The Value of Project Management Presented February 25, 2004 by Kathy Schwalbe, Ph.D, PMP.
Pmp Chapter 10 2004
-
Upload
api-3833133 -
Category
Documents
-
view
323 -
download
0
Transcript of Pmp Chapter 10 2004
2/12/2006
Akram Al-Najjar, PMPPlanning & Cost Control Manager
PMP
Preparation Training
Your key in Successful Project Management
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 2
Chapter 10
Project
Communication Management
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 3
AGENDA
Some term to be familiar with ! What is Communication Management?Communication Management ProcessesHow does the PMBoK® Guide describe Communication Management?Discussion
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 4
Some term to be familiar with !
Information
IdeasPeopleLanguage
Within the ProjectOutside Project
Media
Government
Other Projects
Information
Departments
Provides the Critical LinksProject Communications Management
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 5
Some term to be familiar with !Project Communications Management
nSender-receiver models
nChoice of media
nWriting style
nPresentation techniques
nMeeting management techniques
These are related to..but not the same as Project Communications Management
SUCH ASDoesn’t mean... Communicating Skills
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 6
Some term to be familiar with !
Sender Receiver
Encode
Decode Encode
DecodeMessage
Feedback-Message
Noise
Noise
Communication – basic Model
Medium
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 7
Project Communications Management
Communications Planning
Information Distribution
Performance Reporting
Manage Stakeholders
Processes required to ensure timely and appropriate generation , collection, dissemination,
storage, and, ultimately disposition of project information
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 8
Communication Management
10.1CommunicationsPlanning
Planning
10.3PerformanceReporting
10.4Manage
Stakeholders
Controlling
10.2InformationDistribution
Executing
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 9
CommunicationsPlanning 10.1
InformationDistribution 10.2
PerformanceReporting 10.3
Manage Stakeholders10.4
Enterprise EnvironmentalFactors
Organizational ProcessAssets
Scope Definition5.2
Project Communication Management
Processes Flow Diagram
Direct and ManageProject Execution
4.4
Develop Project Management Plan
4.3
Close Project4.7
Integrated ChangeControl
4.6
Communication Technology
Lesson Learned
Scope Statement
Project Management Plan
Communication Management Plan
Appro
ved ch
an
ge
req
uest &
co
rrectiv
e a
ctionRequested Change
Work performance info. & Deliverables
Organizational
Process
Assets
Requested Change
Corrective action
Performance Report & forecast
Communication Management Plan update Project
Management Plan update
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 10
Communications Planning
Determining the information and communications needs of the stakeholders: who needs what information, when they will need it, and how it will be given to them
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 11
Inputs• Enterprise Environmental
Factors• Organizational Process
Assets• Project Scope Statement• Project Management Plan
Constrains & Assumption
Tools & Techniques• Communications
requirements Analysis• Communication technology
Outputs• Communication
management plan
Communications Planning
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 12
n Communications requirements Analysis –The sum of the information requirements of the project stakeholders and defined by:
Communications Planning
Requirement
Communication requirement includes:- Project Organization, Responsibility relationships - Disciplines, departments, specialties - Logistics (number of, where)- How many individuals and locations - External needs - Media
- Combining - “Type and Format” with: “Analysis of the Value ”
Tools & Techniques
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 13
Tools & Techniquesn Communication technology – Used to
transfer information back and forth among project elements
Communications Planning
Urgency of the need
Availability of Technology
-Conversations-documents-on-line schedules-databases-etc..
Length of the Project
Expected Project Staffing
project environment.
