  • ADVANCED BUILDING MEASUREMENTS

    MEASUREMENT OF PLUMBING WORKS

    Order of measurements

    1. Connection to water authoritys main and all work up to boundary of site, including

    reinstatement of public highway and provision of stop valve near the site boundary.

    2. Underground service and rising main from site boundary up to cold water storage

    tank, including any stop valves, holes through walls, ceiling and floors, lagging of

    pipes, and the like.

    3. Branches to rising main, such as supply to sink, including any associated works.

    4. Cold water storage tank or cistern and associated work such as bearers, overflow,

    cover and insulating lining.

    5. Down service with branches, including any stop valves, holes through walls, ceiling

    and floors and lagging of pipes.

    6. Sanitary appliances such as sinks, wash basins, baths and water closets supply and

    fixing, including supporting brackets, taps and the like.

    7. Discharge pipes (waste, soil and vent pipes) and associated work.

    8. Any other work connected with the plumbing installation, such as painting pipes and

    testing the installation.

    Drawing of plumbing installations -

    The architects drawing normally gives little information on the layout of the water service

    pipes in the building. The information supplied is frequently limited to the point of entry of

    the rising main in to the building, the position of the cold water storage tank or cistern and the

    various sanitary appliances. In these circumstances the quantity surveyor must decide on a

    suitable layout of pipes and plot them on the various drawings, with the consultation of the

    plumbing engineer. It is good practice to draw the various pipes in different colours, such as

    the rising main in red and down service in blue.

    Connection to water main -

    The tapping and insertion of a ferrule to the water authoritys main and the provision of the

    communication pipe from the main to the boundary of the site with a stop valve provided at

    this point, including opening up and reinstatement of the highway and all watching and

    lighting usually covered by a Provisional Sum (SMM A53.1.1 2.0.0).

  • Pipe Work -

    Classified under appropriate headings, such as cold water system (S10 of Common

    Arrangement) measured over all fittings and branches in meters stating the type,

    nominal size, method of jointing and type, spacing and method of fixing supports

    distinguish between straight and curved pipes (SMM Y10.1.1.1.0 and Y10.M3). Pipes are

    deemed to include joints in their running lengths (SMM Y10.C3). The provision of

    everything necessary for jointing is deemed to be included (SMM Y10.C.1). The type of

    background to which the pipe supports fixed is classified in the categories listed in SMM

    General Rules 8.3.

    Details of the kind and quality of materials used in the pipes, gauge and other particulars

    listed in SMM Y10.S1-6, and likely to be included in preamble clauses.

    Made bends, special joints and connections, and fittings such as Y-junctions, reducers,

    elbows, tees, and crosses are enumerated as items extra over the pipes in which they occur

    (SMM Y10.2.1-4).

    Pipe fittings 65 mm diameters are classified according to the number of ends, while those

    of larger diameter are described.

    Valves and cocks are classified as pipe work ancillaries and are enumerated, stating the type,

    nominal size, method of jointing, type, number and method of supports and type of pipe to

    which connected (SMM Y11.8.1.1.0).

    Water storage tanks or Cisterns

    Water storage tanks or cisterns are enumerated giving appropriate particulars (SMM

    Y21.1.1.0.0). Timber supports to tanks are measured in meters with a dimensioned overall

    cross-section description (SMM G20.13.0.1.0). Insulation to tanks or cisterns is enumerated,

    giving the overall size of he tank, or insulations contained in casings can be measured in m2

    (SMM Y50.1.4.1-2.0). Any pipe work located in the roof space should be insulated and this

    insulation is measured in meters giving the type of insulation and nominal size of the pipe

    (SMM Y50.1.1.1.0).

    Holes for pipes

    Cutting holes through the structure for pipes and making good structure are enumerated,

    stating the nature and thickness of the structure and the shape of the hole, and classifying the

    pipes to size in accordance with SMM P31.20.2.1 3.2 & 4. Ex: pipes 55 mm nominal size,

    55 110 mm and > 110 mm.

  • Sanitary Appliances

    Sanitary appliances include low level WC suits, WC pans and cisterns, urinals and cisterns,

    sinks, wash basins, bidets, baths, showers and vanity units (Common Arrangement N13).

