PMP Mock Exam

download PMP Mock Exam

of 56

description

Questions to help prepare for the PMP Exam

Transcript of PMP Mock Exam

  • 7/13/2019 PMP Mock Exam

    1/56

    Question - 1

    Your company has been hired to configure software in 500 computers. All computers need equal time to

    configure. You calculate the time to configure each computer as 5 hours. The cost for labor is calculated at

    $500 each computer. Your Project Sponsor disagrees with your labor estimate. Why is so?

    1.You haven't completed one computer yet, so you don't know how long the work will actually take.

    2.You have not factored in all of the effort applied to the work.

    3.You have not considered the law of diminishing returns.

    4.You have not considered the learning curve.

    Correct Answers are : 4

    Explanation : 4 is the best choice. As the project team completes more and more units, the time to configure

    a computer should take less and less time.

    Question - 2

    You have been asked to provide Cost estimates for a project which would be responsible for the complete

    electrical installation in warehouses. As a project manager - you have had past experience in similar projects

    in your previous organization.The organization you have joined - also has recently done a similar project -

    and there is an urgency in providing the estimate as mandated by executive management - so what

    estimation technique would you adopt ?

    1.Ask your prior organization for the estimates.

    2.Use Parametric Estimating technique.

    3.Use Bottom Up Estimating.

    4.Analogous Estimates

    Correct Answers are : 4

    Explanation : The correct answer is Analogous estimates - since it relies on previous similar project as the

    basis of execution - which is available - so it relies on historical information.This technique is used when

    there is limited amount of detailed information like during early phases of the project , it is less costly and

    less time consuming - and as time is a constraint stated in the question - this is the best choice.

    Question - 3

    An estimate is required for a new project of an R & D nature - and it has been decided to create the estimates

    using WBS - with an emphasis on accuracy of the estimates.Your project manager also indicates sufficient

    time is being made available to provide the estimates - what would be the best estimation approach in this

    case ?

    1.Parametric Estimation approach

    2.Analogous Estimation approach

    3.Top Down Approach

    4.Bottom Up Approach

    Correct Answers are : 4

    Explanation : Parametric and Analogous are clearly not the right choices.Being a new project - we do not

    have any historical data to rely on - so Analogous estimation is not an option.We also dont have any data of

    costs per unit - so Parametric estimation is also not an option.Now between Top down and Bottom up - both

    of these approaches use the WBS to come up with the estimates.Here we start with the high level and then

  • 7/13/2019 PMP Mock Exam

    2/56

    drill down into the lower levels. Bottom-up estimates are more accurate as compared to Top down.Bottom up

    is also a more expensive and time-consuming type of estimate - however the question clearly indicates that

    time is not a concern - so the correct answer is Bottom up approach. Top down approach is used only if we

    have enough historical information on the Project which is not true.

    Question - 4

    You are in the process of making a cost estimate for a large prestigious project. You decide to use the Three

    Point Estimation technique with Triangular Distribution. Based on your analysis and understanding you are

    confident that the project would be completed with a total cost of 108,000 $.You also estimate that a best

    case estimate would be 90000 $ while a worst case scenario would result in the costs incurred to shoot up to

    138000 USD. What would the Three point Cost estimate be using Triangular Distribution ?

    1.112000 $

    2.111000 $

    3.11000 $

    4.26000 $

    Correct Answers are : 1

    Explanation : The correct answer is A.The question states we should use Three point estimate using

    triangular distribution. The formula for this estimation technique is a + b + c / 3 where a = Most Likely

    estimate , b = Estimate based on analysis of the Best case scenario and c = Estimate based on analysis of

    the Worst case scenario. So the Three point estimate using Triangular distribution is 108000 + 90000 +

    138000 / 3 = 336000/3 = 112000 $

    Question - 5

    Rather than use Triangular Distribution while doing Three Point Estimation you choose to use Beta

    Distribution.Based on your analysis and understanding you are confident that the project would be

    completed with a total cost of 108,000 $.You also estimate that a best case estimate would be 90000 $ while a

    worst case scenario would result in the costs incurred to shoot up to 138000 USD. What would the Three

    point Cost estimate be using Beta Distribution ?

    1.110000 $

    2.112000 $

    3.1100000 $

    4.140000 $

    Correct Answers are : 1

    Explanation : The correct answer is B.The question states we should use Three point estimate using Beta

    distribution. The formula for this estimation technique is 4a + b + c / 6 where a = Most Likely estimate , b =

    Estimate based on analysis of the Best case scenario and c = Estimate based on analysis of the Worst case

    scenario. So the Three point estimate using Beta distribution is (4 *108000) + 90000 + 138000 / 3 = 660000/6 =

    110000 $

    Question - 6

    You are a project manager and you are currently finalizing requirements with two stakeholders BUT both

    stakeholder have different views on requirements for the same project. How can you resolve the issue ?

  • 7/13/2019 PMP Mock Exam

    3/56

    1.look at why there is different view on requirements and discuss with both of them

    2.look at why there is different view on requirements and finalize which looks good to you

    3.ask your manager to deal with this

    4.finalize requirement which looks good to you

    Correct Answers are : 1

    Explanation : Best is "look at why there is different view on requirements and discuss with both of them and

    try to resolve the issue". Option is C is an example of avoidance. Option B and D is example of forcing.

    Question - 7

    You are managing a project. This project must satisfy industry standards in order to be accepted by the

    customer. You and your team have studied the requirements and have created a plan to implement the

    deliverables with the level of quality. This process is called ________.

    1.Quality Control

    2.Quality assurance

    3.Plan Quality

    4.All of the above

    Correct Answers are : 3

    Explanation : Plan Quality: Identifying the quality standards that are relevant to the project and determining

    how to meet them.

    Question - 8

    You have just completed developing the Schedule Network Diagram for a project that deals with building

    super sonic state of the art Jet planes.You have identified your critical path which includes building a wind

    tunnel.You see that in addition there is another path which deals with building the tail of the plane - whose

    duration is close to the critical path.You also notice considerable floats on the other paths.You now need to

    assign resources to the tasks - you have a few team members who are highly skilled and a team of resources

    who are relatively enexperienced.What would be the best course of action while assigning resources ?

    1.It is irrelevant which resources are assigned to tasks - resource skills and critical paths have nothing in

    common

    2.Assign all the skilled resources to building the wind tunnel which is the critical path - all other tasks can be

    ignored

    3.Assign the inexperienced staff to the task of building the wind tunnel - and assign the skilled task to all

    other tasks

    4.Assign one half of the skilled resources to the task of building the wind tunnel and the other half to

    building the tail and assign the less experienced staff to all the other tasks

    Correct Answers are : 4

    Explanation : Option 4 is the best option.Option 1 and 3 are just plain wrong - you should always ensure

    actvities on the critical path do not get delayed - so having the best equipped staff on critical path activities

    is important.While Option 2 is an optin - it cannot be the BEST choice since if we assign all the experienced

    staff on building the wind tunnel - the critical path activities are taken care of - but the question also states of

    a path which is near Critical - building of the tail.Not paying attention to this path by assignining

    inexperienced staff is not a good option.Amongst the choices option 4 is the best fit - where you are paying

  • 7/13/2019 PMP Mock Exam

    4/56

    attention to both the critical path and near critical path by assigning your best and most skilled or

    experienced resources to the activities on the Critical path and Near Critical Path.

    Question - 9

    You are in charge of a large software development project.As a part of the project schedule - it was okanned

    to complete two core components by the end of October.You are now in August and you realize that the

    project is falling behind schedule.You do a quick review and decide that the schedule can be met by adding

    additional staff to the activities on the critical path. This is an example of :

    1.Fast Tracking

    2.Resource Levelling

    3.Crashing

    4.Scope Creep

    Correct Answers are : 3

    Explanation : The correct answer is option 3 - As the project is falling behind schedule and deliveries cannot

    be impacted - the manager has chosen to add additional resources to activities on the critical path.This is an

    example of Crashing - NOTE Crashing may result in increasef risk and rework.

    Question - 10

    You have replaced a project manager on a project that is already in the execution phase.The project is

    behind schedule and you have been specifically been brought in to ensure the project meets its

    schedule.You decide to review the schedule network diagram created by the earlier project manager and you

    realize that the project is 3 weeks behind schedule. After reviewing the activities and the network diagram

    you decide to Crash the schedule.So this means you

    1.Decrease the scope of the project after discussing with the sponsors

    2.Add additional resources to the activities on the Critical path

    3.Perform activities in Parallel to decrease the schedule

    4.Discuss with the sponsors and explain how it is not going to be possible to meet the schedule

    Correct Answers are : 2

    Explanation : Option 2 is the correct answer.Crashing is a technique used to shorten the schedule by adding

    resources. Option A and D are clearly not correct - and Option C is really an example of Fast Tracking.

    Question - 11

    Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread

    evenly across all months. The project is now in the fourth month, the work is on schedule, but you have

    already spent $120,000 of the project budget. What is your COST Variance in this case?

