PMP-5th Ed-ITTOs Mapping.html 1 / 4
PM Process Inputs Tools & Techniques Outputs
PROJECT INTEGRETATION MANAGEMENT
Project Statement of Work
Expert JudgementProject Charter
Business Case
Agreements ( contract)
EE Factors & OP Assets Facilitation TechniquesPROJECT INTEGRETATION MANAGEMENT : Develop Project Management Plan - Phase : - PJ PLANNING
Project CharterExpert Judgement
Project Management PlanOutputs from Planning Processes
EE Factors & OP Assets Facilitation TechniquesPROJECT INTEGRETATION MANAGEMENT : Direct & Manage Project Work - Phase: PJ EXECUTING
Project Management Plan EXPERT JUDGMENT Deliverables
Approved Change RequestsProject MGMT Information System
Work Performance DATA
EE Factors & OP Assets Change Requests
MEETINGS PJ. Mgmt Plan (& Pj. DOC) updatesPROJECT INTEGRETATION MANAGEMENT : Monitor and Control Project Work - Phase : - PJ Monitor & Controling
Project Management PlanExpert Judgement Work Performance REPORTS
FORECAST of Schedule & Cost (2)
VALIDATE CHANGES Analytical techniquesChange Requests
Work Performance Information Project MGMT Information System
EE Factors & OP Assets MEETINGS PJ. Mgmt Plan (& Pj. DOC) updatesPROJECT INTEGRETATION MANAGEMENT : Perform Integrated Change Control
Project Management PlanExpert Judgement Approved Change Request
Work Performance Information
Change Requests MEETINGS Change LOG
EE Factors & OP Assets Change Control Tools PJ. Mgmt Plan (& Pj. DOC) updatesPROJECT INTEGRETATION MANAGEMENT : Close Project or Phase
Project Management Plan Expert JudgementFinal Product, Service, or Result Transition
Accepted Deliverables Analytical techniques
Organizational Process Assets MEETINGS OP Asset Updates
PROJECT SCOPE MANAGEMENTPROJECT SCOPE MANAGEMENT : Plan Scope Management
Project Management PlanExpert Judgement Scope Management Plan
Project Charter
EE Factors & OP Assets MEETINGS Requirements Management PlanPROJECT SCOPE MANAGEMENT : Collect Requirements
Scope Management PlanInterviews Focus Groups
Requirements DocumentationFacilitated Workshops
Requirements Management planGroup Creativity Techniques
Group Decision making Techniques
Stakeholder Management PLANQuestionnaires and Surveys
Requirements Traceability MatrixObservations Prototypes
Project Charter Benchmarking Context Diagrams
Stakeholder Register Document AnalysisPROJECT SCOPE MANAGEMENT : Define Scope
Define Scope
Scope Management Plan Expert JudgementProject Scope Statement
Project Charter Alternative generation
Requirements DocumentationProduct Analysis Facilitated Workshops Project Document Updates
Organizational Process AssetsPROJECT SCOPE MANAGEMENT : Create WBS
Create WBS
Scope Management PlanExpert Judgement
Project Scope Statement
Requirements DocumentationDecomposition Project Document Updates
EE Factors & OP AssetsPROJECT SCOPE MANAGEMENT : VALIDATE Scope
Project Management Plan
Inspection
Acceptable Deliverables
Requirements Documentation Change Requests
Requirements Traceability matrixWork performance information
Validated DeliverablesGroup Decision making Techniques
Work Performance DATA Project Document UpdatesPROJECT SCOPE MANAGEMENT : Control Scope
Control Scope
Project Management Plan
Variance Analysis
Work Performance InformationRequirements Documentation
Requirements Traceability Matrix Change Requests
Work Performance DATAUPDATEs of PM Plan, Pj Docs & OPA
Organizational Process Assets
PROJECT TIME MANAGEMENT
Project Management Plan Expert Judgement
Schedule Management PlanProject Charter Analytical techniques
EE Factors & OP Assets MEETINGSPROJECT TIME MANAGEMENT : Define Activities
Define Activities
Schedule Management Plan Decomposition Activity List
Scope Baseline Rolling Wave Planning Activity Attributes
EE Factors & OP Assets (2) Expert Judgement Milestone List
Develop Project Charter
Develop Project
Management Plan
Direct & Manage Project Work
Monitor and Control
Project Work
Perform Integrated
