PM Flashcards
-
Upload
elizaefendi -
Category
Technology
-
view
4.503 -
download
1
description
Transcript of PM Flashcards
20052005 11
Project ManagementProject ManagementFlash CardsFlash Cards
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 22
Project ManagementProject ManagementFlash CardsFlash Cards
A Guide to the Project Management Body of A Guide to the Project Management Body of Knowledge (PMBOK)Knowledge (PMBOK)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The project management standard developed The project management standard developed by the Project Management Institute.by the Project Management Institute.
20052005 33
Project ManagementProject ManagementFlash CardsFlash Cards
AcceptanceAcceptance
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The decision to tolerate the defects that are The decision to tolerate the defects that are found as a result of the quality testing. Also a found as a result of the quality testing. Also a tool for risk response planning.tool for risk response planning.
20052005 44
Project ManagementProject ManagementFlash CardsFlash Cards
Activity definitionActivity definition
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Identifying the activities of the project that need Identifying the activities of the project that need to be performed to produce the product or to be performed to produce the product or service of the project.service of the project.
20052005 55
Project ManagementProject ManagementFlash CardsFlash Cards
Activity duration estimatingActivity duration estimating
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Assessing the number of work periods needed Assessing the number of work periods needed to complete the project activities. Work periods to complete the project activities. Work periods are usually expressed in hours or days. Large are usually expressed in hours or days. Large projects might express duration in weeks or projects might express duration in weeks or months.months.
20052005 66
Project ManagementProject ManagementFlash CardsFlash Cards
Activity sequencingActivity sequencing
Sequencing activities in logical order and Sequencing activities in logical order and determining whether dependencies exist among determining whether dependencies exist among the activities.the activities.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 77
Project ManagementProject ManagementFlash CardsFlash Cards
Administrative closureAdministrative closure
Gathering and disseminating information to Gathering and disseminating information to formalize project closure. The completion of formalize project closure. The completion of each project phase requires administrative each project phase requires administrative closure also.closure also.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 88
Project ManagementProject ManagementFlash CardsFlash Cards
Analogous estimatingAnalogous estimating
An estimating technique that uses the actual An estimating technique that uses the actual duration of a similar, completed activity to duration of a similar, completed activity to determine the duration of the current activity. determine the duration of the current activity. Also called top down estimating.Also called top down estimating.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 99
Project ManagementProject ManagementFlash CardsFlash Cards
Appraisal costsAppraisal costs
Costs that cover the activities that keep the Costs that cover the activities that keep the product defects from reaching the client, product defects from reaching the client, including inspection, testing, and formal quality including inspection, testing, and formal quality audits.audits.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1010
Project ManagementProject ManagementFlash CardsFlash Cards
AssumptionAssumption
An event or action believed to be true. Project An event or action believed to be true. Project assumptions should always be documented.assumptions should always be documented.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1111
Project ManagementProject ManagementFlash CardsFlash Cards
Backward passBackward pass
Calculating a late start and late finish date by Calculating a late start and late finish date by starting at the end of a network diagram and starting at the end of a network diagram and working back through each path until reaching working back through each path until reaching the start of the network diagram. This is a part the start of the network diagram. This is a part of CPM, which is a mathematical technique to of CPM, which is a mathematical technique to develop the project schedule.develop the project schedule.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1212
Project ManagementProject ManagementFlash CardsFlash Cards
BenchmarkingBenchmarking
Compares previous similar activities to the Compares previous similar activities to the current project activities to provide a standard current project activities to provide a standard to measure performance against. It’s often used to measure performance against. It’s often used to derive ideas for quality improvements for the to derive ideas for quality improvements for the project.project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1313
Project ManagementProject ManagementFlash CardsFlash Cards
Benefit measurement methodsBenefit measurement methods
A type of decision model that compares the A type of decision model that compares the benefits obtained from a variety of new project benefits obtained from a variety of new project requests by evaluating them using the same requests by evaluating them using the same criteria and comparing the results.criteria and comparing the results.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1414
Project ManagementProject ManagementFlash CardsFlash Cards
Bottom up estimatingBottom up estimating
Every activity or work item is individually Every activity or work item is individually estimated and then rolled up, or added estimated and then rolled up, or added together, to come up with a total project together, to come up with a total project estimate. This is a very accurate means of estimate. This is a very accurate means of estimating, provided the estimates at the work estimating, provided the estimates at the work package level are accurate.package level are accurate.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1515
Project ManagementProject ManagementFlash CardsFlash Cards
Budget analystBudget analyst
A person in the department or organization who A person in the department or organization who handles the budgetary elements of enterprise.handles the budgetary elements of enterprise.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1616
Project ManagementProject ManagementFlash CardsFlash Cards
Budget at completion (BAC)Budget at completion (BAC)
The total amount of the project budget as The total amount of the project budget as estimated during the planning phase.estimated during the planning phase.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1717
Project ManagementProject ManagementFlash CardsFlash Cards
Business analyst (BA)Business analyst (BA)
Person in charge of understanding the business Person in charge of understanding the business unit’s needs when assessing a project request. unit’s needs when assessing a project request. The business analyst might be assigned directly The business analyst might be assigned directly from the business unit itself, or may be apart of from the business unit itself, or may be apart of the IT organization.the IT organization.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1818
Project ManagementProject ManagementFlash CardsFlash Cards
Business caseBusiness case
Formally documents components of the project Formally documents components of the project assessment, including a description of the assessment, including a description of the analysis method and the results.analysis method and the results.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 1919
Project ManagementProject ManagementFlash CardsFlash Cards
Business process reengineeringBusiness process reengineering
Applying changes to an IT system and putting Applying changes to an IT system and putting those elements into place based on a project those elements into place based on a project request and a business analyst’s examination of request and a business analyst’s examination of the work flow – hoe people handle their work the work flow – hoe people handle their work relative to the request.relative to the request.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2020
Project ManagementProject ManagementFlash CardsFlash Cards
Business requirementsBusiness requirements
The big picture results of fulfilling a project.The big picture results of fulfilling a project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2121
Project ManagementProject ManagementFlash CardsFlash Cards
Commercial off the shelf (COTS)Commercial off the shelf (COTS)
A software application that is purchased from a A software application that is purchased from a reseller, vendor, or manufacturer.reseller, vendor, or manufacturer.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2222
Project ManagementProject ManagementFlash CardsFlash Cards
Communications management planCommunications management plan
Documents the types of information needs the Documents the types of information needs the stakeholders have, when the information should stakeholders have, when the information should be distributed, and how the information will be be distributed, and how the information will be delivered. delivered.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2323
Project ManagementProject ManagementFlash CardsFlash Cards
Communications planningCommunications planning
This planning process determines the This planning process determines the communication needs of the stakeholders, when communication needs of the stakeholders, when and how the information will be received, and and how the information will be received, and who will receive the information.who will receive the information.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2424
Project ManagementProject ManagementFlash CardsFlash Cards
Comprehensive project planComprehensive project plan
Integrates all planning data into one document Integrates all planning data into one document that the project manager can be use as a that the project manager can be use as a guidebook to oversee the project work during guidebook to oversee the project work during the Execution and controlling phases.the Execution and controlling phases.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2525
Project ManagementProject ManagementFlash CardsFlash Cards
Configuration ManagementConfiguration Management
Describes the characteristics of the product of Describes the characteristics of the product of the project and ensures the description is the project and ensures the description is accurate and complete. Controls changes to the accurate and complete. Controls changes to the characteristics of an item, and tracks the characteristics of an item, and tracks the changes made or requested and their status. It changes made or requested and their status. It is usually a subset of the change control process is usually a subset of the change control process in most organizations, or it may serve as the in most organizations, or it may serve as the change control system.change control system.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2626
Project ManagementProject ManagementFlash CardsFlash Cards
Constrained optimization modelsConstrained optimization models
Decision models that use complex principles of Decision models that use complex principles of statistics and other mathematical concepts to statistics and other mathematical concepts to assess a proposed project.assess a proposed project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2727
Project ManagementProject ManagementFlash CardsFlash Cards
ConstraintConstraint
Anything that either restricts the actions of the Anything that either restricts the actions of the project team or dictates the actions of the project team or dictates the actions of the project team.project team.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2828
Project ManagementProject ManagementFlash CardsFlash Cards
Contingency reserveContingency reserve
An amount of money or time set aside and An amount of money or time set aside and dedicated to the project to be used to cover dedicated to the project to be used to cover unforeseen costs within the original scope of the unforeseen costs within the original scope of the project that were not identified as part of the project that were not identified as part of the planning process.planning process.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 2929
Project ManagementProject ManagementFlash CardsFlash Cards
ContractContract
A legal document that covers the work that will be A legal document that covers the work that will be done, how the work will be compensated, and any done, how the work will be compensated, and any penalties for noncompliance.penalties for noncompliance.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3030
Project ManagementProject ManagementFlash CardsFlash Cards
Contract administrationContract administration
