![Page 2: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/2.jpg)
Project: creating the Ganaxa website (1)
![Page 3: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/3.jpg)
Project: creating the Ganaxa website (2)
![Page 4: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/4.jpg)
Assumptions: Work to do
YOU (the PM) must now establish a PROJECT PLAN to be
given to the CO (on May 16, 2017 at the latest...).
The plan must cover everything to be done in order to
complete the project following the agreement on the
requirements (already obtained, as stated on the previous
page...), ie from content creation and site design to project
closure, not forgetting overall project management.
The plan must clearly show the project's tasks, task
sequencing, resources and resource allocation, schedule and
cost.
![Page 5: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/5.jpg)
Assumptions: WBS Content creation Site development Project management
Write bios
Translate bios
Procure other pictures
Produce diagram
Design site
Code site
Integrate content
Test site, fix bugs, re-test
Deploy site & go live
Manage/Supervise project
Accept site
Install & configure Wiki Review, adjust & agree on design
Close project
Call for content
Write other texts
Translate other texts
![Page 6: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/6.jpg)
Assumptions: Resources *
Thibault de la Rivière
TC
TJ
CO
Staff
External contractor
PM (YOU!)
PM
TC
TJ
OC
DD
CO
€
OC group member
OC group member
OC group member
OC group member
Graphic Designer & Web Developer
Company Owner / Project Sponsor
Project Manager (& major contributor)
Translator/Tester – Chinese (& English)
Translator/Tester – Japanese (& French)
Other (minor) Contributors (group of 4)
* No more, no less!
![Page 7: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/7.jpg)
Assumptions: Costs *
Thibault de la Rivière
TC
TJ
CO
Staff
External contractor
PM (YOU!)
PM
TC
TJ
OC
DD
CO
€
OC group member
OC group member
Not taken into account
€ 500 per day
€ 320 per day
€ 300 per day
Not taken into account
€ 650 per day * No costs other than labour!
OC group member
OC group member
![Page 8: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/8.jpg)
Assumptions: Resource assignment Approves* site design; writes his own bio & other texts (in FR); procures pictures; accepts website; participates in closure.
Manages the project part-time [25%]; issues "call for content"; installs wiki; approves* site design; writes his own bio (EN & FR); translates texts (FR <-> EN); draws GPP diagram (EN & FR); participates in testing; accepts website; participates in closure.
Writes her own bio (CH & EN); translates texts (EN -> CH); participates in testing part-time [25%]; participates in closure.
Writes her own bio (JA & FR); translates texts (FR -> JA); participates in testing part-time [25%]; participates in closure.
Write their own bios (in FR). Thibault de la Rivière
TC
TJ
CO
Staff
External contractor
* "approves" is short for "reviews, adjusts and agrees on"
PM (YOU!)
PM
TC
TJ
OC
DD
CO
€
OC group member
OC group member
Designs the site, enhances GPP diagram & approves* site design; codes the site; integrates content; fixes technical bugs; deploys the site; participates in closure.
OC group member
OC group member
![Page 9: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/9.jpg)
Assumptions: Content 17 pages of text in total to write and/or translate:
8 biographies ("bios") (written in FR by each person concerned, translated by PM, TC & TJ)
8 other pages of text (written in FR by CO, translated by PM, TC & TJ)
1 page of text in GPP diagram (written in FR & EN by PM, translated by TC & TJ)
Pictures:
GPP diagram (prepared by PM, translated by TC & TJ, then enhanced by DD for the site)
Other pictures (procured by CO)
Editorial specifications are included in the Requirements
Specification ("editorial design" task not required in the plan).