    1.-$40,000

    2.$40,000

    3.$240,000

    4.$2300

    Correct Answers are : 1

  • 7/13/2019 PMP Mock Exam

    5/56

    Explanation : Cost Variance = Earn Value - Actual Cost Earn Value = (Total Cost/total project months) * total

    months completed = ($240,000 / 12)*4=$80,000 CV = $80,000 - $120,000 = -$40,000

    Question - 12

    Your company has won a project to build a school playground with specific toys and a sandpit.The school

    has mandated that the project be completed prior to start of the school after Holidays .You review the plan

    and see that the estimated completion date is nearly a month after the desired completion date.As resources

    are sparse you do not have the option to add additional resources.However you see that the sand pit work

    can start in parallel to the play kits being installed.Your analysis tells you that by performing these activities

    in parallel - the project would meet its schedule.This is an example of :

    1.Scope Creep

    2.Resource Levellings

    3.Crashing

    4.Fast Tracking

    Correct Answers are : 4

    Explanation : The correct answer is 4 - Crashing deals with adding additional resources which is not an

    option here.Crashing is a schedule compression technique by performing activities in parallel if they can be

    overlapped.NOTE Fast Tracking may result in increasef risk and rework.

    Question - 13

    An activity which is in critical path is delayed. What should you do ?

    1.Compress the schedule

    2.Scope cut

    3.Inform customer about delay

    4.Deliver uncompleted activity

    Correct Answers are : 1

    Explanation : A is the correct answer. Compress the schedule is the best option.

    Question - 14

    Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days. What is the

    PERT weighted average?

    1.6

    2.4

    3.6.3

    4.6.1

    Correct Answers are : 1

    Explanation : Optimistic = Co, most likely = Cm, Pessimistic = Cp. PERT weighted average = (Co + 4Cm +

    Cp)/6 = (3+4*6+9)/6 = 36/6 = 6

    Question - 15

  • 7/13/2019 PMP Mock Exam

    6/56

    Which plan describes when and how human resources will be brought onto, and taken off of, the project

    team?

    1.Scope management plan

    2.Risk management plan

    3.Staffing Management Plan

    4.All of the above

    Correct Answers are : 3

    Explanation : C is the correct answer. Staffing Management Plan - Describes when and how human

    resources will be brought onto, and taken off of, the project team.

    Question - 16

    You are project manager of a software project. Your team member want to technical change to a activity

    which will add more time to that activity. What should you do ?

    1.Check the activity is in critical path

    2.Allow team member to change the activity

    3.Report to senior management

    4.Ignore change in activities.

    Correct Answers are : 1

    Explanation : A is the correct answer. Check the activity is in critical path is the best option.

    Question - 17

    As a project manager of a project , you have just completed Schedule network diagram. What should you do

    NEXT time management activity?

    1.Estimate Activity Resources

    2.Sequence Activities

    3.Estimate Activity Durations

    4.Develop Schedule

    Correct Answers are : 1

    Explanation : A is the correct answer. Schedule network diagram is an output of Sequence Activities, NEXT

    process is Estimate Activity Resources.

    Question - 18

    Your project activity float is negative 10. What is your course of action ?

    1.add more resources

    2.ask more time to complete the project

    3.use less experienced team members

    4.Ignore It.

    Correct Answers are : 1

  • 7/13/2019 PMP Mock Exam

    7/56

    Explanation : A is the correct answer. negative activity float means your project is behind. Add more

    resource is best option.

    Question - 19

    You have been successfully completed a project.You have now been assigned a project which is midway

    into its execution.You have had to take this project due to non availability of the current project manager due

    to health.This is a complex project involving multiple contractors and teams at various geographical

    locations.You decide to look up the requirements of the types of reports and frequency of sending

    them.Where would you find this information?

    1.Project Management Plan

    2.Scope Management Plan

    3.Communciation Management Plan

    4.Stakeholder Analysis

    Correct Answers are : 3

    Explanation : The correct answer is Communication Management Plan.This Plan provides information such

    as frequency of communication , type of communication , who is responsible for communication.Hence this

    is the correct answer.

    Question - 20

    A data point in a control chart that requires investigation is called:

    1.a special cause

    2.a quality fault

    3.a rule of seven

    4.a rule of five

    Correct Answers are : 1

    Explanation : A data point in a control chart that requires investigation is called a special cause.

    Question - 21

    You are in charge of a project that deals with laying out a lavish 18 hole golf course.The project work is in

    progress.You also have a number of contractors working on the project.Being an experienced manager you

    know that communication is key to success of the project.You have identified that you have 10 stakeholders

    with whom you need to communicate.Due to some internal and external organizational changes at the client

    end three new stakeholders have been added with whom you need to communicate with.You also had to

    reduce one of the contractors with whom you were communicating.How many communication channels do

    you have now?

    1.66

    2.67

    3.68

    4.74

    Correct Answers are : 1

    Explanation : Originally you had 10 stakeholders to communciate with - so number of communication

  • 7/13/2019 PMP Mock Exam

    8/56

    channels are 10 * (10-1) /2 = 45.However the question states that 3 new stakeholders got added while 1

    stakeholder got reduced.So total number of stakeholders = 10 + 3 -1 = 12 So the total number of

    communciation channels are (12 * ( 12-1 )) /2 = 66 So the correct answer is option 1.

    Question - 22

    __________includes all activities designed to enhance the skills, knowledge, and capabilities of the project

    team.

    1.Training

    2.Ground Rule

    3.Reward and Recognition System

    4.Recognition System

    Correct Answers are : 1

    Explanation : A is the correct answer. Training: Includes all activities designed to enhance the skills,

    knowledge, and capabilities of the project team. Ground Rules: Ground rules establish clear expectations

    regarding acceptable behavior by project team members.

    Question - 23

    Some risks that are output of ________ will be the candidates for further study.

    1.Perform qualitative risk analysis

    2.Perform quantitative risk analysis

    3.Plan Risk Management

    4.Identify Risks

    Correct Answers are : 1

    Explanation : Some risks that are output of Qualitative Risk Analysis will be the candidates for further study

    during the Quantitative Risk Analysis.

    Question - 24

    Which of the following is NOT the input of Direct and Manage Project Execution process?

    1.Project Management Plan

    2.Approved Change Requests

    3.Enterprise Environmental Factors

    4.Project Charter

    Correct Answers are : 4

    Explanation : Project Charter is not an input of Direct and Manage Project Execution process. Inputs of

    Direct and Manage Project Execution process are: Project Management Plan, Enterprise Environmental

    Factors, Approved Change Requests, and Organizational Process Assets (PMBOK Page no, 104)

    Question - 25

    You are project manager of a project and you have decided to CRASH the project. Which of the following is

  • 7/13/2019 PMP Mock Exam

    9/56

    the most likely outcome of this ?

    1.increased cost

    2.added risk

    3.increased project time

    4.doing activities in parallel

    Correct Answers are : 1

    Explanation : A is the correct answer. CRASHING is reducing project time by expending additional

    resources. Therefore option A is true.

    Question - 26

    Changing the project plan to eliminate the risk and protect the project objectives is called ____________.

    1.Avoidance

    2.Transference

    3.Mitigation

    4.Share

    Correct Answers are : 1

    Explanation : Changing the project plan to eliminate the risk and protect the project objectives is called

    Avoidance.

    Question - 27

    Make-or-Buy Analysis is done in the_______.

    1.Plan Procurements

    2.Conduct Procurements

    3.Administer Procurements

    4.Close Procurements

    Correct Answers are : 1

    Explanation : Make-or-Buy Analysis is done in the Plan Procurements process.

    Question - 28

    Which of the following helps to determine the probability of completing the project?

    1.Monte Carlo Analysis

    2.Impact Analysis

    3.Qualitative Risk Analysis

    4.Quantitative Risk Analysis

    Correct Answers are : 1

    Explanation : Monte Carlo Analysis: A schedule risk assessment technique that performs a project

    simulation many times in order to calculate a distribution of likely results.

    Question - 29

  • 7/13/2019 PMP Mock Exam

    10/56

    You have an urgent requirement on your project and you hire a vendor to start the work immediately. What

    contract is needed now?

    1.Letter contract

    2.Fixed fee

    3.Incentive contract

    4.Fixed Budget

    Correct Answers are : 1

    Explanation : For an immediate work, a letter contract may be sufficient.

    Question - 30

    Work Performance Information is output of________.

    1.Define Scope

    2.Perform Integrated Change Control

    3.Direct and Manage Project Execution

    4.Monitor and Control Project Work

    Correct Answers are : 3

    Explanation : Work Performance Information is output of Direct and Manage Project Execution. (PMBOK

    page no, 115)

    Question - 31

    _________are similar to control chart without displayed limits.

    1.Run charts

    2.Pareto charts

    3.Ishikawa diagrams

    4.Histograms

    Correct Answers are : 1

    Explanation : Run chart is similar to control chart without displayed limits. PMBOK Page no 242.

    Question - 32

    SWOT analysis is done in _________.

    1.Perform Qualitative Risk Analysis

    2.Identify Risks

    3.Plan Risk Responses

    4.Plan Risk Management

    Correct Answers are : 2

    Explanation : SWOT analysis is done in Identify Risks process. (PMBOK page no 305.)

