PMP CH.6

download PMP CH.6

of 35

Transcript of PMP CH.6

  • 7/31/2019 PMP CH.6

    1/35

    1

    GU, PMP Preparatory Course, MODULE 6

    MODULE 6Project Cost Management

    Module Content:Hot TopicsCost RiskInputs to estimating

    Resource planningCost management planCost estimatingProgram reportingEarned value

    Accuracy of estimatesAccuracy standardsProject selection methodsTypes of costsDepreciation

  • 7/31/2019 PMP CH.6

    2/35

    2

    GU, PMP Preparatory Course, MODULE 6

    Cost Management (PMBOK Chapter 7)

  • 7/31/2019 PMP CH.6

    3/35

    3

    GU, PMP Preparatory Course, MODULE 6

    Tips

    You should realize :Estimating should be based on a WBS to improveaccuracy.Estimating should be done by the person doingthe work.Historical information is a key to improvingestimates.Costs (and time, scope and resources) should be

    managed to estimates.A cost (and time, scope and resource) baselineshould be kept and not changed except forapproved project changes.

  • 7/31/2019 PMP CH.6

    4/35

    4

    GU, PMP Preparatory Course, MODULE 6

    Tips(continued)

    Plans should be revised, as necessary, duringcompletion of the work.Corrective action should be taken when costproblems (and time, scope and resourceproblems) occur.A project manager should never just accepttime or cost requirements from management,

    but rather analyze the needs of the project,come up with his own estimate and reconcileany differences.

  • 7/31/2019 PMP CH.6

    5/35

    5

    GU, PMP Preparatory Course, MODULE 6

    COST RISK

    Sometimes a question on the exam willcross boundaries between risk,procurement and cost. Cost risk is best

    explained with an example question:

    "Who has the cost risk in a fixed pricecontract, the buyer or the seller?"

    The answer is the seller.

  • 7/31/2019 PMP CH.6

    6/35

    6

    GU, PMP Preparatory Course, MODULE 6

    INPUTS TO ESTIMATING

    you need the following before you begin estimating:

    WBS

    Network diagram - Costs cannot be estimated untilit is known how the project will flow frombeginning to end.

    Schedule - For multi-year projects, the cost of atask is usually different if it is completed in oneyear compared to another.NOTE: This refers to an overall schedule, not a detailed one.The detailed schedule is created after estimating.

  • 7/31/2019 PMP CH.6

    7/35

    7

    GU, PMP Preparatory Course, MODULE 6

    INPUTS TO ESTIMATING

    Historical information

    Resource pool - An understanding of the availableresources or the resources assigned.

    Risk management plan - because it includes abudget for risk.

    Risks - An understanding of any risk uncovered todate. Remember, a full risk analysis of the detailsof the project will not have been completed beforecosts are estimated.

  • 7/31/2019 PMP CH.6

    8/35

    8

    GU, PMP Preparatory Course, MODULE 6

    RESOURCE PLANNING (page 85)

    The management of resources is asimportant as managing cost, time, qualityand scope.

    Resources must be planned andcoordinated in order to avoid commonproblems such as lack of resources andresources being taken away from theproject.

    Resource planning may be a moreextensive activity than you do on yourprojects.

  • 7/31/2019 PMP CH.6

    9/35

    9

    GU, PMP Preparatory Course, MODULE 6

    What activities are involved in resourceplanning?

    Review WBSIdentify potentially available resourcesReview historical information about the use of

    resources on past or similar projectsReview organizational policies on resource useSolicit expert judgment on what resources areneeded and available

    Quantify resource requirement by taskDevelop a plan as to what types of resources areneeded, in what numbers, when

  • 7/31/2019 PMP CH.6

    10/35

    10

    GU, PMP Preparatory Course, MODULE 6

    COST MANAGEMENT PLAN (page 89)

    Once costs are estimated, the projectmanager can and must put in place a plan foreffectively managing the project to the costbaseline and manage cost variances.This plan is similar to other managementplans (a PMIdD-ism).

    The cost management plan can be formal orinformal,but is part of the project plan.

  • 7/31/2019 PMP CH.6

    11/35

    11GU, PMP Preparatory Course, MODULE 6

    COST ESTIMATING (page 86)

    ANALOGOUS ESTIMATING (Top-Down, page 88) - Top ormiddle managers use expert judgment or the actualtime and cost of a previous, similar project as the basisfor estimating the current project. Analogous estimatingis a form of expert judgment.

