PM592_wk_5

download PM592_wk_5

of 5

Transcript of PM592_wk_5

  • 7/31/2019 PM592_wk_5

    1/5

    Problems 5-1 through 5-2 (Graded)

    5-1 Earned Value Calculation

    You are 4 months into a 6 month project. The project is linear, which means that the progress and

    spending occurs at a constant rate. Our crack project team of highly skilled associates has worked

    diligently and put in extra hours to keep the project going. Our accounting department has provided the

    following data at the end of month 4:

    Actual cost to date = $88,800

    Planned expenditures to date = $101,000

    The CFO is excited and has sent you an email congratulating you for being 12.07% under budget.

    However, is it really time to hold a team celebration? That would be fun but your project manager

    mentality kicks in. Those numbers look good but how are we really doing? To understand the true

    project performance, we need to apply earned value techniques.

    The missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet

    with your team and find that only 6 of the 7 tasks scheduled to be complete by the end of month 4 have

    actually been completed. Task 7 isnt even started! This information gives you the final data you need to

    apply Earned Value and develop an objective analysis.

    1. What are the PV, EV, and AC for the project at the end of month 4?

    PV=BCWP/BCWS 1.78/4=.445

    EV=

    AC= 1475/4= $368.75

    2. What are the SV, CV, SPI, and CPI for the project?

    SV= BCWP-BCWS

    CV=BCWP-ACWP

    -1475overrun is negative

    SPI=BCWP/BCWS

    4

    CPI=BCWP/ACWP

    3.86

  • 7/31/2019 PM592_wk_5

    2/5

    3. Assess the project performance to date? Do you get to have the celebration?

    The Schedule Variance is not negative. This portion is on track. However, the CV has a overrun

    up the good work emails and communication. I believe in celebrating until the job of all tasks are

    completed, sealed and delivered.

    5-2 Earned Value Calculation

    Project Schedule and Budget Data Provided:

    Task Duration (days) Predecessor(s) Budget

    A 2 --- $1,600

    B 5 --- $4,000

    C 3 A $14,050

    D 4 B $5,800

    E 6 B $12,000

    F 4 C,D $5,200

    G 3 E $3,900

    Project Totals: $46,550

    Status of the project at the end of day 6:

    Task % Complete Actual Cost of Work Performed

    A 100% $1,800

    B 100% $4,500

    C 90% $13,500

    D 10% $500

    E 0% $0

    F 0% $0

    G 0% $0

  • 7/31/2019 PM592_wk_5

    3/5

    Project Network Diagram

    Critical Path (CP) = B E G = 14 days

    Tasks Duration (Days)

    A A A

    B B B B B B

    C C C C

    D D D D D

    E E E E E E E

  • 7/31/2019 PM592_wk_5

    4/5

    F F F F

    F

    G G

    G G

    0 1 2 3 4 5 6 7 8 9 10 11 12

    13 14 15 16

    1. Calculate the schedule variance for each task and the total project.

    a- 0

    b- 0

    c- 9132.50

    d- -870

    e- -

    f- -

    g- -

    Total 8262.50

    2. Calculate the cost variance for each task and the total project.

    a. -200

    b. -500

    c. -855

    d. 80

  • 7/31/2019 PM592_wk_5

    5/5

    e.

    f.

    g.

    Total -1475

    2. What is your assessment of the project at this time?

    Overall the project is not completed. Three of the tasks has bot even been started and the Task D only

    10% of this task has been completed. 30% of the project is completed and 70% needs to be completed.

    So the project needs to be placed back on task and need to be monitored daily to stay within the

    schedule restraints.