The process of monitoring vendor performance The process of monitoring vendor performance and ensuring all the requirements of the and ensuring all the requirements of the contract are met. contract are met.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3131
Project ManagementProject ManagementFlash CardsFlash Cards
Contract closeoutContract closeout
The process of completing and settling the The process of completing and settling the terms of the contract and determining whether terms of the contract and determining whether the work described in the contract was the work described in the contract was completed accurately and satisfactorily.completed accurately and satisfactorily.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3232
Project ManagementProject ManagementFlash CardsFlash Cards
Control chartControl chart
A graph of the variance of several samples of A graph of the variance of several samples of the same process over time based on a mean, the same process over time based on a mean, an upper control limit, and a lower control limit.an upper control limit, and a lower control limit.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3333
Project ManagementProject ManagementFlash CardsFlash Cards
Cost baselineCost baseline
The expected cost of the project from the The expected cost of the project from the planning phase. Used as a comparison to actual planning phase. Used as a comparison to actual project expenses.project expenses.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3434
Project ManagementProject ManagementFlash CardsFlash Cards
Cost-benefit analysisCost-benefit analysis
A commonly used benefit measurement method A commonly used benefit measurement method that calculates the cost, the projected savings, that calculates the cost, the projected savings, and projected revenue of a project.and projected revenue of a project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3535
Project ManagementProject ManagementFlash CardsFlash Cards
Cost budgetingCost budgeting
Assigning cost estimates to activities and Assigning cost estimates to activities and creating the cost baseline, which measures the creating the cost baseline, which measures the variance and performance of the project variance and performance of the project throughout the project’s life.throughout the project’s life.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3636
Project ManagementProject ManagementFlash CardsFlash Cards
Cost controlCost control
Managing the changes to project costs using the Managing the changes to project costs using the cost change control system.cost change control system.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3737
Project ManagementProject ManagementFlash CardsFlash Cards
Cost estimatingCost estimating
Developing an approximation of the cost of Developing an approximation of the cost of resources needed for each project activity.resources needed for each project activity.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3838
Project ManagementProject ManagementFlash CardsFlash Cards
Cost of qualityCost of quality
The cost of all of the work required to assure the The cost of all of the work required to assure the project meets the quality standards. The three project meets the quality standards. The three costs associated with the cost of quality are costs associated with the cost of quality are prevention costs, appraisal costs, and failure prevention costs, appraisal costs, and failure costs.costs.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 3939
Project ManagementProject ManagementFlash CardsFlash Cards
Cost performance index (CPI)Cost performance index (CPI)
A project tracking mechanism that compares A project tracking mechanism that compares the budgeted cost to the actual cost using the budgeted cost to the actual cost using ratios. The formula is CPI=EV/ACratios. The formula is CPI=EV/AC
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4040
Project ManagementProject ManagementFlash CardsFlash Cards
Cost reimbursable contractCost reimbursable contract
Provides a seller with payment of all costs Provides a seller with payment of all costs incurred to deliver the product and includes a incurred to deliver the product and includes a fee to cover the seller’s profit.fee to cover the seller’s profit.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4141
Project ManagementProject ManagementFlash CardsFlash Cards
Cost varianceCost variance
The difference between a task’s estimated The difference between a task’s estimated (budgeted) cost and its actual cost.(budgeted) cost and its actual cost.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4242
Project ManagementProject ManagementFlash CardsFlash Cards
CrashingCrashing
Adding resources to a project to reduce the time Adding resources to a project to reduce the time it takes to complete the project.it takes to complete the project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4343
Project ManagementProject ManagementFlash CardsFlash Cards
Critical path (CP)Critical path (CP)
The longest path through the project’s network The longest path through the project’s network diagram that’s made up of activities with zero diagram that’s made up of activities with zero float.float.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4444
Project ManagementProject ManagementFlash CardsFlash Cards
Critical path method (CPM)Critical path method (CPM)
A schedule development method that A schedule development method that determines a single early and late start date, determines a single early and late start date, early and late finish date, and float for each early and late finish date, and float for each activity on the project.activity on the project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4545
Project ManagementProject ManagementFlash CardsFlash Cards
CustomerCustomer
The recipient of the product or service created The recipient of the product or service created by the project. In some organizations this by the project. In some organizations this stakeholder may also be referred to as the stakeholder may also be referred to as the client.client.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4646
Project ManagementProject ManagementFlash CardsFlash Cards
Database administrators (DBAs)Database administrators (DBAs)
People that handle the databases that systems People that handle the databases that systems use.use.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4747
Project ManagementProject ManagementFlash CardsFlash Cards
Database schemaDatabase schema
The structure of a given database, which defines The structure of a given database, which defines the tables in the database and their data the tables in the database and their data elements (fields), as well as the relationships elements (fields), as well as the relationships between the tables.between the tables.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4848
Project ManagementProject ManagementFlash CardsFlash Cards
Data flow diagram (DFD)Data flow diagram (DFD)
A block diagram that describes how data is A block diagram that describes how data is entered into a system resulting in useful entered into a system resulting in useful information.information.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 4949
Project ManagementProject ManagementFlash CardsFlash Cards
DatacenterDatacenter
The primary room in an organization’s building The primary room in an organization’s building where the servers are housed. Often the where the servers are housed. Often the routers, switches, and telephony gear are kept routers, switches, and telephony gear are kept in the datacenter as well, in which case it may in the datacenter as well, in which case it may be called an MDF (Main Data Facility).be called an MDF (Main Data Facility).
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5050
Project ManagementProject ManagementFlash CardsFlash Cards
Decision modelDecision model
A formal method of project selection that helps A formal method of project selection that helps managers make the best use of limited budgets managers make the best use of limited budgets and human resources. Includes benefit and human resources. Includes benefit measurement methods and constrained measurement methods and constrained optimization models.optimization models.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5151
Project ManagementProject ManagementFlash CardsFlash Cards
DecompositionDecomposition
The process of breaking project deliverables The process of breaking project deliverables down into smaller, manageable components so down into smaller, manageable components so that project tasks and activities can be planned that project tasks and activities can be planned and estimated.and estimated.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5252
Project ManagementProject ManagementFlash CardsFlash Cards
Definitive estimateDefinitive estimate
An estimating technique that assigns a cost An estimating technique that assigns a cost estimate to each work package in the project estimate to each work package in the project WBS. The most accurate of the cost estimating WBS. The most accurate of the cost estimating techniques.techniques.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5353
Project ManagementProject ManagementFlash CardsFlash Cards
DemarcationDemarcation
The termination juncture where a The termination juncture where a telecommunications company provides the telecommunications company provides the interface for wide area networking (WAN) interface for wide area networking (WAN) services, such as T1 or ISDN.services, such as T1 or ISDN.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5454
Project ManagementProject ManagementFlash CardsFlash Cards
DependenciesDependencies
The relationship between two project activities.The relationship between two project activities.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5555
Project ManagementProject ManagementFlash CardsFlash Cards
Dependency relationshipsDependency relationships
Identifying the type of dependency between two Identifying the type of dependency between two activities and the specific relationship between activities and the specific relationship between the activities.the activities.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5656
Technology Project Management Technology Project Management Flash CardsFlash Cards
Discounted cash flow (DCF)Discounted cash flow (DCF)
Compares the value of the future cash flows of Compares the value of the future cash flows of the project to today’s dollars.the project to today’s dollars.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5757
Project ManagementProject ManagementFlash CardsFlash Cards
Discretionary dependencyDiscretionary dependency
Something that the project manager and project Something that the project manager and project team choose to impose on the project schedule, team choose to impose on the project schedule, such as the use of an established corporate such as the use of an established corporate practice.practice.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5858
Project ManagementProject ManagementFlash CardsFlash Cards
Document control processDocument control process
Defines how revisions are made, the version Defines how revisions are made, the version numbering system, and the placement of the numbering system, and the placement of the version number and revision date.version number and revision date.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 5959
Project ManagementProject ManagementFlash CardsFlash Cards
Duration compressionDuration compression
The use of techniques such as fast tracking or The use of techniques such as fast tracking or crashing to shorten the planned duration of a crashing to shorten the planned duration of a project or to resolve schedule slippage. project or to resolve schedule slippage.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6060
Project ManagementProject ManagementFlash CardsFlash Cards
Early finish (EF)Early finish (EF)
The earliest date an activity may finish as The earliest date an activity may finish as logically constrained by the network diagram.logically constrained by the network diagram.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6161
Project ManagementProject ManagementFlash CardsFlash Cards
Early start (ES)Early start (ES)
The earliest date an activity may begin as The earliest date an activity may begin as logically constrained by the network diagram.logically constrained by the network diagram.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6262
Project ManagementProject ManagementFlash CardsFlash Cards
Earned value (EV)Earned value (EV)
A measurement of the project’s progress to date A measurement of the project’s progress to date or the value of the work completed to date.or the value of the work completed to date.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6363
Project ManagementProject ManagementFlash CardsFlash Cards
Earned value analysisEarned value analysis
Looks at schedule, cost, and scope project Looks at schedule, cost, and scope project measurements and compares their progress as measurements and compares their progress as of the measurement date against what was of the measurement date against what was expected. Three measurements needed to expected. Three measurements needed to perform earned value analysis are planned perform earned value analysis are planned value (PV), actual cost (AC), and earned value value (PV), actual cost (AC), and earned value (EV).(EV).