    BOTTOM-UP ESTIMATING (page 88) - With thistechnique, the people doing the work create cost andschedule estimates. Estimates, based on the WBS, arerolled up to get a project total.

    PARAMETRIC ESTIMATING - Uses a mathematicalmodel to predict project costs. For example, cost perline of code, cost per linear meter or cost perinstallation.

  • 7/31/2019 PMP CH.6

    12/35

    12GU, PMP Preparatory Course, MODULE 6

    Advantages & Disadvantagesof Analogous Estimating and Bottom-Up Estimating

  • 7/31/2019 PMP CH.6

    13/35

    13GU, PMP Preparatory Course, MODULE 6

    PROGRESS REPORTING(page 122)

    50/50 RULE A task is considered 50% complete when it beginsand gets credit for the last 50% only when it iscompleted. 20/80 RULE A task is considered 20% complete when it beginsand gets credit for the last 80% only when it iscompleted. 0/100 RULE A task does not get credit for partial completion,

    only full completion

  • 7/31/2019 PMP CH.6

    14/35

    14GU, PMP Preparatory Course, MODULE 6

    EARNED VALUE ANALYSIS (page 123

    EVA is a method to measure scope, timeand project performance... Here is whatyou need to know.

  • 7/31/2019 PMP CH.6

    15/35

    15GU, PMP Preparatory Course, MODULE 6

    EARNED VALUE ANALYSIS Formulas and Interpretations to Memorize

  • 7/31/2019 PMP CH.6

    16/35

    16GU, PMP Preparatory Course, MODULE 6

    TRICKS

    Make sure you understand and MEMORIZE thefollowing:

    1. Notice that EV comes first in every formula. Remembering

    this one fact alone should help you get about half the earnedvalue questions right. (Aren't you glad you purchased thisbook?)

    2. If it is a variance, the formula is EV minus something.

    3. If it is an index, it is EV divided by something.

    4. If the formula relates to cost, use AC.

  • 7/31/2019 PMP CH.6

    17/35

    17GU, PMP Preparatory Course, MODULE 6

    Tricks(Continued)

    5. If the formula relates to schedule, use PV.

    6. For interpretation: negative is bad andpositive is good. Thus a -200 costvariance means that you are behind(over) budget.

    7. For interpretation: greater than one isgood, less than one is bad.

  • 7/31/2019 PMP CH.6

    18/35

    18GU, PMP Preparatory Course, MODULE 6

    Tricks(Continued)

  • 7/31/2019 PMP CH.6

    19/35

    19GU, PMP Preparatory Course, MODULE 6

    Old and New Acronym

  • 7/31/2019 PMP CH.6

    20/35

    20GU, PMP Preparatory Course, MODULE 6

    Exercises 1

    CPI and SPI can becharted each month toshow the project

    trends. Based on thefollowing, what wouldyou be more concernedabout, cost or schedule,if you were taking overthis project fromanother projectmanager?

    Answer: The answer isschedule. As of today,SPI is closest to 1.

  • 7/31/2019 PMP CH.6

    21/35

    21GU, PMP Preparatory Course, MODULE 6

    Exercises 2

    You have a project to build anew fence. The fence is foursided.Each side is to take one dayto build and is budgeted forUS $1,000 per side. . Thesides are planned to becompleted one after theother. Today is the end of daythree. Using the projectstatus chart, calculate EV ,

    etc. When completed, checkyour answers on the answersheet on the following page.Interpretation is alsoimportant on the exam. Canyou interpret what eachanswer means?

  • 7/31/2019 PMP CH.6

    22/35

    22GU, PMP Preparatory Course, MODULE 6

    Answer to Exercise 2

  • 7/31/2019 PMP CH.6

    23/35

    23GU, PMP Preparatory Course, MODULE 6

    ACCURACY OF ESTIMATES

    The three levels of estimating accuracy youmust MEMORIZE for the exam are:

    1. ORDER OF MAGNITUDE ESTIMATE - This type of estimate is usually made during the initiating phaseand is in the range of-25% to +75% from actual.

    2. BUDGET ESTIMATE - This type of estimate is usuallymade during the planning phase and is in the range of-10% to +25% from actual.

    3. DEFINITIVE ESTIMATE - This type of estimate is alsomade during the planning phase and is in the range of-5% to +10% from actual.