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 14
Outputs
n Communication management plan – provides:n Collection and filing structure – Methods used to
gather, update, and store various types of informationn Distribution structure – Specifies to whom
information will flow and what method will be used to distribute various types of information.
n Description of information to be distributed –Includes format, content, level of detail, and conventions and definitions to be used
n Production schedules – Showing when each type of communication will be produced
n Methods for accessing informationn Method of updating and refining the
communication management plan as the project progresses
Communications Planning
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 15
Information Distribution
• Includes implementing the communications management plan, as well as responding to unexpected requests for information
Making needed information available to project stakeholders in a timely manner
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 16
Figure 10-1. The Impact of the Number of People on Communications Channels
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 17
Information Distribution
Inputs• Communication
management plan
Tools & Techniques• Communications skills• Information-retrieval
systems• Information-distribution
methods• Lesson Learned Process
Outputs• Organizational Process
assets (updates)• Requested changes
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 18
Tools & Techniques
n Communications skills – Skills for exchanging informationn Written, oral, listening, and speaking
n Internal and external communication
n Formal (reports, briefings) and informal (memos, ad-hoc conversations)
n Vertically, (up and down the organization), and horizontally, (with peers)
Information Distribution
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 19
Tools & Techniques (cont.)n Information-retrieval systems – Information can be
shared by team members and stakeholders through a variety of methods including
n Manual filing systems, electronic -text databases, project management software, and systems which allow access to such technical documentation as engineering drawings
• Manual Filing• Electronic Database• P.M. Software• Drawings
n Information-distribution Methods – Methods such as project meetings, hard-copy document distribution, shared access to networked electronic databases, fax, electronic mail, voice mail, and video conferencing
Information Distribution
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 20
Outputs
nOrganizational Process Assets (Updates)
Project Records – Organized storage and
maintenance of correspondence, memos, reports, and documents describing the project
Project reports – Formal project reports on
project status and/or issues
Project presentations – Provide information
formal or informally to any or all of the project stakeholders
Information Distribution
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 21
Performance Reporting
n This includes status reporting (describing where the project now stand) , progress reporting (describing what the project team has accomplished) , and forecasting reporting (predicting future project status and progress )
n Provides information on scope, schedule, cost, and quality, and possibly on risk and procurement
Collecting and disseminating performance information to provide stakeholders with information about how resources are being used to achieve project objectives
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 22
Performance Reporting
Inputs• Work Performance Information• Performance Measurements• Forecasted Completion• Quality Control Measurements• Project Management Plan• Approved Change Requests• Deliverables
Tools & Techniques• Information Presentation Tools• Performance Information
Gathering and Compilation• Status Review Meetings• Time Reporting Systems• Cost Reporting Systems
Outputs• Performance reports• Forecasts • Requested Changes• Recommended Corrective Actions• Organizational Process Assets (Updates))
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 23
Performance Reporting, Inputs
• Deliverables
Are any unique and verifiable or product, or result to perform a services that must be product to complete a process, phase or project
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 24
Outputs
n Performance report – Organizes and summarizes the information gathered and presents the results of any analysis. Reports should provide the kinds of information and the level of detail required by various stakeholders and documented in the communications management plan
Performance Reporting
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 25
Outputs
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 26
n Earned-value analysis – Integrating scope, cost, and schedule measures to assess project performance
Performance Reporting
n Planned
n planned value = BCWS
n Actual
n Actual costs = ACWP
n Earned Value
n Earned value = BCWP
n BCWPn Task A, which I was supposed to complete today, is
scheduled to cost $1000. I am only 85% done on this task. So, I have done $850 worth of work… which is my earned value (BCWP)
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 27
Case 2
n PV = $ 1,900
n AC = $ 1,700
In this Case, without Earned Value
measurements, it appears we’re in good shape. Expenditures are less than planned.
Spending Variance = - $ 200
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 28
Case 2
n PV = $ 1,900
n EV = $ 1,500
n AC = $ 1,700
But with EV measurements, we see...$400 worth of work is behind schedule in being completed; i.e., we are 21 percent behind where we
planned to be.
SV = EV – PV = - $ 400SV % = SV / PV x 100 = - 21 %
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 29
OutputsPerformance report
0.0010,000,000.0020,000,000.0030,000,000.0040,000,000.0050,000,000.0060,000,000.0070,000,000.0080,000,000.00
Jan-02
Feb-02
Mar-02
Apr-02
May-02
Jun-02
Jul-02
Aug-02
Sep-02
Oct-02
Nov-02
Time
Valu
e .
planeed value
Earned value
Actual Cost
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 30
Manage Stakeholders
n managing stakeholders increases the likelihood that the project will not change direction off track due to unresolved stakeholder issues, enhances the ability of persons to operation, and limits disruptions during the project. The project manager is usually responsible for stakeholder management.
n Stakeholder management refers to managing communications to satisfy the needs of, and resolve issues with, project stakeholders.