![Page 10: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/10.jpg)
Assumptions: Task workloads/durations *
Writing 5 of the 8 bios (the CO's + the OC's)
Procuring other pictures
Writing or translating 1 page of text
Drawing (with text in EN & FR) then enhancing
the GPP diagram (after translation into CH & JA,
and after site design)
5 person-hours spread over 3 days
1 person-day spread over 4 days
4 person-hours
1 person-hour (on average)
(* Including proofreading when relevant, formatting and uploading to the wiki)
4 person-hours
(drawing, with text, by PM) (enhancing, by DD)
Project management 25% of PM's time from day 2 through to deployment
![Page 11: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/11.jpg)
Other assumptions (1) The PM launches the editorial part of the project by issuing a
"call for content" (ie an e-mail to all contributors) on day 1.
Editorial contributors other than the PM start work on day 2.
A wiki is installed & configured (by the PM) on day 1 and used
for delivery of content to the DD (upload/download).
Final content (fully proofread, therefore bug-free, and properly
formatted) is uploaded to the wiki as it is produced by editorial
contributors, then, after the site has been coded, is downloaded
by the DD and integrated into the site ("container").
(Sample content was already given to DD at the preliminary meeting, so there
is no need to include "Sample content preparation/delivery" in the plan.)
![Page 12: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/12.jpg)
Other assumptions (2) CO has committed to writing the "other 8 pages of text" (in
French) on day 2.
CO has committed to "procuring pictures" (other than the GPP
diagram) but cannot work on the task full time, which is why the
assumed 8-person-hours workload is spread over 4 days (starting
whenever possible...).
CO & OC (the group of 4 "Other (minor) Contributors") are not
readily available for "writing their own bios" (in French), which is
why the assumed 5-person-hours workload is spread over 3 days
(starting on day 2).
TC & TJ are available as of day 2.
PM and DD are available as of day 1.
![Page 13: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/13.jpg)
Constraints Start date = May 29, 2017
Total duration of project no longer than 3.5 weeks
(Finish date no later than June 21, 2017)
8 hours per working day (standard setting in MS Project)
5-day weeks (no work on weekends)
Public holidays not taken into account (to keep things simple!)
Nobody to work more than 100% of her/his time, except for
the PM and the CO, who may work up to 130% of their time
Total labour cost of project no greater than € 18,000
![Page 14: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/14.jpg)
Imagine YOU are the PM for this project!
Take into account the relevant information given on the
previous pages of this document.
Download, copy & complete the project plan (.mpp/.pod):
1) define resources (with unit costs) in the "Resource
sheet" (use the given 2-letter abbreviations to name resources!);
2) enter appropriate "Resource Names" information in
the "Gantt chart";
3) enter appropriate "Predecessors" information in the
"Gantt chart", featuring parallelism between tasks
whenever possible.
using MS Project or ProjectLibre
Assignment instructions (1)
Note: you may need to adjust durations at the lowest level of the WP/task hierarchy to their initial values (as they appear in the incomplete plan provided).
PM
![Page 15: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/15.jpg)
Project GANAXA – Plan to complete (.mpp)
Will be (re)calculated automatically
? ?
Durations at the lowest level should have the same values in the completed plan as they have here.
![Page 16: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/16.jpg)
Project GANAXA – Plan to complete (.pod)
Will be (re)calculated automatically
? ?
Durations at the lowest level should have the same values in the completed plan as they have here.
![Page 17: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/17.jpg)
Check & double-check your project plan!!
Send your plan (a single ".mpp" or ".pod" file) to [email protected]
as soon as possible before Wednesday May 17, 2017.
Failure to meet the deadline will result in a 0 (zero) grade!
Name your file as follows: "YOURNAME_GX_PLAN...", where...
"YOURNAME" is your "FAMILY NAME" (eg "SINGH_GX_PLAN.mpp")
Failure to comply with this file naming convention will result in a penalty!
Assignment instructions (2)
(Failure to comply with the resource naming convention ( 2-letter abbr.) will also result in a penalty!)