    Question - 33

  • 7/13/2019 PMP Mock Exam

    11/56

    Which of the following is NOT Tools and Techniques in Quantitative Risk Analysis?

    1.Expected Monetary Value Analysis

    2.Decision Tree Analysis

    3.Sensitivity Analysis

    4.Influence Diagram

    Correct Answers are : 4

    Explanation : Influence Diagram is a technique to identify risks.

    Question - 34

    Which estimating technique is most accurate?

    1.Bottom-up estimating

    2.Analogous estimating

    3.Parametric modeling

    4.None of the above

    Correct Answers are : 1

    Explanation : Bottom-up estimating: Estimating the cost of individual work items and then rolling up the

    costs to arrive at a project total is more accurate.

    Question - 35

    Performance appraisal, recruitment, retention, regulatory issues, and labor relations are generally used in

    the________ area.

    1.General management

    2.Administrative

    3.Project Management

    4.Accounting

    Correct Answers are : 1

    Explanation : Skills such as performance appraisal, recruitment, retention, regulatory issues and labor

    relations are generally considered more administrative than management oriented.

    Question - 36

    Probabilistic Analysis of a project, probability of achieving cost and time objectives and trends in

    Quantitative Risk Analysis results are done during _______.

    1.Perform Qualitative Risk Analysis

    2.Perform Quantitative Risk Analysis

    3.Plan Risk Management

    4.Identify Risks

    Correct Answers are : 2

    Explanation : Probabilistic analysis of a project, probability of achieving cost and time objectives and trends

    in Quantitative Risk Analysis results are done during Quantitative Risk Analysis.

  • 7/13/2019 PMP Mock Exam

    12/56

    Question - 37

    You are the project manager for the large Project. You are currently busy with approximating number of work

    periods required to complete individual activities with estimated resources. Which of the following inputs

    you need for this ?

    1.Activity List

    2.Activity resource requirements

    3.Resource Calendars

    4.All of the above

    Correct Answers are : 3

    Explanation : C is the correct answer. Approximating number of work periods required to complete individual

    activities with estimated resources is done in Estimate Activity Duration process. Activity List,Activity

    resource requirements and Resource Calendars are inputs of Estimate Activity Duration process. PMBOK

    Page no 177.

    Question - 38

    You are newly appointed as a project manager of an ongoing project. You want to see the role, authority,

    responsibility and competencies of all the resources working in the project. Which of the following document

    lists all the above information?

    1.Scope statement

    2.Project Charter

    3.Human Resource Plan

    4.WBS

    Correct Answers are : 3

    Explanation : C is the correct answer. Human Resource Plan lists role, authority, responsibility and

    competencies of all the resources working in the project. PMBOK Page no 253.

    Question - 39

    One activity will be delay three weeks and that will affect the project completion date. Who will approve the

    change ?

    1.Change control board

    2.project manager

    3.Senior management

    4.Team member

    Correct Answers are : 1

    Explanation : A is the correct answer. Change control board approve the change.

    Question - 40

    Cost benefit analysis is done in the ___________process:

  • 7/13/2019 PMP Mock Exam

    13/56

    1.Plan Quality

    2.Perform Quality Assurance

    3.Perform Quality Control

    4.All of the above

    Correct Answers are : 1

    Explanation : Cost benefit analysis is done in the Plan Quality process.

    Question - 41

    Which of the following are output of the Collect Requirements Process?

    1.Requirements Documentation

    2.Requirements Management Plan

    3.Requirements Tractability Matrix

    4.All of the above

    Correct Answers are : 4

    Explanation : The output of Collect Requirements Process are: requirements documentation (stakeholders

    needs), the requirements management plan (how the requirements will be analyzed and documents), and the

    requirements traceability matrix (tracking of requirements throughout the project).

    Question - 42

    In which of the quality management process, cause and effect diagram is used to illustrate how various

    factors might be linked to potential problems or effects?

    1.Plan Quality

    2.Perform Quality Assurance

    3.Perform Quality Control

    4.Quality

    Correct Answers are : 3

    Explanation : The cause and effect diagram is a tool and technique to perform Quality Control . PMBOK Page

    no 222.

    Question - 43

    You are a project manager of a large project and you are identifying some alternative techniques to generate

    different approaches to execute and perform the work of a project. You are doing it as a part of:

    1.Collect Requirements

    2.Control Scope

    3.Verify Scope

    4.Define Scope

    Correct Answers are : 4

    Explanation : This is call an Alternative Identification in the Define Scope process.

  • 7/13/2019 PMP Mock Exam

    14/56

    Question - 44

    At what part of the Procurement Management process does procurement negotiations happen?

    1.Plan Procurements

    2.Conduct Procurements

    3.Administer Procurements

    4.Close Procurements

    Correct Answers are : 2

    Explanation : The negotiations happen at the Conduct Procurements of the Procurement process.

    Question - 45

    Which type of contract has the highest risk for the seller?

    1.Reimbursed time

    2.Time and materials

    3.Fixed price

    4.Reimbursed cost

    Correct Answers are : 3

    Explanation : In Fixed price contract, the seller assumes the greatest risk because the price is fixed and not

    going to change. Fixed price- A fixed total price for a well-defined product may include incentives for

    meeting or exceeding selected project objectives.

    Question - 46

    Which of the following is NOT part of the Perform Quality Control process?

    1.fishbone diagram

    2.Quality audits

    3.Pareto Diagram

    4.Histogram

    Correct Answers are : 2

    Explanation : Quality audits are part of the Perform Quality Assurance process.

    Question - 47

    Who should be consulted when establishing communication requirements in addition to stakeholders?

    1.The customer

    2.The project manager

    3.The sponsor

    4.Management

    Correct Answers are : 2

    Explanation : The project manager should be consulted when establishing communication requirements in

    addition to stakeholders because project manager has very important role in establishing communication

    requirements.

  • 7/13/2019 PMP Mock Exam

    15/56

    Question - 48

    You are a project manager of a company and you are assigned to a project that has already decided to be

    outsourced. As a project manager, you need to organize a formal bid process and select the vendor for this

    project. You own stock in one of the vendor companies who also participated in the bidding process. What is

    the BEST course of action for you?

    1.Get the vendor company selected for the project.

    2.Keep the information to yourself.

    3.Tell your manager and remove yourself from the vendor selection committee.

    4.Ask other members of the selection committee to select your vendor company.

    Correct Answers are : 3

    Explanation : The best option is to tell your manager and remove yourself from the vendor selection

    committee.

    Question - 49

    Which of the following communication method is widely used to explain complex problems?

    1.Written

    2.Verbal

    3.Formal

    4.Non formal

    Correct Answers are : 1

    Explanation : Written is the best option.

    Question - 50

    You are the project manager and you have to choose the best project from available choices. Which of the

    following is the BEST choice?

    1.Benefit cost ratio (BCR) of project A is 2.5

    2.Benefit cost ratio (BCR) of project B is 2.1

    3.Benefit cost ratio (BCR) of project C is 0.6

    4.Benefit cost ratio (BCR) of project D is 1.5

    Correct Answers are : 1

    Explanation : Benefit cost ratio (BCR) : A ratio describing the relationship between the cost and benefits of a

    proposed project. A BCR less than 1 is unfavorable; the higher the BCR, the better.

    Question - 51

    You are project manager and need as many as inputs is possible in the initiation phase. Which of the

    following is the best source of information for your project?

    1.Historical Information

    2.WBS

  • 7/13/2019 PMP Mock Exam

    16/56

    3.Business Plans

    4.Project Closure Document

    Correct Answers are : 1

    Explanation : Historical information is the best input for the initiation phase. WBS is incorrect as the WBS

    would not be ready. Business is incorrect as business plans are not a likely input to the initiation process.

    Question - 52

    In which of the following contract types the seller's profit is limited?

    1.Cost-plus-percentage-cost contract

    2.Cost-plus-fixed-fee contract

    3.Firm Fixed price contract

    4.Fixed-price-incentive fee contract

    Correct Answers are : 2

    Explanation : Cost-plus-fixed-fee contract and Cost-plus-incentive-fee contract where seller's profit is limited

    Question - 53

    You have elected to use parametric modeling in your Estimate Costs for the project. Which one of the

    following is an example of parametric modeling?

    1.$120 per kg

    2.Historical information from a similar project

    3.Estimates built from bottom-up based on the WBS

    4.Estimates based on top-down budgeting

    Correct Answers are : 1

    Explanation : A is correct; $120 per ton is an example of parametric modeling. Parametric modeling: Using

    project characteristics (or parameters) in a mathematical model to predict costs (e.g., price per square foot).

    B is incorrect, as historical information is analogous, not parametric. C is incorrect; bottom-up estimating is

    not a parametric modeling. D is incorrect, top-down budgeting is related to analogous estimating .

    Question - 54

    When the performing organization lacks in-house staff to complete a project, the required services can be

    acquired from outside. This is called ________.