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 31
Manage Stakeholders
Inputs• Communications
Management Plan• Organizational
Process Assets
Tools & Techniques• Communications Methods• Issue Logs
Outputs• Resolved Issues• Approved Change Requests• Approved Corrective Actions• Organizational Process
Assets (Updates)• Project Management
Plan (Updates)
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 32
Tools and Techniquesn Communications Methods :
Face-to-face meetings
Telephone Calls
Electronic Mail
n Issue LogsIs a tool that can be used to document and monitor
the resolution of issues. Issues do not usually rise to the importance of becoming a project or activity, but are usually addressed in order to maintain good, constructive
n working relationships among various stakeholders, including team members.
Manage Stakeholders
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 33
Outputn Resolved Issuesn As stakeholder requirements are identified and
resolved, the issues log will document concerns that have been addressed and closed. examples include:
n Customer agree to a follow on contract
n More staff is added to the project
n Negotiation with function managers
n Issues raised by board members
Manage Stakeholders
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 34
CommunicationsPlanning 10.1
InformationDistribution 10.2
PerformanceReporting 10.3
Manage Stakeholders10.4
Enterprise EnvironmentalFactors
Organizational ProcessAssets
Scope Definition5.2
Project Communication Management
Processes Flow Diagram
Direct and ManageProject Execution
4.4
Develop Project Management Plan
4.3
Close Project4.7
Integrated ChangeControl
4.6
Communication Technology
Lesson Learned
Scope Statement
Project Management Plan
Communication Management Plan
Appro
ved ch
an
ge
req
uest &
co
rrectiv
e a
ctionRequested Change
Work performance info. & Deliverables
Organizational
Process
Assets
Requested Change
Corrective action
Performance Report & forecast
Communication Management Plan update Project
Management Plan update
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 35
nAny questions
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 36
PMBOK® Multiple Choice Quiz
1. What is the communications channel formula?a) (a + 2*b + c ) / 6
b) (n*(n-1)) /2
c) 2n-1 / 2
d) (a*b) / 4c
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 37
2. It is important to collect project records at the end of the project to:
a) document decisions made on the project.
b) recall what happened on the project.
c) support cost decisions.
d) support the risks on the project.
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 38
3. The MOST likely result of communication blockers is that:
a) the project is delayed.
b) trust level is enhanced.
c) conflict occurs.
d) senior management is displeased.
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 39
4. How much time does a Project Manager spend communicating?
a) 95-97%b) 70-90%c) 64-87%d) 35-50%
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 40
5. In the context of Communications Management, what is noise?
a) too many participants on a project team
b) the message itself
c) any interference or disturbance that confuses the message
d) the person for whom the message is intended
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 41
6. A report that is focused on predicting future project status is called a:
a) trend report.
b) forecasting report.
C) status report.
d) variance report.
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 42
7. Which is not a basic of interpersonal communication?
a) symptom (or noise)
b) signal (or message)
c) sender (or encoder)
d) receiver (or decoder)
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 43
8 . The project status meeting is not going well. Everyone is talking at the same time, there are people who are not participating and many topics are being discussed at random. Which of the following rules for effective meetings is NOT being adhered to?
a) Courtesy and consideration of each other
b) Schedule meetings in advance
c) Have a purpose for the meeting
d) Create and publish an agenda
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 44
9. The project manager is working to clearly describe the level of involvement expected from everyone involved in the project in order to prevent rework, conflict and coordination problems. Which of the following BEST describes the project manager's efforts?