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6464
Project ManagementProject ManagementFlash CardsFlash Cards
Economic modelEconomic model
One of the benefit measurement methods. It is a One of the benefit measurement methods. It is a series of financial calculations that provide data series of financial calculations that provide data on the overall financials of the project.on the overall financials of the project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6565
Project ManagementProject ManagementFlash CardsFlash Cards
End UserEnd User
The person (s) who directly uses the product The person (s) who directly uses the product that is the end result of the project.that is the end result of the project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6666
Project ManagementProject ManagementFlash CardsFlash Cards
EnterpriseEnterprise
The computing basis of the organization as a The computing basis of the organization as a whole. whole.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6767
Project ManagementProject ManagementFlash CardsFlash Cards
Enterprise projectEnterprise project
A project that will be used by users throughout A project that will be used by users throughout the enterprise.the enterprise.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6868
Project ManagementProject ManagementFlash CardsFlash Cards
Enterprise resource planning (ERP)Enterprise resource planning (ERP)
A business planning methodology that A business planning methodology that encompasses all facets of the business. ERP encompasses all facets of the business. ERP software handles such things as human software handles such things as human resources, accounting, manufacturing, and so resources, accounting, manufacturing, and so forth.forth.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 6969
Project ManagementProject ManagementFlash CardsFlash Cards
Entity relationship diagramsEntity relationship diagrams
A block-type diagram that shows the logic flow A block-type diagram that shows the logic flow between various system entities.between various system entities.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7070
Project ManagementProject ManagementFlash CardsFlash Cards
EquipmentEquipment
(a) Resources such as servers, specialized test (a) Resources such as servers, specialized test equipment, or additional PCs that are required equipment, or additional PCs that are required for a project.for a project.
(b) One of the categories of project resources. It (b) One of the categories of project resources. It includes test tools, servers, PCs, or other related includes test tools, servers, PCs, or other related items required to complete the project.items required to complete the project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7171
Project ManagementProject ManagementFlash CardsFlash Cards
Estimate at completion (EAC)Estimate at completion (EAC)
A forecast of the total cost of the project based A forecast of the total cost of the project based on both current project performance and on both current project performance and remaining work. The formula is EAC=AC+ETC.remaining work. The formula is EAC=AC+ETC.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7272
Project ManagementProject ManagementFlash CardsFlash Cards
Estimate to complete (ETC)Estimate to complete (ETC)
The cost estimate for the remaining project The cost estimate for the remaining project work.work.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7373
Project ManagementProject ManagementFlash CardsFlash Cards
Expert judgmentExpert judgment
A project selection method that relies on A project selection method that relies on information provided by those with expertise on information provided by those with expertise on the requested product. Expert judgment can the requested product. Expert judgment can come from stakeholders, other departments, come from stakeholders, other departments, consultants, or industry groups.consultants, or industry groups.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7474
Project ManagementProject ManagementFlash CardsFlash Cards
External dependencyExternal dependency
A relationship between a project task and a A relationship between a project task and a factor outside of the project, such as weather factor outside of the project, such as weather conditions, that drives the scheduling of that conditions, that drives the scheduling of that task.task.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7575
Project ManagementProject ManagementFlash CardsFlash Cards
Failure costsFailure costs
Covers the cost of activities generated if the Covers the cost of activities generated if the product fails including downtime, user support, product fails including downtime, user support, rework, and scrapping the project.rework, and scrapping the project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7676
Project ManagementProject ManagementFlash CardsFlash Cards
Fast trackingFast tracking
A schedule compression technique where two A schedule compression technique where two activities that were previously scheduled to start activities that were previously scheduled to start sequentially start at the same time. Fast sequentially start at the same time. Fast tracking reduces schedule duration.tracking reduces schedule duration.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7777
Project ManagementProject ManagementFlash CardsFlash Cards
Feasibility studyFeasibility study
Undertaken to determine whether the project is Undertaken to determine whether the project is a viable project, the probability of project a viable project, the probability of project success, and the viability of the product of the success, and the viability of the product of the project.project.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7878
Project ManagementProject ManagementFlash CardsFlash Cards
Finish to finish (FF)Finish to finish (FF)
A project task relationship in which the finish of A project task relationship in which the finish of the successor task is dependent on the finish of the successor task is dependent on the finish of the predecessor task.the predecessor task.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 7979
Project ManagementProject ManagementFlash CardsFlash Cards
Finish to start (FS)Finish to start (FS)
A project task relationship in which the A project task relationship in which the successor task cannot begin until the successor task cannot begin until the predecessor task has completed.predecessor task has completed.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8080
Project ManagementProject ManagementFlash CardsFlash Cards
Fixed price contractsFixed price contracts
A fixed fee for the work that the vendor will A fixed fee for the work that the vendor will provide.provide.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8181
Project ManagementProject ManagementFlash CardsFlash Cards
Float timeFloat time
The amount of time the early start of a task may The amount of time the early start of a task may be delayed without delaying the finish date of be delayed without delaying the finish date of the project. Also known as slack time.the project. Also known as slack time.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8282
Project ManagementProject ManagementFlash CardsFlash Cards
FlowchartFlowchart
A diagram that shows the logical steps that A diagram that shows the logical steps that must be performed in order to accomplish an must be performed in order to accomplish an objective. It can show how the individual objective. It can show how the individual elements of a system interrelate.elements of a system interrelate.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8383
Project ManagementProject ManagementFlash CardsFlash Cards
Formal communicationsFormal communications
Planned communications such as project kickoff Planned communications such as project kickoff meetings, team status meetings, written status meetings, team status meetings, written status reports, or team-building sessions.reports, or team-building sessions.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8484
Project ManagementProject ManagementFlash CardsFlash Cards
Forward passForward pass
The process of working from the left to the right The process of working from the left to the right of a network diagram in order to calculate early of a network diagram in order to calculate early start and early finish dates for each activity.start and early finish dates for each activity.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8585
Project ManagementProject ManagementFlash CardsFlash Cards
Functional organizationFunctional organization
A form of organizational structure. Functional A form of organizational structure. Functional organizations are traditional organizations with organizations are traditional organizations with hierarchical reporting structures.hierarchical reporting structures.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8686
Project ManagementProject ManagementFlash CardsFlash Cards
Functional requirementsFunctional requirements
Define what the product of the project will do by Define what the product of the project will do by focusing on how the end user will interact with focusing on how the end user will interact with the product.the product.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8787
Project ManagementProject ManagementFlash CardsFlash Cards
High-level requirementsHigh-level requirements
Explain the major characteristics of the product Explain the major characteristics of the product and describe the relationship between the and describe the relationship between the business need and the product requested. Also business need and the product requested. Also referred to as a product description.referred to as a product description.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8888
Project ManagementProject ManagementFlash CardsFlash Cards
Human resourcesHuman resources
The people with the background and skills to The people with the background and skills to complete the tasks on the project schedule.complete the tasks on the project schedule.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 8989
Project ManagementProject ManagementFlash CardsFlash Cards
Human resources planningHuman resources planning
Defining team member roles and Defining team member roles and responsibilities, establishing an appropriate responsibilities, establishing an appropriate structure for team reporting, securing the right structure for team reporting, securing the right team members, and bringing them on the team members, and bringing them on the project as needed for the appropriate length of project as needed for the appropriate length of time.time.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 9090
Project ManagementProject ManagementFlash CardsFlash Cards
Informal communicationsInformal communications
Unplanned or ad hoc communications including Unplanned or ad hoc communications including phone calls, emails, conversations in the phone calls, emails, conversations in the hallway, or impromptu meetings.hallway, or impromptu meetings.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 9191
Project ManagementProject ManagementFlash CardsFlash Cards
Information distributionInformation distribution
Providing stakeholders with information Providing stakeholders with information regarding the project in a timely manner via regarding the project in a timely manner via status reports, project meetings, review status reports, project meetings, review meetings, email, an so on. The communications meetings, email, an so on. The communications management plan is put into action during this management plan is put into action during this process.process.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 9292
Project ManagementProject ManagementFlash CardsFlash Cards
InfrastructureInfrastructure
The backbone of the organization’s computing The backbone of the organization’s computing environment. Typically the infrastructure will environment. Typically the infrastructure will include such elements as the network cabling, include such elements as the network cabling, routers and switchers, and termination points.routers and switchers, and termination points.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 9393
Project ManagementProject ManagementFlash CardsFlash Cards
Interactive voice response (IVR)Interactive voice response (IVR)
A system that uses telephony and allows users A system that uses telephony and allows users to connect to a database using a touch-tone to connect to a database using a touch-tone telephone for the retrieval of information or to telephone for the retrieval of information or to interact with the system in other ways.interact with the system in other ways.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 9494
Project ManagementProject ManagementFlash CardsFlash Cards
InitiationInitiation
The first process in a project life cycle. It is the The first process in a project life cycle. It is the formal acknowledgment that the project should formal acknowledgment that the project should begin using a charter.begin using a charter.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 9595
Project ManagementProject ManagementFlash CardsFlash Cards
InspectionInspection
A quality control technique that includes A quality control technique that includes examining, measuring, or testing work results.examining, measuring, or testing work results.
