PMP Lecture 5

download PMP Lecture 5

of 26

Transcript of PMP Lecture 5

  • 7/25/2019 PMP Lecture 5

    1/26

    AUC TechnologiesConsulting | Development | Mentoring | Training

    Project Management With PMP Exam Preparation

  • 7/25/2019 PMP Lecture 5

    2/26

    Agenda

    Define Activity

    Sequence Activity

    Estimate Activity Resource

    Develop Human Resource Plan

  • 7/25/2019 PMP Lecture 5

    3/26

    Importance of Project Schedules

    Managers often cite delivering projects on time as one of their

    biggest challenges

    50% of IT projects were challenged in the 2003 CHAOS

    study, and their average time overrun increased to 82% from

    a low of 63% in 2000

    Schedule issues are the main reason for conflicts on projects,

    especially during the second half of projects

    Time has the least amount of flexibility; it passes no matter

    what happens on a project

  • 7/25/2019 PMP Lecture 5

    4/26

    Define Activity

    Define Activity involves developing a more detailed WBS and

    supporting explanations to understand all the work to be done

    so you can develop realistic cost and duration estimates

    Identifying the specific schedule activities that need to be

    performed to produce the various project deliverables.

  • 7/25/2019 PMP Lecture 5

    5/26

    Define Activity

    1.Scope baseline

    2.EnterpriseEnvironmentalFactors

    3.Organizational

    process assets

    1. Decomposition

    2. Templates

    3. Rolling wave

    planning

    4. Expert Judgment

    1. Activity List

    2. Activity

    attributes

    3. Milestone list

    InputOutput

    Tools

  • 7/25/2019 PMP Lecture 5

    6/26

    Activity Lists and Attributes

    An activity list is a tabulation of activities to be included on a

    project schedule that includes

    the activity name

    an activity identifier or number

    a brief description of the activity

    Activity attributes provide more information such as

    predecessors, successors, logical relationships, leads and

    lags, resource requirements, constraints, imposed dates, and

    assumptions related to the activity

  • 7/25/2019 PMP Lecture 5

    7/26

    Milestones

    A milestone is a significant event that normally has no

    duration

    It often takes several activities and a lot of work to complete amilestone

    Theyre useful tools for setting schedule goals and monitoring

    progress

    Examples include obtaining customer sign-off on key

    documents or completion of specific products

  • 7/25/2019 PMP Lecture 5

    8/26

    SequenceActivity

    Involves reviewing activities and determining dependencies

    A dependency or relationship is the sequencing of project

    activities or tasks

    You mustdetermine dependencies in order to use critical

    path analysis

    Identifying and documenting dependencies among

    schedule activities

  • 7/25/2019 PMP Lecture 5

    9/26

    Activity Sequencing

    1. Activity List

    2. Activity Attributes

    3. Milestone list

    4. Scope Statement

    5. Organizational

    Process Asset

    1. Preceding

    DiagrammingMethod

    2. Dependency

    Determination

    3. Applying Leads and

    Lags

    4. Schedule Network

    Templates

    1. Project Schedule

    network diagrams

    2. Project Document

    Updates

    Input Output

    Tools

  • 7/25/2019 PMP Lecture 5

    10/26

    Three types of Dependencies

    Mandatory dependencies: inherent in the nature of the work

    being performed on a project, sometimes referred to as hard

    logic

    Discretionary dependencies: defined by the project team.,

    sometimes referred to as soft logic and should be used with

    care since they may limit later scheduling options

    External dependencies: involve relationships between project

    and non-project activities

  • 7/25/2019 PMP Lecture 5

    11/26

    Task Dependency Types

  • 7/25/2019 PMP Lecture 5

    12/26

    Network Diagrams

    Network diagrams are the preferred technique for showing

    activity sequencing

    A network diagram is a schematic display of the logical

    relationships among, or sequencing of, project activities

  • 7/25/2019 PMP Lecture 5

    13/26

    PDM Network Diagram Template

  • 7/25/2019 PMP Lecture 5

    14/26

    Precedence Diagramming Method (PDM)

    Activities are represented by boxes

    Arrows show relationships between activities

    More popular than ADM method and used by project

    management software

    Better at showing different types of dependencies

  • 7/25/2019 PMP Lecture 5

    15/26

    Estimate Activity Resource

    Consider important issues in estimating

    resources

    How difficult will it be to do specific activities on this project?

    What is the organizations history in doing similar activities?

    Are the required resources available?

    Estimating the type and quantities of resources required to

    perform each schedule activity

  • 7/25/2019 PMP Lecture 5

    16/26

    Estimate Activity Resource

    1. Activity List

    2. Activity attributes

    3. Enterprise

    Calendar

    4. Enterprise

    Environment

    Factor

    5. OPA

    1. Expert Judgment

    2. Alternatives analysis

    3. Published

    estimating data

    4. project

    management

    software

    5. Bottom-up

    estimating

    1. Activity Resource

    Requirements

    2. Resource

    breakdown

    structure

    3. Project document

    updates

    Input Output

    Tools

  • 7/25/2019 PMP Lecture 5

    17/26

    Develop Human Resource Plan

    Develop Human Resource Plan determines project roles,

    responsibilities, and reporting relationships, and creates the

    Human Resource Plan.

  • 7/25/2019 PMP Lecture 5

    18/26

    Develop Human Resource Plan

    1. Organizational

    Process Asset

    2. Activity Resource

    Requirement

    3. Enterprise

    Environmental

    Factor

    1. Organization Charts

    and position

    Descriptions

    2. Networking

    3. Organizational

    Theory

    1. Human Resource

    Plan

    InputOutput

    Tools

  • 7/25/2019 PMP Lecture 5

    19/26

    Project Organizational Chart

  • 7/25/2019 PMP Lecture 5

    20/26

    Responsibility Assignment Matrices (RAM)

    A responsibility assignment matrix (RAM) is a matrix that

    maps the work of the project as described in the WBS to the

    people responsible for performing the work as described in

    the OBS

    Can be created in different ways to meet unique project needs

  • 7/25/2019 PMP Lecture 5

    21/26

    Responsibility Assignment Matrix Template

  • 7/25/2019 PMP Lecture 5

    22/26

    Resource Histograms

    A resource histogram is a column chart that shows the

    number of resources assigned to a project over time

  • 7/25/2019 PMP Lecture 5

    23/26

    Resource Histogram Template

  • 7/25/2019 PMP Lecture 5

    24/26

    Human Resource Plan

    The Human Resource plan details the resources needed for

    the project

    Plan can be formal or informal, detailed or broadly stated

    On a project with a smaller scope, the plan may be informal

    The detail and formality of the staffing management plan

    depends on the

    needs of the project

  • 7/25/2019 PMP Lecture 5

    25/26

    Summary

    Define Activity helps to identify the tasks without considering

    the amount of time, cost , and people required to perform the

    activity .

    Milestones are important elements which helps to present

    progress to board or sponsor

    Sequencing guides logical sequencing of tasks with the help of

    PDM network diagrams

    Develop Human Resource Plan involves identifying policies

    and resource which will be used during project execution

  • 7/25/2019 PMP Lecture 5

    26/26

    THANK YOU