Change Control
Close Project or Phase
Plan Scope Management
Collect Requirements
Scope Baseline (Includes WBS & WBS Dictionary)
VALIDATE Scope
Plan Schedule Management
-
PMP-5th Ed-ITTOs Mapping.html 2 / 4
PM Process Inputs Tools & Techniques OutputsPROJECT TIME MANAGEMENT : Sequence Activities
Schedule Management Plan Precedence Diagramming Method (PDM)Project Schedule Network Diagram
MileStones -Activity List & Attributes (3) Dependency Determination
Project Scope StatementApplying Leads and Lags Project Document Updates
EE Factors & OP AssetsPROJECT TIME MANAGEMENT : Estimate Activity Resources
Schedule Management Plan Expert JudgementActivity Resource Requirements
Activity List & Attributes (2) Alternative Analysis
Resource Calendars Published Estim.DataResource Breakdown Structure
Risk RegisterBottom up Estimating
Activity Cost EstimatesProject Document Updates
EE Factors & OP Assets Project Management SoftwarePROJECT TIME MANAGEMENT : Estimate Activity Durations
Schedule Management Plan Expert Judgement
Activity Duration EstimatesActivity List & Attributes (2)
Analogous, Parametric, 3 Point Estimating (3)Activity Resource Requirements
Resource Calendars Group Decision technique
Project Scope Statement
Reserve Analysis Project Document UpdatesRisk Register
Resource BreakDown Structure
EE Factors & OP AssetsPROJECT TIME MANAGEMENT : Develop Schedule
Schedule Management PlanSchedule Network Analysis Schedule BASELINE
Activity List & Attributes (2)
Project Schedule Network Diagrams Critical Path MethodProject Schedule
Activity Resource Requirements Critical Chain Method
Resource Calendars Resource optimization techniques Schedule Data
Activity Duration Estimates
Project Scope Statement Modelling techniques
PROJECT CALENDARSRisk RegisterLeads and Lags
Project Staff Assignment
Resource BreakDown Structure Schedule CompressionPJ. Mgmt Plan (& Pj. DOC) updates
EE Factors & OP Assets Scheduling TOOLS
PROJECT TIME MANAGEMENT : Control Schedule
Project Management Plan Performance Reviews Schedule FORECAST
Project Schedule Project Management SoftwareWork Performance Information
Work Performance DATA Resource optimization techniques
Schedule DATA Modelling techniques Leads and Lags Change Requests
EE Factors & OP Assets Schedule Compression & TOOLS (2) UPDATEs of PM Plan, Pj Docs & OPA
PROJECT COST MANAGEMENTPROJECT COST MANAGEMENT : PLAN COST Management
Project Management Plan Expert Judgement
Cost Management PlanProject Charter analytical techniques
EE Factors & OP Assets MEETINGSPROJECT COST MANAGEMENT : Estimate Costs
Estimate Costs
Cost Management Plan Expert Judgement Vendor Bid AnalysisActivity Cost Estimates
Human Resource Management Plan
Scope BaselineBasis of Estimates
Project Schedule Reserve Analysis Cost of Quality
Risk Register Project Management SoftwareProject Document Updates
EE Factors & OP Assets Group Decision-Making techniquePROJECT COST MANAGEMENT : Determine Budget
Cost Management Plan & OP Assets Cost AggregationsCost Baseline
Scope BaselineReserve Analysis
Activity Cost Estimate- Basis of Estimates
Project ScheduleExpert Judgment
Project Funding Requirements Resource Calendars
Risk Register Historical Relationships
AGREEMENTS Funding Limit Reconciliation Project Document Updates
PROJECT COST MANAGEMENT : Control Costs
Control Costs
Project Management Plan Earned Value MGMT Forecasting COST Forecasts
Project Funding Requirements To-Complete Performance Index (TCPI) Work Performance Information
Work Performance DATA Performance Reviews Change Requests
Organizational Process Assets PM Software RESERVE ANALYSIS UPDATEs of PM Plan, Pj Docs & OPA
PROJECT QUALITY MANAGEMENTPROJECT QUALITY MANAGEMENT : Plan Quality Management
Project Management Plan Cost Benefit Analysis Quality Management Plan
Stakeholder Register Cost of Quality Benchmarking Process Improvement Plan