![Page 18: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/18.jpg)
Reminder: Project phases (1)
Business case
Advisability study
Feasibility study
Execution Closure Planning
Plan implementation
Product creation
Project supervision
Requirements
Charter
Scope
Schedule
Budget
Product launch
Project plan
Summary requirements
![Page 19: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/19.jpg)
Reminder: Project phases (2)
Business case
Advisability study
Feasibility study
Execution Closure Planning
Plan implementation
Product creation
Project supervision
Requirements
Charter
Scope
Schedule
Budget
Product launch
Project plan
Requirements Integration Design Testing &
Acceptance Deployment
Content creation
Software coding
Summary requirements
![Page 20: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/20.jpg)
Execution
Project phases relevant to assignment
Business case
Advisability study
Feasibility study
Closure Planning
Plan implementation
Product creation
Project supervision
Requirements
Product launch
Project plan
Requirements Integration
Design
Testing & Acceptance
Deployment
Content creation
Software coding
Charter
Scope
Schedule
Budget
Provided by the Company Owner
Done by the Project Manager
Summary requirements
Produced in preliminary meeting/workshop
![Page 21: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/21.jpg)
Project plan
Project phases to be covered by the plan
Business case
Advisability study
Feasibility study
Execution Closure Planning
Plan implementation
Product creation
Project supervision
Requirements
Charter
Scope
Schedule
Budget
Product launch
Requirements Integration Testing &
Acceptance Deployment
Content creation
Software coding
Design
![Page 22: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/22.jpg)
Reminder: Project planning processes
Define scope & collect
requirements
Develop schedule Determine budget
Create WBS
Define tasks
Sequence tasks
Estimate task resources
Plan procurements
Estimate costs
Plan communications
Plan quality
Estimate task durations
Develop human resource plan
Plan risk management,
identify & analyze risks
![Page 23: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/23.jpg)
Processes relevant to assignment
Define scope & collect
requirements
Develop schedule
Create WBS
Define tasks
Sequence tasks
Estimate task resources
Plan procurements
Plan communications
Plan quality
Estimate task durations
Develop human resource plan
Plan risk management,
identify & analyze risks
Determine budget Estimate costs
![Page 24: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/24.jpg)
Reminder: Interdependent processes
Sequence tasks
Estimate task resources
Estimate task durations
Develop schedule
![Page 25: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/25.jpg)
Questions?
![Page 26: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/26.jpg)
A project plan
![Page 27: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/27.jpg)
Assumptions: WBS Content creation Site development Project management
Write bios
Translate bios
Procure other pictures
Produce diagram
Design site
Code site
Integrate content
Test site, fix bugs, re-test
Deploy site & go live
Manage/Supervise project
Accept site
Install & configure Wiki Review, adjust & agree on design
Close project
Call for content
Write other texts
Translate other texts
![Page 28: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/28.jpg)
Content creation diagram (1) Create Wiki
Call for content
PM PM
done on day 1
![Page 29: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/29.jpg)
Content creation diagram (2)
Write own bio in English & French
Draw diagram
Create Wiki
Call for content
CO
PM
Write 5 bios in French
Write other 8 pages of text in French
PM PM
PM
CO
Write own bio in Japanese & French
Write own bio in Chinese & English
TJ
TC
OC
started on day 2, spread over 3 days
done on day 2
done on day 2
![Page 30: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/30.jpg)
Content creation diagram (3)
Write own bio in English & French
Draw diagram
Create Wiki
Call for content
CO
PM
Write 5 bios in French
Write other 8 pages of text in French
PM PM
PM
CO
Translate diagram text into Japanese
Translate diagram text into Chinese
TJ
TC
