PMI_SAP
Click here to load reader
-
Upload
govind-vikram-aggarwal -
Category
Documents
-
view
213 -
download
0
Transcript of PMI_SAP
8/13/2019 PMI_SAP
http://slidepdf.com/reader/full/pmisap 1/5
PMI Virtual Library
© 2013 Sailendra Nath Swain
Stakeholder Management in SAPImplementation Projects
Developed in the early 1970s, SAP has evolved
into one of the most popular enterprise resource
planning (ERP) products, with continuous iterative
developments achieved through sustained R&D work. In
this paper, the focus will be on the challenges faced during
managing the stakeholders in an SAP project and the means
for addressing them. Tis can be helpful to the project
managers handling SAP projects and those aspiring to handle
SAP projects.
One of the major activities involved in a typical SAP
project during the initial stages is requirements gathering.
As one of the most critical activities of the plan anddefine phase, its cascading effect can be felt deeply in the
subsequent stages and/or phases. If not properly carried out,
the resultant effort can be scope creep and/or budget over-
run. As one of the most successfully packaged products in
the world, it has created belief among people that it can do
wonders at the touch of a button. Te majority of people
ignore the fact that it is a two-way process; in other words, it
involves the participation of both sides. All ERP products are
developed and improved on a continuous basis by adopting a
collaborative approach; hence, every effort should be made to
foster a collaborative approach during this phase. Tis can beachieved by adopting the following approach (Figure 1).
By Sailendra Nath Swain, PMP
STAKEHOLDER ANALYSIS: OVERVIEW
Tis is one of the most critical activities of an SAP project and
it needs to be executed with utmost care, because this is one of
the key elements that will be driving the project. Tis is where
caution needs to be observed, because most project managers
make mistakes at this stage. Stakeholder selection should be a
collaborative effort between the client and the project team,
with the sponsor and project manager leading from both sides.
Objective:
Stakeholder analysis is the process that
Is intended for group stakeholders•
Understands what stakeholders expect from the project•
and what they need in relation to potential risks
Identifies actions to minimize project risks and maximize•
benefits by working with the stakeholders.
Te purpose of this document is to outline a strategy for
conducting stakeholder analysis on the project; the objective
of this strategy is to define:
Guiding principles for conducting stakeholder analysis•
and planning and monitoring stakeholder actions
Key stakeholder groups impacted by and influencing the•
project
Figure 1: Flow diagram.
8/13/2019 PMI_SAP
http://slidepdf.com/reader/full/pmisap 2/5
PMI Virtual Library | www.PMI.org | © 2013 Sailendra Nath Swain
2
Stakeholder expectations by group; how they can be•
measured; and, a summary of project tasks and milestones
that will need to be put in place to satisfy stakeholder
expectations if they represent a project risk.
Te following life cycle needs to be followed for the same:
Provisional list— Analysis — Impact — Filtering —
Interview — Final list — Continuous update.
Figure 2 depicts the impact of stakeholders on an
implementation project.
Based on the scope of the project, a list should be drawn
up from the respective departments/organizations, and
formal/informal discussion needs to be carried out with each
stakeholder.
Stakeholder categorization will be carried out as per the
following P&I (positional influence and impact) diagram (see
Figure 3).
Example:
SL. No Name Influence Impact Net
1 X .95 .9 0.855
2 Y 0.75 0.75 0.56
3 Z 0.5 0.5 0.25
4 W 0.25 0.25 0.06
Figure 3: P&I diagram.
Initial list
preparationCategorization Interview
Impact
Analysis
Confirm
Stakeholder
Needs and
Expectations
Action Plan
Figure 2: Impact of stakeholder influence on cost of changes during different phases of the project.
Te diagram in Figure 3 indicates X as one of the critical
stakeholders.
In SAP projects, stakeholders can be broadly classified
into the following categories, based on the above P&Idiagram (see Figure 4).
Based on the same diagram, a strategy can be drawn to
handle the respective customer/stakeholder for the following:
Communication strategy 1.
Degree of involvement in various stages2.
Inclusion in different committees3.
8/13/2019 PMI_SAP
http://slidepdf.com/reader/full/pmisap 3/5
PMI Virtual Library | www.PMI.org | © 2013 Sailendra Nath Swain
3
As a consequence to the completion of stakeholder
analysis, an action plan needs to be devised for each
The XXXXX Organization
Businesses
Affected
BusinessesNot Directly
Affected
End Users Business
Managers
Steering
Group
External
Stakeholders
Reporting
Users
C u s t o m e r s
S u p p l i e r s
Indirect
Users
Figure 4: Stakeholder categories.
MANAGING STAKEHOLDERS
SL
Number
Type of User Requirements Details
1 Business leads To be involved in strategy formulation for change management
Involvement in business process re-orientation exercise
Access and information on availability of MIS
(management information) reports
Awareness on the new system to be implemented in order to facilitate:
Business process mapping•
Providing input to the requirements gathering process•
Deeper involvement in scope freezing process•
2 Steering committee members Regular updates on projects
Access to financial information related to project (i.e., budgetary status, etc.)
Updates on important issues and risks afflicting the project
3 End users Need to know about the upcoming changes to be effected in the existing set up
Regular updates on the project progress
Need to know about the business processes to be implemented in order to
facilitate:
Business process mapping•
Deeper involvement in plan and define phases•
4 Power users Access to regular updates on the project
Access to critical information related to their specific domains
To be provided with training in SAP to help in carrying out their activities
Need to understand the process changes to be carried out to facilitate business
process mapping
Table 1: Gathering Requirements from Stakeholders.
stakeholder category for effective stakeholder management,
which is explained and illustrated below (ables 1 and 2).
8/13/2019 PMI_SAP
http://slidepdf.com/reader/full/pmisap 4/5
PMI Virtual Library | www.PMI.org | © 2013 Sailendra Nath Swain
4
5 Indirect users Need to be informed about the change in their activities and in the new
environment
Need to be informed about the changes to be done to their existing modes of
operation
To have basic understanding of the new processes and system to be introduced
6 Project team members Access to regular updates on the project
Access to scope-related information
Conduct frequent interactive session with business usersTo be appraised of their roles and responsibilities in the team
To be informed about the project standards and quality processes
Access to project schedule and high-level plan
7 External parties (i.e.,
customers and vendors)
To be informed of the high-level activity plans that wil l affect them during the
project
Access to project updates
To be informed of changes to procedures and documentation on the project
*Requirements will be gathered from the stakeholders after holding several sessions with them.
SL
Number
Type of User Action Plan Communication Strategy
1 Business leads More involvement during planning phase Regular project status meetings1.
Email communication2.
Facilitating workshops3.
OCM (organizational change4.
management) workshops
CCB (change control board)5.
Meetings
Involvement in key business decisions
Involvement in impact analysis
Involvement in organizational change
management team
Stay informed of the project updates
2 Steering committee
members
Access to information related to financial and
budgetary status of the projects
Steering committee meetings1.
Governance review meeting2.
Regular status call3.
Email communication4.Access to major risks and issues afflicting the
project
3 End users Information on project updates Regular project status call1.
Email communication2.
Training session on different SAP3.
modules and business processes
To learn the new processes under each
assigned area
4 Power users Information on project updates Regular project status calls1.
Training session on different2.
processes
Change management workshops3.
Updates on key business processes
Training on key business processes
5 Indirect users Information on impacted processes Training session on impacted1.
processes
Change management workshops2.
Table 1: Gathering Requirements from Stakeholders (continued).
Table 2: Action Plans for the Stakeholders Requirements.
8/13/2019 PMI_SAP
http://slidepdf.com/reader/full/pmisap 5/5