PMP Lecture 5
Transcript of PMP Lecture 5
-
7/25/2019 PMP Lecture 5
1/26
AUC TechnologiesConsulting | Development | Mentoring | Training
Project Management With PMP Exam Preparation
-
7/25/2019 PMP Lecture 5
2/26
Agenda
Define Activity
Sequence Activity
Estimate Activity Resource
Develop Human Resource Plan
-
7/25/2019 PMP Lecture 5
3/26
Importance of Project Schedules
Managers often cite delivering projects on time as one of their
biggest challenges
50% of IT projects were challenged in the 2003 CHAOS
study, and their average time overrun increased to 82% from
a low of 63% in 2000
Schedule issues are the main reason for conflicts on projects,
especially during the second half of projects
Time has the least amount of flexibility; it passes no matter
what happens on a project
-
7/25/2019 PMP Lecture 5
4/26
Define Activity
Define Activity involves developing a more detailed WBS and
supporting explanations to understand all the work to be done
so you can develop realistic cost and duration estimates
Identifying the specific schedule activities that need to be
performed to produce the various project deliverables.
-
7/25/2019 PMP Lecture 5
5/26
Define Activity
1.Scope baseline
2.EnterpriseEnvironmentalFactors
3.Organizational
process assets
1. Decomposition
2. Templates
3. Rolling wave
planning
4. Expert Judgment
1. Activity List
2. Activity
attributes
3. Milestone list
InputOutput
Tools
-
7/25/2019 PMP Lecture 5
6/26
Activity Lists and Attributes
An activity list is a tabulation of activities to be included on a
project schedule that includes
the activity name
an activity identifier or number
a brief description of the activity
Activity attributes provide more information such as
predecessors, successors, logical relationships, leads and
lags, resource requirements, constraints, imposed dates, and
assumptions related to the activity
-
7/25/2019 PMP Lecture 5
7/26
Milestones
A milestone is a significant event that normally has no
duration
It often takes several activities and a lot of work to complete amilestone
Theyre useful tools for setting schedule goals and monitoring
progress
Examples include obtaining customer sign-off on key
documents or completion of specific products
-
7/25/2019 PMP Lecture 5
8/26
SequenceActivity
Involves reviewing activities and determining dependencies
A dependency or relationship is the sequencing of project
activities or tasks
You mustdetermine dependencies in order to use critical
path analysis
Identifying and documenting dependencies among
schedule activities
-
7/25/2019 PMP Lecture 5
9/26
Activity Sequencing
1. Activity List
2. Activity Attributes
3. Milestone list
4. Scope Statement
5. Organizational
Process Asset
1. Preceding
DiagrammingMethod
2. Dependency
Determination
3. Applying Leads and
Lags
4. Schedule Network
Templates
1. Project Schedule
network diagrams
2. Project Document
Updates
Input Output
Tools
-
7/25/2019 PMP Lecture 5
10/26
Three types of Dependencies
Mandatory dependencies: inherent in the nature of the work
being performed on a project, sometimes referred to as hard
logic
Discretionary dependencies: defined by the project team.,
sometimes referred to as soft logic and should be used with
care since they may limit later scheduling options
External dependencies: involve relationships between project
and non-project activities
-
7/25/2019 PMP Lecture 5
11/26
Task Dependency Types
-
7/25/2019 PMP Lecture 5
12/26
Network Diagrams
Network diagrams are the preferred technique for showing
activity sequencing
A network diagram is a schematic display of the logical
relationships among, or sequencing of, project activities
-
7/25/2019 PMP Lecture 5
13/26
PDM Network Diagram Template
-
7/25/2019 PMP Lecture 5
14/26
Precedence Diagramming Method (PDM)
Activities are represented by boxes
Arrows show relationships between activities
More popular than ADM method and used by project
management software
Better at showing different types of dependencies
-
7/25/2019 PMP Lecture 5
15/26
Estimate Activity Resource
Consider important issues in estimating
resources
How difficult will it be to do specific activities on this project?
What is the organizations history in doing similar activities?
Are the required resources available?
Estimating the type and quantities of resources required to
perform each schedule activity
-
7/25/2019 PMP Lecture 5
16/26
Estimate Activity Resource
1. Activity List
2. Activity attributes
3. Enterprise
Calendar
4. Enterprise
Environment
Factor
5. OPA
1. Expert Judgment
2. Alternatives analysis
3. Published
estimating data
4. project
management
software
5. Bottom-up
estimating
1. Activity Resource
Requirements
2. Resource
breakdown
structure
3. Project document
updates
Input Output
Tools
-
7/25/2019 PMP Lecture 5
17/26
Develop Human Resource Plan
Develop Human Resource Plan determines project roles,
responsibilities, and reporting relationships, and creates the
Human Resource Plan.
-
7/25/2019 PMP Lecture 5
18/26
Develop Human Resource Plan
1. Organizational
Process Asset
2. Activity Resource
Requirement
3. Enterprise
Environmental
Factor
1. Organization Charts
and position
Descriptions
2. Networking
3. Organizational
Theory
1. Human Resource
Plan
InputOutput
Tools
-
7/25/2019 PMP Lecture 5
19/26
Project Organizational Chart
-
7/25/2019 PMP Lecture 5
20/26
Responsibility Assignment Matrices (RAM)
A responsibility assignment matrix (RAM) is a matrix that
maps the work of the project as described in the WBS to the
people responsible for performing the work as described in
the OBS
Can be created in different ways to meet unique project needs
-
7/25/2019 PMP Lecture 5
21/26
Responsibility Assignment Matrix Template
-
7/25/2019 PMP Lecture 5
22/26
Resource Histograms
A resource histogram is a column chart that shows the
number of resources assigned to a project over time
-
7/25/2019 PMP Lecture 5
23/26
Resource Histogram Template
-
7/25/2019 PMP Lecture 5
24/26
Human Resource Plan
The Human Resource plan details the resources needed for
the project
Plan can be formal or informal, detailed or broadly stated
On a project with a smaller scope, the plan may be informal
The detail and formality of the staffing management plan
depends on the
needs of the project
-
7/25/2019 PMP Lecture 5
25/26
Summary
Define Activity helps to identify the tasks without considering
the amount of time, cost , and people required to perform the
activity .
Milestones are important elements which helps to present
progress to board or sponsor
Sequencing guides logical sequencing of tasks with the help of
PDM network diagrams
Develop Human Resource Plan involves identifying policies
and resource which will be used during project execution
-
7/25/2019 PMP Lecture 5
26/26
THANK YOU