Write own bio in Japanese & French
Write own bio in Chinese & English
TJ
TC
OC
done on day 2
started on day 2, spread over 3 days
done on day 2
done on day 2
![Page 31: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/31.jpg)
Content creation diagram (4)
Write own bio in English & French
Draw diagram
Create Wiki
Call for content
PM
CO
PM
Write 5 bios in French
Write other 8 pages of text in French
Translate 8 pages into English
Translate 8 pages into Japanese
PM PM
PM
TJ
CO
Translate diagram text into Japanese
Translate diagram text into Chinese
TJ
TC
Write own bio in Japanese & French
Write own bio in Chinese & English
TJ
TC
CO
Procure other pictures
OC
done on day 3
started on day 3, spread over 4 days
started on day 2, spread over 3 days
![Page 32: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/32.jpg)
Content creation diagram (5)
Write own bio in English & French
Draw diagram
Create Wiki
Call for content
PM
CO
PM
Write 5 bios in French
Write other 8 pages of text in French
Translate 8 pages into English
Translate 8 pages into Chinese
Translate 8 pages into Japanese
PM PM
PM
TC
TJ
CO
Translate diagram text into Japanese
Translate diagram text into Chinese
TJ
TC
Write own bio in Japanese & French
Write own bio in Chinese & English
TJ
TC
CO
Procure other pictures
OC
done on day 4
completed on day 4
started on day 3, spread over 4 days
![Page 33: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/33.jpg)
Content creation diagram (6)
Write own bio in English & French
Translate 7 bios into English (or French)
Draw diagram
Create Wiki
Call for content
PM
CO
PM
Write 5 bios in French
Write other 8 pages of text in French
Translate 8 pages into English
Translate 8 pages into Chinese
Translate 8 pages into Japanese
PM PM
PM
PM
TC
TJ
CO
Translate diagram text into Japanese
Translate diagram text into Chinese
TJ
TC
Write own bio in Japanese & French
Write own bio in Chinese & English
TJ
TC
CO
Procure other pictures
OC
done on day 5
started on day 3, spread over 4 days
![Page 34: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/34.jpg)
Content creation diagram (7)
Write own bio in English & French
Translate 7 bios into English (or French)
Draw diagram
Create Wiki
Call for content
PM
CO
PM
Write 5 bios in French
Write other 8 pages of text in French
Translate 7 bios into Chinese
Translate 8 pages into English
Translate 8 pages into Chinese
Translate 8 pages into Japanese
PM PM
PM
PM TC
TC
TJ
CO
Translate 7 bios into Japanese
TJ
Translate diagram text into Japanese
Translate diagram text into Chinese
TJ
TC
Write own bio in Japanese & French
Write own bio in Chinese & English
TJ
TC
CO
Procure other pictures
OC
done on day 6
completed on day 6
![Page 35: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/35.jpg)
Content creation diagram (8)
Write own bio in English & French
Translate 7 bios into English (or French)
Draw diagram
Create Wiki
Call for content
PM
CO
PM
Write 5 bios in French
Write other 8 pages of text in French
Translate 7 bios into Chinese
Translate 8 pages into English
Translate 8 pages into Chinese
Translate 8 pages into Japanese
PM PM
PM
PM TC
TC
TJ
Enhance diagram
DD
CO
Translate 7 bios into Japanese
TJ
Translate diagram text into Japanese
Translate diagram text into Chinese
TJ
TC
Write own bio in Japanese & French
Write own bio in Chinese & English
TJ
TC
CO
Procure other pictures
OC
![Page 36: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/36.jpg)
Project network diagram (1) Create Wiki
Call for content
Design site
PM
DD
PM
done on day 1
started on day 1
![Page 37: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/37.jpg)
Project network diagram (2)
Write other texts
Draw diagram
Create Wiki
Translate diagram
Call for content
Overall project management
Design site
Write bios
PM
CO
PM [25%]
DD
TC, TJ, OC
PM PM TC, TJ
CO
PM
started on day 2, spread over 3 days for CO & OC
done on day 2
continued on day 2
done on day 2 as of day 2
![Page 38: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/38.jpg)
Project network diagram (3)
Write other texts
Translate other texts
Draw diagram
Create Wiki
Translate diagram
Call for content
Overall project management
Design site
Write bios
Translate bios
PM
CO
PM [25%]
DD
TC, TJ, OC