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
20052005 9696
Project ManagementProject ManagementFlash CardsFlash Cards
Integrated change controlIntegrated change control
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A process that influences the things that cause A process that influences the things that cause change, determines that change is needed or change, determines that change is needed or has happened, and manages change. All other has happened, and manages change. All other change control processes are integrated with change control processes are integrated with this process.this process.
20052005 9797
Project ManagementProject ManagementFlash CardsFlash Cards
Integrated systemIntegrated system
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A computing system that draws its data A computing system that draws its data elements from various sources, such as an elements from various sources, such as an Oracle database and a SQL Server database.Oracle database and a SQL Server database.
20052005 9898
Project ManagementProject ManagementFlash CardsFlash Cards
Integration testingIntegration testing
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The process of testing several distinct software The process of testing several distinct software modules (called units) as one intact entity. modules (called units) as one intact entity. Integration testing proves that the various Integration testing proves that the various unique software modules work together in unique software modules work together in harmony.harmony.
20052005 9999
Project ManagementProject ManagementFlash CardsFlash Cards
Intermediate data facilities (IDF)Intermediate data facilities (IDF)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A room that houses necessary infrastructure A room that houses necessary infrastructure components and is connected by network components and is connected by network cabling to the datacenter, but is not considered cabling to the datacenter, but is not considered to be the datacenter. Typically, in large to be the datacenter. Typically, in large buildings there are several IDFs spread around buildings there are several IDFs spread around so that it’s easier and cheaper to run network so that it’s easier and cheaper to run network cabling to user endpoints. Servers generally are cabling to user endpoints. Servers generally are not placed in the IDFs, but are kept at the not placed in the IDFs, but are kept at the datacenter, also called the Main Data Facility.datacenter, also called the Main Data Facility.
20052005 100100
Project ManagementProject ManagementFlash CardsFlash Cards
Internal rate of return (IRR)Internal rate of return (IRR)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The discount rate when the present value of the The discount rate when the present value of the cash inflows equals the original investment. cash inflows equals the original investment. Projects with higher IRR values are generally Projects with higher IRR values are generally considered better than projects with lower IRR considered better than projects with lower IRR values. Assumes that cash inflows are values. Assumes that cash inflows are reinvested at the IRR value.reinvested at the IRR value.
20052005 101101
Project ManagementProject ManagementFlash CardsFlash Cards
Iterative processIterative process
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Any process that is repeated more than once. Any process that is repeated more than once. The five process groups are repeated The five process groups are repeated throughout the project’s life due to change throughout the project’s life due to change requests, responses to change, corrective requests, responses to change, corrective action, and so on.action, and so on.
20052005 102102
Project ManagementProject ManagementFlash CardsFlash Cards
Late finish (LF)Late finish (LF)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The latest date an activity can complete without The latest date an activity can complete without impacting the project end date.impacting the project end date.
20052005 103103
Project ManagementProject ManagementFlash CardsFlash Cards
Late startLate start
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The latest date an activity can start without The latest date an activity can start without impacting the project end date.impacting the project end date.
20052005 104104
Project ManagementProject ManagementFlash CardsFlash Cards
Loaded rateLoaded rate
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A rate used for cost estimating of human A rate used for cost estimating of human resources that includes a percentage of the resources that includes a percentage of the salary to cover employee benefits, such as salary to cover employee benefits, such as medical, disability, or pension plans.medical, disability, or pension plans.
20052005 105105
Project ManagementProject ManagementFlash CardsFlash Cards
Main Data Facility (MDF)Main Data Facility (MDF)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The primary location where the servers, The primary location where the servers, telephony gear, routers, and demarcation points telephony gear, routers, and demarcation points are kept.are kept.
20052005 106106
Project ManagementProject ManagementFlash CardsFlash Cards
Major deliverablesMajor deliverables
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Outputs that must be produced to bring the Outputs that must be produced to bring the phase or project to completion. Deliverables are phase or project to completion. Deliverables are tangible and can be measured and easily tangible and can be measured and easily proved.proved.
20052005 107107
Project ManagementProject ManagementFlash CardsFlash Cards
Make or buy analysisMake or buy analysis
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Looking at the trade-offs between doing Looking at the trade-offs between doing something in-house versus procuring it outside something in-house versus procuring it outside the organization.the organization.
20052005 108108
Project ManagementProject ManagementFlash CardsFlash Cards
Managerial reserveManagerial reserve
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An amount set aside by upper management to An amount set aside by upper management to cover future situations that cannot be predicted.cover future situations that cannot be predicted.
20052005 109109
Project ManagementProject ManagementFlash CardsFlash Cards
Mandatory dependencyMandatory dependency
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A relationship between two tasks that is created A relationship between two tasks that is created by the type of work the project requires.by the type of work the project requires.
20052005 110110
Project ManagementProject ManagementFlash CardsFlash Cards
MaterialsMaterials
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A catchall category of project resources that A catchall category of project resources that includes software, utility requirements such as includes software, utility requirements such as electricity or water, any supplies needed for the electricity or water, any supplies needed for the project, or other consumable goods.project, or other consumable goods.
20052005 111111
Project ManagementProject ManagementFlash CardsFlash Cards
Mathematical analysisMathematical analysis
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Calculating theoretical early and late start and Calculating theoretical early and late start and finish dates for all project activities.finish dates for all project activities.
20052005 112112
Project ManagementProject ManagementFlash CardsFlash Cards
Matrix managementMatrix management
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Using people from different business entities in Using people from different business entities in a project for at least a part of their time; team a project for at least a part of their time; team members report to both their functional members report to both their functional manager and the project manager. Matrix manager and the project manager. Matrix management is common in IT projects.management is common in IT projects.
20052005 113113
Project ManagementProject ManagementFlash CardsFlash Cards
Matrix organizationMatrix organization
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An organization structure where employees An organization structure where employees report to one functional manager and at least report to one functional manager and at least one project manager. Functional managers one project manager. Functional managers assign employees to projects and carry out assign employees to projects and carry out administrative duties, while project managers administrative duties, while project managers assign tasks associated with the project to team assign tasks associated with the project to team members and execute the project.members and execute the project.
20052005 114114
Project ManagementProject ManagementFlash CardsFlash Cards
MetricMetric
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A standard of measurement that specifically A standard of measurement that specifically defines how something will be measured.defines how something will be measured.
20052005 115115
Project ManagementProject ManagementFlash CardsFlash Cards
MilestoneMilestone
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A major deliverable or key event in the project A major deliverable or key event in the project used to measure project progress.used to measure project progress.
20052005 116116
Project ManagementProject ManagementFlash CardsFlash Cards
Multiple business unit projectMultiple business unit project
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A project that is initiated by multiple business A project that is initiated by multiple business units.units.
20052005 117117
Project ManagementProject ManagementFlash CardsFlash Cards
Net present value (NPV)Net present value (NPV)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Evaluation of the cash inflows using the Evaluation of the cash inflows using the discounted cash flow technique, which is applied discounted cash flow technique, which is applied to each period the inflows are expected. The to each period the inflows are expected. The total present value of the cash flows is deducted total present value of the cash flows is deducted from the initial investment; assumes that cash from the initial investment; assumes that cash inflows are reinvested at the cost of capital. inflows are reinvested at the cost of capital. Similar to discounted cash flows.Similar to discounted cash flows.
20052005 118118
Project ManagementProject ManagementFlash CardsFlash Cards
Network diagramNetwork diagram
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A depiction of project activities and the A depiction of project activities and the interrelationships between these activities.interrelationships between these activities.
20052005 119119
Project ManagementProject ManagementFlash CardsFlash Cards
Network operating system (NOS)Network operating system (NOS)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Server software that allows the creation of Server software that allows the creation of network user accounts, and provides other network user accounts, and provides other functionality such as network printing, etc.functionality such as network printing, etc.
20052005 120120
Project ManagementProject ManagementFlash CardsFlash Cards
NormalizationNormalization
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The process of reducing data elements in a The process of reducing data elements in a database to their base elements so as to reduce database to their base elements so as to reduce redundancy. Typically many different tables will redundancy. Typically many different tables will be needed in a database system to be needed in a database system to accommodate the various sections of data.accommodate the various sections of data.
20052005 121121
Project ManagementProject ManagementFlash CardsFlash Cards
NormalizingNormalizing
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The process of normalizing a database.The process of normalizing a database.
20052005 122122
Project ManagementProject ManagementFlash CardsFlash Cards
Order of magnitudeOrder of magnitude
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A high-level estimate of the time and cost of a A high-level estimate of the time and cost of a project based on the actual cost and duration of project based on the actual cost and duration of a completed similar project.a completed similar project.