    1.Virtual Teams

    2.Acquisition

    3.Pre-Assignment

    4.All of the above

    Correct Answers are : 2

    Explanation : B is the correct answer. Acquisition: When the performing organization lacks the in house staff

    needed to complete the project, the required services can be acquired from outside sources.

  • 7/13/2019 PMP Mock Exam

    17/56

    Question - 55

    A project manager determines the number and types of tests and their impact on cost of quality. This task

    belongs to ___ process.

    1.Plan Quality

    2.Perform Quality Control

    3.Perform Quality Assurance

    4.Identify risk

    Correct Answers are : 1

    Explanation : Determining the number and types of tests and their impact on cost of quality is called Design

    of experiments which is done in Plan Quality process. PMBOK page no 228.

    Question - 56

    Control chart helps:

    1.determine if the process is "in control"

    2.how various elements of a system are interrelated

    3.show trends in a process over time

    4.shows the pattern of a relationship between two variables

    Correct Answers are : 1

    Explanation : Control Charts: Control charts are graphic display of the results over a time of a process. They

    are used to determine if the process is "in control".

    Question - 57

    You are a project manager for a project. While reviewing the cost estimates for the project, you notice that

    one of the cost estimates for an element in the WBS is 20% higher than the previous project for a very similar

    work. What should you do next?

    1.Accept the estimate.

    2.Ask the person responsible about the difference.

    3.Ignore it.

    4.Reduce the estimate.

    Correct Answers are : 2

    Explanation :

    Best option is to ask the person responsible about the difference and create the most accurate estimate that

    is practical.

    Question - 58

    Which of the following is a common problem in administrative closure?

    1.Completing a project charter

    2.Retaining resources to complete the project

    3.Completing a project plan

    4.Completing a QA plan

  • 7/13/2019 PMP Mock Exam

    18/56

    Correct Answers are : 2

    Explanation : The biggest problem is retaining team members until closure of the project.

    Question - 59

    A unilateral contract under which the seller is paid a preset amount per unit of service is called __________

    1.A cost reimbursable contract

    2.A lump sum contract

    3.A time and material contract

    4.A fixed price contract

    Correct Answers are : 3

    Explanation : A unilateral contract under which the seller is paid a preset amount per unit of service is called

    time and material contract.

    Question - 60

    Your project has a budget of $10,000 and is expect to last for 1 year, with the work and budget spread evenly

    across all months. Right now CPI is 0.8. What is Variance at Completion in this case?

    1.-$2,500

    2.$10,000

    3.$12,500

    4.$12,000

    Correct Answers are : 1

    Explanation : Variance at Completion = BAC - EAC Estimate at Completion (EAC) = BAC / CPI = $10,000 / .8 =

    $12,500 Variance at Completion = $10,000 - $12,500 = -$2,500

    Question - 61

    You are the project manager of a project which is scheduled to last for 18 months. You have elected to rent a

    piece of equipment for the duration of a project, even though you will need the equipment only for 6 months.

    The costs of the equipment rental per month are $120. This is an example of ___________.

    1.Fixed Costs

    2.Parametric Costs

    3.Variable Costs

    4.Parametric Budget

    Correct Answers are : 1

    Explanation : This is an example of Fixed Costs because $120 per month is fixed.

    Question - 62

    Three estimates are : Pessimistic (P) : 30 Most Likely (M) : 25 Optimistic (O) : 14 What is activity duration

    (PERT) ?

  • 7/13/2019 PMP Mock Exam

    19/56

    1.24

    2.20

    3.18

    4.32

    Correct Answers are : 1

    Explanation : A is the correct answer. Activity duration (PERT)= (P + 4M + O) / 6 then (30+4*25+14)/6 = 144/6 =

    24

    Question - 63

    If you are the project manager of a project and you changed the scope of a project by dropping some parts,

    you have ______________ the project.

    1.Rewritten

    2.Truncated

    3.De scoped

    4.Deleted

    Correct Answers are : 3

    Explanation : When you change the project plan by removing parts of the final deliverable, you have de-

    scoped the project.

    Question - 65

    ___________ is the process of performing the work defined in the project management plan to achieve the

    project's objectives.

    1.Define Scope

    2.Perform Integrated Change Control

    3.Direct and Manage Project Execution

    4.Monitor and Control Project Work

    Correct Answers are : 3

    Explanation : Direct and Manage Project Execution is the process of performing the work defined in the

    project management plan to achieve the project's objectives. (PMBOK page no, 114)

    Question - 66

    You are the project manager for the large Project. You are identifying external dependencies for the activities

    with management team. Identifying external dependencies are done in ______?

    1.Define Activities

    2.Sequence Activities

    3.Develop Schedule

    4.Control Schedule

    Correct Answers are : 2

    Explanation : B is the correct answer. Identifying external dependencies are done in Sequence Activities.

  • 7/13/2019 PMP Mock Exam

    20/56

    Question - 67

    You are the project manager and decided to outsource a part of the project to a vendor. You have offered a

    bonus to the vendor if the work is completed in two months. This is an example of _____________.

    1.project incentive

    2.project goal

    3.fixed price contract

    4.fixed budget

    Correct Answers are : 1

    Explanation : This is an example of project incentive.

    Question - 68

    Development activities of a software projects is depends on the third party vendor, who provides hardware

    for this activity. Is called ______.

    1.external dependencies

    2.internal dependencies

    3.Discretionary dependencies

    4.All of the above

    Correct Answers are : 1

    Explanation : A is the correct answer. external dependencies are usually outside of project team control.

    PMPBOK Page no 171.

    Question - 69

    You are the project manager of the MKTG Project. This project will last for 1 year and it has many

    stakeholders. How often should Identify Risks take place?

    1.Once at the beginning of the project

    2.Throughout the execution processes

    3.Throughout the QA processes

    4.Throughout the project

    Correct Answers are : 4

    Explanation : Identify Risks is an iterative process that should happen throughout the project life. Identify

    Risks is an iterative process, involving the project team, management team, stakeholders and subject matter

    experts.

    Question - 70

    Overtime associated with the execution effort of a project is estimated at 120 hours with probability 0.5, 250

    hours with probability 0.6, and 300 hours with probability 0.3. What is the monetary value of the amount of

    overtime?

    1.300 hours

  • 7/13/2019 PMP Mock Exam

    21/56

    2.670 hours

    3.250 hours

    4.100 hours

    Correct Answers are : 1

    Explanation : The Monetary Value of the amount of overtime is (120 x 0.5) + (250 x 0.6) + (300 x 0.3) = 300

    hours.

    Question - 71

    If you are the project manager of a project and you break down the WBS into smaller _______ to get detail so

    that you can construct a schedule.

    1.Work packages

    2.Section

    3.Issues

    4.Time

    Correct Answers are : 1

    Explanation : A is the correct answer. The work packages give you the detail you need to construct a

    schedule.

    Question - 72

    Which of the following tools are used in the quality plan?

    1.Quality Checklists

    2.Quality audits

    3.Histogram

    4.Process Analysis

    Correct Answers are : 1

    Explanation : Quality Checklists are used in the quality plan.

    Question - 73

    You are a project manager of a construction company. You want to know with whom you will be

    communicating during the project. Which of the below document you should refer to?

    1.Project Plan

    2.Scope Statement

    3.Statement of Work

    4.Project Charter

    Correct Answers are : 2

    Explanation : The project plan say what, when, and how much you will communicate. It also says with whom

    you will communicate during the project.

    Question - 74

  • 7/13/2019 PMP Mock Exam

    22/56

    You are the project manager for a project to create a new product for the marketing industry. You recently

    came to know that a competitor is also working on a similar project with an additional web-based tool, which

    your project does not offer. You initiate a change request to update your project. This is an example of:

    1.A change due to an external event

    2.A change due to an error and omission in the initiation phase

    3.A change due to an error or omission in the planning phase

    4.A change due to a legal issue

    Correct Answers are : 1

    Explanation : The change is requested to remain competitive with the competition an external event.

    Question - 75

    A project team member, on his own initiative, added a new tool which was not part of the project plan.

    However, the team member decided that the tool was necessary to increase productivity. The project team's

    experts were in agreement with the decision. This is an example of _________?

    1.Ineffective change control

    2.Control Costs

    3.Self led teams

    4.Value added change

    Correct Answers are : 1

    Explanation : The project team member did not follow the change management plan's method of

    incorporating changes into the scope. This is an example of Ineffective change control.

    Question - 76

    You are the project manager for the large Project. You have identified and documented relationship among

    the project activities and created project schedule network diagram. What is your NEXT step ?

    1.Define Activities

    2.Sequence Activities

    3.Develop Schedule

    4.Control Schedule

    Correct Answers are : 3

    Explanation : C is the correct answer. project schedule network diagram is input of Develop Schedule.

    PMBOK Page no 168.

    Question - 77

    You are a project manager and the project is to install ACs into hotel rooms. You did project cost and time

    estimates and informed the customer that the project estimates will be accurate if the requirements such as

    wooden coating are met. This is an example of which of the following?