PM, TC, TJ
PM PM TC, TJ
PM, TC, TJ
CO
PM
Procure other pictures
CO
done on day 3 and day 4
done on day 5 and day 6
continued on day 3
started on day 3, spread over 4 days
![Page 39: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/39.jpg)
Project network diagram (4)
Write other texts
Translate other texts
Draw diagram
Enhance diagram
Create Wiki
Translate diagram
Call for content
Overall project management
Design site
Write bios
Translate bios
PM
CO
PM [25%]
DD
TC, TJ, OC
PM, TC, TJ
PM PM
DD
TC, TJ
PM, TC, TJ
CO
PM
Procure other pictures
CO
completed on day 3
![Page 40: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/40.jpg)
Project network diagram (5)
Write other texts
Translate other texts
Draw diagram
Enhance diagram
Create Wiki
Translate diagram
Review, adjust & agree on design
Call for content
Overall project management
Design site
Write bios
Translate bios
PM
CO
PM [25%]
DD
TC, TJ, OC
PM, TC, TJ
PM PM
DD
TC, TJ
PM, DD, CO
PM, TC, TJ
CO
PM
Procure other pictures
CO
done on day 4
![Page 41: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/41.jpg)
Project network diagram (6)
Write other texts
Translate other texts
Draw diagram
Enhance diagram
Code site
Create Wiki
Translate diagram
Review, adjust & agree on design
Call for content
Overall project management
Design site
Write bios
Translate bios
PM
CO
PM [25%]
DD DD
TC, TJ, OC
PM, TC, TJ
PM PM
DD
TC, TJ
PM, DD, CO
PM, TC, TJ
CO
PM
Procure other pictures
CO
![Page 42: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/42.jpg)
Project network diagram (7)
Write other texts
Translate other texts
Draw diagram
Enhance diagram
Code site
Integrate content
Create Wiki
Translate diagram
Review, adjust & agree on design
Call for content
Overall project management
Design site
Write bios
Translate bios
PM
CO
PM [25%]
DD DD DD
TC, TJ, OC
PM, TC, TJ
PM PM
DD
TC, TJ
PM, DD, CO
PM, TC, TJ
CO
PM
Procure other pictures
CO
![Page 43: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/43.jpg)
Project network diagram (8)
Write other texts
Translate other texts
Draw diagram
Enhance diagram
Code site
Integrate content
Create Wiki
Test, debug, re-test site
Accept site
Translate diagram
Review, adjust & agree on design
Call for content
Overall project management
Design site
Deploy site
Close project
Write bios
Translate bios
PM
DD
CO
PM [25%]
PM, TC[25%], TJ[25%], DD
PM, TC, TJ, DD, CO
PM, CO DD DD DD
TC, TJ, OC
PM, TC, TJ
PM PM
DD
TC, TJ
PM, DD, CO
PM, TC, TJ
CO
PM
Procure other pictures
CO
![Page 44: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/44.jpg)
Questions?
![Page 45: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/45.jpg)
A plan using MS Project
(or ProjectLibre)
![Page 46: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/46.jpg)
List of tasks (in MS Project)
![Page 47: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/47.jpg)
List of tasks (in ProjectLibre)
![Page 48: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/48.jpg)
Resource sheet (.mpp & .pod)
![Page 49: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/49.jpg)
Gantt view (.mpp) – Resource assignment
![Page 50: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/50.jpg)
Gantt view (.pod) – Resource assignment
![Page 51: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/51.jpg)
Gantt view (.mpp) – Task sequencing
![Page 52: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/52.jpg)
Gantt view (.pod) – Task sequencing
![Page 53: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/53.jpg)
Gantt view (.mpp) – Complete plan
![Page 54: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/54.jpg)
Gantt view (.pod) – Complete plan
![Page 55: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/55.jpg)
Gantt view (.mpp) – Diagram
![Page 56: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/56.jpg)
Gantt view (.pod) – Diagram
![Page 57: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/57.jpg)
Resource usage (.mpp)
![Page 58: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/58.jpg)
Resource usage (.pod)
![Page 59: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/59.jpg)
Resource costs for project (.mpp & .pod)
![Page 60: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/60.jpg)
Questions?
