04/08/23
A PLC system: CPU module (left) and an I/O rack (right) (Allen Bradley PLC-5) (Courtesy of Allen-Bradley)
![Page 2: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/2.jpg)
04/08/23
A small PLC (Allen Bradley MicroLogix 1000)(Courtesy of Allen-Bradley).
![Page 3: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/3.jpg)
04/08/23
Definition of PLC
PLC is a digitally operating electronic apparatus which uses a programmable memory for the internal storage of instructions by implementing specific functions such as logic sequencing, timing, counting, and arithmetic to control, through digital or analog input/output modules, various types of machines or processes.
![Page 4: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/4.jpg)
04/08/23
Inputs and outputs of PLC
• Inputs of PLC – Discrete signal from switch, approximate sensor,
push buttons– Analog signal from thermal couple, voltmeters,
etc.
• Outputs of PLC– Most often is the control signal to motor, valves,
etc.
![Page 5: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/5.jpg)
04/08/23
Types of switches
![Page 6: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/6.jpg)
04/08/23
A Relay
![Page 7: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/7.jpg)
04/08/23
A counter
![Page 8: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/8.jpg)
04/08/23
Counter timing diagram (the countvalue is 5)
![Page 9: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/9.jpg)
04/08/23
A timer
![Page 10: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/10.jpg)
04/08/23
Timer timing diagram (the timingvalue is 5)
![Page 11: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/11.jpg)
04/08/23
Ladder diagram for the circuit
![Page 12: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/12.jpg)
04/08/23
Wiring diagram
![Page 13: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/13.jpg)
04/08/23
Programmable logic controller system structure
![Page 14: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/14.jpg)
04/08/23
Memory
• ROM• RAM• PROM• EPROM• etc
![Page 15: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/15.jpg)
04/08/23
I/O modules (Courtesy of Allen-Bradley)
![Page 16: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/16.jpg)
04/08/23
Input/output module• Analog inputs
– Flow sensors– Humidity sensors– Potentiometers– Pressure sensors– Temperature sensors
• Analog outputs– Analog meters– Analog valves and actuators– DC and AC motor drives
• Digital input/output– Bar code, encoder– Display
• Special purpose I/O– PID controller– Fast input– Network module
![Page 17: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/17.jpg)
04/08/23
Power input connections: (a) AC, (b) DC, and (c) TTL
![Page 18: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/18.jpg)
04/08/23
Power output connections: (a) AC, (b) DC, and (c) TTL
![Page 19: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/19.jpg)
04/08/23
Peripherals
• Operator console• Printer• Simulator• EPROM loader• Network communication• PC based programming software
![Page 20: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/20.jpg)
04/08/23
Human interface terminal (Courtesy of Allen-Bradley)
![Page 21: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/21.jpg)
04/08/23
PC-based programming software
![Page 22: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/22.jpg)
04/08/23
A ladder diagram (also called contact symbology) is a means of graphically representing the logic required in a relay logic system.
![Page 23: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/23.jpg)
04/08/23
Some relay diagram symbols
![Page 24: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/24.jpg)
04/08/23
A ladder diagram
![Page 25: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/25.jpg)
04/08/23
PLC wiring diagram
![Page 26: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/26.jpg)
04/08/23
PLC scan
![Page 27: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/27.jpg)
04/08/23
Functions of PLC
• Relay• Timer and counter• Program control• Arithmetic• Data manipulation• Data transfer• Others, such as sequencers
![Page 28: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/28.jpg)
04/08/23
Basic logic
![Page 29: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/29.jpg)
04/08/23
And logic
![Page 30: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/30.jpg)
04/08/23
OR logic
![Page 31: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/31.jpg)
04/08/23
Combine AND and OR logic
![Page 32: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/32.jpg)
04/08/23
Example
A robot is used to load/unload parts to a machine from a conveyor. A part comes along the conveyor. When it touches a microswitch, it is scanned by a bar-code reader to identify it. If the part is the desired one, a stopper is activated to stop it. A robot picks up the part and loads it onto the machine if it is idle. Otherwise, the robot waits to unload the machine.
![Page 33: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/33.jpg)
04/08/23
Cell layout
![Page 34: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/34.jpg)
04/08/23
Example
![Page 35: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/35.jpg)
04/08/23
Program
![Page 36: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/36.jpg)
04/08/23
Wiring diagram
![Page 37: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/37.jpg)
04/08/23
EXPLANATION OF THE PROGRAM
Rung 1. If a part arrives and no part is stopped, trigger the barcode reader.Rung 2. If it is a right part, activate the stopper.Rung 3. If the stopper is up, the machine is not busy and the robot is not busy; load thepart onto the machine.Rung 4. If the task is completed and the robot is not busy, unload the machine.