    1.Risk

    2.Assumption

    3.Constraint

  • 7/13/2019 PMP Mock Exam

    23/56

    4.Budget analysis

    Correct Answers are : 2

    Explanation : This is an example of assumption because estimates provided will be accurate if the rooms

    meet the requirements like (wooden coated). A and C are incorrect because the scenario did not describe a

    risk or constraint.

    Question - 78

    Change Request is an input of _________.

    1.Define Scope

    2.Perform Integrated Change Control

    3.Direct and Manage Project Execution

    4.Monitor and Control Project Work

    Correct Answers are : 2

    Explanation : Change Request is an input of Perform Integrated Change Control. (PMBOK page no, 104)

    Question - 79

    If the project is terminated early, then the level and extent of completion should be documented. This is done

    as a part of:

    1.Collect Requirements

    2.Control Scope

    3.Verify Scope

    4.Define Scope

    Correct Answers are : 3

    Explanation : Verify Scope

    Question - 80

    You are the project manager and have been assigned a new project. You have a good relation with the

    sponsor and senior management. Your senior management and sponsor forcing you to start the project

    immediately. What is your response ?

    1.Start project immediately because your senior management is asking the same.

    2.Require a project charter be written and signed off on by all stakeholders before proceeding.

    3.Suggest that a scope statement be written.

    4.Suggest that a project plan should be written.

    Correct Answers are : 2

    Explanation : The project should be start with a project charter that authorizes the project to begin, assigns

    the project manager, and describes the project objectives and business need for the project.

    Question - 81

  • 7/13/2019 PMP Mock Exam

    24/56

    Estimating the number of work periods likely to be needed to complete each activity is called :

    1.Estimate Activity Resources

    2.Sequence Activities

    3.Estimate Activity Durations

    4.Define Activities

    Correct Answers are : 3

    Explanation : C is the correct answer. Estimating the number of work periods likely to be needed to complete

    each activity is called Estimate Activity Durations .

    Question - 82

    Which of the following is NOT Tools and Techniques in Monitor and Control Risks?

    1.Risk Audits

    2.Reserve Analysis

    3.Sensitivity Analysis

    4.Risk Reassessment

    Correct Answers are : 3

    Explanation : Sensitivity analysis is NOT Tools and Techniques in Monitor and Control Risks .

    Question - 83

    Starting a new task before finish the old one is an example of a __________ dependency.

    1.Start-to-finish

    2.Finish-to-start

    3.Start-to-start

    4.Finish-to-Finish

    Correct Answers are : 1

    Explanation : A is the correct answer. Start-to-finish An activity must start before the next activity can finish.

    Question - 84

    This project was originally scheduled for completion in 1 year but 2 years have already passed and even now

    the project is in execution phase. Which statement is TRUE about the project?

    1.It is a temporary project

    2.The requirements were added later, hence the delay

    3.A key resource has left the organization, hence the delay

    4.The company has a limited development license environment, hence the delay

    Correct Answers are : 1

    Explanation : Project is continuing to expand means it is temporary project. Other options can be achievable

    to complete the project if it is important for organization.

    Question - 85

  • 7/13/2019 PMP Mock Exam

    25/56

    You are the project manager for the large Project. You are identifying and documenting relationship among

    the project activities. This process is called ______?

    1.Define Activities

    2.Sequence Activities

    3.Develop Schedule

    4.Control Schedule

    Correct Answers are : 2

    Explanation : B is the correct answer. Sequence Activities - identifying and documenting relationship among

    the project activities. PMBOK Page no 167.

    Question - 86

    You are a project manager and now you are comparing proposals received from sellers. Comparing

    proposals received from sellers is done in _______ .

    1.Plan Procurements

    2.Conduct Procurements

    3.Administer Procurements

    4.Close Procurements

    Correct Answers are : 2

    Explanation : Comparing proposals received from sellers done in the Conduct Procurements.

    Question - 87

    During the project execution phase, one of the team member asked about his or her work. Which of the

    following document you will ask the person to refer?

    1.Work Breakdown Structure (WBS) dictionary

    2.Scope Statement

    3.Activity List

    4.Project Charter

    Correct Answers are : 1

    Explanation : The WBS dictionary defines each element in the WBS. Therefore, descriptions of the work

    packages are in the WBS dictionary.

    Question - 88

    Who is primarily responsible for creating design and test specifications?

    1.Quality Control

    2.Engineering

    3.Support

    4.Management

    Correct Answers are : 2

    Explanation : Engineering is primarily responsible for creating design and test specifications.

  • 7/13/2019 PMP Mock Exam

    26/56

    Question - 89

    Project Management Plan is an input to all of the following processes EXCEPT_________.

    1.Direct and Manage Project Execution process

    2.Perform Integrated Change Control

    3.Close Project or Phase

    4.Develop Project Charter

    Correct Answers are : 4

    Explanation : Project Management Plan is NOT an input to Develop Project Charter. (PMBOK page no, 104)

    Question - 90

    The market conditions are a part of the________.

    1.Enterprise environmental factors

    2.Project management concerns

    3.Organizational process assets

    4.Project Charter

    Correct Answers are : 1

    Explanation : The market conditions will influence all factors of procurement.

    Question - 91

    You are a project manager of a project. Till today you have actually completed $34,000 of work, but based on

    the cost plan it should be $50,000. What is percentage Schedule Variance (SV) in this case?

    1.-32%

    2.-16%

    3.32%

    4.10%

    Correct Answers are : 4

    Explanation : Schedule Variance (SV): Any difference between the scheduled completion of an activity and

    the actual completion of that activity. SV % = (EV - PV) / PV SV % = ($34,000 - $50,000) / $50,000 = -32%

    Question - 92

    Which is the least risky phase of a project?

    1.Planning

    2.Closing

    3.Execution

    4.Control

    Correct Answers are : 1

  • 7/13/2019 PMP Mock Exam

    27/56

    Explanation : The Planning phase is the phase with the least risk attached because you have not committed

    the major part of your project.

    Question - 93

    Which of the following project management process gets MOST of a project's budget expended?

    1.Project Executing

    2.Project Planning

    3.Project Closing

    4.Project Monitoring

    Correct Answers are : 1

    Explanation : Most of the resources are involved in the project executing process, therefore most of a

    project's budget are expended on this process.

    Question - 94

    In which of the following situation network diagram is better than bar chart ?

    1.to show inter dependencies between activities

    2.analysis of schedule progress

    3.analysis of WBS

    4.analysis of project plan

    Correct Answers are : 1

    Explanation : A is the correct answer. network diagram is best to show Interdependencies between activities.

    Question - 95

    You are a project manager of a company. You have been assigned as the project manager in the middle of

    the project. The customer is not happy with the performance of the project. What is the FIRST thing you

    should do?

    1.Talk to customer about the concerns.

    2.Try to achieve the performance.

    3.Ignore the customer.

    4.Leave the project and ask your manager to assign another project.

    Correct Answers are : 1

    Explanation : The best option is to talk to the customer about the concerns.

    Question - 96

    The purpose of a contract is to distribute a reasonable amount of ____________between the buyer and seller.

    1.Risk

    2.Responsibility

    3.Reward

    4.Quality

  • 7/13/2019 PMP Mock Exam

    28/56

    Correct Answers are : 1

    Explanation : A fair contract shares a reasonable amount of risk between the buyer and the seller.

    Question - 97

    If there are two people in the communication system, then how many communication channels will there be?

    1.1

    2.5

    3.8

    4.4

    Correct Answers are : 1

    Explanation : Number of communication channel will be calculated using formula n*(n-1)/2 where n is the

    number of people involved in the communication. Then Number of communication channel = 2(2-1)/2=2*1/2=1

    Question - 98

    A project manager has created a document and wants some of the team member should have read access

    and some of them should have write access also. The project manager should create __________.

    1.Configuration Management System

    2.Project Management Information System

    3.Project Management System

    4.Control Management System

    Correct Answers are : 1

    Explanation : Configuration Management System addresses controlling documents.

    Question - 99

    Teamwork is a critical factor for project success. Who is responsible to create an environment that facilitates

    teamwork?

    1.Team lead

    2.Team members

    3.Project Manager

    4.Sponsor

    Correct Answers are : 3

    Explanation : C is the correct answer. Project Manager is responsible to create an environment that

    facilitates teamwork. PMBOK Page no 260.

    Question - 100

    In the quality management process, which of the following is not an attribute of the cost of non-

    conformance?

    1.Rework

  • 7/13/2019 PMP Mock Exam

    29/56

    2.Safety measures

    3.Downtime

    4.Uptime

    Correct Answers are : 2

    Explanation : Safety measures are not an attribute of the cost of nonconformance.

    Question - 101

    You are the project manager for the Project. You are updating the WBS during Define Activities, are often

    called ________?

    1.Refinements

    2.Updates

    3.Activities

    4.Supporting detail

    Correct Answers are : 1

    Explanation : A is the correct answer. updating the WBS during Define Activities, are often called

    Refinements. It occurs with riskier projects.

    Question - 102

    You are the project manager of a marketing project. You want a vendor to offer you one price to do all the

    detailed work. Which type of document are you looking for?

