PLATO Phase A/B1 Status TOU Meeting Catania 28 Feb 2011 PLAnetary Transits and Oscillation of stars.

20
PLATO Phase A/B1 Status TOU Meeting Catania 28 Feb 2011 PLAnetary Transits and Oscillation of stars

Transcript of PLATO Phase A/B1 Status TOU Meeting Catania 28 Feb 2011 PLAnetary Transits and Oscillation of stars.

PLATO Phase A/B1 Status

TOU Meeting

Catania 28 Feb 2011

PLAnetary Transits and Oscillation of stars

2

Mission Requirements (1/2)

Launch from French Guiana by a Soyuz 2-1b launch vehicle

Max launch mass: 2100 Kg plus adapter (GAIA baseline).

Operations in a large orbit around the Earth-Sun Lagrange Point 2 (L2)

Nominal mission duration of 6 years after commissioning

Spacecraft sized for 8 years

Long observation runs above +60 degree and below -60 degree ecliptic latitude

Step-and-Stare Phase with observation at any ecliptic latitude and longitude subject

to Sun in favourable direction

Quarterly 90deg rotation around the mean Line of Sight of the Spacecraft

3

Mission Requirements (1/2)

Three days autonomy without ground contact

Seven days in Survival Mode

Communication with S/C via X band

Use of 15 m antenna in Kourou

Use of 35 m antenna in Cebreros and New Norcia

24 hours coverage during LEOP

During science operations up/downlink is time-limited

4 hours per day coverage during nominal operations

3.5 hrs / day for data downlink

0.5 hrs / day for setup / ranging

4

Project Schedule

Program Milestones

Assessment Phase in 2008- Aug 2009 (Completed)

ESA internal review: Sep – Oct 2009 (Completed)

First down-selection of M-class missions to enter the Definition Phase (A/B1): Feb 2010 (Completed)

Definition Phase (A/B1) K.O.: 01 July 2010 (Done)

Second down-selection for M1/M2: October 2011

Completion of the Definition Phase (A/B1): 31 December 2011

Final adoption for the Implementation Phase (B2/C/D/E1): before Feb 2012

Start of the Implementation Phase: by July 2012

Launch: by end 2018

5

Industrial Activities (1/2)

PLATO is in the Definition phase (A/B1) which is conducted according to the following plan

Two parallel and competitive studies are performed

The studies are conducted by EADS Astrium (SAS) and Thales Alenia Space which were selected as result of the tenders evaluation

Both studies are progressing nominally.

6

Industrial Activities (2/2)

The Preliminary Configuration Definition Review (PCDR) was successfully completed in week 42 (18-22 Oct) for both Contractors with identified criticalities and recommendations

Spacecraft Configurations capable of accommodating the payload and consistent with the established mission requirements have been identified

Preliminary analyses have demonstrated consistency of the design with the established ESA requirements

Go-ahead has been given to initiate the post PCDR tasks i.e. detailed system design, programmatic aspects and costs evaluation

All Phase A activities shall be completed by May 15, 2011 and will be subject to the planned PRR.

7

Technology DevelopmentPLATO CCD development activity

Development of dedicated PLATO CCDs

For each telescope: 4 CCDs of 45102 pixels18μm pixel pitch; 15 arcse/pixel plate scale 136 CCDs in total; FPA size: 164mm2

Temperature: Nominal -70C

Normal telescopes (32): full frame operation25 sec observation cyclemagnitude range: 8 – 11 mV

Fast telescopes (2): frame transfer operation; also for AOCS information2.5 sec observation cyclemagnitude range: 4 – 8 mV

8

Spacecraft and Payload Configuration

Payload Electrical Configuration

9

Technology Development

Development of dedicated PLATO CCDs

For each telescope: 4 CCDs of 45102 pixels18μm pixel pitch; 15 arcse/pixel plate scale 136 CCDs in total; FPA size: 164mm2

Temperature: Nominal -70C

Normal telescopes (32): full frame operation25 sec observation cyclemagnitude range: 8 – 11 mV

Fast telescopes (2): frame transfer operation; also for AOCS information2.5 sec observation cyclemagnitude range: 4 – 8 mV

10

Spacecraft and Payload Configuration

SVM Electrical Configuration (option)

11

Spacecraft and Payload Configuration

12

Spacecraft and Payload Configuration

13

Spacecraft and Payload Configuration

Units accommodation in the SVM

14

Spacecraft and Payload Configuration

Spacecraft alternative configuration

15

Spacecraft and Payload Configuration

Spacecraft alternative configuration

16

16

Mission Timeline

1. Commissioning starts during Transfer, and ends no later than 2 months after arrival in L2 (goal: ends upon arrival)

2. Nominal Science Ops = 6 years

3. Extended Science Ops = 2 years

4. TOTAL LIFETIME = 8 years

Spacecraft and Mission Description

17

17

Roll around LOS

1. Problem: body-mounted solar arrays must be occasionally re-pointed towards Sun

2. Strategy: rotate around LOS by 90° every 3 months

LOS stays fixed on the field

3. Maximum solar aspect angle 45° in azimuth 30° in elevation

Max azimuth of Sun = 45°

Rotate 90°

3 months with inertially stable attitude

Spacecraft and Mission Description

18

18

Operational Orbit

19

Conclusions

All PLATO activities are progressing nominally

No show-stoppers have been identified

To come:

Spacecraft detailed design (on going)

AO intermediate review: in March

Issue of the updated AO: in April

Spacecraft PRR and Consortium PIRR (from mid May)

Phase A conclusion: end June

Updated AO response and evaluation: in Jul

Decision for implementation: October 2011

20

Thank You