Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port...
Transcript of Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port...
![Page 1: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/1.jpg)
Port of San Diego
Resiliency in Terminal Operations at Tenth Avenue Marine Terminal
![Page 2: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/2.jpg)
22
The Port Act and Tidelands Trust Doctrine
Promote commerce,
navigation, recreation,
fisheries, and environmental
stewardship
Manage San Diego Bay and
the Waterfront ‘Tidelands’
Details responsibility on behalf of
the people of the State of
California
Resiliency in Terminal Operations at the Port of San Diego 11/6/19
![Page 3: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/3.jpg)
33 3
Coronado
San Diego
National City
Chula Vista
Imperial Beach
3
Port of San DiegoJurisdiction
34miles of waterfront
2,403acres of land
3,535acres of water
Port Tidelands
Submerged Tidelands
11/6/19Resiliency in Terminal Operations at the Port of San Diego
![Page 4: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/4.jpg)
44
18hotels
9museums &
attractions
5public piers
22parks
70artworks
74restaurants
80+sponsored
events
4
Economic EngineMore than $1.7 Billion Invested Since 1963
4terminals
Resiliency in Terminal Operations at the Port of San Diego 11/6/19
![Page 5: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/5.jpg)
55
Climate Planning Timeline
2100 HIGH
2030
2050
2100 LOW
0.8 ft
1.6 ft
2.5 ft
4.9 ft
2018 0.7 ft
Green Port
Program
Climate Action Plan
Adopted Climate Adaptation & Resiliency Planning
Resiliency in Terminal Operations at the Port of San Diego 11/6/19
Green
Business
Network
2013 Climate Action Plan Implementation 201920102008
![Page 6: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/6.jpg)
66
Climate Action PlanGreenhouse Gas Emission Reduction Targets
-10% by 2020
-25% by 2035
Resiliency in Terminal Operations at the Port of San Diego 11/6/19
Note: Timescale is drawn for illustrative purposes.
![Page 7: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/7.jpg)
77 11/6/19Resiliency in Terminal Operations at the Port of San Diego
Demonstrate Business Case for Advanced Microgridsin Support of California's Energy and GHG Policies
Grant Funding Opportunity-17-302
Project Title Grant RecipientEPIC Funding
(Match )
Port of Long Beach Microgrid Port of Long Beach $5M ($2.12M)
Camp Parks Microgrid Lawrence Berkeley National Laboratory $5M ($11.41M)
Miramar Marine Air Station Microgrid University of California, San Diego $5M ($6M)
Port of San Diego Microgrid San Diego Unified Port District $4.98M ($4.63M)
Port Hueneme Server Farm Building Microgrid Electric Power Research Institute $4.99M ($3.5M)
Chemehuevi Indian Reservation Microgrid Handbook Holdings, LLC $4.99M ($8.4M)
Virtual Wide Area Urban Microgrids Gridscape $4.99M ($3.28M)
Rialto Microgrid Rialto Bioenergy Facility $5M ($6.66M)
Redwood Coast Airport Microgrid Humboldt State University $5M ($6.32M)
Santa Rosa Junior College Microgrid Sonoma County Junior College District $4.99M ($8.69M)
Total AwardEPIC - $49.97M
Match - $61.02M
Electric Program
Investment Charge
• 17 microgrid projects at 23
sites.
• Total: $75.6 million CEC funds
and $71.4 million match funds.
• Projects are located in the CA
Investor Owned Utility territories.
