  the  Proponent  should  be  required  to  make  spatial provision for shore power  for vessels, so that  it could be  installed on the site  in future,  in the event this becomes a viable option. 

 10. Minimising emissions from coal wagons 

The  Commission  recommends  any  approval  should  include  conditions  that  ensure  coal should only be accepted at the project site where  it has been appropriately profiled within the wagon and where the coal at the top of the wagon (i.e. that exposed to the wind) meets appropriate moisture content levels, or has been treated with an effective chemical veneer. 

 11. Cleaning of coal wagons 

The Commission recommends any approval should  include conditions that require wagons leaving the site to be completely empty, with dump doors fully closed and sufficiently clean to ensure there is no visible evidence of coal deposition on the ballast around the rail tracks from trains leaving the site. 

 Noise In relation to the noise limits that should apply to the project, the Commission recommends: 

12. That  noise  limits  should  be  included  for  locations  at  Warabrook  and  Sandgate  (as recommended by the EPA);  

13. That  options  to  tighten  the  noise  limits  that  would  apply  to  T4  in  concert  with  the Kooragang Coal Terminal should be further explored;   

14. That additional noise limits specific to the T4 project should also be considered.  

Other 15. The  Commission  recommends  that  where  the  conditions  specify  that  issues  shall  be 

managed in accordance with the relevant guidelines, the condition specifies that the latest 

version of the policy or guideline would apply.   

 

16. The Commission recommends that the Proponent and the Department consider the  latest 

coal pricing and demand  forecasts  in  justifying  the  final  throughput capacity and resulting 

onsite development  footprint,  layout and  staging plans,  to ensure environmental  impacts 

are minimised. 

   

Page 77: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

68  

ReferencesARTC (2014), 2014‐2023 Hunter Valley Corridor Capacity Strategy, July, p.7.  Bulga Milbrodale Progress Association Inc v Minister for Planning and Infrastructure and Warkworth Mining Limited [2013] NSWLEC 48. http://www.caselaw.nsw.gov.au/action/pjudg?jgmtid=164038 accessed 28 November 2014.  Department of Environment Website. 2014. http://www.environment.gov.au/climate‐change/emissions‐reduction‐fund accessed 6 November 2014  Department of Environment. 2014 http://www.climatechange.gov.au/reducing‐carbon/reducing‐australias‐emissions accessed 6 November 2014.  ENVIRON. 2013. Locomotive Emissions Project: Scoping Study of Potential Measures to Reduce Emissions from New and In‐service Locomotives in NSW and Australia. http://www.epa.nsw.gov.au/resources/air/locoemissrep.pdf accessed 6 November 2014  Gray v The Minister for Planning and Ors [2006] NSWLEC 720 138, http://www.lawlink.nsw.gov.au/lecjudgments/2006nswlec.nsf/c45212a2bef99be4ca256736001f37bd/dc4df619de3b3f02ca257228001de798?OpenDocument accessed 28 October 2014  International Energy Agency, 2013, World Energy Outlook 2013 http://www.iea.org/publications/freepublications/publication/WEO2013_Executive_Summary_English.pdf accessed 21 October 2014  International Energy Agency, 2014, World Energy Outlook 2014 http://www.iea.org/Textbase/npsum/WEO2014SUM.pdf accessed 13 November 2014.  National Environment Protection (Ambient Air Quality) Measure, Schedule 2, http://www.comlaw.gov.au/Details/C2004H03935 accessed 6 November 2014.  National Environmental Protection Council Service Corporation. 2011. National Environmental Protection (Ambient Air Quality) Measure Review – Review Report. http://www.scew.gov.au/resource/national‐environment‐protection‐ambient‐air‐quality‐measure‐review‐review‐report accessed 28 November 2014.  Newcastle Port Corporation. 2013. Draft Strategic Development Plan for the Port of Newcastle http://pandora.nla.gov.au/pan/139583/20130403‐1108/newcastleportplan.com.au/document/show/9.pdf accessed 28 October 2014  NSW Department of Environment and Conservation. 2005. Approved Methods for the Modelling and Assessment of Air Pollutants in New South Wales. http://www.epa.nsw.gov.au/resources/air/ammodelling05361.pdf accessed 6 November 2014.    NSW Department of Planning. 2006. Lower Hunter Regional Strategy 2006 – 2031. http://www.planning.nsw.gov.au/regional/pdf/lowerhunter_regionalstrategy.pdf accessed 28 October 2014.  NSW Department of Planning and Infrastructure. 2012. Upper Hunter Strategic Regional Land Use Plan. 