    These appliances are enumerated giving details of the type, size, pattern and capacity, and

    method of fixing (SMM N13.4.1.1.6). The supply of appliances is frequently covered by

    prime cost sum, including relevant particulars and provision for main contractors profit

    (SMM A52.1.1.1.0). Another alternative is to give supply and fix items with full details

    (SMM General Rules 6.1).

    Builders work in connection with plumbing installations

    Builders work in connection with a plumbing installation is identified under an appropriate

    heading (SMM P31.M2). Unless identified in SMM work sections P30 and P31, all other

    items of builders work are given in accordance with the appropriate work sections (SMM

    P31.M1).

    Example Refer drawing in page no 8.

    ADVANCED BUILDING MEASUREMENTS

    MEASUREMENT OF MECHANICAL WORKS

    General Background

    The measurement of mechanical services installations requires a detailed knowledge of

    technology. The drawings from which the quantity surveyor must work are those that are

    prepared by the consulting services engineer. Consulting engineers are normally required to

    prepare drawings and specifications sufficient to obtain tenders. These drawings are

    schematic only, because trade practice is for the contractor to prepare all necessary working

    drawings and to include in his tender for a complete working installation. The exact route of

    pipe work and duct work is often left to the craft operatives doing the work. Therefore, the

    quantity surveyor must put himself in the position of the operative and include in the bill of

    quantities all items necessary for the complete installation.

    Measurement Procedure

    The first task is full study and understanding the drawings and specifications provided. A

    study of these documents will lead to queries. These queries must be first submitted to the

    consulting services engineer and clarified.

  • Approach to Measurement

    Having acquired adequate information and full understanding of the scheme, taking off can

    begin. Firstly, the drawings should be coloured up using a suitable colour code to illustrate

    the various services to be measured. The drawings are mainly in the form of floor plans and it

    is often helpful to draw a sketch of complicated sections of the work to be taken off in

    isometric projection to illustrate the full extent of the work involved.

    The process of measurement is relatively straightforward, comprising enumerated items of

    plant at the source, a connecting network of pipe work or ducting measured linearly, with

    enumerated fittings taken as extra over pipes and ducting, enumerated ancillaries, and finally

    enumerated items for the emission plant and equipment. Special supports and sleeves for

    pipes and ducting generate further enumerated items.

    Work in plant rooms is identified separately because of the restricted working conditions

    (SMM Y10/20/30.M2). Everything necessary for jointing is deemed to be included (SMM

    Y10/20/30.C1) and full requirement of materials shall be given as prescribed in SMM

    Y10/20/30.S1-6. Thermal insulation to pipelines and ducting is measured in meters giving the

    nominal size of the pipeline or ducting, while insulation to equipment is enumerated giving

    the overall size or measured in m2 (SMM Y50.1.1, 3 & 4.1.0).

    Pipe fittings 65 mm diameters are grouped together irrespective of type, stating the number

    of ends. With larger fittings the type is stated (SMM Y10.2.3 4.2 6.1 2). Examples of

    pipe work ancillaries are draw-off taps, stop valves, control valves, non-return valves, drain

    cocks, stop cocks, air cocks, mixing valves, steam traps, strainers, gauges and thermometers

    and automatic controls.

    Other Measurement Aspects

    Work Sections

    The rules for the measurement of mechanical services given in Work Group Y are billed

    under separate work sections. Those work sections are;

    R Disposal system includes sewage pumping and refuses chutes.

    S Piped supply system includes cold water, hot water, steam, fire hose reels, dry risers, wet

    risers and sprinklers.

    T Mechanical Heating / Cooling / Refrigeration Systems includes gas / oil fired boilers,

    coal fired boilers, heat pumps, solar collectors, low temperature hot water heating, steam

    heating, warm air heating and central refrigeration plant.

    U Ventilation / Air Conditioning System include toilet and kitchen extracts, smoke extracts

    / smoke control and various forms of air conditioning.