    1.IFB

    2.Proposal

    3.RFI

    4.RFP

    Correct Answers are : 1

    Explanation : An IFB is a sealed document that lists the seller's price to complete the detailed work.

    Question - 103

    Which of the following document justify the project - whether the project is worth or not?

    1.Business Case

    2.Project Charter

    3.Project Management plan

    4.Scope statement

    Correct Answers are : 1

    Explanation : Business Case contains business need and cost-benefit analysis. Business Case document

    justify the project - whether the project is worth or not. PMBOK page no , 106

    Question - 104

  • 7/13/2019 PMP Mock Exam

    30/56

    If project manager can approve the changes, this is still part of the ___________.

    1.Project Plan

    2.Change Control System

    3.Charter

    4.Scope Statement

    Correct Answers are : 2

    Explanation : Any change requests must go through review process, and so need to be part of Change

    Control System.

    Question - 105

    A project team with members located in the India, the US, and the UK would be called a ___________. They

    don't spent time meeting face to face.

    1.Virtual team

    2.Scattered team

    3.Universal team

    4.None of the above

    Correct Answers are : 1

    Explanation : A is the correct answer. Virtual Teams: Virtual teams can be defined as groups of people with a

    shared goal, who fulfill their roles with little or no time spent meeting face to face.

    Question - 106

    You are a project manager of MKTG project. The customers of the project have requested additions to the

    project scope. You have to do additional risk planning and need to add it to the project schedule. Why is so?

    1.Risk planning should always occur whenever the scope is adjusted.

    2.Risk planning should only occur at the project manager's discretion.

    3.Risk planning does not need to happen at every change in the project.

    4.All of the above

    Correct Answers are : 1

    Explanation : Risk Planning should always occur whenever the scope is change and adjusted.

    Question - 107

    You are a project manager of a company and your project is currently in execution phase. The customer has

    requested you for additional work. This work will affect the budget, but not the schedule of the project. What

    should you do next?

    1.Add the additional requirements to the project plan.

    2.Ignore the request.

    3.Explain the change procedure and ask to submit a request for change.

    4.Discuss with the project team about the change.

    Correct Answers are : 3

    Explanation :

  • 7/13/2019 PMP Mock Exam

    31/56

    Explain the change procedure and ask to submit a request for change is the best choice.

    Question - 108

    Comparing target dates with the actual or forecast start and finish dates is called :

    1.Variance Analysis

    2.Earned Value

    3.Progress Reporting

    4.Crashing

    Correct Answers are : 1

    Explanation : A is the correct answer. Variance Analysis : Comparing target dates with the actual or forecast

    start and finish dates.

    Question - 109

    You are the project manager and are considering recommending a project that costs $210,000; expected

    inflows are $5,000 per month for the first three years and then $6,000 per month thereafter. What is the

    payback period?

    1.41 months

    2.36 months

    3.45 months

    4.21 months

    Correct Answers are : 1

    Explanation : Payback period : The number of time periods required until inflows equal, or exceed, costs.

    Total inflows for first three years is 36 months * $5000 = $180,000. Money left = $210,000 - $180,000 = $30,000.

    Months need for $30,000 is ($30,000/$6,000)=5 months Total payback period = 36 + 5 = 41 months.

    Question - 110

    A risk is ____________ occurrence that has a positive or a negative effect on a project .

    1.Known

    2.Uncertain

    3.Known

    4.Potential

    Correct Answers are : 2

    Explanation : Risks are not planned, they are left to chance.

    Question - 111

    The OBS (Organization Breakdown Structure), WBS, and RBS (Resource Breakdown Structure) are all

    examples of ________.

    1.Control charts

    2.Hierarchical charts

  • 7/13/2019 PMP Mock Exam

    32/56

    3.Project standard

    4.Run chart

    Correct Answers are : 2

    Explanation : B is the correct answer. The OBS (Organization Breakdown Structure), WBS, and RBS

    (Resource Breakdown Structure) are all examples of Hierarchical charts.

    Question - 112

    Project Performance Appraisal is part of the:

    1.Acquire Project Team

    2.Develop Project Team

    3.Develop Human Resource Plan

    4.Manage Project Team

    Correct Answers are : 4

    Explanation : D is the correct answer. Project Performance Appraisal is part of the Manage Project Team.

    Question - 113

    A project has three critical path. How this affects the project ?

    1.It increased project risk.

    2.It need more resources.

    3.It need more time.

    4.It costs more.

    Correct Answers are : 1

    Explanation : A is the correct answer. It increased project risk.

    Question - 114

    What is the purpose of a status meeting?

    1.Exchange information about the project.

    2.Get the status from each team member

    3.Review of the activities

    4.Create status report

    Correct Answers are : 1

    Explanation : Best option is exchange information about the project.

    Question - 115

    Your company policy allow to gift exchange with customer within certain limit. By mistake, you have given a

    gift to the customer's representative already which is beyond the limit mentioned in your company policy.

    What should you do?

    1.Forget it and don't tell anyone.

  • 7/13/2019 PMP Mock Exam

    33/56

    2.Contact your company's senior management and ask for assistance.

    3.Ask your customer to return the gift.

    4.Ask your customer to give you a gift which has the same cost

    Correct Answers are : 2

    Explanation :

    Best option is to contact your company's senior management and ask for assistance.

    Question - 116

    You are a project manager of a project and want to report the actual project result and the planned status.

    You should use?

    1.Forecasting report

    2.Trend reports

    3.Status report

    4.Variance report

    Correct Answers are : 4

    Explanation : variance report: An actual project result and planned status of a project.

    Question - 117

    Which of the following is NOT the activity in Define Activities ?

    1.Decomposition

    2.An activity list from a previous project

    3.Progressive elaboration planning

    4.Create project charter

    Correct Answers are : 4

    Explanation : D is the correct answer. Create project charter is activity in initiation phase.

    Question - 118

    Make-or-buy decisions measure the cost of both options. What are these two options?

    1.Direct, Indirect

    2.Tactical, Strategic

    3.Management, Project

    4.Direct,Management

    Correct Answers are : 1

    Explanation : Make-or-buy decisions measure the cost of both options. When doing this analysis, it should

    include both direct and indirect costs so that the final decision is based on comparisons that are equal.

    Question - 119

    An organization's quality policy should come from the_________.

  • 7/13/2019 PMP Mock Exam

    34/56

    1.Project manager

    2.Top management

    3.Customers

    4.All of the above

    Correct Answers are : 2

    Explanation : An organization's quality policy should come from the top management.

    Question - 120

    You are project manager of a software project. You have just analyzed activity sequences, durations,

    resource requirements , schedule constraints and created project schedule. The above task belongs to

    which process?

    1.Define Activities

    2.Sequence Activities

    3.Develop Schedule

    4.Control Schedule

    Correct Answers are : 3

    Explanation : C is the correct answer. analyzing activity sequences, durations, resource requirements ,

    schedule constraints and created project schedule is belongs to Develop Schedule process.

    Question - 121

    All of the following are inputs of Perform Qualitative Risk Analysis EXCEPT ________.

    1.Risk Register

    2.Project Scope Statement

    3.Risk Management Plan

    4.Stakeholder Register

    Correct Answers are : 4

    Explanation : Stakeholder Register is input of Identify Risks.

    Question - 122

    You were the project manager of X company for a long time, and had done lots of project management

    practices. Recently, you have joined another company Y and assigned to a project. You should _________.

    1.Use the forms of company Y

    2.Use the forms of company X and instruct about the good project management practices

    3.Talk to change control board

    4.Use the forms of company Y and instruct about the good project management practices

    Correct Answers are : 4

    Explanation : The best option is to use the forms of company Y and instruct about the good project

    management practices.

  • 7/13/2019 PMP Mock Exam

    35/56

    Question - 123

    If a project has an 80% chance of activity will take 2 weeks or less. what is the probability of the event?

    1.75%

    2.65%

    3.50%

    4.20%

    Correct Answers are : 4

    Explanation : 20% probability of exceeding 2 weeks - 80% chance of activity will take 2 weeks or less

    Question - 124

    Risk Probability and Impact Assessment, and Risk Categorization are done during ________.

    1.Perform Qualitative Risk Analysis

    2.Perform Quantitative Risk Analysis

    3.Plan Risk Management

    4.Identify Risks

    Correct Answers are : 1

    Explanation : Risk Probability and Impact Assessment, and Risk Categorization are done during Qualitative

    Risk Analysis.

    Question - 125

    The ___________ shows departments or units of the organization and is not organized the deliverables.

    1.OBS

    2.WBS

    3.RBS

    4.Scope statement

    Correct Answers are : 1

    Explanation : A is the correct answer. OBS(Organization Breakdown Structure) shows departments or units

    of the organization and is not organized the deliverables. OBS(Organization Breakdown Structure) shows the

    organization's units and departments as a top-down graph.

    Question - 126

    The buyer and seller are bound by a________.

    1.Contract

    2.Responsibilities

    3.WBS

    4.Identification

    Correct Answers are : 1

    Explanation : The buyer and seller are bound by a contract.