Page 78: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

69  

http://www.planning.nsw.gov.au/Portals/0/StrategicPlanning/FINAL%20low%20res%20Upper%20Hunter%20SRLUP.pdf accessed 28 October 2014  NSW Department of Planning and Infrastructure. 2012. Project Approval, Kooragang Coal Terminal Mod 3. https://majorprojects.affinitylive.com/public/d5ca8de27579d43ce753fabb7f9bd2d3/Consolidated%20Approval%20(MODS%201,%202%20&%203)_Nov%202012.pdf Accessed 28 November 2014  NSW Department of Planning and Environment. 2014. Secretary’s Preliminary Environmental Assessment.  NSW EPA. 2014. Review of regulation of railway systems activities under the ‘Protection of the Environment Operations Act 1997, Position paper. August 2014 http://www.epa.nsw.gov.au/resources/epa/14657railpospap.pdf accessed 5 November 2014  NSW EPA. 2014. Correspondence to the PAC dated 25 August 2014 (see Appendix 6)  NSW EPA 2014. Correspondence to the PAC. Dated 10 October 2014 (see Appendix 6)  NSW Government. 2012. Hunter Regional Action Plan. https://www.nsw.gov.au/sites/default/files/regions/regional_action_plan‐hunter.pdf accessed 28 October 2014  NSW Government. 2013. NSW Freight and Ports Strategy. http://freight.transport.nsw.gov.au/documents/tfnsw‐freight‐and‐ports‐strategy‐low‐res.pdf accessed 28 October 2014  NSW Health, Hunter New England Local Health District. 2013. Letter to the NSW Department of Planning and Infrastructure titled Port Waratah Coal Services Limited Response to Community Submissions – Terminal 4 project, dated 17 November 2013. https://majorprojects.affinitylive.com/public/eb4f2c8a90b25f949e221a6a94f58cd7/HNE_EH_Planning_T4.pdf accessed 11 November 2014  NSW Office of Environment and Heritage. 2014. Emissions Overview 2011/12. http://www.environment.nsw.gov.au/climatechange/emissionsoverview.htm accessed 21 October 2014  PAEHolmes. 2011. Potential Measures for Air Emissions from NSW Ports: Preliminary Study. Prepared for the NSW Office of Environment and Heritage, 23 June 2011. http://www.epa.nsw.gov.au/resources/air/PortsPreliminaryStudy.pdf accessed 5 November 2014.  PWCS/EMM. 2012 T4 Project, Environmental Assessment. February 2012.  PWCS/EMM. 2013. T4 Project, Response to Submissions and Preferred Project Report. September 2013.  PWCS/EMM. 2014. Response to Submissions on Preferred Project.  January 2014.  PWCS. 2014. KCT Annual Noise Investigation Report (2014).  

Page 79: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

70  

The City of Newcastle. 2012.  Newcastle Urban Strategy, A 25 year Revitalisation Plan for Newcastle ‐ Update July 2012, http://www.newcastle.nsw.gov.au/__data/assets/pdf_file/0015/116421/Newcastle_Urban_Strategy_Update_2012.pdf accessed 27 October 2014  The City of Newcastle. 2013. Draft Local Planning Strategy, Working Paper – Infrastructure. http://www.newcastle.nsw.gov.au/__data/assets/pdf_file/0004/213997/Working_Paper_‐_Infrastructure_FINAL.pdf accessed 27 October 2014.  The Guardian, 22 July 2014, Germany, UK and Poland top ‘dirty 30’ list of EU coal‐fired power stations, http://www.theguardian.com/environment/2014/jul/22/germany‐uk‐poland‐top‐dirty‐30‐list‐eu‐coal‐fired‐power‐stations accessed 20 October 2014   The White House. 2014. FACT SHEET: U.S.‐China Joint Announcement on Climate Change and Clean Energy Cooperation. http://www.whitehouse.gov/the‐press‐office/2014/11/11/fact‐sheet‐us‐china‐joint‐announcement‐climate‐change‐and‐clean‐energy‐c accessed 13 November 2014  United Nations Website http://www.un.org/climatechange/summit/2014/09/ban‐seeks‐vision‐concrete‐action‐world‐leaders‐un‐climate‐summit/ accessed 20 October 2014  United Nations Website http://www.un.org/climatechange/science-and-solutions/ accessed 20 October 2014  United Nations Website http://www.un.org/climatechange/summit/2014/09/2014‐climate‐change‐summary‐chairs‐summary/ accessed 20 October 2014  U.S. Energy Information Administration website http://www.eia.gov/countries/country‐data.cfm?fips=gm accessed 20 October 2014  WHO. 2013. Review of evidence on health aspects of air pollution – REVIHAAP Project: Technical Report. http://www.euro.who.int/__data/assets/pdf_file/0004/193108/REVIHAAP‐Final‐technical‐report‐final‐version.pdf accessed 3 November 2014      

Page 80: Port Waratah Coal Services Terminal 4 Project Review Report...Port Waratah Coal Services Terminal 4 Project PAC Review Report© State of New South Wales through the NSW Planning Assessment

 

Planning Assessment Commission Review Report 2014 Port Waratah Coal Services Terminal 4 Project 

71  

ListofAppendices 

1. Minister’s Terms of Reference 2. List of Speakers at the Public Hearing 3. Summary of Meetings 

a. 22 July 2014 – Briefing from the Department of Planning and Environment b. 14 August 2014 c. 14 August 2014 d. 15 August 2014 e. 15 August 2014 f. 12 September 2014 – Briefing to the CIE g. 15 September 2014 – Meeting with Department of Planning and Environment h. 15 September 2014 – Meeting with the EPA i. 24 September 2014 – Meeting with the EPA j. 1 October 2014 – Meeting with the CIE k. 1 October 2014 – Meeting with NSW Health l. 30 October 2014 – Meeting with the CIE m. 6 November 2014 – Meeting with the Department of Planning and Environment 

4. Additional information from the Proponent 5. Additional Information from the Department of Planning and Environment 

a. 10 September 2014 b. 26 November 2014 

6. Agency Correspondence a. EPA correspondence dated 25 August 2014 and 10 October 2014 b. Commonwealth Department of Environment tables supplied 10 October 2014 c. NSW Health correspondence dated 24 October 2014 

7. Independent advice from the Centre for International Economics