![Page 61: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/61.jpg)
A plan using Excel
![Page 62: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/62.jpg)
Project plan (with Excel) – List of tasks
![Page 63: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/63.jpg)
Project plan – Resources & unit costs
![Page 64: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/64.jpg)
Project plan – Durations
![Page 65: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/65.jpg)
Project plan – Schedule
![Page 66: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/66.jpg)
Project plan – Costs
![Page 67: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/67.jpg)
Questions?
![Page 68: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/68.jpg)
Risk analysis
![Page 69: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/69.jpg)
Assumptions & risks - 1 Assumption: the site design needs to be reviewed and agreed
upon by both the PM and the developer, as well as by the
project owner.
Risk: none (there would have been a significant risk if these tasks had not been performed!).
The PM and the project owner should approve the design before development starts.
The PM and the project owner should also both validate the
website before it is opened to the public.
![Page 70: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/70.jpg)
Assumption: 20 hours for design, 40 hours for coding, 16 hours for content integration, 32 hours for testing and bug
fixing, 4 hours for acceptance, 4 hours for deployment, etc.
Risk: these duration estimates may be optimistic or pessimistic.
Possible negative or positive impact on schedule
The risk is low because the assumptions are reasonable and the figures result from the cooperative requirements analysis
and discussion with the developer and other people involved.
Assumptions & risks - 2
![Page 71: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/71.jpg)
Assumption: people supposed to provide content are available to do so.
Risk: people may not be available as expected.
Possible negative impact on schedule
The PM should…
check the actual availability of contributors,
make a call for content as early as possible, set a deadline for contributions and send reminders as necessary,
ask the project owner for help in motivating contributors to respond without delay,
make a provision for this risk in the schedule.
Assumptions & risks - 3
![Page 72: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/72.jpg)
Assumption: a wiki needs to be installed to upload/download content; this should take 7 hours.
Risk: creating the wiki may take longer than planned.
Possible negative impact on schedule
The risk is low because the estimated duration of this task is based on experience.
If a wiki had not been created, some other mechanism for uploading/downloading content would have had to be set up.
Assumptions & risks - 4
![Page 73: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/73.jpg)
Assumption: the use of a wiki to upload/download content does not present any problem as regards text in Chinese and
Japanese.
Risk: Chinese and Japanese text may be corrupted.
Negative impact on quality of content
A test should be performed with representative samples of Chinese and Japanese text.
If necessary, an alternative method should be devised for
sending content in Chinese and Japanese to the developer.
Assumptions & risks - 5
![Page 74: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/74.jpg)
Assumption: the translators proofread their own translations.
Risk: translation errors and typos may be overlooked.
Possible negative impact on quality of content
With this particular project, the risk may be considered minor,
given the relatively small quantity of text and the quality of the persons involved.
As a rule, text should be reviewed by a qualified professional proofreader for each language.
Assumptions & risks - 6
![Page 75: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/75.jpg)
Assumption: apart from proofreading, only one person (the PM) is involved full-time in the testing tasks, and there is only
one bug-fixing task.
Risk: some bugs may be overlooked or not fixed.
Negative impact on quality of website
With this particular project, the risk is very low, given the relative simplicity of the website.
As a rule, a website (or any other product) should be tested
(after "internal testing" by the developer) by more people than just the PM, and there should be more than a single sequence of "testing, bug-fixing, re-testing".
Assumptions & risks - 7
![Page 76: PM - Ganaxa case study & assignment - a project planneil.minkley.fr/epita/REF_GX_SOLUTION.pdf · Ganaxa case study & assignment: a project plan ... not forgetting overall project](https://reader034.fdocuments.us/reader034/viewer/2022051909/5ffdb7858c4abc11ee29192a/html5/thumbnails/76.jpg)
Questions?