20052005 123123
Project ManagementProject ManagementFlash CardsFlash Cards
Organizational planningOrganizational planning
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The process of addressing interfaces that may The process of addressing interfaces that may impact how to manage a project team, define impact how to manage a project team, define roles and responsibilities for project team roles and responsibilities for project team members, identify how the project team will be members, identify how the project team will be organized, and document a staffing organized, and document a staffing management plan.management plan.
20052005 124124
Project ManagementProject ManagementFlash CardsFlash Cards
Parametric modelingParametric modeling
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A mathematical model that uses parameters, or A mathematical model that uses parameters, or project characteristics, to forecast project costs.project characteristics, to forecast project costs.
20052005 125125
Project ManagementProject ManagementFlash CardsFlash Cards
Pareto diagramPareto diagram
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A quality control technique used to rank A quality control technique used to rank importance of a problem based on its frequency importance of a problem based on its frequency of occurrence over time. This diagram is based of occurrence over time. This diagram is based on the Pareto principle, more commonly on the Pareto principle, more commonly referred to as the 80/20 rule, which says that referred to as the 80/20 rule, which says that the majority of defects are caused by a small the majority of defects are caused by a small set of problems.set of problems.
20052005 126126
Project ManagementProject ManagementFlash CardsFlash Cards
Payback periodPayback period
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The length of time it takes a company to The length of time it takes a company to recover the initial cost of producing the product recover the initial cost of producing the product or service of the project.or service of the project.
20052005 127127
Project ManagementProject ManagementFlash CardsFlash Cards
Performance reportingPerformance reporting
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Collecting information regarding project Collecting information regarding project progress and project accomplishments and progress and project accomplishments and reporting it to the stakeholders, project team reporting it to the stakeholders, project team members, management team, and other members, management team, and other interested parties. It also makes predictions interested parties. It also makes predictions regarding future project performance.regarding future project performance.
20052005 128128
Project ManagementProject ManagementFlash CardsFlash Cards
Pilot testPilot test
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Building and testing a proposed system in a Building and testing a proposed system in a small environment that includes a handful of small environment that includes a handful of users (also called pilot mode). The purpose of users (also called pilot mode). The purpose of pilot testing is to develop a fully functioning pilot testing is to develop a fully functioning system and then put it out for a small system and then put it out for a small component of people to test to see if it meets component of people to test to see if it meets the expectations of the project. From successful the expectations of the project. From successful pilot testing it’s easy to put the system into full pilot testing it’s easy to put the system into full production.production.
20052005 129129
Project ManagementProject ManagementFlash CardsFlash Cards
Planned value (PV)Planned value (PV)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The cost of work that’s been budgeted for an The cost of work that’s been budgeted for an activity during a certain time period. This was activity during a certain time period. This was formerly referred to as budgeted cost of work formerly referred to as budgeted cost of work scheduled (BCWS).scheduled (BCWS).
20052005 130130
Project ManagementProject ManagementFlash CardsFlash Cards
Precedence diagramming method (PDM)Precedence diagramming method (PDM)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A diagramming method that places activities on A diagramming method that places activities on nodes, which connect to dependent activities nodes, which connect to dependent activities using arrows. Also known as activity on node using arrows. Also known as activity on node (AON).(AON).
20052005 131131
Project ManagementProject ManagementFlash CardsFlash Cards
PredecessorPredecessor
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A task that exists on a path with another task A task that exists on a path with another task and occurs before the other task.and occurs before the other task.
20052005 132132
Project ManagementProject ManagementFlash CardsFlash Cards
Preliminary investigationPreliminary investigation
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An investigation at project request time to An investigation at project request time to determine the costs and benefits of the project, determine the costs and benefits of the project, as well as examine alternatives to the proposed as well as examine alternatives to the proposed solution in order to determine the feasibility of solution in order to determine the feasibility of carrying out the project.carrying out the project.
20052005 133133
Project ManagementProject ManagementFlash CardsFlash Cards
Preventative actionPreventative action
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The review of potential risks to determine if any The review of potential risks to determine if any steps can be taken to prevent the problem from steps can be taken to prevent the problem from occurring or reduce the probability that the occurring or reduce the probability that the problem will occur.problem will occur.
20052005 134134
Project ManagementProject ManagementFlash CardsFlash Cards
Prevention costsPrevention costs
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Costs of the activities performed to avoid quality Costs of the activities performed to avoid quality problems including quality planning, training, problems including quality planning, training, and any product or process testing.and any product or process testing.
20052005 135135
Project ManagementProject ManagementFlash CardsFlash Cards
Procurement planningProcurement planning
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Identifying what goods or services will be Identifying what goods or services will be purchased from outside of the organization. Also purchased from outside of the organization. Also uses make or buy analysis to determine uses make or buy analysis to determine whether goods or services should be purchased whether goods or services should be purchased or performed by the organization. or performed by the organization.
20052005 136136
Project ManagementProject ManagementFlash CardsFlash Cards
Product descriptionProduct description
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Explains the major characteristics of the product Explains the major characteristics of the product and describes the relationship between the and describes the relationship between the business need and the product. Also referred to business need and the product. Also referred to as high-level requirements.as high-level requirements.
20052005 137137
Project ManagementProject ManagementFlash CardsFlash Cards
ProgramProgram
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A grouping of related projects that are managed A grouping of related projects that are managed together. The individual projects are usually part together. The individual projects are usually part of one bigger project.of one bigger project.
20052005 138138
Project ManagementProject ManagementFlash CardsFlash Cards
Program evaluation and review technique (PERT)Program evaluation and review technique (PERT)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Uses expected value, or weighted average, of Uses expected value, or weighted average, of critical path tasks to determine project duration critical path tasks to determine project duration by establishing three estimates: most likely, by establishing three estimates: most likely, pessimistic and optimistic.pessimistic and optimistic.
20052005 139139
Project ManagementProject ManagementFlash CardsFlash Cards
Progress reportsProgress reports
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Reports from project team members listing the Reports from project team members listing the tasks each member is working on, the current tasks each member is working on, the current progress of each task, and the work remaining.progress of each task, and the work remaining.
20052005 140140
Project ManagementProject ManagementFlash CardsFlash Cards
ProjectProject
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A project is temporary in nature, has definitive A project is temporary in nature, has definitive start and end dates, creates a unique product or start and end dates, creates a unique product or service, and is completed when the goals and service, and is completed when the goals and objectives of the project have been met and objectives of the project have been met and signed off on by the stakeholders.signed off on by the stakeholders.
20052005 141141
Project ManagementProject ManagementFlash CardsFlash Cards
Project championProject champion
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
This person, usually not the project sponsor, is This person, usually not the project sponsor, is one who fully understands, believes in, and one who fully understands, believes in, and espouses the benefits of the project.espouses the benefits of the project.
20052005 142142
Project ManagementProject ManagementFlash CardsFlash Cards
Project charterProject charter
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An official, written acknowledgment and An official, written acknowledgment and recognition that a project exists. It’s issued by recognition that a project exists. It’s issued by senior management and gives the project senior management and gives the project manager authority to assign organizational manager authority to assign organizational resources to the work of the project.resources to the work of the project.
20052005 143143
Project ManagementProject ManagementFlash CardsFlash Cards
Project closureProject closure
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The formal acceptance of a project and the The formal acceptance of a project and the activities required to formally end the project activities required to formally end the project work.work.
20052005 144144
Project ManagementProject ManagementFlash CardsFlash Cards
Project descriptionProject description
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Documents the key characteristics of the Documents the key characteristics of the product or service that will be created by the product or service that will be created by the project and the work required to deliver the project and the work required to deliver the product.product.
20052005 145145
Project ManagementProject ManagementFlash CardsFlash Cards
Project executionProject execution
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Carrying out the project plan. Activities are Carrying out the project plan. Activities are clarified, the work is authorized to begin, clarified, the work is authorized to begin, resources are committed and assigned to resources are committed and assigned to activities, and the product or service of the activities, and the product or service of the project is created. The largest portion of the project is created. The largest portion of the project budget will be spent during this process.project budget will be spent during this process.
20052005 146146
Project ManagementProject ManagementFlash CardsFlash Cards
Project justificationProject justification
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Documentation in the project scope statement Documentation in the project scope statement that includes the reason the project is being that includes the reason the project is being undertaken and the business need the project undertaken and the business need the project will address.will address.
20052005 147147
Project ManagementProject ManagementFlash CardsFlash Cards
Project life cycleProject life cycle
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The grouping of project phases in a sequential The grouping of project phases in a sequential order from the beginning of the project to the order from the beginning of the project to the close.close.
20052005 148148
Project ManagementProject ManagementFlash CardsFlash Cards
Project managementProject management
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The process that’s used to initiate, plan, The process that’s used to initiate, plan, execute, monitor, control, and close out projects execute, monitor, control, and close out projects by applying skills, knowledge, and project by applying skills, knowledge, and project management tools and techniques to fulfill the management tools and techniques to fulfill the project requirements.project requirements.
20052005 149149
Project ManagementProject ManagementFlash CardsFlash Cards
Project Management Institute (PMI)Project Management Institute (PMI)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The world’s leading professional project The world’s leading professional project management association.management association.
