Polish DP „First Shift” – Status: May 2006 Polish DP „First Shift” – Status: May 2006 www.venet-eu.com Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift Status: May 2006 Piotr Bastek, Piotr Suliga Chamber of Crafts and Small and Medium Enterprises in Katowice, Poland 3rd TCA Meeting in Werl, Germany May 2006

Transcript of Polish DP „First Shift” – Status: May 2006 Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in...

Page 1: Polish DP „First Shift” – Status: May 2006  Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift.

Polish DP „First Shift” – Status: May 2006Polish DP „First Shift” – Status: May 2006

www.venet-eu.comPiotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006

Project: First shiftStatus: May 2006

Piotr Bastek, Piotr SuligaChamber of Crafts and Small and Medium Enterprises

in Katowice, Poland

3rd TCA Meeting in Werl, Germany May 2006

Page 2: Polish DP „First Shift” – Status: May 2006  Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift.

Polish DP „First Shift” – Status: May 2006Polish DP „First Shift” – Status: May 2006

www.venet-eu.comPiotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006

Agenda:

1. Main results:– Market research– Recruitment process– Theoretical training programme

2. Mutual influence of DP and TCA3. Challenges4. Next steps

Page 3: Polish DP „First Shift” – Status: May 2006  Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift.

Polish DP „First Shift” – Status: May 2006Polish DP „First Shift” – Status: May 2006

www.venet-eu.comPiotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006

Main results: Market research1. A part of the labour market research appointed to

the entrepreneurs have been carried out by 34 pollsters;

2. As a result we got information on future trends in the employment in crafts’ professions. There is a need for workers in the following trades: Food trade, Building trade, Hairdressing trade and Automotive trade;

3. One of reasons of the lack of new places of employment is a difficulty of finding good workers due to their emigration to other EU countries;

4. There can be noticed growing difference between micro enterprises (below 10 employees) and small and medium enterprises in their market situation.

Page 4: Polish DP „First Shift” – Status: May 2006  Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift.

Polish DP „First Shift” – Status: May 2006Polish DP „First Shift” – Status: May 2006

www.venet-eu.comPiotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006

Main results: Recruitment1. There had been identified and then

recruited a pilot group of 50 beneficiaries;2. Huge interest in taking part in the project

among potential beneficiaries.

Page 5: Polish DP „First Shift” – Status: May 2006  Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift.

Polish DP „First Shift” – Status: May 2006Polish DP „First Shift” – Status: May 2006

www.venet-eu.comPiotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006

Main results: Theoretical training programme

1. There is already prepared a training cycle focused on a soft skills development – 5 groups of 10 beneficiaries: June 2006;

2. Each beneficiary is provided with a vocational guidance provided by the vocational advisors. Additionally everyone who needs a psychosocial support will have a possibility to talk to professional advisor (starting from October 2006).

Page 6: Polish DP „First Shift” – Status: May 2006  Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift.

Polish DP „First Shift” – Status: May 2006Polish DP „First Shift” – Status: May 2006

www.venet-eu.comPiotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006

Mutual influence of DP and TCA:1. All information concerning VENet model is

regularly sent to our national partners;2. Bigger influence will be noticed in the following

stages of our project as it is still in his initial phase.

Page 7: Polish DP „First Shift” – Status: May 2006  Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift.

Polish DP „First Shift” – Status: May 2006Polish DP „First Shift” – Status: May 2006

www.venet-eu.comPiotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006

Challenges:

1. Permanent changes of the budget;2. Public Procurement regulations;3. Supervising the beneficiaries;4. Coordination of the cooperation between

partners in our DP;

Page 8: Polish DP „First Shift” – Status: May 2006  Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift.

Polish DP „First Shift” – Status: May 2006Polish DP „First Shift” – Status: May 2006

www.venet-eu.comPiotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006

Next steps:

• To finish the labour market research analysis and prepare proper reports: end of June 2006;

• To carry out soft skills training programme: June 2006;• To carry out vocational training programme: beginning of

July 2006;• To organize a conference in order to promote next stages of

the project: June 2006 / July 2006;• To organize 4th TCA meeting in Katowice: October 2006.

Page 9: Polish DP „First Shift” – Status: May 2006  Piotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006 Project: First shift.

Polish DP „First Shift” – Status: May 2006Polish DP „First Shift” – Status: May 2006

www.venet-eu.comPiotr Bastek, Piotr Suliga, 3rd TCA Meeting in Werl, Germany; May 2006

Any questions?