Requirements Documentation 7 Basic Qo tools Statistical samplings Quality Metrics
Risk Register Design of experiments Quality Checklists
EE Factors & OP Assets Add Q Plann. Tools MEETINGS Project Document Updates
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Control Schedule
PLAN COST Management
Analogous, Parametric, 3 Point, Bottom up Estimating (4)
Determine Budget
Plan Quality Management
-
PMP-5th Ed-ITTOs Mapping.html 3 / 4
PM Process Inputs Tools & Techniques OutputsPROJECT QUALITY MANAGEMENT : Perform Quality Assurance
Quality Management PlanQuality Management & Control Tools Change Requests
Process Improvement Plan
Quality Metrics Quality Audits
UPDATEs of PM Plan, Pj Docs & OPAQuality Control MeasurementsProcess Analysis
Project Documents
PROJECT QUALITY MANAGEMENT : Control Quality
Project Management Plan 7 Basic Qo tools Quality Control Measurements
Quality Metrics & Checklist (2) Statistical samplings Validated Changes
Work Performance DATA Inspections Validated Deliverables
Approved Change Requests
Approved change Request Review
Work Performance Information
Deliverables Change Requests
Organizational Process Assets UPDATEs of PM Plan, Pj Docs & OPA
PROJECT HR MANAGEMENTProject Management Plan Organizational Charts & Position Descriptions
Human Resource Management PlanActivity Resource Requirements Networking Organizational Theory
EE Factors & OP Assets Expert Judgement MEETINGSPROJECT HR MANAGEMENT : Acquire Project Team
Human Resource Management PlanPre-assignment Negotiations Project Staff Assignments
Acquisition Virtual Teams Resource Calendars
EE Factors & OP Assets Multi-Criteria decision Analysis Project management Plan UpdatesPROJECT HR MANAGEMENT : Develop Project Team
Human Resource Management PlanInterpersonal Skills
Team Performance AssessmentTeam building Activities
Project Staff Assignments Training Ground Rules
Resource CalendarsCo-location Recognition&Rewards
EE Factors UpdatesPersonnel Assessment Tools
PROJECT HR MANAGEMENT : Manage Project TeamHuman Resource Management Plan Observation & Conversation
Change RequestsProject Staff Assignments Project Performance Appraisals
Team Performance Assessment Conflict Management
EE Factors Updates
ISSUE LOG
UPDATEs of PM Plan, Pj Docs & OPAWork Performance ReportsInterpersonal Skills
Organizational Process Assets
PROJECT COMMUNICATION MANAGEMENT
Project Management Plan Communications Requirements Analysis Communications Management Plan
Stakeholder Register Communication Tech, Model & Methods (3)Project Document Updates
EE Factors & OP Assets MEETINGSPROJECT COMMUNICATION MANAGEMENT : Manage Communications
Communications Management Plan Communication Tech, Model & Methods (3)PROJECT COMMUNICATIONS
Work Performance Reports INFORMATION Management Systems
EE Factors & OP Assets Performance Reporting UPDATEs of PM Plan, Pj Docs & OPA
Project Management Plan & OPA Updates INFORMATION MGMT Systems Work Performance Information
Project CommunicationsExpert Judgement Change Requests
ISSUE LOG
Work Performance DATA MEETINGS UPDATEs of PM Plan, Pj Docs & OPA
PROJECT RISK MANAGEMENTProject Management Plan Analytical Techniques
Risk Management PlanProject Charter
Expert JudgementStakeholder Register
EE Factors & OP Assets MEETINGSPROJECT RISK MANAGEMENT : Identify Risks
Identify Risks
Risk Management Plan Documentation Reviews
Risk Register
Cost, Schedule, Qo, HR Mgt Plans (4) Information Gathering Techniques
Activity Cost & Duration Estimates (2) Checklist Analysis
Scope Baseline Assumptions Analysis
Stakeholder Register Diagramming Techniques
Project & Procurement Documents SWOT Analysis
EE Factors & OP Assets Expert JudgmentPROJECT RISK MANAGEMENT : Perform Qualitative Risk Analysis
Risk Management Plan Risk Probability & Impact Assessment
Project DOC UpdatesRisk Register Probability and Impact Matrix
Scope Baseline Risk (Data Quality Assessment & Categorization)