![Page 38: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/38.jpg)
04/08/23
Procedure for developing automation system using PLC
1. Define the process to be controlled.2. Make a sketch of the process operation.3. Create a written step sequence listing for the process.4. Add sensors on the sketch as needed to carry out the control
sequence.5. Add manual controls as needed for process setup or
operational checking.6. Consider the safety of the operating personnel and make
additions and adjustments as needed.7. Add master stop switches as required for safe shutdown.8. Create the ladder logic diagram that will be used as a basis for
the PLC program.9. Consider the "what if's" where the process sequence may go
astray.
![Page 39: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/39.jpg)
04/08/23
1. Define the problem
We wish to set up a system for spray-painting parts. A part is to be placed on a mandrel. (A mandrel is a shaft or bar whose end is inserted into a workpiece to hold it during an operation.) When the part is in place, two pushbuttons are pressed and the mandrel rises. After the part rises to the top and is in the hood, it is to have spray paint applied for a period of 6 seconds. At the end of the 6 seconds, the mandrel returns to the original position. The painted part is then removed from the mandrel by hand.
![Page 40: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/40.jpg)
04/08/23
2. Process sketch
![Page 41: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/41.jpg)
04/08/23
3. List of operation sequence1. Turn on the paint pump and pneumatic air supply.2. Turn the system on. This requires pushbuttons other than the system buttons.3. Put the part on the mandrel. A sensor indicates that the part is in place.4. Push the Master Start button and the two system start buttons. Having to push two
system start buttons (with both hands) reduces the possibility of the operator's hands being injured by the rising mandrel.
5. The mandrel is raised by a pneumatic cylinder energized by the opening of an electrically actuated air valve when the system start buttons are pressed. (The mandrel will return by gravity and downward spring action when the valve is reopened.) When the mandrel rises, the part-in-place sensor at the bottom becomes de-energized. (Note: The part-in-place sensor does not rise with the mandrel.)
6. When the part reaches the top and is under the hood, it is held against a stop by air pressure. A sensor has indicated that the part has reached the top.
7. A timer starts and runs for 6 seconds.8. During the timing period of 6 seconds, paint is applied by the sprayer.9. At the end of 6 seconds, painting stops and the mandrel, with the part on it, lowers.10. The up sensor is deenergized when the mandrel with the part on it descends.11. The part arrives at the bottom, reenergizing the part-in-place sensor.12. The part is removed from the mandrel.13. The system resets so that we may start at step 3 again.
![Page 42: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/42.jpg)
04/08/23
4. Add sensors
![Page 43: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/43.jpg)
04/08/23
5. Add manual control
We may need a manual pushbutton to raise the mandrel to the top for setup purposes. The manual up position is needed when we set the spray-gun pressure for optimum paint coverage. We include pushbutton up (PBU) on our ladder diagram to accomplish this manual control.
![Page 44: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/44.jpg)
04/08/23
6. Consider safety
One basic way to keep hands out of a process is to have two start buttons. Then both hands must be away from the work to depress both buttons (which works until the operator figures out how to use one knee and one hand). Other considerations, which we do not cover in detail here, might be operating a fan to disperse fumes during spraying, or perhaps a photocell proximity-personnel-system-stop device.
![Page 45: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/45.jpg)
04/08/23
7. Add emergency stop
Add emergency and master stop switches as needed for operator safety. This may seem to be part of step 6 because both steps deal with operator safety. It is a continuation of the safety issue, but emergency stop switches are so important that they need special consideration as an additional step.
![Page 46: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/46.jpg)
04/08/23
Create Ladder Diagram
![Page 47: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/47.jpg)
04/08/23
9. Determine what-ifs
• All possible situations and emergencies should be listed. In this example, some of them might be:– What if no part is in place when the start buttons are
pushed?– What if the power fails during the cycle when the part
is rising, during painting, or at any other time?– What if the sprayer runs out of paint?– What if the same part is left in for a double coat?– What if the master stop button is pushed? Does the
stop button really stop the entire process, or can the mandrel move and create a safety problem after the stop button is depressed (it can)?
![Page 48: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/48.jpg)
04/08/23
System I/O
![Page 49: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/49.jpg)
04/08/23
Truth table
![Page 50: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/50.jpg)
04/08/23
![Page 51: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/51.jpg)
04/08/23
Ladder diagram for a three-switch system
![Page 52: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/52.jpg)
04/08/23
Ladder diagram for Example 10.2
![Page 53: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/53.jpg)
04/08/23
State diagram for a two-state and transition system
![Page 54: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/54.jpg)
04/08/23
Ladder diagram for Example 10.3
![Page 55: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/55.jpg)
04/08/23
Ladder diagram forthe state diagram in Figure 10.27
![Page 56: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/56.jpg)
04/08/23
State diagram for Example 10.4
![Page 57: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/57.jpg)
04/08/23
![Page 58: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/58.jpg)
04/08/23
State diagram for Example 10.5
![Page 59: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/59.jpg)
04/08/23
![Page 60: PLC](https://reader031.fdocuments.us/reader031/viewer/2022013114/5457c9f5b1af9ff7618b4b33/html5/thumbnails/60.jpg)
04/08/23
State diagram for Example 10.6