  • 7/13/2019 PMP Mock Exam

    36/56

    Question - 127

    The Scope Statement does not provide___________?

    1.Project Justification

    2.Project Product

    3.Project Manager Authority

    4.Project Objective

    Correct Answers are : 3

    Explanation : The project charter provides the project manager with authority.

    Question - 128

    You are a project manager of a company and you have been assigned to a project. You are now comparing

    actual project performance against project management plan. This belongs to which process?

    1.Define Scope

    2.Perform Integrated Change Control

    3.Direct and Manage Project Execution

    4.Monitor and Control Project Work

    Correct Answers are : 4

    Explanation : Comparing actual project performance against project management plan belongs to Monitor

    and Control Project Work process.

    Question - 129

    As a project manager of a project , you have just completed Schedule network diagram. Which of the

    following time management activity you have completed?

    1.Estimate Activity Resources

    2.Sequence Activities

    3.Estimate Activity Durations

    4.Develop Schedule

    Correct Answers are : 2

    Explanation : B is the correct answer. Schedule network diagram is an output of Sequence Activities.

    Question - 130

    Comparing your project with actual or planned project practices to generate ideas for improvement is called:

    1.Benchmarking

    2.Benefit/Cost analysis

    3.Quality audits

    4.Process Analysis

    Correct Answers are : 1

  • 7/13/2019 PMP Mock Exam

    37/56

    Explanation : Comparing your project with actual or planned project practices to generate ideas for

    improvement is called Benchmarking.

    Question - 131

    You are a project manager of a pharmaceutical company. A new pharmaceutical regulation is passed that

    changes your project scope. For the project to be in accordance with the new regulation, what should be

    your next action?

    1.Present the change to the Change Control Board (CCB)

    2.Notify Management

    3.Prepare a new baseline to reflect the changes

    4.No need to do anything

    Correct Answers are : 1

    Explanation : You must present the change to the Change Control Board (CCB) for new changes.

    Question - 132

    A project manager has created a document and wants to track the changes made in the document. The

    project manager should create _______.

    1.Configuration Management System

    2.Project Management Information System

    3.Project Management System

    4.Control Management System

    Correct Answers are : 4

    Explanation : Control Management System tracks the changes.

    Question - 133

    Your project has a budget of $10,000 and is expect to last for 1 year, with the work and budget spread evenly

    across all months. Right now CPI is 0.8. What is Estimate at Completion (EAC) in this case?

    1.$12,500

    2.$10,000

    3.2.5

    4.3.0

    Correct Answers are : 1

    Explanation : Estimate at Completion (EAC) = BAC / CPI = $10,000 / .8 = $12,500

    Question - 134

    You are a project manager of a Project. Which of the following techniques will you use to create the Risk

    Management Plan?

    1.Planning Meetings

    2.Status Meetings

  • 7/13/2019 PMP Mock Exam

    38/56

    3.Variance Meetings

    4.Risk Tolerance

    Correct Answers are : 1

    Explanation : Planning meetings are used to create the Risk Management plan. Planning Meetings and

    Analysis: Attendees are the PM, leadership team, key stakeholders and those in the organization responsible

    to manage project risks.

    Question - 135

    The Pareto chart helps:

    1.Focus on critical issues to improve quality.

    2.Determine how various factors are linked to potential problems

    3.Determine whether or not process is stable and within set limits.

    4.Focus on root cause analysis

    Correct Answers are : 1

    Explanation : Pareto chart: Focus on critical issues to improve quality Fishbone diagram/Ishikawa:

    Determines how various factors linked to potential problems or effects, root cause Control chart: Determines

    whether or not process is stable and within set limits .

    Question - 136

    You are a project manager of a company. You are taking over a project during the planning process, and you

    discovered that many individuals have signed the project charter. Which of the following should be areas of

    concern for you?

    1.Who will be a member of the change control board?

    2.Who are the stakeholders for the project?

    3.Need to spend more time on configuration management.

    4.Determining the reporting structure.

    Correct Answers are : 3

    Explanation : Because of many individual signed in the project charter, areas concerned with this project are

    many. You should be concern with communications requirements, competing needs and requirements

    impacting your efforts on configuration management.

    Question - 137

    If a customer requests for additional work that is not in the contract, then what type of communication the

    customer should use?

    1.Formal Written

    2.Verbal

    3.Informal Verbal

    4.Noise

    Correct Answers are : 1

    Explanation : The formal written is the best for this type of request.

  • 7/13/2019 PMP Mock Exam

    39/56

    Question - 138

    You are the project manager of a new project and you have collected the necessary input information and

    delivered the project charter to the stakeholders. What should you do next?

    1.Get the project charter signed.

    2.Start the initial project planning process.

    3.Develop the project scope statement.

    4.Start to create project plan

    Correct Answers are : 1

    Explanation : After delivered the project charter to the stakeholders, First thing you have to do get the

    project charter signed.. Project charter is the only authorized document to start project.

    Question - 139

    3 sigma is equal to ______ percentage of fall between two control limits.

    1.99.99%

    2.99.73%

    3.95.46%

    4.68.26%

    Correct Answers are : 2

    Explanation : memorize 3 sigma = 95.73% 1 sigma = 68.26% 2 sigma = 95.46% 6 sigma = 99.99%

    Question - 140

    The project quality policy should be written by ________.

    1.Project team

    2.Customer

    3.Management

    4.Accounting

    Correct Answers are : 1

    Explanation : The project team, led by the project manager, must write the quality policy for each project.

    Question - 141

    All of the following are examples of Acquire Project Team EXCEPT:

    1.Negotiations

    2.Acquisition

    3.Pre-assignments

    4.Training

    Correct Answers are : 4

  • 7/13/2019 PMP Mock Exam

    40/56

    Explanation : D is the correct answer. Training is part of Develop Project Team, others are part of Acquire

    Project Team. PMBOK Page no 248.

    Question - 142

    Which of the following chart shows position and relationships in top-down format?

    1.Hierarchical-type chart

    2.Matrix-based charts

    3.Text-Oriented format

    4.All of the above

    Correct Answers are : 1

    Explanation : A is the correct answer. Hierarchical-type chart shows position and relationships in top-down

    format. PMBOK Page no 253.

    Question - 143

    Which of the following document can be used to guide all the work in both project executing and project

    monitoring and controlling phase of a project?

    1.Project Management Plan

    2.Project Risk Plan

    3.Project QA Plan

    4.Project Charter

    Correct Answers are : 1

    Explanation : Project Management plan can be used to guide all the work in both project executing and

    project monitoring and controlling phase of a project.

    Question - 144

    Which of the following is NOT an example of Cost of Conformance?

    1.Rework

    2.Testing

    3.Equipment

    4.Training

    Correct Answers are : 1

    Explanation : Rework is part of Cost of Nonconformance. Others are part of Cost of Conformance. PMBOK

    Page no 226.

    Question - 145

    Budget forecasts are inputs of ___________.

    1.Identify Stakeholders

    2.Plan communications

    3.Manage stakeholder expectations

  • 7/13/2019 PMP Mock Exam

    41/56

    4.Reports performance

    Correct Answers are : 4

    Explanation : Budget forecasts are inputs of Reports performance. PMBOK page no 275.

    Question - 146

    You are a project manager of a construction company. You want to manage the variance between what was

    planned and what actually occurred. Which of the following methodology you should use?

    1.Earned Value Management (EVM)

    2.Earned Value (EV)

    3.Planned Value

    4.Accounting

    Correct Answers are : 1

    Explanation : There could be confusion between Option A and Option B. Earned Value Management (EVM) is

    the methodology and Earned Value (EV) is the technique. And so Option A is true.

    Question - 147

    You are a project manager of a company and you are assigned to a project that has already been decided to

    out source. As a project manager, you need to organize a formal bid process and select the vendor for this

    project. Your senior management is forcing you to select a vendor which has good relation with your senior

    management. What is the BEST course of action for you?

    1.Follow the formal bid process, and show the senior management about why the favored vendor is or is not

    the best choice.

    2.Report to legal department of your company.

    3.Report to your Manager about this.

    4.Get a written permission from your senior management to bypass the formal bid process.

    Correct Answers are : 1

    Explanation : The best option is to follow the formal bid process, and show the senior management about

    why the favored vendor is or is not the best choice.

    Question - 148

    What is the purpose of fishbone diagram?

    1.To illustrate how various factors might be linked to potential problems or effects

    2.Are used to determine if the process are in control

    3.Show trends in a process over time

    4.Shows the pattern of relationship between two variables

    Correct Answers are : 1

    Explanation : Fishbone diagram : To illustrate how various factors might be linked to potential problems or

    effects.

  • 7/13/2019 PMP Mock Exam

    42/56

    Question - 149

    Which of the following tool help you determine the most common cause of problems in a process by number

    ?

    1.Status Reports

    2.Pareto Charts

    3.Ishikawa Diagrams

    4.Histogram

    Correct Answers are : 4

    Explanation : Histogram: ordered by frequency of occurrence, that shows how many results were generated

    by type or category of identified cause. PMBOK Page no 241.