20052005 150150
Project ManagementProject ManagementFlash CardsFlash Cards
Project management knowledge areasProject management knowledge areas
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
This nine project management groupings, or This nine project management groupings, or knowledge areas, bring together common or knowledge areas, bring together common or related processes – Integration, Scope, Time, related processes – Integration, Scope, Time, cost, Quality, Human Resources, cost, Quality, Human Resources, Communications, Risk, Procurement.Communications, Risk, Procurement.
20052005 151151
Project ManagementProject ManagementFlash CardsFlash Cards
Project management offices (PMO)Project management offices (PMO)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Established by organizations to create and Established by organizations to create and maintain procedures and standards for project maintain procedures and standards for project management methodologies to be used management methodologies to be used throughout the organization.throughout the organization.
20052005 152152
Project ManagementProject ManagementFlash CardsFlash Cards
Project managerProject manager
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The person responsible for applying the skills, The person responsible for applying the skills, knowledge, and project management tools and knowledge, and project management tools and techniques to the project activities in order to techniques to the project activities in order to successfully complete the project objectives.successfully complete the project objectives.
20052005 153153
Project ManagementProject ManagementFlash CardsFlash Cards
Project performance indicatorsProject performance indicators
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Measures the project manager uses to Measures the project manager uses to determine whether the project is on track, such determine whether the project is on track, such as any deviation from the baseline schedule or as any deviation from the baseline schedule or the baseline budget.the baseline budget.
20052005 154154
Project ManagementProject ManagementFlash CardsFlash Cards
Project planProject plan
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A document, or assortment of documents, that A document, or assortment of documents, that constitutes what the project is, what the project constitutes what the project is, what the project will deliver, and how all the processes will be will deliver, and how all the processes will be managed. Used as the guideline throughout the managed. Used as the guideline throughout the project executing and controlling phrases to project executing and controlling phrases to track and measure project performance and to track and measure project performance and to make future project decisions. Also used as a make future project decisions. Also used as a communication and information tool for communication and information tool for stakeholders, team members, and stakeholders, team members, and management.management.
20052005 155155
Project ManagementProject ManagementFlash CardsFlash Cards
Project reviewProject review
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A formal presentation by the project manager or A formal presentation by the project manager or project team members to the sponsor, the project team members to the sponsor, the client, and other executive stakeholders.client, and other executive stakeholders.
20052005 156156
Project ManagementProject ManagementFlash CardsFlash Cards
Project scheduleProject schedule
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Determines the start and finish dates for project Determines the start and finish dates for project activities and assigns resources to the activities.activities and assigns resources to the activities.
20052005 157157
Project ManagementProject ManagementFlash CardsFlash Cards
Project selectionProject selection
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Used to determine which proposed projects are Used to determine which proposed projects are approved to move forward.approved to move forward.
20052005 158158
Project ManagementProject ManagementFlash CardsFlash Cards
Projectized organizationProjectized organization
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An organizational structure focused on projects. An organizational structure focused on projects. Project managers generally have ultimate Project managers generally have ultimate authority over the project, and, sometimes, authority over the project, and, sometimes, supporting departments like human resources supporting departments like human resources and accounting might report to the project and accounting might report to the project manager. Project managers are responsible for manager. Project managers are responsible for making project decisions and acquiring and making project decisions and acquiring and assigning resources.assigning resources.
20052005 159159
Project ManagementProject ManagementFlash CardsFlash Cards
Proof of conceptProof of concept
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A project that undertakes to prove that a A project that undertakes to prove that a specific activity can be done or an idea can be specific activity can be done or an idea can be accomplished.accomplished.
20052005 160160
Project ManagementProject ManagementFlash CardsFlash Cards
Qualitative risk analysisQualitative risk analysis
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Determining the impact of identified risks on the Determining the impact of identified risks on the project and the probability they’ll occur; puts project and the probability they’ll occur; puts the risks in priority order according to their the risks in priority order according to their effect on the project.effect on the project.
20052005 161161
Project ManagementProject ManagementFlash CardsFlash Cards
Quality controlQuality control
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Monitoring work results to see whether they Monitoring work results to see whether they fulfill the quality standards set out in the quality fulfill the quality standards set out in the quality management plan; determines whether the end management plan; determines whether the end product conforms to the requirements and product conforms to the requirements and product description defined during the planning product description defined during the planning processes.processes.
20052005 162162
Project ManagementProject ManagementFlash CardsFlash Cards
Quality management planQuality management plan
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Describes how the project management team Describes how the project management team will enact the quality policy and documents the will enact the quality policy and documents the resources needed to carry out the quality plan, resources needed to carry out the quality plan, the responsibilities of the project team in the responsibilities of the project team in implementing quality, and all the processes and implementing quality, and all the processes and procedures the project team and organization procedures the project team and organization will use to satisfy quality requirements.will use to satisfy quality requirements.
20052005 163163
Project ManagementProject ManagementFlash CardsFlash Cards
Quality planningQuality planning
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Identifying the quality standards applicable for Identifying the quality standards applicable for the project and how to fulfill the standards.the project and how to fulfill the standards.
20052005 164164
Project ManagementProject ManagementFlash CardsFlash Cards
Quantitative risk analysisQuantitative risk analysis
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Assigning numeric probabilities to each Assigning numeric probabilities to each identified risk and examining their potential identified risk and examining their potential impact to the project objectives.impact to the project objectives.
20052005 165165
Project ManagementProject ManagementFlash CardsFlash Cards
Quantitatively based durationsQuantitatively based durations
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A duration estimate obtained by applying a A duration estimate obtained by applying a productivity rate of the resources performing productivity rate of the resources performing the task.the task.
20052005 166166
Project ManagementProject ManagementFlash CardsFlash Cards
RebaseliningRebaselining
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Setting a new project baseline if there are Setting a new project baseline if there are substantial changes to the schedule or the substantial changes to the schedule or the budget.budget.
20052005 167167
Project ManagementProject ManagementFlash CardsFlash Cards
Request for proposal (RFP)Request for proposal (RFP)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A document that is sent out to potential vendors A document that is sent out to potential vendors requesting them to provide a proposal on a requesting them to provide a proposal on a product or service.product or service.
20052005 168168
Project ManagementProject ManagementFlash CardsFlash Cards
RequirementRequirement
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The specifications of the goal or deliverable.The specifications of the goal or deliverable.
20052005 169169
Project ManagementProject ManagementFlash CardsFlash Cards
Resource planningResource planning
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Definition of all the resources needed and the Definition of all the resources needed and the quantity of resources needed to perform project quantity of resources needed to perform project activities.activities.
20052005 170170
Project ManagementProject ManagementFlash CardsFlash Cards
Resource pool descriptionResource pool description
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A list of all job titles within a company or A list of all job titles within a company or department with a brief description of the job. department with a brief description of the job. May identify the number of people currently May identify the number of people currently employed in each job title.employed in each job title.
20052005 171171
Project ManagementProject ManagementFlash CardsFlash Cards
Resource requirementsResource requirements
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A document containing a description of the A document containing a description of the resources needed from all three resource types resources needed from all three resource types for work package items from the WBS.for work package items from the WBS.
20052005 172172
Project ManagementProject ManagementFlash CardsFlash Cards
Responsibility assignment matrix (RAM)Responsibility assignment matrix (RAM)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Ties roles and responsibilities with the WBS Ties roles and responsibilities with the WBS elements to ensure that each element has a elements to ensure that each element has a resource assigned. Usually displayed in chart resource assigned. Usually displayed in chart form.form.
20052005 173173
Project ManagementProject ManagementFlash CardsFlash Cards
RevisionRevision
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An update to the approved start or end date of An update to the approved start or end date of the schedule baseline, typically a result of the schedule baseline, typically a result of approved scope changes.approved scope changes.
20052005 174174
Project ManagementProject ManagementFlash CardsFlash Cards
ReworkRework
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Any action that is taken as a result of quality Any action that is taken as a result of quality activities to correct a defect.activities to correct a defect.
20052005 175175
Project ManagementProject ManagementFlash CardsFlash Cards
RiskRisk
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An element of uncertainty that can have either An element of uncertainty that can have either negative or positive consequences.negative or positive consequences.
20052005 176176
Project ManagementProject ManagementFlash CardsFlash Cards
Risk analysisRisk analysis
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The process used to identify and focus on those The process used to identify and focus on those risks that are the most critical to the success of risks that are the most critical to the success of your project.your project.
20052005 177177
Project ManagementProject ManagementFlash CardsFlash Cards
Risk identificationRisk identification
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Identifying the potential project risks and Identifying the potential project risks and documents their characteristics.documents their characteristics.
20052005 178178
Project ManagementProject ManagementFlash CardsFlash Cards
Risk management planRisk management plan
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Details how risk management processes will be Details how risk management processes will be implemented, monitored, and controlled implemented, monitored, and controlled throughout the life of the project. It does not throughout the life of the project. It does not define responses to individual risks.define responses to individual risks.