a) Smoothing, control, goodwill, gold plating b) Integration management, control, communications
planningc) Scope verification, quality control, executiond) Risk assessment, scheduling, lessons learned, stakeholder
management
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 45
10. You are a project manager for a US $3,000,000 product development project. Your project is well into the execution phase and remains on time, on budget and on specification. This morning, your project sponsor called to express concern about the project. Based on the schedule baseline, the project should be nearing implementation, but the sponsor does not know the current status of the project. You remind the sponsor that your team produces a detailed status report weekly and distributes it via e-mail. The sponsor indicates that e-mail is too impersonal and verbal updates are preferred. This situationsuggests problems with which of the following project management processes??
a) Communications planning
b) Information distributionc) Performance reportingd) Stakeholder management
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 46
11. Your project is managed under a projectized organization. It has just entered closure. Under the circumstances, which of the following should be your GREATEST concern?
a) Setting yourself up to take over a large multi-year project
b) The team is not focused on completing the project.
c) You will have extra pressure from the customer.d) Making sure your manager knows the project is
almost completed
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 47
12. What is not a basic channel of communication?
a) Upward
b) Laterally
c) Downward
d) Orbicular
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 48
13. All of the following are non-verbal listening behaviors except?
a) Being expressive and alert
b) Paraphrasing what the speaker has said
c) Moving closer to the speaker
d) Making eye contact
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 49
How many more lines of communication are there if the team increases from 3 to 7?
a) 4
b) 21
c) 18
d) 9
c. 18 (3*(3-1))/2 = 3 lines of communication. (7* (7-1))/2 = 21 lines of communication. 21 - 3 = 18.
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 50
How much time does a Project Manager spend communicating?
a) 95-97%b) 70-90%c) 64-87%d) 35-50%
b. 70-90% (approx. 45% is spent listening / 30% is spent talking. About 50% of their time is spent in meetings.)
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 51
In the context of Communications Management, what is noise?
a) too many participants on a project team
b) the message itself
c) any interference or disturbance that confuses the message
d) the person for whom the message is intended
c. Interference or disturbance
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 52
Which is not a basic of interpersonal communication?
a) symptom (or noise)
b) signal (or message)
c) sender (or encoder)
d) receiver (or decoder)
a. Symptom (or noise) (There are only three basics of interpersonal communication: sender, signal, and receiver)
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 53
The main aim of business writing is that it should be:
a) complex and written at a university levelb) written for business users only c) understood clearly when read quicklyd) full of jargon intended for team
members
c. Understood clearly when read quickly
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 54
What is not a basic channel of communication?
a) Upward
b) Laterally
c) Downward
d) Orbicular
d. Orbicular (Upward, Downward and Laterally - with vertical, diagonal and horizontal directions)
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 55
All of the following are non-verbal listening behaviors except?
a) Being expressive and alert
b) Paraphrasing what the speaker has said
c) Moving closer to the speaker
d) Making eye contact
b. (Paraphrasing is a verbal listening behaviors)
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 56
Which of the following is not a major communication style?
a) concrete- sequential (Mr/Ms Fix-It)
b) concrete- directive (Mr/Ms In-Charge)
c) abstract-random (Intuitive Free Thinker)
d) abstract-sequential (Organizer)
b. concrete-directive (the other major communication style is concrete-random - Explorer / Entrepreneur)
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 57
Macro- barriers to successful communication include all but :
a) Homogeneity
b) Number of links
c) Organizational climate
d) Information overload
a. homogeneity (it is our cultural differences that create macro-barriers to successful communication)
PMBOK® Multiple Choice Quiz
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 58
Micro- barriers to successful communication include all but :
a) Lack of Subject Knowledge
b) Perceptions
c) Message Competition
d) Project jargon and terminology
a. Lack of subject knowledge (this is a macro-barrier)
PMBOK® Multiple Choice Quiz
2/12/2006
Akram Al-Najjar, PMP.+20105394312
Source: pmbok guide 2004 Slide 59
What percentage of the message is lost in upward communication?
a) 5-15%b) 12-17%c) 23-27%d) 25-30%
c. 23-27% - be aware of entropy
PMBOK® Multiple Choice Quiz