    Question - 150

    As a project manager it is important to collect project records at the end of the project. What is the use of

    "collect project records"?

    1.Recall what happened on the project, good or bad.

    2.Recall decisions made on the project.

    3.To see cost decisions.

    4.To support the risks on the project.

    Correct Answers are : 1

    Explanation : The best use of "collect project records" is to recall what happened on the project, good or

    bad.

    Question - 151

    You are the project manager of a large project. Your project sponsor and management want portions of the

    project to be outsourced and you have been given the responsibility to outsource. The project sponsor and

    management have approved you to outsource portions of the project. Who must ensure that all of the project

    work is authorized, contracted properly, and funded?

    1.Project sponsor

    2.Management

    3.Vendor

    4.Project Manager

    Correct Answers are : 4

    Explanation : Project manager has the responsibility to ensure that the project work is authorized,

    contracted, and funded.

    Question - 152

    You area project manager of a project and have done risk response plan. What should you do NEXT?

    1.Update Project Management Plan

    2.Update Risk Identification Check list

    3.Root causes of risks

  • 7/13/2019 PMP Mock Exam

    43/56

    4.Corrective action

    Correct Answers are : 1

    Explanation : Update Project Management Plan is an output of risk response plan.

    Question - 153

    Performance Report is input of the:

    1.Acquire Project Team

    2.Develop Project Team

    3.Develop Human Resource Plan

    4.Manage Project Team

    Correct Answers are : 4

    Explanation : D is the correct answer. Performance Report is input of the Manage Project Team.

    Question - 154

    You are a project manager of a company and you have been assigned to take over managing a project that

    should have been 60 percent complete according to the schedule. After evaluation, you discover that the

    project is running far behind schedule, and that the project will probably take double the time originally

    estimated by the previous project manager. However, the sponsor has been told that the project is on

    schedule. What is the BEST course of action you will take?

    1.Add new resource to the project and complete the project on schedule.

    2.Show your evaluation to sponsor.

    3.Ask your senior manager to deal with this.

    4.Turn the project back to the previous project manager.

    Correct Answers are : 2

    Explanation : You can't turn the project back to the previous project manager because he or she may be

    busy with other project. The best option is to show your evaluation to sponsor.

    Question - 155

    The Create Procurement document is done in the_______.

    1.Plan Procurements

    2.Conduct Procurements

    3.Administer Procurements

    4.Close Procurements

    Correct Answers are : 1

    Explanation : The Create Procurement document is done in the Plan Procurements process.

    Question - 156

    The ___________ is used to document changes that occur during a project?

  • 7/13/2019 PMP Mock Exam

    44/56

    1.Issue Log

    2.Change Log

    3.Project Management Plan

    4.Scope statement

    Correct Answers are : 2

    Explanation : The Change Log is used to document changes that occur during a project. PMBOK page no

    294.

    Question - 157

    Finding out all people or organizations impacted by the project is called_________.

    1.Identify Stakeholders

    2.Plan communications

    3.Manage stakeholder expectations

    4.Reports performance

    Correct Answers are : 1

    Explanation : Finding out all people or organizations impacted by the project is called Identify Stakeholders.

    PMBOK page no 277.

    Question - 158

    You are the project manager of a company and currently doing strategic planning with senior management.

    What is the best reason for doing strategic planning?

    1.To determine which projects will be sponsored in order to achieve the organizational goals

    2.To determine the project resources

    3.To determine the project deliverables

    4.To determine the functional activities

    Correct Answers are : 1

    Explanation : The strategic planning conducted by an organization's management determines which projects

    will be sponsored in order to achieve the organizational goals.

    Question - 159

    You are the project manager of a Project. Your project will cost your organization $50,000 to complete over

    the next 3 months. Once the project is completed, the deliverables will let the company earn $5000 per

    month. What is the time to recover the costs of the project?

    1.10 Months

    2.1 Year

    3.2 Years

    4.3 Years

    Correct Answers are : 1

    Explanation : This is calculated by dividing the ROI of $5000 per month into the project cost. 50000/5000 = 10

    months

  • 7/13/2019 PMP Mock Exam

    45/56

    Question - 160

    The line in the middle of a control chart is called:

    1.mean

    2.rule of seven

    3.rule of five

    4.specification limit

    Correct Answers are : 1

    Explanation : The line in the middle of a control chart is called mean.

    Question - 161

    You are a project manager of a project. How you determine whether it is better to make a product or buy a

    product?

    1.Decision Tree Analysis

    2.ROI Analysis

    3.Ishikawa Diagram

    4.None of the above

    Correct Answers are : 1

    Explanation : A Decision Tree model can separate the pros and cons of buying product versus building

    product. Ishikawa Diagram shows cause and effect, not pros and cons.

    Question - 162

    You are a project manager and you are working for a large project with more than hundreds of

    stakeholders.Which of the following is the BEST course of action you are going to take ?

    1.Consider needs of all stakeholders.

    2.Consider needs of important stakeholders.

    3.Eliminate some of them.

    4.Ask your manager to manage the stakeholders.

    Correct Answers are : 1

    Explanation : Consider needs of all stakeholders is the best choice.

    Question - 163

    You are working in an organization where all the employees are divided into groups by specialty such as

    sales, support and engineering. In which type of organization you are working in ?

    1.Functional

    2.Strong matrix

    3.Weak matrix

    4.Tight Matrix

  • 7/13/2019 PMP Mock Exam

    46/56

    Correct Answers are : 1

    Explanation : In a functional organization, all employees are divided into groups such as sales, support and

    engineering. Projects in a functional organization generally only involve one department.

    Question - 164

    Which of the following is a part of the Project Scope Management?

    1.Verify Scope

    2.Collect Requirements

    3.Control Scope

    4.All of the above

    Correct Answers are : 4

    Explanation : Verify Scope, Collect Requirements and Control Scope are all part of the Project Scope

    Management.

    Question - 165

    ___________ is a group of process required to purchase or acquire products, services, or results needed

    from outside the project team to perform the work.

    1.Procurement Management

    2.Planning Management

    3.Scope Management

    4.Control Management

    Correct Answers are : 1

    Explanation : Procurement Management is a groups of processes required to to purchase or acquire the

    products, services, or results needed from outside the project team to perform the work.

    Question - 166

    You have just started a project. The project team member reported that 20 percent of the project is done. You

    agree with their completion status, but do not change any of the progress in your report to the customer.

    This is an example of which one of the following?

    1.0/100 Rule

    2.50/50 Rule

    3.Percent Complete Rule

    4.20/20 rule

    Correct Answers are : 1

    Explanation : The 0/100 Rule allows for zero percent credit on an activity until it is 100 percent complete. B is

    wrong (50/50 rule): 50 percent completion when the work begins and 50 percent when the work is completed.

    Question - 167

    During the project execution phase, a risk is found which was not included in the Risk Register. What should

  • 7/13/2019 PMP Mock Exam

    47/56

    you do?

    1.Ask senior management to deal with this.

    2.Keep with yourself.

    3.Find workaround.

    4.Re-evaluate Risk Management process.

    Correct Answers are : 3

    Explanation : The best option is to find a workaround and solve the issue.

    Question - 168

    You are the project manager of a global project having team members in the US and India. The client has a

    budget not exceeding $12 million. Due to global concerns, the final budget must be in the U.S. dollars. This is

    an example of which of the following?

    1.Internationalization

    2.Budget constraint

    3.Management constraint

    4.Technical constraint

    Correct Answers are : 2

    Explanation : This is an example of a budget constraint. The budget must not exceed $12 million.

    Question - 169

    Your company has been hired to configure software in 500 computers. All computers need equal time to

    configure. The contract for the project is set at a fixed cost, and the incentive based on how fast the project

    work is going to be completed. Management has requested that you study the work method to determine a

    faster, less costly, and a better method to complete the project. This scenario is an example of _________.

    1.Time Constraint

    2.Schedule Constraint

    3.Value Analysis

    4.Learning Curve

    Correct Answers are : 3

    Explanation : Value Analysis is a systematic approach to find less costly ways to complete the same work. A

    and B are incorrect, as this situation does not describe a specific time or cost constraint. D is incorrect: the

    learning curve happens as the project team completes the work.

    Question - 170

    A Heuristics is best described as :

    1.thumb rule.

    2.activity diagram.

    3.workaround.

    4.control tool.

  • 7/13/2019 PMP Mock Exam

    48/56

    Correct Answers are : 1

    Explanation : A is the correct answer. Heuristics is thumb rule. Examples are cost per square feet etc.

    Question - 171

    Project X has a payback period of 26 months. Project Y has a cost of $500,000, with expected cash inflows of

    $200,000 the first year and $50,000 per quarter after that. Which project should you recommend?

    1.Project X because of lower payback period.

    2.Project Y because of higher payback period.

    3.Project Y because of payback period 25.

    4.Project Y because of payback period 30.

    Correct Answers are : 1

    Explanation : Project Y has a cost of $500,000. After 1 year r