20052005 179179
Project ManagementProject ManagementFlash CardsFlash Cards
Risk monitoring and controlRisk monitoring and control
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Process of responding to risks as they occur Process of responding to risks as they occur based on the risk management plan, which based on the risk management plan, which details how risks are managed, and the risk details how risks are managed, and the risk response plan, which details how risk response response plan, which details how risk response strategies are implemented in the event of an strategies are implemented in the event of an actual risk event.actual risk event.
20052005 180180
Project ManagementProject ManagementFlash CardsFlash Cards
Risk planningRisk planning
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A process determining how areas of uncertainty A process determining how areas of uncertainty will be managed for a project.will be managed for a project.
20052005 181181
Project ManagementProject ManagementFlash CardsFlash Cards
Risk response planningRisk response planning
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The plan for steps to reduce threats and take The plan for steps to reduce threats and take advantage of opportunities; assigns advantage of opportunities; assigns departments or individual staff members the departments or individual staff members the responsibility of carrying out the risk response responsibility of carrying out the risk response plans developed in this process.plans developed in this process.
20052005 182182
Project ManagementProject ManagementFlash CardsFlash Cards
Risk triggerRisk trigger
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An event that warns a risk is imminent and a An event that warns a risk is imminent and a contingency plan should be implemented.contingency plan should be implemented.
20052005 183183
Project ManagementProject ManagementFlash CardsFlash Cards
Schedule baselineSchedule baseline
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A copy of the schedule prior to the start of A copy of the schedule prior to the start of project work that is used during project project work that is used during project execution to monitor project progress.execution to monitor project progress.
20052005 184184
Project ManagementProject ManagementFlash CardsFlash Cards
Schedule controlSchedule control
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Documenting and managing changes to the Documenting and managing changes to the project schedule.project schedule.
20052005 185185
Project ManagementProject ManagementFlash CardsFlash Cards
Schedule developmentSchedule development
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Calculating and preparing the schedule of Calculating and preparing the schedule of project activities, which becomes the schedule project activities, which becomes the schedule baseline. It determines activity start and finish baseline. It determines activity start and finish dates, and finalizes activity sequences and dates, and finalizes activity sequences and durations; assigning resources to activities is durations; assigning resources to activities is done in resource planning, a cost management done in resource planning, a cost management planning process.planning process.
20052005 186186
Project ManagementProject ManagementFlash CardsFlash Cards
Schedule performance index (SPI)Schedule performance index (SPI)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The ratio of work completed to the work The ratio of work completed to the work planned, measured over time. The SPI indicator planned, measured over time. The SPI indicator acts as an efficiency rating. The formula is SPI= acts as an efficiency rating. The formula is SPI= EV/PVEV/PV
20052005 187187
Project ManagementProject ManagementFlash CardsFlash Cards
Schedule updateSchedule update
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Any change that is made to the project schedule Any change that is made to the project schedule as part of the ongoing work involved with as part of the ongoing work involved with managing the project.managing the project.
20052005 188188
Project ManagementProject ManagementFlash CardsFlash Cards
Schedule variance (SV)Schedule variance (SV)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The difference between a task’s progress as The difference between a task’s progress as compared to its estimated progress represented compared to its estimated progress represented in terms of cost. The formula is SV=EV-PV.in terms of cost. The formula is SV=EV-PV.
20052005 189189
Project ManagementProject ManagementFlash CardsFlash Cards
ScopeScope
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The size of the work involved to complete the The size of the work involved to complete the project. Can define both what is included in the project. Can define both what is included in the project as well as what is excluded from the project as well as what is excluded from the project.project.
20052005 190190
Project ManagementProject ManagementFlash CardsFlash Cards
Scope change controlScope change control
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Documenting and managing changes to project Documenting and managing changes to project scope. Any modification to the agreed on WBS is scope. Any modification to the agreed on WBS is considered a scope change. Changes in product considered a scope change. Changes in product scope will require changes to project scope.scope will require changes to project scope.
20052005 191191
Project ManagementProject ManagementFlash CardsFlash Cards
Scope creepScope creep
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The minor changes or small additions that are The minor changes or small additions that are made to the project outside of a formal scope made to the project outside of a formal scope change process.change process.
20052005 192192
Project ManagementProject ManagementFlash CardsFlash Cards
Scope definitionScope definition
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The process of breaking down the major The process of breaking down the major deliverables from the scope statement to create deliverables from the scope statement to create the WBS.the WBS.
20052005 193193
Project ManagementProject ManagementFlash CardsFlash Cards
Scope management planScope management plan
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Analyzes the reliability and stability of the Analyzes the reliability and stability of the project scope. Documents the process that project scope. Documents the process that manages project scope and changes to project manages project scope and changes to project scope.scope.
20052005 194194
Project ManagementProject ManagementFlash CardsFlash Cards
Scope planningScope planning
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The work of the project, culminating in the The work of the project, culminating in the scope statement, which describes the project scope statement, which describes the project deliverables, objectives, and justification.deliverables, objectives, and justification.
20052005 195195
Project ManagementProject ManagementFlash CardsFlash Cards
Scope statementScope statement
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Documents the project goals, deliverables, and Documents the project goals, deliverables, and requirements, which are used as a baseline for requirements, which are used as a baseline for future project decisions. It also includes the future project decisions. It also includes the project objectives and the business justification project objectives and the business justification for the project.for the project.
20052005 196196
Project ManagementProject ManagementFlash CardsFlash Cards
Scope verificationScope verification
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Formal acceptance of the project scope; Formal acceptance of the project scope; primarily concerned with the acceptance of primarily concerned with the acceptance of work results.work results.
20052005 197197
Project ManagementProject ManagementFlash CardsFlash Cards
Scoring modelScoring model
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
One of the benefit measurement methods. It One of the benefit measurement methods. It contains a predefined list of criteria against contains a predefined list of criteria against which each project is ranked. Each criterion has which each project is ranked. Each criterion has a scoring range and a weighting factor.a scoring range and a weighting factor.
20052005 198198
Project ManagementProject ManagementFlash CardsFlash Cards
SequencingSequencing
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Putting the project activities in the order in Putting the project activities in the order in which they will take place.which they will take place.
20052005 199199
Project ManagementProject ManagementFlash CardsFlash Cards
Sidebar systemsSidebar systems
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Systems that arise out of end-user frustration Systems that arise out of end-user frustration with the limitations of the primary system. End with the limitations of the primary system. End users may use a spreadsheet or database to users may use a spreadsheet or database to help them work through some of the processing help them work through some of the processing requirements of an ERP system. Sidebar requirements of an ERP system. Sidebar systems often don’t show up at requirements systems often don’t show up at requirements gathering time because people are afraid to gathering time because people are afraid to reveal sidebar systems.reveal sidebar systems.
20052005 200200
Project ManagementProject ManagementFlash CardsFlash Cards
Slack timeSlack time
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The amount of time allowed to delay the early The amount of time allowed to delay the early start of a task without delaying the finish date of start of a task without delaying the finish date of the project. Also known as float time.the project. Also known as float time.
20052005 201201
Project ManagementProject ManagementFlash CardsFlash Cards
Software development life cycle (SDLC)Software development life cycle (SDLC)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A methodology that describes five distinct A methodology that describes five distinct phases involved in building any system. The five phases involved in building any system. The five phases are Planning, Analysis, Design, phases are Planning, Analysis, Design, Implementation and Operations, and Support. Implementation and Operations, and Support. Also known as the systems development life Also known as the systems development life cycle.cycle.
20052005 202202
Project ManagementProject ManagementFlash CardsFlash Cards
Sole sourceSole source
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A requirement that a product or service must be A requirement that a product or service must be obtained from a single vendor in government obtained from a single vendor in government work; also includes justification.work; also includes justification.
20052005 203203
Project ManagementProject ManagementFlash CardsFlash Cards
SolicitationSolicitation
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Obtaining bids and proposals form vendors in Obtaining bids and proposals form vendors in response to RFPs and similar documents response to RFPs and similar documents prepared during the solicitation planning prepared during the solicitation planning process.process.
20052005 204204
Project ManagementProject ManagementFlash CardsFlash Cards
SponsorSponsor
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An executive in the organization with authority An executive in the organization with authority to assign resources and enforce decisions to assign resources and enforce decisions regarding the project.regarding the project.
20052005 205205
Project ManagementProject ManagementFlash CardsFlash Cards
Staff acquisitionStaff acquisition
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Attaining human resources and assigning them Attaining human resources and assigning them to the project. Human resources may come from to the project. Human resources may come from inside or outside the organization.inside or outside the organization.
20052005 206206
Project ManagementProject ManagementFlash CardsFlash Cards
Staffing management planStaffing management plan
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Documents when and how human resources will Documents when and how human resources will be added to and released from the project team be added to and released from the project team and what they will be working on while they are and what they will be working on while they are part of the team. Adding the releasing resources part of the team. Adding the releasing resources may be an informal or a formal process, may be an informal or a formal process, depending on the organization.depending on the organization.
20052005 207207
Project ManagementProject ManagementFlash CardsFlash Cards
StakeholderStakeholder
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A person or organization who has a vested A person or organization who has a vested interest in the project and stands to gain or lose interest in the project and stands to gain or lose something as a result of the project.something as a result of the project.