![Page 8: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/8.jpg)
88
Project Overview – Goals of Microgrid Grant
Electrification
Resiliency
Technological Advancement
Replicability
Tenth Avenue Marine Terminal
11/6/19Resiliency in Terminal Operations at the Port of San Diego
![Page 9: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/9.jpg)
99
• 1 of 17 U.S. Department of
Transportation Strategic
Ports - Supply of Emergency
Goods / Services
• Critical Infrastructure:
o Jet Fuel Storage for San
Diego International Airport
o Security Gates/Facilities
o Site Lighting
11/6/19Resiliency in Terminal Operations at the Port of San Diego
Port of San Diego – Strategic Port
![Page 10: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/10.jpg)
1010
Microgrid Project Overview
• Project Consultants
o Burns & McDonnell (BMcD) – System Design and Construction Admin Support
o Electric Power Research Institute (EPRI) – Cyber Security Assessment,
Testing/Evaluation, and Knowledge Transfer
o UC San Diego (UCSD) – Project Evaluation and Knowledge Transfer
• Application Ask
o CEC Funding: $4,985,272
o District Match: $4,427,973
o UCSD Match: $201,963
• Overview
o Solar PV power, battery storage, and microgrid controller
o Energy Efficient Lighting Retrofits
o Decrease electricity costs 60%
Estimated Project Budget $9.6 M
11/6/19Resiliency in Terminal Operations at the Port of San Diego
![Page 11: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/11.jpg)
1111
SDRS 12 kV
Warehouse B Warehouse C
Fuel Storage
Area
Bulk Handling Facility
Main Security Gate
CEMEX 12 kV
District 12 kV
Dole 12 kV
Dole
Shorepower
12 kV
NAT 12 kV
![Page 12: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/12.jpg)
1212
Microgrid Preliminary Site Plan
858,000 kWh
Reduction
Solar 700 kW
Battery Storage
700 kW / 2,500 kWh
280,000 kWh
Reduction
Energy Efficient Site
Lighting Retrofits
Estimated Reduction
360 MTCO2e
11/6/19Resiliency in Terminal Operations at the Port of San Diego
![Page 13: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/13.jpg)
1313
700-kW Solar
PV Array
Battery Energy
Storage System /
Electrical
Infrastructure
Resiliency & Adaptation Planning at the Port of San Diego 10/18/19
Not to drawn to scale.
Energy ResiliencyTenth Avenue Marine Terminal Microgrid Project
11/6/19Resiliency in Terminal Operations at the Port of San Diego
![Page 14: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/14.jpg)
1414
Microgrid Technical Tasks
1 – General Project Tasks
2 – Microgrid Design
3 – Microgrid Construction
4 – Operation and Maintenance
5 – Testing and Evaluation
6 – Evaluation of Project Benefits
7 – Technology/Knowledge Transfer Activities
11/6/19Resiliency in Terminal Operations at the Port of San Diego
100% Design Phase
Technical Advisory Committee
Consultant Role:
UCSD, EPRI, and BMcD
Committee:
San Diego Gas & Electric
City of San Diego
Navy Region Southwest
California Air Resources Board
San Diego International Airport
San Diego Refrigerated Services
(TAMT Tenant)
![Page 15: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/15.jpg)
1515
Grant ReportingConstruction
July - SeptApr - June
Mic
rog
rid
Pro
jec
t
Grant Agreement
Development
FY 18
Grant
July - Sept Jan - Mar Apr - JuneOct - Dec July - Sept Jan - MarOct - Dec
FY 19
Apr - June
FY 20
Anticipated Microgrid Project Schedule
11/6/19Resiliency in Terminal Operations at the Port of San Diego
Oct - Dec
FY 21
Testing, Evaluation and Reporting
(Through to 3/2023)
ProcurementDesign
Construction
Battery Storage / Microgrid Control System
Solar / Electrical Infrastructure Upgrades
ProcurementMicrogrid Design
Lighting InstallationProcurementEnergy Efficient
Site Lighting
Retrofit
Roof ConstructionProcurementRoof Replacement
Relevant Tasks:
– Cyber Security Architecture Assessment
– Operation and Maintenance Plan
– Testing and Evaluation
– Evaluation of Project Benefits
– Technology/Knowledge Transfer Activities
![Page 16: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/16.jpg)
161616
Maritime Clean Air
Strategy
Clean Air Act
(1970)
California Clean Air Act
(1988)
AB 617 - Community Air
Protection Program
(2018)
Clean Air
Climate Action Plan
Update
Executive Orders
(2005 and 2013)
AB 32 – Global Warming
Solutions Act
(2006)
SB 32 – Global Warming
Solutions Act
(2016)
Climate Change
Port Master Plan
Sustainable Communities and
Climate Protection Act
(2008)
Sustainable Freight Action
Plan
(2016)
Land Use & Mobility
California State Legislative & Policy Framework
11/6/19Resiliency in Terminal Operations at the Port of San Diego
![Page 17: Port of San Diego Resiliency in Terminal Operations at ...aapa.files.cms-plus.com/PDFs/Nov 2019 Port of San Diego_TAMT Mi… · Climate Action Plan Adopted Climate Adaptation & Resiliency](https://reader033.fdocuments.us/reader033/viewer/2022050415/5f8ba8bdaa555e1cbb04c071/html5/thumbnails/17.jpg)
171717
California State Legislative & Policy Framework
11/6/19Resiliency in Terminal Operations at the Port of San Diego