  • Pipe work generally

    Pipes are classified under appropriate headings such as hot water supply and measured over

    all fittings and branches in meters, stating the type, nominal size, method of jointing and type,

    spacing and method of fixing supports, and distinguishing between straight and curved pipes

    (SMM Y10.1.1.1.0 and Y10.M3). Pipes are deemed to include joints in their running length

    (SMM Y10.C3) and the provision of everything necessary for jointing (SMM Y10.C1),

    without the need for specific mention. The type of background to which the pipe supports are

    fixed will be classified in the categories listed in SMM General rule 8.3.

    Details of the kind and quality of materials used in the pipes, gauge and other relevant

    particulars listed in SMM Y10.S1 6 are to be included in preamble clauses.

    Made bends, special joints and connections and fittings such as Y-junctions, reducers,

    elbows, tees and crosses are all enumerated as items extra over the pipes in which they occur

    (SMM Y10.2.1 4). In the case of special joints, the type and method of jointing is to be

    stated and they comprise joints which differ from those generally occurring in the running

    length or are connections to pipes of a different profile or material, connections to existing

    pipes or to equipment, appliances or ends of flue pipes (SMM Y10.D2).

    Pipe fittings 65 mm diameters are classified according to the number of ends, while those

    of larger diameter are described. The method of jointing is stated where different from the

    pipe in which the fitting occurs.

    Valves and cocks are classified as pipe work ancillaries and are enumerated, stating the type,

    nominal size, method of jointing, type, number and method of fixing supports and the type of

    pipe to be connected (SMM Y11.8.1.1.0). Those located in ducts or trenches are each kept

    separate and so described.

    Cutting holes through the structure for pipes and making good surfaces are enumerated,

    stating the nature and thickness of the structure and the shape of the hole, classifying the

    pipes as to size in accordance with SMM P31.20.2.1 3.2 & 4; for example pipes 55 mm

    nominal size, 55 110 mm and > 110 mm.

    Equipment

    When measuring mechanical equipments, such details as type, size and pattern, rated duty,

    capacity, loading as appropriate and method of fixing are stated. Specification cross

    references are often inserted for mechanical equipment as provided for in SMM

    Y20/40.1.1.1.0. Examples of equipments include boilers, generators, water treatment and

    pressurisation plant, tanks, cylinders, clarifiers, pumps, compressors, fans, filters, humidifiers

    and refrigeration units.

  • Air Duct lines

    Ducting is classified as to whether straight, curved stating radii or flexible and giving the

    type, shape, size, method of jointing and spacing and method of fixing supports, and

    background, and is measured in meters (SMM Y30.1.1 5.1.1). It is measured over all

    fittings and branches (SMM Y30.M3) and is deemed to include joints in running lengths and

    stiffeners (SMM Y30.C3).

    Items measured extra over include;

    1. Lining ducting internally in meters, stating type and thickness of lining materials and

    internal size of ducting (SMM Y30.2.1.1.0).

    2. Special joints and connections, (SMM Y30.D2), enumerated stating type, size,

    ducting size and method of jointing.

    3. Fittings such as stop ends, bends, offsets, diminishing pieces, changes of section

    pieces and junction pieces, access openings and covers for doors, nozzle outlets, and

    test holes and covers are each enumerated stating the type (SMM Y30.3-6.1.1).

    Ancillaries to ducting, such as grilles, diffusers, dampers, shutters, cowls, terminals, roof

    ventilators, attenuators and anti-vermin screens are enumerated giving necessary information

    (SMM Y30.4.1.1.0). Breaking in to existing ducting is given as item, stating the type, size

    and location of duct and purpose of breaking in (SMM Y30.5.1.1 4).

    Ducting sleeves are enumerated (SMM Y30.7.1 2.11 -2).

    Pipe and Ducting Supports

    Pipe and ducting supports which differ from those given with pipe or duct lines are separately

    enumerated, giving details of the nominal size of pipe or shape and size of duct, type and size

    of support, method of fixing pipe or duct support and nature of background (SMM

    Y10.9.0.1.3 and Y30.6.0.1.3).

    Builders work in connection with mechanical installations

    Builders work in connection with a mechanical installation is identified under an appropriate

    heading (SMM P31.M2). Unless identified in SMM work sections P30 and P31, all other

    items of builders work are given in accordance with the appropriate work sections (SMM

    P31.M1).

    Example:

    The example covers the measurement of low pressure hot water heating and ventilation

    system. Refer drawing in page no 7.