20052005 208208
Project ManagementProject ManagementFlash CardsFlash Cards
Start to finish (SF)Start to finish (SF)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A task relationship where the finish of the A task relationship where the finish of the successor task is dependent on the start of its successor task is dependent on the start of its predecessor.predecessor.
20052005 209209
Project ManagementProject ManagementFlash CardsFlash Cards
Start to start (SS)Start to start (SS)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A project task relationship where the start of the A project task relationship where the start of the successor task depends on the start of the successor task depends on the start of the predecessor task.predecessor task.
20052005 210210
Project ManagementProject ManagementFlash CardsFlash Cards
Statement of work (SOW)Statement of work (SOW)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Contains the details of a procurement item in Contains the details of a procurement item in clear, concise terms and includes the project clear, concise terms and includes the project objectives, a description of the work of the objectives, a description of the work of the project, concise specifications of the product or project, concise specifications of the product or services required, and a project schedule.services required, and a project schedule.
20052005 211211
Project ManagementProject ManagementFlash CardsFlash Cards
Status dateStatus date
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The date when the project manager measures The date when the project manager measures how much has been spent on a specific task.how much has been spent on a specific task.
20052005 212212
Project ManagementProject ManagementFlash CardsFlash Cards
Storage area network (SAN)Storage area network (SAN)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A network of storage arrays, designed to A network of storage arrays, designed to provide the safekeeping of information. May be provide the safekeeping of information. May be connected by fiber-optic cabling using the fiber connected by fiber-optic cabling using the fiber channel protocol, but this doesn’t have to be the channel protocol, but this doesn’t have to be the case. May be connected by Ethernet, or other case. May be connected by Ethernet, or other protocols.protocols.
20052005 213213
Project ManagementProject ManagementFlash CardsFlash Cards
Storage arrayStorage array
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A device that houses multiple disks designed to A device that houses multiple disks designed to provide a highly fault-tolerant and highly provide a highly fault-tolerant and highly available place where information can be available place where information can be stored. At a minimum, provides a method of stored. At a minimum, provides a method of making the information available to users and a making the information available to users and a system for monitoring the health of the array.system for monitoring the health of the array.
20052005 214214
Project ManagementProject ManagementFlash CardsFlash Cards
Success criteriaSuccess criteria
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A definition of the measurable business results A definition of the measurable business results the product is expected to produce.the product is expected to produce.
20052005 215215
Project ManagementProject ManagementFlash CardsFlash Cards
SuccessorSuccessor
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A task that exists on a common path with A task that exists on a common path with another task and occurs after the other task.another task and occurs after the other task.
20052005 216216
Project ManagementProject ManagementFlash CardsFlash Cards
System design specificationSystem design specification
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The final outcome of the design phase of SDLC; The final outcome of the design phase of SDLC; a document detailing what the system will do, a document detailing what the system will do, how it will do it, and what it will cost. Used by how it will do it, and what it will cost. Used by systems developers who will actually build the systems developers who will actually build the new system.new system.
20052005 217217
Project ManagementProject ManagementFlash CardsFlash Cards
System requestSystem request
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A request made by business unit stakeholders A request made by business unit stakeholders for a new system.for a new system.
20052005 218218
Project ManagementProject ManagementFlash CardsFlash Cards
Systems analysisSystems analysis
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Analyzing the details of a systems project Analyzing the details of a systems project request to determine how the current system (if request to determine how the current system (if any) flow and how the new system will change any) flow and how the new system will change in its flows. Involves understanding the way that in its flows. Involves understanding the way that the business organization currently does its the business organization currently does its work and how that work translates into a new work and how that work translates into a new system. Also involves understanding how the system. Also involves understanding how the various system components will connect various system components will connect physically and logically together. This is the physically and logically together. This is the second phase of an SDLC.second phase of an SDLC.
20052005 219219
Project ManagementProject ManagementFlash CardsFlash Cards
Systems analyst (SA)Systems analyst (SA)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Person specially trained in the analysis and Person specially trained in the analysis and design of a business request for a new system.design of a business request for a new system.
20052005 220220
Project ManagementProject ManagementFlash CardsFlash Cards
Systems designSystems design
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Designing a new system after obtaining a Designing a new system after obtaining a request from a business unit for a new project request from a business unit for a new project and analyzing the flows of the system. This is and analyzing the flows of the system. This is the third phase of an SDLC.the third phase of an SDLC.
20052005 221221
Project ManagementProject ManagementFlash CardsFlash Cards
Systems implementationSystems implementation
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Deploying the new system. This is the fourth Deploying the new system. This is the fourth phase of an SDLC.phase of an SDLC.
20052005 222222
Project ManagementProject ManagementFlash CardsFlash Cards
Systems operations and supportSystems operations and support
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Maintaining, upgrading, and enhancing the Maintaining, upgrading, and enhancing the released system. This is the fifth and final stage released system. This is the fifth and final stage of an SDLC.of an SDLC.
20052005 223223
Project ManagementProject ManagementFlash CardsFlash Cards
Systems planningSystems planning
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Receiving a request for a new project from a Receiving a request for a new project from a business unit, examining the requirements of business unit, examining the requirements of that request, and formulating it into a working that request, and formulating it into a working project document. This is the first phase of an project document. This is the first phase of an SDLC.SDLC.
20052005 224224
Project ManagementProject ManagementFlash CardsFlash Cards
Team developmentTeam development
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
Creating an open, encouraging environment for Creating an open, encouraging environment for stakeholders to contribute, as well as stakeholders to contribute, as well as developing the project team into an effective, developing the project team into an effective, functioning, coordinating group.functioning, coordinating group.
20052005 225225
Project ManagementProject ManagementFlash CardsFlash Cards
Time and materials contractTime and materials contract
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The buyer and the seller agree on a unit rate, The buyer and the seller agree on a unit rate, such as the hourly rate for a programmer, but such as the hourly rate for a programmer, but the total cost is unknown and will depend on the the total cost is unknown and will depend on the amount of time spent to produce the product.amount of time spent to produce the product.
20052005 226226
Project ManagementProject ManagementFlash CardsFlash Cards
To-complete performance index (TCPI)To-complete performance index (TCPI)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The performance that must be achieved in the The performance that must be achieved in the remaining elements of the project in order to remaining elements of the project in order to satisfy financial or schedule goals.satisfy financial or schedule goals.
20052005 227227
Project ManagementProject ManagementFlash CardsFlash Cards
Top down estimatingTop down estimating
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
An estimating technique that uses actual An estimating technique that uses actual durations from similar activities on a previous durations from similar activities on a previous project. Also referred to as analogous project. Also referred to as analogous estimating.estimating.
20052005 228228
Project ManagementProject ManagementFlash CardsFlash Cards
Trend analysisTrend analysis
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A mathematical technique that can be used to A mathematical technique that can be used to predict future defects based on historical predict future defects based on historical results.results.
20052005 229229
Project ManagementProject ManagementFlash CardsFlash Cards
Triple constraintTriple constraint
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The link between impacts of the constraints put The link between impacts of the constraints put on a project by time, cost, and quality.on a project by time, cost, and quality.
20052005 230230
Project ManagementProject ManagementFlash CardsFlash Cards
Unit testingUnit testing
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The successful completion and testing on a The successful completion and testing on a single software module.single software module.
20052005 231231
Project ManagementProject ManagementFlash CardsFlash Cards
User acceptance testing (UAT)User acceptance testing (UAT)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The final phase in a software development The final phase in a software development process during which the intended audience process during which the intended audience receives the software so they can test for receives the software so they can test for functionality.functionality.
20052005 232232
Project ManagementProject ManagementFlash CardsFlash Cards
Variance analysisVariance analysis
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The comparison of planned project results with The comparison of planned project results with actual project results.actual project results.
20052005 233233
Project ManagementProject ManagementFlash CardsFlash Cards
Work breakdown structure (WBS)Work breakdown structure (WBS)
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
A deliverables-oriented hierarchy that defines A deliverables-oriented hierarchy that defines the total work of the project. Each level has the total work of the project. Each level has more detailed information than the previous more detailed information than the previous level.level.
20052005 234234
Project ManagementProject ManagementFlash CardsFlash Cards
Work effortWork effort
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The total time it would take for a person to The total time it would take for a person to complete the task if they did nothing else from complete the task if they did nothing else from the time they started until the task was the time they started until the task was complete.complete.
20052005 235235
Project ManagementProject ManagementFlash CardsFlash Cards
Work packageWork package
© Elza Efendi© Elza Efendi, PMP |, PMP | All rights reserved All rights reserved
The lowest level in a WBS. Team assignments, The lowest level in a WBS. Team assignments, time estimates, and cost estimates can be made time estimates, and cost estimates can be made when this level represents tasks or activities. On when this level represents tasks or activities. On very large projects, this level is handed off to very large projects, this level is handed off to subproject managers who develop their own subproject managers who develop their own WBS to fulfill the requirements of the work WBS to fulfill the requirements of the work package deliverable.package deliverable.