EE Factors & OP Assets Risk Urgency Assessm. Expert JudgmentPROJECT RISK MANAGEMENT : Perform Quantitative Risk Analysis
Risk Management PlanData Gathering & Representation Techniques
Project DOC Updates
Cost Management Plan
Schedule Management PlanQuantitative Risk Analysis & Modeling Techniques
Risk Register
EE Factors & OP Assets Expert Judgment
Perform Quality Assurance
Control Quality
Plan Human Resource
Managment
Acquire Project Team
Develop Project Team
Manage Project Team
Plan Communications
Manage Communications
Control Communications
Plan Risk Management
Perform Qualitative Risk
Analysis
Perform Quantitative Risk Analysis
-
PMP-5th Ed-ITTOs Mapping.html 4 / 4
PM Process Inputs Tools & Techniques OutputsPROJECT RISK MANAGEMENT : Plan Risk Responses
Risk Management PlanStrategies for [+/-] Risk or Oppor./Threats
PJ. Mgmt Plan (& Pj. DOC) updatesContingency Response strategies
Risk Register Expert JudgmentPROJECT RISK MANAGEMENT : Control Risks
Control Risks
Project Management Plan Risk Reassessment & Risk AuditsWork Performance Information
Risk Register Variance & Trend Analysis
Work Performance DATA Technical Performance Measurement Change Requests
Work Performance Reports Reserve Analysis & Meetings (2) UPDATEs of PM Plan, Pj Docs & OPA
PROJECT PROCURAMENT MANAGEMENTProject Management Plan
Make or Buy Analysis
Procurement Management Plan
Requirements Documentation Procurement Statements of Work
Risk RegisterProcurement Documents
Activity Resource RequirementsExpert judgment
Project Schedule Source Selection Criteria
Activity Cost Estimates market research Make or Buy Decisions
Stakeholder RegisterMEETINGS
Change requests
EE Factors & OP Assets PROJECT DOCMENTS updatesPROJECT PROCURAMENT MANAGEMENT : Conduct Procurements
Procurement Management Plan & DOCs Bidder Conferences Advertising Selected Sellers
Procurement statement of work Proposal Evaluation Techniques AGREEMENTS
Source Selection Criteria Independent Estimates Resource Calendars
Seller Proposals - Make or Buy Decisions Expert Judgment Analytical techniques Change Requests
Project DOCs & OP Assets Procurement Negotiations PJ. Mgmt Plan (& Pj. DOC) updatesPROJECT PROCURAMENT MANAGEMENT : Control Procurements
Project Management Plan Contract Change Control System Work Performance Information
Procurement Documents Procurement Performance Reviews Change Requests
AGREEMENTS Inspections and Audits
UPDATEs of PM Plan, Pj Docs & OPAApproved Change Requests Performance Reporting
Work Performance Reports Payment Systems Claims Administration
Work Performance DATA Records Management SystemPROJECT PROCURAMENT MANAGEMENT : Close Procurements
Project Management Plan Procurement Audits & negotiations (2) Closed Procurement
Procurement Documentation Records Management System OP Assets Updates
PROJECT STAKEHOLDER MANAGEMENTProject Charter Stakeholder Analysis
Stakeholder RegisterProcurement Documents Expert Judgment
EE Factors & OP Assets MEETINGSPROJECT STAKEHOLDER MANAGEMENT : Plan Stakeholder Management
Project management Plan Expert Judgment STAKEHOLDERs Management Plan
Stakeholder Register MEETINGSProject Document Updates
EE Factors & OP Assets Analytical TechniquesPROJECT STAKEHOLDER MANAGEMENT : Manage Stakeholder Engagement
Stakeholders Management Plan Communications Methods ISSUE LOG
Communications Management Plan Interpersonal Skills Change Requests
Change LOG & op ASSETS Management Skills UPDATEs of PM Plan, Pj Docs & OPAPROJECT STAKEHOLDER MANAGEMENT : CONTROL Stakeholder Engagement
Project Management Plan INFORMATION MGMT Systems Work Performance Information
ISSUE LOGExpert Judgment Change Requests
Work Performance DATA
Project DOCs MEETINGS UPDATEs of PM Plan, Pj Docs & OPA
Plan Risk Responses
Plan Procurements
Conduct Procurements
Control Procurements
Close Procurements
Identify Stakeholders
Plan Stakeholder Management
Manage Stakeholder Engagement
CONTROL Stakeholder Engagement