  • 7/31/2019 PMP CH.6

    24/35

    24GU, PMP Preparatory Course, MODULE 6

    ACCOUNTING STANDARDS I

    PRESENT VALUE: Present value means thevalue today of future cash flows and can befound by the formula:

    NET PRESENT VALUE (NPV) This means the present value of the total benefits

    (income or revenue) less the costs

  • 7/31/2019 PMP CH.6

    25/35

    25GU, PMP Preparatory Course, MODULE 6

    ACCOUNTING STANDARDS II

    INTERNAL RATE OF RETURN (IRR ): The rate (read it as interest rate) at

    which the project inflows (revenues) andproject outflows (costs) are equal.

    PAYBACK PERIOD: The number of time periods it takes torecover your investment in the projectbefore you start accumulating profit

  • 7/31/2019 PMP CH.6

    26/35

    26GU, PMP Preparatory Course, MODULE 6

    ACCOUNTING STANDARDSIII

    BENEFIT COST RATIO (BCR):

    A BCR of>l means the benefits aregreater than the costs. A BCR of

  • 7/31/2019 PMP CH.6

    27/35

    27GU, PMP Preparatory Course, MODULE 6

    Exercise

    For each row on the following chart, enter theletter of the project you would select if thefollowing information were provided.

  • 7/31/2019 PMP CH.6

    28/35

    28GU, PMP Preparatory Course, MODULE 6

    ACCOUNTING STANDARDSIV

    SUNK COSTS : Expended costs .

    LAW OF DIMINISHING RETURNS: The more you

    put into something, the less you get out of it. Forexample, adding twice as many resources to a taskmay not get the task done in half the time.

    WORKING CAPITAL: Current assets minuscurrent liabilities, or the amount of money thecompany has to invest, including investment inprojects.

  • 7/31/2019 PMP CH.6

    29/35

    29GU, PMP Preparatory Course, MODULE 6

    PROJECT SELECTION METHODS

    Present Value

    Net PresentValue

    Internal Rate of Return

    Payback Period

    Benefit CostRatio

  • 7/31/2019 PMP CH.6

    30/35

    30GU, PMP Preparatory Course, MODULE 6

    TYPES OF COST

    A cost can be either variable or fixed

    VARIABLE COST - Any cost thatchanges with the amount of production or the amount of work.Examples include the cost of material,supplies and wages.

    FIXED COST - Costs that do notchange as production changes.Examples include set up, rental, etc.

  • 7/31/2019 PMP CH.6

    31/35

    31GU, PMP Preparatory Course, MODULE 6

    TYPES OF COST

    A cost can be either direct or indirect:

    DIRECT COST - Costs that are directly

    attributable to the work on the project.Examples are team travel, team wages,recognition and costs of material used on theproject.

    INDIRECT COST - Overhead items or costsincurred for the benefit of more than oneproject. Examples include taxes, fringe benefitsand janitorial services.

  • 7/31/2019 PMP CH.6

    32/35

    32GU, PMP Preparatory Course, MODULE 6

    DEPRECIATION

    Large assets (e.g., equipment) lose value over time. Accountingstandards call this depreciation. Several methods are used toaccount for depreciation

    There are two forms of depreciation:

    1. STRAIGHT LINE DEPRECIATION - The same amount of depreciation is taken each year

    2. ACCELERATED DEPRECIATION There are two forms of accelerated depreciation..

    Double Declining BalanceSum of the Years Digits

    Accelerated depreciation depreciates faster than straightline.

  • 7/31/2019 PMP CH.6

    33/35

    33GU, PMP Preparatory Course, MODULE 6

    New Concepts

    LIFE CYCLE COSTING : The project we are working on has a life afterit is completed.

    Project manager and the company want theproject costs to be as low as possible.However, if the project manager does notconsider the life cycle costs, project costs

    may be low at the expense of greater overallcosts for the rest of the life of the project.For example the operations and maintenancephase.

  • 7/31/2019 PMP CH.6

    34/35

    34GU, PMP Preparatory Course, MODULE 6

    New Concepts

    VALUE ANALYSIS: (Sometimes referred to as valueengineering in the real world.)

    Find a less costly way to do the same scope of work.It requires the systematic use of techniques to identifythe required project functions, assign values to thesefunctions and provide functions at the lowest overallcost without loss of performance.If a team or someone else is looking at decreasingproject cost but maintaining the same scope of work,they are performing value analysis.

  • 7/31/2019 PMP CH.6

    35/35

    35

    Practice for theCAPM and PMP Exams

    Project Cost Management